Free Flow Power Missouri 2, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests, 71592-71593 [2013-28541]

Download as PDF sroberts on DSK5SPTVN1PROD with NOTICES 71592 Federal Register / Vol. 78, No. 230 / Friday, November 29, 2013 / Notices 480(c)(1)) is considered an independent student for purposes of title IV, HEA program assistance eligibility, and therefore does not have to provide parental income and asset information to apply for title IV, HEA program assistance. (20 U.S.C. 1087vv(d)(1)(D)). 3. Authority for Conducting the Matching Program. ED is authorized to participate in the matching program under sections 480(c)(1) and 480(d)(1)(D) of the HEA (20 U.S.C. 1087vv(c)(1) and (d)(1)(D)). VA is authorized to participate in the matching program under 38 U.S.C. 523. 4. Categories of Records and Individuals Covered by the Match. ED will provide the Social Security number and other identifying information of each applicant for financial assistance under title IV of the HEA who indicates veteran status. This information will be disclosed from the Federal Student Aid Application File system of records (18–11–01), which was most recently published in the Federal Register on August 3, 2011 (74 FR 46774–46781). ED will disclose this information to VA under routine use 14 of the system of records (18–11–01). ED data will be matched against data in the Veterans and Beneficiaries Identification and Records Location Subsystem—VA (38VA21) system of records, under routine use 21, as added to that system of records (38VA21) by a notice published in the Federal Register on June 4, 2001 (66 FR 30049–30050). 5. Effective Dates of the Matching Program. The matching program will be effective on the latest of the following three dates: (A) December 30, 2013; (B) 30 days from the date ED publishes a Computer Matching Notice in the Federal Register as required by 5 U.S.C. 552a(e)(12); or, (C) 40 days from the date that ED transmits the report of the matching program, as required by 5 U.S.C. 552a(r), to OMB, the U.S. House Committee on Oversight and Government Reform, and the U.S. Senate Committee on Homeland Security and Governmental Affairs, unless OMB waives 10 or fewer days of the 40-day review period for compelling reasons, in which case 30 days plus whatever number of days that OMB did not waive from the date of ED’s transmittal of the matching program report. 6. Address for Receipt of Public Comments or Inquiries. Individuals wishing to comment on this matching program or obtain additional information about the program, including requesting a copy of the CMA between ED and VA, should contact Ms. Marya Dennis, Management VerDate Mar<15>2010 17:56 Nov 27, 2013 Jkt 232001 and Program Analyst, U.S. Department of Education, Federal Student Aid, Union Center Plaza, 830 First Street NE., Washington, DC 20202. Telephone: (202) 377–3385. If you use a telecommunications device for the deaf (TDD) or a text telephone (TTY), call the Federal Relay Service (FRS), toll free, at 1–800–877–8339. Accessible Format: Individuals with disabilities can obtain this document in an accessible format (e.g., braille, large print, audiotape, or compact disc) by contacting the person listed in the preceding paragraph. Electronic Access to This Document: The official version of this document is the document published in the Federal Register. Free Internet access to the official edition of the Federal Register and the Code of Federal Regulations is available via the Federal Digital System at: www.gpo.gov. At this site you can view this document, as well as all other documents of this Department published in the Federal Register, in text or Adobe Portable Document Format (PDF). To use PDF you must have Adobe Acrobat Reader, which is available free at the site. You may also access documents of the Department published in the Federal Register by using the article search feature at: www.federalregister.gov. Specifically through the advanced search feature at this site, you can limit your search to documents published by the Department. Dated: November 18, 2013. James W. Runcie, Chief Operating Officer, Federal Student Aid. [FR Doc. 2013–28622 Filed 11–27–13; 8:45 am] BILLING CODE 4000–01–P DEPARTMENT OF ENERGY National Coal Council Department of Energy, Office of Fossil Energy. ACTION: Notice of renewal. AGENCY: Pursuant to Section 14(a)(2)(A) of the Federal Advisory Committee Act, (Pub. L. 92–463), and in accordance with Title 41 of the Code of Federal Regulations, Section 102–3.65, and following consultation with the Committee Management Secretariat, General Services Administration, notice is hereby given that the National Coal Council (NCC) will be renewed for a two-year period. The Committee will continue to provide advice and recommendations to the Secretary of Energy on general policy matters relating to coal issues. SUMMARY: PO 00000 Frm 00032 Fmt 4703 Sfmt 4703 Additionally, the renewal of the National Coal Council has been determined to be essential to conduct business of the Department of Energy and to be in the public interest in connection with the performance of duties imposed upon the Department of Energy by law and agreement. The Committee will continue to operate in accordance with the provisions of the Federal Advisory Committee Act, adhering to the rules and regulations in implementation of that Act. FOR FURTHER INFORMATION CONTACT: Dr. Robert Wright at (202) 586–0429. Issued in Washington, DC on November 22, 2013. Carol A. Matthews, Committee Management Officer. [FR Doc. 2013–28683 Filed 11–27–13; 8:45 am] BILLING CODE 6450–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13701–002] Free Flow Power Missouri 2, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Major. b. Project No.: P–13701–002. c. Date filed: November 13, 2013. d. Applicant: Free Flow Power Missouri 2, LLC. e. Name of Project: Sardis Lake Hydroelectric Project. f. Location: At the U.S. Army Corps of Engineers’ (Corps) existing Sardis Lake Dam, on the Little Tallahatchie River, near the Town of Sardis, Panola County, Mississippi. The proposed project would occupy approximately 59 acres of federal lands administered by the Corps. