Erie Boulevard Hydropower, L.P.; Notice of Application Accepted for Filing, Soliciting Motions To Intervene and Protests, Ready for Environmental Analysis, and Soliciting Comments, Recommendations, Preliminary Terms and Conditions, and Preliminary Fishway Prescriptions, 70546-70547 [2013-28257]
Download as PDF
70546
Federal Register / Vol. 78, No. 228 / Tuesday, November 26, 2013 / Notices
respectively. In determining the
appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
o. Filing and Service of Responsive
Documents: Any filing must (1) bear in
all capital letters the title
‘‘COMMENTS’’, ‘‘PROTEST’’, or
‘‘MOTION TO INTERVENE’’ as
applicable; (2) set forth in the heading
the name of the applicant and the
project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, motions to intervene, or
protests must set forth their evidentiary
basis and otherwise comply with the
requirements of 18 CFR 4.34(b). All
comments, motions to intervene, or
protests should relate to project works
that are the subject of the license
amendment. Agencies may obtain
copies of the application directly from
the applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. If an intervener files
comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency. A copy of all
other filings in reference to this
application must be accompanied by
proof of service on all persons listed in
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
Dated: November 19, 2013.
Kimberly D. Bose,
Secretary.
emcdonald on DSK67QTVN1PROD with NOTICES
[FR Doc. 2013–28258 Filed 11–25–13; 8:45 am]
BILLING CODE 6717–01–P
VerDate Mar<15>2010
18:04 Nov 25, 2013
Jkt 232001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 7518–015]
Erie Boulevard Hydropower, L.P.;
Notice of Application Accepted for
Filing, Soliciting Motions To Intervene
and Protests, Ready for Environmental
Analysis, and Soliciting Comments,
Recommendations, Preliminary Terms
and Conditions, and Preliminary
Fishway Prescriptions
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
License.
b. Project No.: 7518–015.
c. Date Filed: September 30, 2013.
d. Applicant: Erie Boulevard
Hydropower, L.P.
e. Name of Project: Hogansburg
Hydroelectric Project.
f. Location: On the St. Regis River in
Franklin County, New York. The project
does not occupy any federal lands.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Steven Murphy,
Licensing Manager, Erie Boulevard
Hydropower, L.P., 33 West 1st Street
South, Fulton, New York, 13069, (315)
598–6130 or email at steven.murphy@
brookfieldpower.com.
i. FERC Contact: John Mudre at (202)
502–8902 or email at john.mudre@
ferc.gov.
j. Deadline for filing motions to
intervene and protests, comments,
recommendations, preliminary terms
and conditions, and preliminary
prescriptions: 60 days from the issuance
date of this notice; reply comments are
due 105 days from the issuance date of
this notice.
The Commission strongly encourages
electronic filing. Please file motions to
intervene, protests, comments,
recommendations, preliminary terms
and conditions, and preliminary
fishway prescriptions using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–7518–015.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
for filing and is now ready for
environmental analysis.
l. Project Description: The existing
Hogansburg Project consists of: (1) A
reservoir having a surface area of about
18.6 acres and a maximum storage
capacity of approximately 112 acre-feet;
(2) a 247-foot-long, 11.5-foot-high
concrete gravity dam with a spillway
crest elevation of 165.2 feet above mean
sea level; (3) a 34-foot-long, 22-foot-high
stoplog gate structure; (4) a 45-foot by
48-foot integrated intake/powerhouse
structure at the dam’s right abutment;
(5) a single S. Morgan Smith vertical
propeller generating unit having a rated
capacity of 485 kilowatts; (6) a 600-footlong tailrace having varying widths
between 24 feet and 100 feet; and (7)
2.4-kilovolt (kV) generator leads
extending about 25 feet to an adjacent
electrical substation containing a 2.4/
4.8-kV, 600-kilovolt-amperes, step-up
transformer bank. A transmission line
owned and operated by National Grid
Corporation connects directly to the
substation. Power generated at the
project interconnects with the electrical
grid at the substation.
At the time the Commission issued
the original license for the Hogansburg
Project (1985), the Commission’s
regulations did not require minor
projects occupying non-federal lands to
have an established project boundary.
