Inspections, Tests, Analyses, and Acceptance Criteria; Vogtle Electric Generating Plant, Unit 3, 65007 [2013-25815]
Download as PDF
Federal Register / Vol. 78, No. 210 / Wednesday, October 30, 2013 / Notices
determination made by the NCD
Chairperson.
CONTACT PERSON FOR MORE INFORMATION:
Rebecca Cokley, NCD Executive
Director, 1331 F Street NW., Suite 850,
Washington, DC 20004; 202–272–2004
(V), 202–272–2074 (TTY).
Dated: October 28, 2013.
Rebecca Cokley,
Executive Director.
[FR Doc. 2013–25871 Filed 10–28–13; 11:15 am]
BILLING CODE 6820–MA–P
NUCLEAR REGULATORY
COMMISSION
SUPPLEMENTARY INFORMATION:
[Docket No. 052–00026; NRC–2008–0252]
Licensee Notification of Completion of
ITAAC
Inspections, Tests, Analyses, and
Acceptance Criteria; Vogtle Electric
Generating Plant, Unit 3
Nuclear Regulatory
Commission.
ACTION: Determination of inspections,
tests, analyses, and acceptance criteria
completion.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) staff has determined
that the inspections, tests, and analyses
have been successfully completed, and
that the specified acceptance criteria are
met for Inspections, Tests, Analyses,
and Acceptance Criteria (ITAAC),
2.1.03.11 for the Vogtle Electric
Generating Plant, Unit 3.
ADDRESSES: Please refer to Docket ID
NRC–2008–0252 when contacting the
NRC about the availability of
information regarding this document.
You may access publicly-available
information related to this action by the
following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2008–0252. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–287–3442;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may access publicly
available documents online in the NRC
Library at https://www.nrc.gov/readingrm/adams.html. To begin the search,
select ‘‘ADAMS Public Documents’’ and
then select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
emcdonald on DSK67QTVN1PROD with NOTICES
SUMMARY:
VerDate Mar<15>2010
16:58 Oct 29, 2013
ADAMS accession number for each
document referenced in this document
(if that document is available in
ADAMS) is provided the first time that
a document is referenced.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT:
David H. Jaffe, Office of New Reactors,
U.S. Nuclear Regulatory Commission,
Washington, DC 20555–0001; telephone:
301–415–1439, email: david.jaffe@
nrc.gov.
Jkt 232001
On August 1, 2013, Southern Nuclear
Operating Company, Inc. (the licensee)
submitted an ITAAC closure
notification (ICN) under § 52.99(c)(1) of
Title 10 of the Code of Federal
Regulations (10 CFR), informing the
NRC that the licensee has successfully
performed the required inspections,
tests, and analyses for ITAAC 2.1.03.11,
and that the specified acceptance
criteria are met for Vogtle Electric
Generating Plant, Unit 3 (ADAMS
Accession No. ML13213A155). This
ITAAC was approved as part of the
issuance of the combined license,
NPF–91, for this facility.
NRC Staff Determination of Completion
of ITAAC
The NRC staff has determined that the
inspections, tests, and analyses have
been successfully completed, and that
the specified acceptance criteria are met
for Vogtle Electric Generating Plant,
Unit 3, ITAAC 2.1.03.11. This notice
fulfills the staff’s obligations under 10
CFR 52.99(e)(1) to publish a notice in
the Federal Register of the NRC staff’s
determination of the successful
completion of inspections, tests and
analyses.
The documentation of the NRC staff’s
determination is in the ITAAC Closure
Verification Evaluation Form (VEF),
dated September 24, 2013 (ADAMS
Accession No. ML13274A279). The VEF
is a form that represents the NRC staff’s
structured process for reviewing ICNs.
The ICN presents a narrative description
of how the ITAAC was completed, and
the NRC’s ICN review process involves
a determination on whether, among
other things, (1) the ICN provides
sufficient information, including a
summary of the methodology used to
perform the ITAAC, to demonstrate that
the inspections, tests, and analyses have
been successfully completed; (2) the
PO 00000
Frm 00101
Fmt 4703
Sfmt 4703
65007
ICN provides sufficient information to
demonstrate that the acceptance criteria
are met; and (3) any inspections for the
ITAAC have been completed and any
ITAAC findings associated with the
ITAAC have been closed.
The NRC staff’s determination of the
successful completion of this ITAAC is
based on information available at this
time and is subject to the licensee’s
ability to maintain the condition that
the acceptance criteria are met. If new
information disputes the NRC staff’s
determination, this ITAAC will be
reopened as necessary. The NRC staff’s
determination will be used to support a
subsequent finding, pursuant to 10 CFR
52.103(g), at the end of construction that
all acceptance criteria in the combined
license are met. The ITAAC closure
process is not finalized for this ITAAC
until the NRC makes an affirmative
finding under 10 CFR 52.103(g). Any
future updates to the status of this
ITAAC will be reflected on the NRC’s
Web site at https://www.nrc.gov/reactors/
new-reactors/oversight/itaac.html.
Dated at Rockville, Maryland, this 23rd day
of October 2013.
For the Nuclear Regulatory Commission.
David H. Jaffe,
Senior Project Manager, Licensing Branch 4,
Division of New Reactor Licensing, Office of
New Reactors.