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Mr. Thomas Feldman, Vice President of Project Development, Free Flow Power Corporation, 239 Causeway Street, Suite 300, Boston, MA 02114, (978) 283–2822. i. FERC Contact: Patti Leppert, (202) 502–6034, patricia.leppert@ferc.gov. j. Cooperating agencies: Federal, state, local, and tribal agencies with jurisdiction and/or special expertise with respect to environmental issues that wish to cooperate in the preparation of the environmental document should follow the E:\FR\FM\29NON1.SGM 29NON1 sroberts on DSK5SPTVN1PROD with NOTICES Federal Register / Vol. 78, No. 230 / Friday, November 29, 2013 / Notices instructions for filing such requests described in item l below. Cooperating agencies should note the Commission’s policy that agencies that cooperate in the preparation of the environmental document cannot also intervene. See, 94 FERC ¶ 61,076 (2001). k. Pursuant to 18 CFR section 4.32(b)(7) of the Commission’s regulations, if any resource agency, Indian Tribe, or person believes that an additional scientific study should be conducted in order to form an adequate factual basis for a complete analysis of the application on its merit, the resource agency, Indian Tribe, or person must file a request for a study with the Commission not later than 60 days from the date of filing of the application, and serve a copy of the request on the applicant. l. Deadline for filing additional study requests and requests for cooperating agency status: January 13, 2014. The Commission strongly encourages electronic filing. Please file additional study requests and requests for cooperating agency status using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The first page of any filing should include docket number P–13701–002. m. The application is not ready for environmental analysis at this time. n. The proposed project would utilize the existing Corps’ Sardis Lake Dam and Reservoir, and would consist of the following new facilities: (1) A steel liner installed within the existing concrete outlet tunnel; (2) a steel-lined, reinforced concrete bifurcation at the end of the existing conduit dividing flows between the existing stilling basin and the powerhouse; (3) a 15.5-footdiameter, 250-foot-long steel penstock; (4) a powerhouse with two generating units having a total installed capacity of 14.6 megawatts; (5) a 200-foot-long tailrace channel; (6) a 6,210-foot-long transmission line; and (7) appurtenant facilities. o. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. A copy is also available VerDate Mar<15>2010 17:56 Nov 27, 2013 Jkt 232001 for inspection and reproduction at the address in item h above. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. p. With this notice, we are initiating consultation with the Mississippi State Historic Preservation Officer, as required by section 106 of the National Historic Preservation Act and the regulations of the Advisory Council on Historic Preservation, 36 CFR 800.4. q. Procedural schedule: The application will be processed according to the following preliminary Hydro Licensing Schedule. Revisions to the schedule will be made as appropriate. Issue Notice of Acceptance—March 2014. Issue Scoping Document 1 for comments—April 2014. Comments on Scoping Document 1— May 2014. Issue Scoping Document 2 (if necessary)—July 2014. Issue notice of ready for environmental analysis—July 2014. Commission issues EA or draft EA— January 2015. Comments on EA or draft EA— February 2015. Commission issues final EA (if necessary) April 2015. Dated: November 21, 2013. Kimberly D. Bose, Secretary. [FR Doc. 2013–28541 Filed 11–27–13; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13702–002] Free Flow Power Missouri 2, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Major. b. Project No.: P–13702–002. c. Date filed: November 13, 2013. d. Applicant: Free Flow Power Missouri 2, LLC. e. Name of Project: Grenada Lake Hydroelectric Project. f. Location: At the U.S. Army Corps of Engineers’ (Corps) existing Grenada PO 00000 Frm 00033 Fmt 4703 Sfmt 4703 71593 Lake Dam, on the Yalobusha River, near the Town of Grenada, Grenada County, Mississippi. The proposed project would occupy approximately 35.5 acres of federal lands administered by the Corps. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r). h. Applicant Contact: Mr. Thomas Feldman, Vice President of Project Development, Free Flow Power Corporation, 239 Causeway Street, Suite 300, Boston, MA 02114, (978) 283–2822. i. FERC Contact: Patti Leppert, (202) 502–6034, patricia.leppert@ferc.gov. j. Cooperating Agencies: Federal, state, local, and tribal agencies with jurisdiction and/or special expertise with respect to environmental issues that wish to cooperate in the preparation of the environmental document should follow the instructions for filing such requests described in item l below. Cooperating agencies should note the Commission’s policy that agencies that cooperate in the preparation of the environmental document cannot also intervene. See, 94 FERC ¶ 61,076 (2001). k. Pursuant to 18 CFR 4.32(b)(7) of the Commission’s regulations, if any resource agency, Indian Tribe, or person believes that an additional scientific study should be conducted in order to form an adequate factual basis for a complete analysis of the application on its merit, the resource agency, Indian Tribe, or person must file a request for a study with the Commission not later than 60 days from the date of filing of the application, and serve a copy of the request on the applicant. l. Deadline for filing additional study requests and requests for cooperating agency status: January 13, 2014. The Commission strongly encourages electronic filing. Please file additional study requests and requests for cooperating agency status using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The first page of any filing should include docket number P–13702–002. m. The application is not ready for environmental analysis at this time. n. The proposed project would utilize the existing Corps’ Grenada Lake Dam and Reservoir, and would consist of the following new facilities: (1) A steel liner installed within the existing concrete outlet tunnel; (2) a steel-lined, E:\FR\FM\29NON1.SGM 29NON1

