Pepperell Hydro Company, LLC; Notice of Application Tendered for Filing With the Commission and Soliciting Additional Study Requests, 64933-64934 [2013-25700]
Download as PDF
Federal Register / Vol. 78, No. 210 / Wednesday, October 30, 2013 / Notices
Minutes: The minutes of the meeting
will be available within 45 days for
public review and copying at https://
biomassboard.gov/committee/
meetings.html.
Issued at Washington, DC, on October 23,
2013.
LaTanya R. Butler,
Deputy Committee Management Officer.
[FR Doc. 2013–25813 Filed 10–29–13; 8:45 am]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP14–4–000]
emcdonald on DSK67QTVN1PROD with NOTICES
Texas Eastern Transmission, LP;
Notice of Application
Take notice that on October 10, 2013,
Texas Eastern Transmission, (Texas
Eastern), having its principal place of
business at 5400 Westheimer Court,
Houston, Texas, 77056, filed an
application in Docket No. CP14–4–000
pursuant to Section 7(b) and Section
7(c) of the Natural Gas Act (NGA), and
Part 157 of the Commission’s
regulations, for a certificate of public
convenience and necessity to construct
its Emerald Longwall Mine Panel D1
Project. Texas Eastern states in its
application that, due to anticipated
longwall mining activities of Emerald
Coal Resources, LP (Emerald) in Greene
County, Pennsylvania in Panel D1 of
Emerald’s mine, ground subsidence may
occur. In order to maintain the
operation of their existing pipeline
facilities throughout the duration of the
subsidence anticipated from the mining
activities, Texas Eastern proposes to
excavate, elevate, replace, and/or
abandon by removal certain sections of
five different pipelines and appurtenant
facilities located in Greene County,
Pennsylvania, all as more fully set forth
in the application, which is on file with
the Commission and open to public
inspection. This filing may also be
viewed on the web at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TYY, (202)
502–8659.
Any questions regarding this
application should be directed to Lisa
A. Connolly, General Manager, Rates
and Certificates, Texas Eastern
Transmission, LP, P.O. Box 1642,
Houston, Texas, 77251, or by calling
VerDate Mar<15>2010
16:58 Oct 29, 2013
Jkt 232001
(713) 627–4102 (telephone) or (713)
627–5947 (fax) laconnolly@
spectraenergy.com.
Pursuant to section 157.9 of the
Commission’s regulations, 18 CFR
157.9, within 90 days of this Notice, the
Commission’s staff will either complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission’s staff issuance of the EA
for this proposal. The filing of the EA
in the Commission’s public record for
this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to reach a final
decision on a request for federal
authorization within 90 days of the date
of issuance of the Commission staff’s
EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
7 copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
64933
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenters will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenters will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commenters
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and 5 copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426. See, 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site under the ‘‘e-Filing’’ link.
Comment Date: November 13, 2013.
Dated: October 23, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–25699 Filed 10–29–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12721–006]
Pepperell Hydro Company, LLC; Notice
of Application Tendered for Filing With
the Commission and Soliciting
Additional Study Requests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Original Major
License.
b. Project No.: P–12721–006.
c. Date filed: October 9, 2013.
d. Applicant: Pepperell Hydro
Company, LLC.
E:\FR\FM\30OCN1.SGM
30OCN1
emcdonald on DSK67QTVN1PROD with NOTICES
64934
Federal Register / Vol. 78, No. 210 / Wednesday, October 30, 2013 / Notices
e. Name of Project: Pepperell
Hydroelectric Project.
f. Location: On the Nashua River, in
the town of Pepperell, Middlesex
County, Massachusetts. The project
would not occupy lands of the United
States.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)—825(r).
h. Applicant Contact: Dr. Peter B.
Clark, 823 Bay Road, P.O. Box 149,
Hamilton, MA 01936; (978) 468–3999;
or pclark@swiftrivercompany.com.
i. FERC Contact: Brandon Cherry at
(202) 502–8328 or brandon.cherry@
ferc.gov.
j. Cooperating agencies: Federal, state,
local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item l below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See 94
FERC ¶ 61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian Tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian Tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for filing additional study
requests and requests for cooperating
agency status: December 9, 2013.
The Commission strongly encourages
electronic filing. Please file additional
study requests and requests for
cooperating agency status using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov, (866) 208–3676 (toll free), or
(202) 502–8659 (TTY). In lieu of
electronic filing, please send a paper
copy to: Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC. 20426. The first
page of any filing should include docket
number P–12721–006.
m. The application is not ready for
environmental analysis at this time.
n. The existing, unlicensed Pepperell
Hydroelectric Project consists of: (1) The
23.5-foot-high, 251-foot-long concrete
gravity ogee Pepperell Paper dam that
VerDate Mar<15>2010
16:58 Oct 29, 2013
Jkt 232001
includes a 244-foot-long spillway with a
crest elevation of 197.0 feet North
American Vertical Datum 1988
(NAVD88) and 3-foot-high wooden
flashboards; (2) a 3.5-mile-long, 294-acre
impoundment with a normal water
surface elevation of 200.0 feet NAVD88;
(3) a 25-foot-long, 26-foot-wide intake
structure with two 7.75-foot-wide, 14.0foot-high leaf intake gates; (4) a 12-footdiameter, 565.5-foot-long penstock; (5) a
14.0 to 58.0-foot-wide, 25.5-foot-long
forebay structure that includes a 1.5foot-diameter gate with low level drain
pipe and a 4.25-foot-wide, 3.5-foot-high
trash sluice gate; (6) six 8-foot-wide, 10foot-high turbine bay headgates with
17.33-foot-high trashracks with 1.75inch clear bar spacing; (7) a 62-footwide, 41-foot-long powerhouse
containing three 640-kilowatt (kW)
turbine-generating units for a total
installed capacity 1,920 kW; (8) three
11.5-foot-long turbine draft tubes; (9)
three 265-foot-long, 600-volt
transmission lines; and (10) appurtenant
facilities.