[FR Doc. 2013–25815 Filed 10–29–13; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
Advisory Committee On Reactor
Safeguards (ACRS) Meeting of the
ACRS Subcommittee on Planning and
Procedures; Notice of Meeting
The ACRS Subcommittee on Planning
and Procedures will hold a meeting on
November 6, 2013, Room T–2B3, 11545
Rockville Pike, Rockville, Maryland.
The meeting will be open to public
attendance with the exception of a
portion that may be closed pursuant to
5 U.S.C. 552b (c)(2) and (6) to discuss
organizational and personnel matters
that relate solely to the internal
personnel rules and practices of the
ACRS, and information the release of
which would constitute a clearly
unwarranted invasion of personal
privacy.
The agenda for the subject meeting
shall be as follows:
Wednesday, November 6, 2013—12:00
p.m. Until 1:00 p.m.
The Subcommittee will discuss
proposed ACRS activities and related
matters. The Subcommittee will gather
E:\FR\FM\30OCN1.SGM
30OCN1
Agencies
[Federal Register Volume 78, Number 210 (Wednesday, October 30, 2013)]
[Notices]
[Page 65007]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-25815]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 052-00026; NRC-2008-0252]
Inspections, Tests, Analyses, and Acceptance Criteria; Vogtle
Electric Generating Plant, Unit 3
AGENCY: Nuclear Regulatory Commission.
ACTION: Determination of inspections, tests, analyses, and acceptance
criteria completion.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) staff has
determined that the inspections, tests, and analyses have been
successfully completed, and that the specified acceptance criteria are
met for Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC),
2.1.03.11 for the Vogtle Electric Generating Plant, Unit 3.
ADDRESSES: Please refer to Docket ID NRC-2008-0252 when contacting the
NRC about the availability of information regarding this document. You
may access publicly-available information related to this action by the
following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2008-0252. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-287-
3442; email: Carol.Gallagher@nrc.gov. For technical questions, contact
the individual listed in the FOR FURTHER INFORMATION CONTACT section of
this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may access publicly available documents online in the NRC
Library at https://www.nrc.gov/reading-rm/adams.html. To begin the
search, select ``ADAMS Public Documents'' and then select ``Begin Web-
based ADAMS Search.'' For problems with ADAMS, please contact the NRC's
Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-
4737, or by email to pdr.resource@nrc.gov. The ADAMS accession number
for each document referenced in this document (if that document is
available in ADAMS) is provided the first time that a document is
referenced.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: David H. Jaffe, Office of New
Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001; telephone: 301-415-1439, email: david.jaffe@nrc.gov.
SUPPLEMENTARY INFORMATION:
Licensee Notification of Completion of ITAAC
On August 1, 2013, Southern Nuclear Operating Company, Inc. (the
licensee) submitted an ITAAC closure notification (ICN) under Sec.
52.99(c)(1) of Title 10 of the Code of Federal Regulations (10 CFR),
informing the NRC that the licensee has successfully performed the
required inspections, tests, and analyses for ITAAC 2.1.03.11, and that
the specified acceptance criteria are met for Vogtle Electric
Generating Plant, Unit 3 (ADAMS Accession No. ML13213A155). This ITAAC
was approved as part of the issuance of the combined license, NPF-91,
for this facility.
NRC Staff Determination of Completion of ITAAC
The NRC staff has determined that the inspections, tests, and
analyses have been successfully completed, and that the specified
acceptance criteria are met for Vogtle Electric Generating Plant, Unit
3, ITAAC 2.1.03.11. This notice fulfills the staff's obligations under
10 CFR 52.99(e)(1) to publish a notice in the Federal Register of the
NRC staff's determination of the successful completion of inspections,
tests and analyses.
The documentation of the NRC staff's determination is in the ITAAC
Closure Verification Evaluation Form (VEF), dated September 24, 2013
(ADAMS Accession No. ML13274A279). The VEF is a form that represents
the NRC staff's structured process for reviewing ICNs. The ICN presents
a narrative description of how the ITAAC was completed, and the NRC's
ICN review process involves a determination on whether, among other
things, (1) the ICN provides sufficient information, including a
summary of the methodology used to perform the ITAAC, to demonstrate
that the inspections, tests, and analyses have been successfully
completed; (2) the ICN provides sufficient information to demonstrate
that the acceptance criteria are met; and (3) any inspections for the
ITAAC have been completed and any ITAAC findings associated with the
ITAAC have been closed.
The NRC staff's determination of the successful completion of this
ITAAC is based on information available at this time and is subject to
the licensee's ability to maintain the condition that the acceptance
criteria are met. If new information disputes the NRC staff's
determination, this ITAAC will be reopened as necessary. The NRC
staff's determination will be used to support a subsequent finding,
pursuant to 10 CFR 52.103(g), at the end of construction that all
acceptance criteria in the combined license are met. The ITAAC closure
process is not finalized for this ITAAC until the NRC makes an
affirmative finding under 10 CFR 52.103(g). Any future updates to the
status of this ITAAC will be reflected on the NRC's Web site at https://www.nrc.gov/reactors/new-reactors/oversight/itaac.html.
Dated at Rockville, Maryland, this 23rd day of October 2013.
For the Nuclear Regulatory Commission.
David H. Jaffe,
Senior Project Manager, Licensing Branch 4, Division of New Reactor
Licensing, Office of New Reactors.
[FR Doc. 2013-25815 Filed 10-29-13; 8:45 am]
BILLING CODE 7590-01-P