Agencies

[Federal Register Volume 78, Number 230 (Friday, November 29, 2013)]
[Notices]
[Pages 71592-71593]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-28541]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13701-002]


Free Flow Power Missouri 2, LLC; Notice of Application Tendered 
for Filing With the Commission and Soliciting Additional Study Requests

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Major.
    b. Project No.: P-13701-002.
    c. Date filed: November 13, 2013.
    d. Applicant: Free Flow Power Missouri 2, LLC.
    e. Name of Project: Sardis Lake Hydroelectric Project.
    f. Location: At the U.S. Army Corps of Engineers' (Corps) existing 
Sardis Lake Dam, on the Little Tallahatchie River, near the Town of 
Sardis, Panola County, Mississippi. The proposed project would occupy 
approximately 59 acres of federal lands administered by the Corps.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Mr. Thomas Feldman, Vice President of Project 
Development, Free Flow Power Corporation, 239 Causeway Street, Suite 
300, Boston, MA 02114, (978) 283-2822.
    i. FERC Contact: Patti Leppert, (202) 502-6034, 
patricia.leppert@ferc.gov.
    j. Cooperating agencies: Federal, state, local, and tribal agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues that wish to cooperate in the preparation of the 
environmental document should follow the

[[Page 71593]]

instructions for filing such requests described in item l below. 
Cooperating agencies should note the Commission's policy that agencies 
that cooperate in the preparation of the environmental document cannot 
also intervene. See, 94 FERC ] 61,076 (2001).
    k. Pursuant to 18 CFR section 4.32(b)(7) of the Commission's 
regulations, if any resource agency, Indian Tribe, or person believes 
that an additional scientific study should be conducted in order to 
form an adequate factual basis for a complete analysis of the 
application on its merit, the resource agency, Indian Tribe, or person 
must file a request for a study with the Commission not later than 60 
days from the date of filing of the application, and serve a copy of 
the request on the applicant.
    l. Deadline for filing additional study requests and requests for 
cooperating agency status: January 13, 2014.
    The Commission strongly encourages electronic filing. Please file 
additional study requests and requests for cooperating agency status 
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support 
at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 
502-8659 (TTY). In lieu of electronic filing, please send a paper copy 
to: Secretary, Federal Energy Regulatory Commission, 888 First Street 
NE., Washington, DC 20426. The first page of any filing should include 
docket number P-13701-002.
    m. The application is not ready for environmental analysis at this 
time.
    n. The proposed project would utilize the existing Corps' Sardis 
Lake Dam and Reservoir, and would consist of the following new 
facilities: (1) A steel liner installed within the existing concrete 
outlet tunnel; (2) a steel-lined, reinforced concrete bifurcation at 
the end of the existing conduit dividing flows between the existing 
stilling basin and the powerhouse; (3) a 15.5-foot-diameter, 250-foot-
long steel penstock; (4) a powerhouse with two generating units having 
a total installed capacity of 14.6 megawatts; (5) a 200-foot-long 
tailrace channel; (6) a 6,210-foot-long transmission line; and (7) 
appurtenant facilities.
    o. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at https://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    p. With this notice, we are initiating consultation with the 
Mississippi State Historic Preservation Officer, as required by section 
106 of the National Historic Preservation Act and the regulations of 
the Advisory Council on Historic Preservation, 36 CFR 800.4.
    q. Procedural schedule: The application will be processed according 
to the following preliminary Hydro Licensing Schedule. Revisions to the 
schedule will be made as appropriate.
    Issue Notice of Acceptance--March 2014.
    Issue Scoping Document 1 for comments--April 2014.
    Comments on Scoping Document 1--May 2014.
    Issue Scoping Document 2 (if necessary)--July 2014.
    Issue notice of ready for environmental analysis--July 2014.
    Commission issues EA or draft EA--January 2015.
    Comments on EA or draft EA--February 2015.
    Commission issues final EA (if necessary) April 2015.

    Dated: November 21, 2013.
Kimberly D. Bose,
 Secretary.
[FR Doc. 2013-28541 Filed 11-27-13; 8:45 am]