Therefore, the boundary for the project
is being established through this
relicensing process.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
Register online at https://
www.ferc.gov/docs-filing/
E:\FR\FM\26NON1.SGM
26NON1
Federal Register / Vol. 78, No. 228 / Tuesday, November 26, 2013 / Notices
emcdonald on DSK67QTVN1PROD with NOTICES
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Anyone may submit comments, a
protest, or a motion to intervene in
accordance with the requirements of
Rules of Practice and Procedure, 18 CFR
385.210, .211, and .214. In determining
the appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
All filings must (1) bear in all capital
letters the title ‘‘PROTEST’’, ‘‘MOTION
TO INTERVENE’’, ‘‘COMMENTS,’’
‘‘REPLY COMMENTS,’’
‘‘RECOMMENDATIONS,’’
‘‘PRELIMINARY TERMS AND
CONDITIONS,’’ or ‘‘PRELIMINARY
FISHWAY PRESCRIPTIONS;’’ (2) set
forth in the heading the name of the
applicant and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
protesting or intervening; and (4)
otherwise comply with the requirements
of 18 CFR 385.2001 through 385.2005.
All comments, recommendations, terms
and conditions or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requirements
of 18 CFR 4.34(b). Agencies may obtain
copies of the application directly from
the applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. A copy of all other filings
in reference to this application must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
4.34(b) and 385.2010.
o. Procedural Schedule:
The application will be processed
according to the following revised
Hydro Licensing Schedule. Revisions to
the schedule may be made as
appropriate.
Milestone
Target date
Filing of recommendations,
preliminary terms and conditions, and preliminary
fishway prescriptions.
Commission issues Draft EA
Comments on Draft EA .........
Modified Terms and Conditions.
January 2014.
VerDate Mar<15>2010
18:04 Nov 25, 2013
July 2014.
August 2014.
October 2014.
Jkt 232001
Milestone
Target date
Commission Issues Final EA
January 2015.
p. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of this notice.
q. A license applicant must file no
later than 60 days following the date of
issuance of the notice of acceptance and
ready for environmental analysis
provided for in 5.22: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
Dated: November 19, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–28257 Filed 11–25–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #2
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC14–31–000.
Applicants: Prairie Breeze Wind
Energy LLC.
Description: Application for
Authorization under Section 203 of the
Federal Power Act and Request for
Waivers and Expedited Action of Prairie
Breeze Wind Energy LLC.
Filed Date: 11/18/13.
Accession Number: 20131118–5077.
Comments Due: 5 p.m. e.t. 12/9/13.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER14–417–000.
Applicants: Duke Energy Carolinas,
LLC.
Description: NCMPA1 RS 318
Amendment to be effective 12/31/2013.
Filed Date: 11/18/13.
Accession Number: 20131118–5090.
Comments Due: 5 p.m. e.t. 12/9/13.
Docket Numbers: ER14–418–000.
Applicants: Southwest Power Pool,
Inc.
Description: City of Coffeyville
Revised Stated Rate to be effective 7/1/
2013.
Filed Date: 11/18/13.
Accession Number: 20131118–5094.
Comments Due: 5 p.m. e.t. 12/9/13.
Docket Numbers: ER14–419–000.
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
70547
Applicants: Michigan Electric
Transmission Company, LLC.
Description: Filing of CIAC
Agreement with Wolverine Power
Supply Cooperative, Inc. to be effective
1/18/2014.
Filed Date: 11/18/13.
Accession Number: 20131118–5095.
Comments Due: 5 p.m. e.t. 12/9/13.
Docket Numbers: ER14–420–000.
Applicants: Macquarie Energy LLC.
Description: First Rev MBR Tariff to
be effective 3/1/2014.
Filed Date: 11/18/13.
Accession Number: 20131118–5096.
Comments Due: 5 p.m. e.t. 12/9/13.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: November 18, 2013.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2013–28347 Filed 11–25–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC14–24–000.
Applicants: Steele Flats Wind Project,
LLC, Tuscola Wind II, LLC.
Description: Amendment to
November 6, 2013 Application for
Authorization Under Section 203 of the
Federal Power Act of Steele Flats Wind
Project, LLC, et al.
Filed Date: 11/15/13.
Accession Number: 20131115–5235.
Comments Due: 5 p.m. E.T. 11/27/13.
Docket Numbers: EC14–30–000.
Applicants: Shiloh IV Lessee, LLC.
E:\FR\FM\26NON1.SGM
26NON1
Agencies
[Federal Register Volume 78, Number 228 (Tuesday, November 26, 2013)]
[Notices]
[Pages 70546-70547]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-28257]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 7518-015]
Erie Boulevard Hydropower, L.P.; Notice of Application Accepted
for Filing, Soliciting Motions To Intervene and Protests, Ready for
Environmental Analysis, and Soliciting Comments, Recommendations,
Preliminary Terms and Conditions, and Preliminary Fishway Prescriptions
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Subsequent License.
b. Project No.: 7518-015.
c. Date Filed: September 30, 2013.
d. Applicant: Erie Boulevard Hydropower, L.P.
e. Name of Project: Hogansburg Hydroelectric Project.
f. Location: On the St. Regis River in Franklin County, New York.
