North Side Canal Company; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene, 69847-69848 [2013-27958]
Download as PDF
Federal Register / Vol. 78, No. 225 / Thursday, November 21, 2013 / Notices
Commission, 888 First Street NE.,
Washington, DC 20426. This filing is
accessible on-line at https://www.ferc.gov
using the ‘‘eLibrary’’ link and is
available for review in the
Commission’s Public Reference Room in
Washington, DC. There is an
‘‘eSubscription’’ link on the Web site
that enables subscribers to receive email
notification when a document is added
to a subscribed docket(s). For assistance
with any FERC Online service, please
email FERCOnlineSupport@ferc.gov, or
call (866) 208–3676 (toll free). For TTY,
call (202) 502–8659.
Comment Date: 5:00 p.m. Eastern
Time on December 6, 2013.
Dated: November 15, 2013.
Kimberly D. Bose,
Secretary.
Merlin One, LLC ..................
Goal Line L.P. ......................
RE Columbia 3 LLC .............
RE Columbia, LLC ...............
RE Yakima LLC ....................
Allegany Generating Station
LLC ...................................
EG13–51–000
EG13–52–000
EG13–53–000
EG13–54–000
EG13–55–000
EG13–56–000
Take notice that during the month of
October 2013, the status of the abovecaptioned entities as Exempt Wholesale
Generators became effective by
operation of the Commission’s
regulations. 18 CFR 366.7(a).
Dated: November 15, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–27955 Filed 11–20–13; 8:45 am]
BILLING CODE 6717–01–P
[FR Doc. 2013–27953 Filed 11–20–13; 8:45 am]
DEPARTMENT OF ENERGY
BILLING CODE 6717–01–P
Federal Energy Regulatory
Commission
DEPARTMENT OF ENERGY
[Docket No. CD14–10–000]
Federal Energy Regulatory
Commission
Notice of Effectiveness of Exempt
Wholesale Generator Status
Buffalo Dunes Wind Project,
LLC ...................................
Whitetail Wind Energy, LLC
North Side Canal Company; Notice of
Preliminary Determination of a
Qualifying Conduit Hydropower
Facility and Soliciting Comments and
Motions To Intervene
On November 5, 2013, North Side
Canal Company, filed a notice of intent
EG13–49–000
EG13–50–000
69847
to construct a qualifying conduit
hydropower facility, pursuant to section
30 of the Federal Power Act, as
amended by section 4 of the
Hydropower Regulatory Efficiency Act
of 2013 (HREA). The Head of U Canal
Hydro Project would be located along
North Side Canal Company’s irrigation
system on the U Canal in Jerome
County, Idaho.
Applicant Contact: Alan W. Hansten,
Manager, North Side Canal Company,
Ltd., 921 North Lincoln, Jerome, ID
83338, Phone No. (208) 324–2319.
FERC Contact: Christopher Chaney,
Phone No. (202) 502–6778, email:
christopher.chaney@ferc.gov.
Qualifying Conduit Hydropower
Facility Description: The proposed
project would consist of: (1) A proposed
30-foot-long by 30-foot-wide control
building; (2) eight proposed siphon
turbine/generating units, each with a
capacity of 150 kilowatts, for a total
installed capacity of 1,200 kilowatts;
and (3) appurtenant facilities. The
proposed project would have an
estimated annual generating capacity of
4,200 megawatt-hours.
A qualifying conduit hydropower
facility is one that is determined or
deemed to meet all of the criteria shown
in the table below.
TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY
Statutory provision
Description
Satisfies
(Y/N)
FPA 30(a)(3)(A), as amended by HREA ..
The conduit the facility uses is a tunnel, canal, pipeline, aqueduct, flume, ditch, or
similar manmade water conveyance that is operated for the distribution of water
for agricultural, municipal, or industrial consumption and not primarily for the generation of electricity.
The facility is constructed, operated, or maintained for the generation of electric
power and uses for such generation only the hydroelectric potential of a non-federally owned conduit.
