Download as PDF Federal Register / Vol. 78, No. 214 / Tuesday, November 5, 2013 / Rules and Regulations PART 558—NEW ANIMAL DRUGS FOR USE IN ANIMAL FEEDS 9. The authority citation for 21 CFR part 558 continues to read as follows: ■ Authority: 21 U.S.C. 360b, 371. § 558.355 10. In § 558.355, in the introductory text in paragraph (f)(3)(iii), remove ‘‘Monensin, 25 to 400 grams’’ and in its place add ‘‘Monensin, 15 to 400 grams’’. ■ Dated: October 31, 2013. Bernadette Dunham, Director, Center for Veterinary Medicine. [FR Doc. 2013–26473 Filed 11–4–13; 8:45 am] BILLING CODE 4160–01–P DEPARTMENT OF HOMELAND SECURITY Coast Guard 33 CFR Part 117 [USCG–2013–0901] Drawbridge Operation Regulations; Reynolds Channel, Lawrence, NY Coast Guard, DHS. Notice of temporary deviation from regulations. AGENCY: ACTION: The Commander, First Coast Guard District, has issued a temporary deviation from the regulations governing the operation of the Atlantic Beach Bridge, mile 0.4, across Reynolds Channel, at Lawrence, New York. This temporary deviation authorizes the Atlantic Beach Bridge to operate under an alternate schedule for 29 days, to complete bridge rehabilitation. DATES: This deviation is effective from December 2, 2013 through December 31, 2013. ADDRESSES: Documents mentioned in this preamble as being available in the docket are part of docket USCG–2013– 0901 and are available online at www.regulations.gov, inserting USCG– 2013–0901 in the ‘‘Keyword’’ and then clicking ‘‘Search’’. They are also available for inspection or copying at the Docket Management Facility (M–30), U.S. Department of Transportation, West Building Ground Floor, Room W12–140, 1200 New Jersey Avenue SE., Washington, DC 20590, between 9 a.m. and 5 p.m., Monday through Friday, except Federal holidays. FOR FURTHER INFORMATION CONTACT: If you have questions on this rule, call or email Ms. Judy Leung-Yee, Project Officer, First Coast Guard District, telephone (212) 668–7165, email wreier-aviles on DSK5TPTVN1PROD with RULES VerDate Mar<15>2010 14:54 Nov 04, 2013 Jkt 232001 The Atlantic Beach Bridge, across Reynolds Channel, mile 0.4, at Lawrence, New York, has a vertical clearance in the closed position of 25 feet at mean high water and 30 feet at mean low water. The existing drawbridge operation regulations are listed at 33 CFR 117.799(e). A temporary deviation for the drawbridge operations (78 FR 56610) is currently in effect. During ongoing rehabilitation of the bridge the contractor discovered more severe damage than originally anticipated, resulting from Super Storm Sandy in 2012. The owner of the bridge, Nassau County Bridge Authority, is requesting additional bridge closures in order to complete the bridge rehabilitation. The waterway has commercial and seasonal recreational vessels of various sizes. Under this temporary deviation the draw of the Atlantic Beach Bridge at mile 0.4, across Reynolds Channel shall operate as follows: From December 2, 2013 through December 31, 2013, the bridge shall operate a single span on signal at 6 a.m., 12 p.m., 4 p.m., and 8 p.m. and at any time between 8 p.m. and 6 a.m. The draw shall open both spans at all times for commercial vessel traffic after at least a 48 hour advance notice is given by calling the number posted at the bridge. The draw may remain in the closed position between 12 a.m. and 5 a.m. on December 3, and December 4, 2013. The Coast Guard contacted all known commercial waterway users regarding this deviation and no objections were received. In accordance with 33 CFR 117.35(e), the bridge must return to its regular operating schedule immediately at the end of the designated time period. This deviation from the operating regulations is authorized under 33 CFR 117.35. SUPPLEMENTARY INFORMATION: [Amended] SUMMARY: judy.k.leung-yee@uscg.mil. If you have questions on viewing the docket, call Barbara Hairston, Program Manager, Docket Operations, telephone 202–366– 9826. Dated: October 21, 2013. Gary Kassof, Bridge Program Manager, First Coast Guard District. [FR Doc. 2013–26517 Filed 11–4–13; 8:45 am] BILLING CODE 9110–04–P PO 00000 Frm 00017 Fmt 4700 Sfmt 4700 66265 DEPARTMENT OF HOMELAND SECURITY Coast Guard 33 CFR Part 117 [Docket No. USCG–2013–0910] Drawbridge Operation Regulation; Elizabeth River, Eastern Branch, Norfolk, VA Coast Guard, DHS. Notice of deviation from drawbridge regulation. AGENCY: ACTION: The Coast Guard has issued a temporary deviation from the operating schedule that governs the draw of the Norfolk Southern #5 Railroad Bridge, across the Elizabeth River Eastern Branch, mile 1.1, at Norfolk, VA. This deviation is necessary to facilitate replacing the broken tread plates and milling the top of the plates and webs to create a flat surface on the Norfolk Southern #5 Railroad drawbridge. The final phase of repairs is shimming the tread plates into place. This temporary deviation allows the drawbridge to remain in the closed to navigation position. DATES: This deviation is effective from November 5, 2013 through December 8, 2013, and has been enforced with actual notice since November 4, 2013. ADDRESSES: The docket for this deviation, [USCG–2013–0910] is available at https://www.regulations.gov. Type the docket number in the ‘‘SEARCH’’ box and click ‘‘SEARCH.’’ Click on Open Docket Folder on the line associated with this deviation. You may also visit the Docket Management Facility in Room W12–140 on the ground floor of the Department of Transportation West Building, 1200 New Jersey Avenue SE., Washington, DC 20590, between 9 a.m. and 5 p.m., Monday through Friday, except Federal holidays. FOR FURTHER INFORMATION CONTACT: If you have questions on this temporary deviation, call or email Mrs. Kashanda Booker, Bridge Administration Branch Fifth District, Coast Guard; telephone (757) 398–6227, email Kashanda.l.booker@uscg.mil. If you have questions on reviewing the docket, call Barbara Hairston, Program Manager, Docket Operations, 202–366–9826. SUPPLEMENTARY INFORMATION: The Norfolk Southern Corporation, who owns and operates this drawbridge, has requested a temporary deviation from the current operating regulation set out in 33 CFR 117.5 to facilitate thermite welding on the rails. SUMMARY: E:\FR\FM\05NOR1.SGM 05NOR1 66266 Federal Register / Vol. 78, No. 214 / Tuesday, November 5, 2013 / Rules and Regulations Under the regular operating schedule, the Norfolk Southern #5 Railroad Bridge, mile 1.1, in Norfolk, VA, the draw must open promptly and fully for the passage of vessels when a request or signal to open is given. The draw normally is open and only closes for train crossings or periodic maintenance. The Norfolk Southern #5 railroad Bridge, at mile 1.1, across the Elizabeth River (Eastern Branch) in Norfolk, VA, has a vertical clearance in the closed position to vessels of 6 feet above mean high water. Under this temporary deviation, the drawbridge will be maintained in the closed to navigation position each day, from 7 a.m. to 5 p.m., on November 4, 2013 until December 8, 2013 the bridge will operate under normal operating schedule at all other times. The bridge normally is maintained in the open-tonavigation position with several vessels transiting a week and only closes when trains transit. Emergency openings cannot be provided. There are no alternate routes for vessels transiting this section of the Elizabeth River Eastern Branch but vessels may pass before 7 a.m. and after 5 p.m. The Elizabeth River Eastern Branch is used by a variety of vessels including military, tug, commercial, and recreational vessels. The Coast Guard has carefully coordinated the restrictions with these waterway users. The Coast Guard will also inform additional waterway users through our Local and Broadcast Notices to Mariners of the closure periods for the bridge so that vessels can arrange their transits to minimize any impacts caused by the temporary deviation. Mariners able to pass under the bridge in the closed position may do so at any time and are advised to proceed with caution. In accordance with 33 CFR 117.35(e), the drawbridge must return to its regular operating schedule immediately at the end of the designated time period. This deviation from the operating regulations is authorized under 33 CFR 117.35. wreier-aviles on DSK5TPTVN1PROD with RULES Dated: October 21, 2013. Waverly W. Gregory, Jr., Bridge Program Manager, Fifth Coast Guard