Federal Register / Vol. 78, No. 230 / Friday, November 29, 2013 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13704–002]
sroberts on DSK5SPTVN1PROD with NOTICES
Free Flow Power Missouri 2, LLC;
Notice of Application Tendered for
Filing With the Commission and
Soliciting Additional Study Requests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Major.
b. Project No.: P–13704–002.
c. Date Filed: November 13, 2013.
d. Applicant: Free Flow Power
Missouri 2, LLC.
e. Name of Project: Arkabutla Lake
Hydroelectric Project.
f. Location: At the U.S. Army Corps of
Engineers’ (Corps) existing Arkabutla
Lake Dam, on the Coldwater River, near
the Town of Hernando, Tate and DeSoto
Counties, Mississippi. The proposed
project would occupy approximately
48.2 acres of federal lands administered
by the Corps.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Mr. Thomas
Feldman, Vice President of Project
Development, Free Flow Power
Corporation, 239 Causeway Street, Suite
300, Boston, MA 02114, (978) 283–2822.
i. FERC Contact: Patti Leppert, (202)
502–6034, patricia.leppert@ferc.gov.
j. Cooperating Agencies: Federal,
state, local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See, 94
FERC ¶ 61,076 (2001).
k. Pursuant to 18 CFR section
4.32(b)(7) of the Commission’s
regulations, if any resource agency,
Indian Tribe, or person believes that an
additional scientific study should be
conducted in order to form an adequate
factual basis for a complete analysis of
the application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: January 13, 2014.
VerDate Mar<15>2010
17:56 Nov 27, 2013
Jkt 232001
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–13704–002.
m. The application is not ready for
environmental analysis at this time.
n. The proposed project would utilize
the existing Corps’ Arkabutla Lake Dam
and Reservoir, and would consist of the
following new facilities: (1) A steel liner
installed within the existing concrete
outlet tunnel; (2) a steel-lined,
reinforced concrete bifurcation at the
end of the existing conduit dividing
flows between the existing stilling basin
and the powerhouse; (3) a 12-footdiameter, 272-foot-long penstock; (4) a
powerhouse with two generating units
having a total installed capacity of 5.1
megawatts; (5) a 200-foot-long tailrace
channel; (6) a 2,712-foot-long
transmission line; and (7) appurtenant
facilities.
o. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. With this notice, we are initiating
consultation with the Mississippi State
Historic Preservation Officer, as
required by section 106 of the National
Historic Preservation Act and the
regulations of the Advisory Council on
Historic Preservation, 36 CFR 800.4.
q. Procedural schedule: The
application will be processed according
to the following preliminary Hydro
Licensing Schedule. Revisions to the
schedule will be made as appropriate.
Issue Notice of Acceptance—March
2014.
PO 00000
Frm 00036
Fmt 4703
Sfmt 4703
Issue Scoping Document 1 for
comments—April 2014.
Comments on Scoping Document 1—
May 2014.
Issue Scoping Document 2 (if
necessary)—July 2014.
Issue notice of ready for
environmental analysis—July 2014.
Commission issues EA or draft EA—
January 2015.
Comments on EA or draft EA—
February 2015.
Commission issues final EA (if
necessary)—April 2015.
Dated: November 21, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–28544 Filed 11–27–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Filings Instituting Proceedings
Docket Numbers: RP14–191–000.
Applicants: Enable Gas Transmission,
LLC.
Description: Annual Sligo Lease
LUFG Percentage Tracker Tariff Filing
of Enable Gas Transmission, LLC.
Filed Date: 11/20/13.
Accession Number: 20131120–5041.
Comments Due: 5 p.m. ET 12/2/13.
Docket Numbers: RP14–192–000.
Applicants: Dominion Transmission,
Inc.
Description: DTI—November 20, 2013
Volume 1A Changes to be effective 12/
20/2013.
Filed Date: 11/20/13.
Accession Number: 20131120–5051.
Comments Due: 5 p.m. ET 12/2/13.