The facility has an installed capacity that does not exceed 5 megawatts ..................
Y
FPA 30(a)(3)(C)(i), as amended by HREA
tkelley on DSK3SPTVN1PROD with NOTICES
FPA 30(a)(3)(C)(ii), as amended
HREA.
FPA 30(a)(3)(C)(iii), as amended
HREA.
by
by
On or before August 9, 2013, the facility is not licensed, or exempted from the licensing requirements of Part I of the FPA.
Preliminary Determination: Based
upon the above criteria, Commission
staff preliminarily determines that the
proposal satisfies the requirements for a
qualifying conduit hydropower facility
not required to be licensed or exempted
from licensing.
Comments and Motions To Intervene:
Deadline for filing comments contesting
whether the facility meets the qualifying
criteria is 45 days from the issuance
date of this notice.
Deadline for filing motions to
intervene is 30 days from the issuance
date of this notice.
Anyone may submit comments or a
motion to intervene in accordance with
VerDate Mar<15>2010
17:17 Nov 20, 2013
Jkt 232001
the requirements of Rules of Practice
and Procedure, 18 CFR 385.210 and
385.214. Any motions to intervene must
be received on or before the specified
deadline date for the particular
proceeding.
Filing and Service of Responsive
Documents: All filings must (1) bear in
all capital letters the ‘‘COMMENTS
CONTESTING QUALIFICATION FOR A
CONDUIT HYDROPOWER FACILITY’’
or ‘‘MOTION TO INTERVENE,’’ as
applicable; (2) state in the heading the
name of the applicant and the project
number of the application to which the
filing responds; (3) state the name,
address, and telephone number of the
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
Y
Y
Y
person filing; and (4) otherwise comply
with the requirements of sections
385.2001 through 385.2005 of the
Commission’s regulations.1 All
comments contesting Commission staff’s
preliminary determination that the
facility meets the qualifying criteria
must set forth their evidentiary basis.
The Commission strongly encourages
electronic filing. Please file motions to
intervene and comments using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
1 18
E:\FR\FM\21NON1.SGM
CFR 385.2001–2005 (2013).
21NON1
69848
Federal Register / Vol. 78, No. 225 / Thursday, November 21, 2013 / Notices
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
A copy of all other filings in reference
to this application must be accompanied
by proof of service on all persons listed
in the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
Locations of Notice of Intent: Copies
of the notice of intent can be obtained
directly from the applicant or such
copies can be viewed and reproduced at
the Commission in its Public Reference
Room, Room 2A, 888 First Street NE.,
Washington, DC 20426. The filing may
also be viewed on the Web at https://
www.ferc.gov/docs-filing/elibrary.asp
using the ‘‘eLibrary’’ link. Enter the
docket number (e.g., CD14–10) in the
docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or email
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659.
Dated: November 14, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–27958 Filed 11–20–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP14–19–000]
tkelley on DSK3SPTVN1PROD with NOTICES
Questar Pipeline Company; Notice of
Request Under Blanket Authorization
Take notice that on November 7,
2013, Questar Pipeline Company
(Questar), 333 South State Street, P.
45360, Salt Lake City, Utah, filed in
Docket No. CP14–19–000, an
application pursuant to sections 157.205
and 157.208(b) of the Commission’s
Regulations under the Natural Gas Act
(NGA) as amended, requesting
authorization to replace a section of its
existing Main Line (ML) 3 in Davis and
Morgan Counties, Utah. The
authorizations are requested under
Questar’s blanket certificate issued in
Docket No. CP82–491–000,1 all as more
1 See Mountain Fuel Resources, Inc., 20 FERC ¶
62,580 (1982).
VerDate Mar<15>2010
17:17 Nov 20, 2013
Jkt 232001
fully set forth in the application which
is on file with the Commission and open
to public inspection.
Questar proposes in its Weber Canyon
Replacement Project (Project) to replace
approximately 3.26 miles of its existing
16-inch ML 3 pipeline on the south side
of Interstate 84 in Weber Canyon
southeast of Ogden Utah. Questar
proposes to isolate the line, remove the
existing pipe, and install new pipe in
the same trench within the existing
right-of-way. The estimated cost of the
project is approximately $29,392,000.