District. [FR Doc. 2013–26533 Filed 11–4–13; 8:45 am] BILLING CODE 9110–04–P VerDate Mar<15>2010 14:54 Nov 04, 2013 Jkt 232001 DEPARTMENT OF HOMELAND SECURITY Coast Guard 33 CFR Part 117 [Docket No. USCG–2013–0909] Drawbridge Operation Regulation; Atlantic Intracoastal Waterway (AIWW), Chesapeake, VA Coast Guard, DHS. Notice of deviation from drawbridge regulations. AGENCY: ACTION: The Coast Guard has issued a temporary deviation from the operating schedule that governs the I64 Bridge across the Atlantic Intracoastal Waterway, South Branch of the Elizabeth River, mile 7.1, at Chesapeake, VA. This deviation is necessary to facilitate maintenance work on the rotary span limit switches. This temporary deviation allows the drawbridge to remain in the closed to navigation position. DATES: This deviation is effective from 7 a.m. on November 15, 2013 to 12 p.m. November 17, 2013. ADDRESSES: The docket for this deviation, [USCG–2013–0909] is available at https://www.regulations.gov. Type the docket number in the ‘‘SEARCH’’ box and click ‘‘SEARCH.’’ Click on Open Docket Folder on the line associated with this deviation. You may also visit the Docket Management Facility in Room W12–140 on the ground floor of the Department of Transportation West Building, 1200 New Jersey Avenue SE., Washington, DC 20590, between 9 a.m. and 5 p.m., Monday through Friday, except Federal holidays. FOR FURTHER INFORMATION CONTACT: If you have questions on this temporary deviation, call or email Mrs. Kashanda Booker, Bridge Administration Branch Fifth District, Coast Guard; telephone (757) 398–6227, email Kashanda.l.booker@uscg.mil. If you have questions on reviewing the docket, call Barbara Hairston, Program Manager, Docket Operations, (202) 366–9826. SUPPLEMENTARY INFORMATION: The Virginia Department of Transportation, who owns and operates this drawbridge, has requested a temporary deviation from the current operating regulation set out in 33 CFR 117.997(e), to facilitate maintenance of the moveable spans on the structure. The current operating schedule for the drawbridge is set out in 33 CFR 117.997(e) which requires the drawbridge open on signal if at least 24 SUMMARY: PO 00000 Frm 00018 Fmt 4700 Sfmt 4700 hours notice is given. The I64 Bridge has a vertical clearance in the closed position of 65 feet above mean high water. Under this temporary deviation, the drawbridge will be closed to navigation from 7 a.m., on Friday, November 15, 2013 to 12 p.m., on Sunday, November 17, 2013. Vessels able to pass under the drawbridge in the closed position may do so at anytime and are advised to proceed with caution. The drawbridge will not be able to open for emergencies. The Coast Guard will also inform additional waterway users through our Local and Broadcast Notices to Mariners of the closure periods for the drawbridge so that vessels can arrange their transits to minimize any impacts caused by the temporary deviation. In accordance with 33 CFR 117.35(e), the drawbridge must return to its regular operating schedule immediately at the end of the effective period of this temporary deviation. This deviation from the operating regulations is authorized under 33 CFR 117.35. Dated: October 21, 2013. Waverly W. Gregory, Jr., Bridge Program Manager, Fifth Coast Guard District. [FR Doc. 2013–26534 Filed 11–4–13; 8:45 am] BILLING CODE 9110–04–P DEPARTMENT OF HOMELAND SECURITY Coast Guard 33 CFR Part 117 [USCG–2013–0880] Drawbridge Operation Regulations; Hackensack River, Jersey City, NJ Coast Guard, DHS. Notice of temporary deviation from regulations. AGENCY: ACTION: The Commander, First Coast Guard District, has issued a temporary deviation from the regulations governing the operation of the Path (Railroad) Bridge across the Hackensack River, mile 3.0, at Jersey City, New Jersey. Under this temporary deviation, the bridge may remain in the closed position for 26 consecutive weekends to facilitate bridge repairs. DATES: This deviation is effective on weekends from 12:01 a.m. Saturday November 23, 2013 through 12:01 Monday May 19, 2014. ADDRESSES: The docket for this deviation, [USCG–2013–0880] is available at https://www.regulations.gov. SUMMARY: E:\FR\FM\05NOR1.SGM 05NOR1