The project does not occupy any federal lands.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Steven Murphy, Licensing Manager, Erie
Boulevard Hydropower, L.P., 33 West 1st Street South, Fulton, New York,
13069, (315) 598-6130 or email at steven.murphy@brookfieldpower.com.
i. FERC Contact: John Mudre at (202) 502-8902 or email at
john.mudre@ferc.gov.
j. Deadline for filing motions to intervene and protests, comments,
recommendations, preliminary terms and conditions, and preliminary
prescriptions: 60 days from the issuance date of this notice; reply
comments are due 105 days from the issuance date of this notice.
The Commission strongly encourages electronic filing. Please file
motions to intervene, protests, comments, recommendations, preliminary
terms and conditions, and preliminary fishway prescriptions using the
Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000
characters, without prior registration, using the eComment system at
https://www.ferc.gov/docs-filing/ecomment.asp. You must include your
name and contact information at the end of your comments. For
assistance, please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to:
Secretary, Federal Energy Regulatory Commission, 888 First Street NE.,
Washington, DC 20426. The first page of any filing should include
docket number P-7518-015.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
k. This application has been accepted for filing and is now ready
for environmental analysis.
l. Project Description: The existing Hogansburg Project consists
of: (1) A reservoir having a surface area of about 18.6 acres and a
maximum storage capacity of approximately 112 acre-feet; (2) a 247-
foot-long, 11.5-foot-high concrete gravity dam with a spillway crest
elevation of 165.2 feet above mean sea level; (3) a 34-foot-long, 22-
foot-high stoplog gate structure; (4) a 45-foot by 48-foot integrated
intake/powerhouse structure at the dam's right abutment; (5) a single
S. Morgan Smith vertical propeller generating unit having a rated
capacity of 485 kilowatts; (6) a 600-foot-long tailrace having varying
widths between 24 feet and 100 feet; and (7) 2.4-kilovolt (kV)
generator leads extending about 25 feet to an adjacent electrical
substation containing a 2.4/4.8-kV, 600-kilovolt-amperes, step-up
transformer bank. A transmission line owned and operated by National
Grid Corporation connects directly to the substation. Power generated
at the project interconnects with the electrical grid at the
substation.
At the time the Commission issued the original license for the
Hogansburg Project (1985), the Commission's regulations did not require
minor projects occupying non-federal lands to have an established
project boundary. Therefore, the boundary for the project is being
established through this relicensing process.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at the address in item h above.
Register online at https://www.ferc.gov/docs-filing/
[[Page 70547]]
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Anyone may submit comments, a protest, or a motion to intervene
in accordance with the requirements of Rules of Practice and Procedure,
18 CFR 385.210, .211, and .214. In determining the appropriate action
to take, the Commission will consider all protests or other comments
filed, but only those who file a motion to intervene in accordance with
the Commission's Rules may become a party to the proceeding. Any
comments, protests, or motions to intervene must be received on or
before the specified comment date for the particular application.
All filings must (1) bear in all capital letters the title
``PROTEST'', ``MOTION TO INTERVENE'', ``COMMENTS,'' ``REPLY COMMENTS,''
``RECOMMENDATIONS,'' ``PRELIMINARY TERMS AND CONDITIONS,'' or
``PRELIMINARY FISHWAY PRESCRIPTIONS;'' (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person protesting or intervening; and (4) otherwise
comply with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, recommendations, terms and conditions or prescriptions must
set forth their evidentiary basis and otherwise comply with the
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the
application directly from the applicant. A copy of any protest or
motion to intervene must be served upon each representative of the
applicant specified in the particular application. A copy of all other
filings in reference to this application must be accompanied by proof
of service on all persons listed in the service list prepared by the
Commission in this proceeding, in accordance with 18 CFR 4.34(b) and
385.2010.
o. Procedural Schedule:
The application will be processed according to the following
revised Hydro Licensing Schedule. Revisions to the schedule may be made
as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Filing of recommendations, preliminary January 2014.
terms and conditions, and preliminary
fishway prescriptions.
Commission issues Draft EA............... July 2014.
Comments on Draft EA..................... August 2014.
Modified Terms and Conditions............ October 2014.
Commission Issues Final EA............... January 2015.
------------------------------------------------------------------------
p. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of this notice.
q. A license applicant must file no later than 60 days following
the date of issuance of the notice of acceptance and ready for
environmental analysis provided for in 5.22: (1) A copy of the water
quality certification; (2) a copy of the request for certification,
including proof of the date on which the certifying agency received the
request; or (3) evidence of waiver of water quality certification.
Dated: November 19, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-28257 Filed 11-25-13; 8:45 am]
BILLING CODE 6717-01-P