The Project will have no impact on
the certificated parameters of the
Questar pipeline. In addition, there will
be no abandonment or decrease in
service to Questar customers as a result
of the proposed Project. As described in
the application, ground-disturbing
activities necessary to construct the
project will result in minimal
environmental impacts. Questar also
requests waiver of the requirements of
Commissions regulations section
157(203)(d)(2) regarding a weekly
Environmental Inspector’s report.
The filing may also be viewed on the
Web at https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, please contact
FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at (866) 208–3676, or TTY, contact
(202) 502–8659.
Any questions concerning this
application should be directed to L.
Bradley Burton, General Manager,
Federal Regulatory Affairs, and FERC
Compliance Officer, Questar Pipeline
Company, 180 East 100 South, P.O. Box
45360, Salt Lake City, Utah 84145–0360,
phone (801)324–2459, email
brad.burton@questar.com.
Any person or the Commission’s staff
may, within 60 days after issuance of
the instant notice by the Commission,
file pursuant to Rule 214 of the
Commission’s Procedural Rules (18 CFR
385.214) a motion to intervene or notice
of intervention and pursuant to Section
157.205 of the regulations under the
NGA (18 CFR 157.205), a protest to the
request. If no protest is filed within the
time allowed therefore, the proposed
activity shall be deemed to be
authorized effective the day after the
time allowed for filing a protest. If a
protest is filed and not withdrawn
within 30 days after the allowed time
for filing a protest, the instant request
shall be treated as an application for
authorization pursuant to Section 7 of
the NGA.
Persons who wish to comment only
on the environmental review of this
PO 00000
Frm 00035
Fmt 4703
Sfmt 4703
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenter’s will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenter’s will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentary,
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and 7 copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
Comment Date: 5:00 p.m. Eastern
Time on January 14, 2014.
Dated: November 15, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–27954 Filed 11–20–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13102–003—Alabama
Demopolis Lock and Dam Hydroelectric
Project]
Birch Power Company; Notice of
Proposed Revised Restricted Service
List for a Programmatic Agreement
Rule 2010 of the Federal Energy
Regulatory Commission’s (Commission)
Rules of Practice and Procedure, 18 CFR
385.2010, provides that, to eliminate
unnecessary expense or improve
administrative efficiency, the Secretary
may establish a restricted service list for
a particular phase or issue in a
proceeding. The restricted service list
should contain the names of persons on
the service list who, in the judgment of
the decisional authority establishing the
list, are active participants with respect
to the phase or issue in the proceeding
for which the list is established.
The Commission staff is consulting
with the Alabama Historical
E:\FR\FM\21NON1.SGM
21NON1
Agencies
[Federal Register Volume 78, Number 225 (Thursday, November 21, 2013)]
[Notices]
[Pages 69847-69848]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-27958]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CD14-10-000]
North Side Canal Company; Notice of Preliminary Determination of
a Qualifying Conduit Hydropower Facility and Soliciting Comments and
Motions To Intervene
On November 5, 2013, North Side Canal Company, filed a notice of
intent to construct a qualifying conduit hydropower facility, pursuant
to section 30 of the Federal Power Act, as amended by section 4 of the
Hydropower Regulatory Efficiency Act of 2013 (HREA). The Head of U
Canal Hydro Project would be located along North Side Canal Company's
irrigation system on the U Canal in Jerome County, Idaho.
Applicant Contact: Alan W. Hansten, Manager, North Side Canal
Company, Ltd., 921 North Lincoln, Jerome, ID 83338, Phone No. (208)
324-2319.
FERC Contact: Christopher Chaney, Phone No. (202) 502-6778, email:
christopher.chaney@ferc.gov.