Agencies

[Federal Register Volume 78, Number 214 (Tuesday, November 5, 2013)]
[Rules and Regulations]
[Pages 66265-66266]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-26533]


-----------------------------------------------------------------------

DEPARTMENT OF HOMELAND SECURITY

Coast Guard

33 CFR Part 117

[Docket No. USCG-2013-0910]


Drawbridge Operation Regulation; Elizabeth River, Eastern Branch, 
Norfolk, VA

AGENCY: Coast Guard, DHS.

ACTION: Notice of deviation from drawbridge regulation.

-----------------------------------------------------------------------

SUMMARY: The Coast Guard has issued a temporary deviation from the 
operating schedule that governs the draw of the Norfolk Southern 
5 Railroad Bridge, across the Elizabeth River Eastern Branch, 
mile 1.1, at Norfolk, VA. This deviation is necessary to facilitate 
replacing the broken tread plates and milling the top of the plates and 
webs to create a flat surface on the Norfolk Southern 5 
Railroad drawbridge. The final phase of repairs is shimming the tread 
plates into place. This temporary deviation allows the drawbridge to 
remain in the closed to navigation position.

DATES: This deviation is effective from November 5, 2013 through 
December 8, 2013, and has been enforced with actual notice since 
November 4, 2013.

ADDRESSES: The docket for this deviation, [USCG-2013-0910] is available 
at https://www.regulations.gov. Type the docket number in the ``SEARCH'' 
box and click ``SEARCH.'' Click on Open Docket Folder on the line 
associated with this deviation. You may also visit the Docket 
Management Facility in Room W12-140 on the ground floor of the 
Department of Transportation West Building, 1200 New Jersey Avenue SE., 
Washington, DC 20590, between 9 a.m. and 5 p.m., Monday through Friday, 
except Federal holidays.

FOR FURTHER INFORMATION CONTACT: If you have questions on this 
temporary deviation, call or email Mrs. Kashanda Booker, Bridge 
Administration Branch Fifth District, Coast Guard; telephone (757) 398-
6227, email Kashanda.l.booker@uscg.mil. If you have questions on 
reviewing the docket, call Barbara Hairston, Program Manager, Docket 
Operations, 202-366-9826.

SUPPLEMENTARY INFORMATION: The Norfolk Southern Corporation, who owns 
and operates this drawbridge, has requested a temporary deviation from 
the current operating regulation set out in 33 CFR 117.5 to facilitate 
thermite welding on the rails.

[[Page 66266]]

    Under the regular operating schedule, the Norfolk Southern 
5 Railroad Bridge, mile 1.1, in Norfolk, VA, the draw must 
open promptly and fully for the passage of vessels when a request or 
signal to open is given. The draw normally is open and only closes for 
train crossings or periodic maintenance. The Norfolk Southern 
5 railroad Bridge, at mile 1.1, across the Elizabeth River 
(Eastern Branch) in Norfolk, VA, has a vertical clearance in the closed 
position to vessels of 6 feet above mean high water.
    Under this temporary deviation, the drawbridge will be maintained 
in the closed to navigation position each day, from 7 a.m. to 5 p.m., 
on November 4, 2013 until December 8, 2013 the bridge will operate 
under normal operating schedule at all other times. The bridge normally 
is maintained in the open-to-navigation position with several vessels 
transiting a week and only closes when trains transit. Emergency 
openings cannot be provided. There are no alternate routes for vessels 
transiting this section of the Elizabeth River Eastern Branch but 
vessels may pass before 7 a.m. and after 5 p.m.
    The Elizabeth River Eastern Branch is used by a variety of vessels 
including military, tug, commercial, and recreational vessels. The 
Coast Guard has carefully coordinated the restrictions with these 
waterway users. The Coast Guard will also inform additional waterway 
users through our Local and Broadcast Notices to Mariners of the 
closure periods for the bridge so that vessels can arrange their 
transits to minimize any impacts caused by the temporary deviation. 
Mariners able to pass under the bridge in the closed position may do so 
at any time and are advised to proceed with caution.
    In accordance with 33 CFR 117.35(e), the drawbridge must return to 
its regular operating schedule immediately at the end of the designated 
time period. This deviation from the operating regulations is 
authorized under 33 CFR 117.35.

    Dated: October 21, 2013.
Waverly W. Gregory, Jr.,
Bridge Program Manager, Fifth Coast Guard District.
[FR Doc. 2013-26533 Filed 11-4-13; 8:45 am]
BILLING CODE 9110-04-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.