Docket Numbers: RP14–193–000.
Applicants: Natural Gas Pipeline
Company of America.
Description: Natural Gas Pipeline
Company of America LLC submits tariff
filing per 154.204: Castleton—
Negotiated Rate Filing to be effective 11/
21/2013.
Filed Date: 11/20/13.
Accession Number: 20131120–5106.
Comments Due: 5 p.m. ET 12/2/13.
Docket Numbers: RP14–194–000.
Applicants: WBI Energy
Transmission, Inc.
Description: WBI Energy
Transmission, Inc. submits tariff filing
per 154.204: 2013 Revised Non-
E:\FR\FM\29NON1.SGM
29NON1
Agencies
[Federal Register Volume 78, Number 230 (Friday, November 29, 2013)]
[Notices]
[Page 71596]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-28544]
[[Page 71596]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 13704-002]
Free Flow Power Missouri 2, LLC; Notice of Application Tendered
for Filing With the Commission and Soliciting Additional Study Requests
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Major.
b. Project No.: P-13704-002.
c. Date Filed: November 13, 2013.
d. Applicant: Free Flow Power Missouri 2, LLC.
e. Name of Project: Arkabutla Lake Hydroelectric Project.
f. Location: At the U.S. Army Corps of Engineers' (Corps) existing
Arkabutla Lake Dam, on the Coldwater River, near the Town of Hernando,
Tate and DeSoto Counties, Mississippi. The proposed project would
occupy approximately 48.2 acres of federal lands administered by the
Corps.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Mr. Thomas Feldman, Vice President of Project
Development, Free Flow Power Corporation, 239 Causeway Street, Suite
300, Boston, MA 02114, (978) 283-2822.
i. FERC Contact: Patti Leppert, (202) 502-6034,
patricia.leppert@ferc.gov.
j. Cooperating Agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item l below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See, 94 FERC ]
61,076 (2001).
k. Pursuant to 18 CFR section 4.32(b)(7) of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and serve a copy of
the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: January 13, 2014.
The Commission strongly encourages electronic filing. Please file
additional study requests and requests for cooperating agency status
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support
at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202)
502-8659 (TTY). In lieu of electronic filing, please send a paper copy
to: Secretary, Federal Energy Regulatory Commission, 888 First Street
NE., Washington, DC 20426. The first page of any filing should include
docket number P-13704-002.
m. The application is not ready for environmental analysis at this
time.
n. The proposed project would utilize the existing Corps' Arkabutla
Lake Dam and Reservoir, and would consist of the following new
facilities: (1) A steel liner installed within the existing concrete
outlet tunnel; (2) a steel-lined, reinforced concrete bifurcation at
the end of the existing conduit dividing flows between the existing
stilling basin and the powerhouse; (3) a 12-foot-diameter, 272-foot-
long penstock; (4) a powerhouse with two generating units having a
total installed capacity of 5.1 megawatts; (5) a 200-foot-long tailrace
channel; (6) a 2,712-foot-long transmission line; and (7) appurtenant
facilities.
o. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at the address in item h above.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
p. With this notice, we are initiating consultation with the
Mississippi State Historic Preservation Officer, as required by section
106 of the National Historic Preservation Act and the regulations of
the Advisory Council on Historic Preservation, 36 CFR 800.4.
q. Procedural schedule: The application will be processed according
to the following preliminary Hydro Licensing Schedule. Revisions to the
schedule will be made as appropriate.
Issue Notice of Acceptance--March 2014.
Issue Scoping Document 1 for comments--April 2014.
Comments on Scoping Document 1--May 2014.
Issue Scoping Document 2 (if necessary)--July 2014.
Issue notice of ready for environmental analysis--July 2014.
Commission issues EA or draft EA--January 2015.
Comments on EA or draft EA--February 2015.
Commission issues final EA (if necessary)--April 2015.
Dated: November 21, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-28544 Filed 11-27-13; 8:45 am]
BILLING CODE 6717-01-P