Qualifying Conduit Hydropower Facility Description: The proposed
project would consist of: (1) A proposed 30-foot-long by 30-foot-wide
control building; (2) eight proposed siphon turbine/generating units,
each with a capacity of 150 kilowatts, for a total installed capacity
of 1,200 kilowatts; and (3) appurtenant facilities. The proposed
project would have an estimated annual generating capacity of 4,200
megawatt-hours.
A qualifying conduit hydropower facility is one that is determined
or deemed to meet all of the criteria shown in the table below.
Table 1--Criteria for Qualifying Conduit Hydropower Facility
------------------------------------------------------------------------
Satisfies (Y/
Statutory provision Description N)
------------------------------------------------------------------------
FPA 30(a)(3)(A), as amended by The conduit the Y
HREA. facility uses is a
tunnel, canal,
pipeline, aqueduct,
flume, ditch, or
similar manmade water
conveyance that is
operated for the
distribution of water
for agricultural,
municipal, or
industrial
consumption and not
primarily for the
generation of
electricity.
FPA 30(a)(3)(C)(i), as amended The facility is Y
by HREA. constructed,
operated, or
maintained for the
generation of
electric power and
uses for such
generation only the
hydroelectric
potential of a non-
federally owned
conduit.
FPA 30(a)(3)(C)(ii), as amended The facility has an Y
by HREA. installed capacity
that does not exceed
5 megawatts.
FPA 30(a)(3)(C)(iii), as On or before August 9, Y
amended by HREA. 2013, the facility is
not licensed, or
exempted from the
licensing
requirements of Part
I of the FPA.
------------------------------------------------------------------------
Preliminary Determination: Based upon the above criteria,
Commission staff preliminarily determines that the proposal satisfies
the requirements for a qualifying conduit hydropower facility not
required to be licensed or exempted from licensing.
Comments and Motions To Intervene: Deadline for filing comments
contesting whether the facility meets the qualifying criteria is 45
days from the issuance date of this notice.
Deadline for filing motions to intervene is 30 days from the
issuance date of this notice.
Anyone may submit comments or a motion to intervene in accordance
with the requirements of Rules of Practice and Procedure, 18 CFR
385.210 and 385.214. Any motions to intervene must be received on or
before the specified deadline date for the particular proceeding.
Filing and Service of Responsive Documents: All filings must (1)
bear in all capital letters the ``COMMENTS CONTESTING QUALIFICATION FOR
A CONDUIT HYDROPOWER FACILITY'' or ``MOTION TO INTERVENE,'' as
applicable; (2) state in the heading the name of the applicant and the
project number of the application to which the filing responds; (3)
state the name, address, and telephone number of the person filing; and
(4) otherwise comply with the requirements of sections 385.2001 through
385.2005 of the Commission's regulations.\1\ All comments contesting
Commission staff's preliminary determination that the facility meets
the qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------
\1\ 18 CFR 385.2001-2005 (2013).
---------------------------------------------------------------------------
The Commission strongly encourages electronic filing. Please file
motions to intervene and comments using the Commission's eFiling system
at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit
brief comments up to 6,000 characters, without prior
[[Page 69848]]
registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information
at the end of your comments. For assistance, please contact FERC Online
Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper
copy to: Secretary, Federal Energy Regulatory Commission, 888 First
Street NE., Washington, DC 20426. A copy of all other filings in
reference to this application must be accompanied by proof of service
on all persons listed in the service list prepared by the Commission in
this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
Locations of Notice of Intent: Copies of the notice of intent can
be obtained directly from the applicant or such copies can be viewed
and reproduced at the Commission in its Public Reference Room, Room 2A,
888 First Street NE., Washington, DC 20426. The filing may also be
viewed on the Web at https://www.ferc.gov/docs-filing/elibrary.asp using
the ``eLibrary'' link. Enter the docket number (e.g., CD14-10) in the
docket number field to access the document. For assistance, call toll-
free 1-866-208-3676 or email FERCOnlineSupport@ferc.gov. For TTY, call
(202) 502-8659.
Dated: November 14, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-27958 Filed 11-20-13; 8:45 am]