The existing project also includes a
downstream fish passage facility that
consists of: (1) A 3-foot-wide, 23-footlong concrete intake with a 4-foot-wide,
8-foot-high entrance gate; (2) a
collection channel with a 2-foot-high, 2foot-wide overflow stoplog notch; and
(3) a 5-foot-deep plunge pool.
The existing project bypasses
approximately 700 feet of the Nashua
River.
Pepperell Hydro Company, LLC
proposes to increase the capacities of
two turbine-generating units to 764 kW
and 735 kW and install a new 67.5-kW
low flow turbine-generating unit at the
dam for a total installed capacity of
2,206.5 kW. Pepperell Hydro Company,
LLC proposes to operate the project in
a run-of-river mode and release: (1) 46
cubic feet per second (cfs) or inflow to
the bypassed reach from April 1 through
November 30, which would include 17
cfs or inflow through the existing
downstream fish passage facility from
June 15 through October 30; and (2) 15
cfs or inflow to the bypassed reach from
December 1 through March 31. The
project would have an estimated average
annual generation of 7,997 megawatthours.
o. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. With this notice, we are initiating
consultation with the Massachusetts
Historical Commission, as required by
section 106 of the National Historic
Preservation Act and the regulations of
the Advisory Council on Historic
Preservation, 36 CFR 800.4.
q. Procedural schedule: The
application will be processed according
to the following preliminary Hydro
Licensing Schedule. Revisions to the
schedule will be made as appropriate.
Issue Deficiency Letter—December 2013
Issue Notice of Acceptance—February
2014
Issue Scoping Document—March 2014
Issue Notice of Ready for Environmental
Analysis—May 2014
Issue Notice of the Availability of the
EA—October 2014
Dated: October 23, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–25700 Filed 10–29–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER14–120–000]
BTG Pactual Commodities (US) LLC;
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization
This is a supplemental notice in the
above-referenced proceeding, of BTG
Pactual Commodities (US) LLC’s
application for market-based rate
authority, with an accompanying rate
schedule, noting that such application
includes a request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
E:\FR\FM\30OCN1.SGM
30OCN1
Agencies
[Federal Register Volume 78, Number 210 (Wednesday, October 30, 2013)]
[Notices]
[Pages 64933-64934]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-25700]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12721-006]
Pepperell Hydro Company, LLC; Notice of Application Tendered for
Filing With the Commission and Soliciting Additional Study Requests
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Original Major License.
b. Project No.: P-12721-006.
c. Date filed: October 9, 2013.
d. Applicant: Pepperell Hydro Company, LLC.
[[Page 64934]]
e. Name of Project: Pepperell Hydroelectric Project.
f. Location: On the Nashua River, in the town of Pepperell,
Middlesex County, Massachusetts. The project would not occupy lands of
the United States.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)--825(r).
h. Applicant Contact: Dr. Peter B. Clark, 823 Bay Road, P.O. Box
149, Hamilton, MA 01936; (978) 468-3999; or
pclark@swiftrivercompany.com.
i. FERC Contact: Brandon Cherry at (202) 502-8328 or
brandon.cherry@ferc.gov.
j. Cooperating agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item l below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See 94 FERC ]
61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and serve a copy of
the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: December 9, 2013.
The Commission strongly encourages electronic filing. Please file
additional study requests and requests for cooperating agency status
using the Commission's eFiling system at https://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support
at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or (202)
502-8659 (TTY). In lieu of electronic filing, please send a paper copy
to: Secretary, Federal Energy Regulatory Commission, 888 First Street
NE., Washington, DC. 20426. The first page of any filing should include
docket number P-12721-006.
m. The application is not ready for environmental analysis at this
time.
n. The existing, unlicensed Pepperell Hydroelectric Project
consists of: (1) The 23.5-foot-high, 251-foot-long concrete gravity
ogee Pepperell Paper dam that includes a 244-foot-long spillway with a
crest elevation of 197.0 feet North American Vertical Datum 1988
(NAVD88) and 3-foot-high wooden flashboards; (2) a 3.5-mile-long, 294-
acre impoundment with a normal water surface elevation of 200.0 feet
NAVD88; (3) a 25-foot-long, 26-foot-wide intake structure with two
7.75-foot-wide, 14.0-foot-high leaf intake gates; (4) a 12-foot-
diameter, 565.5-foot-long penstock; (5) a 14.0 to 58.0-foot-wide, 25.5-
foot-long forebay structure that includes a 1.5-foot-diameter gate with
low level drain pipe and a 4.25-foot-wide, 3.5-foot-high trash sluice
gate; (6) six 8-foot-wide, 10-foot-high turbine bay headgates with
17.33-foot-high trashracks with 1.75-inch clear bar spacing; (7) a 62-
foot-wide, 41-foot-long powerhouse containing three 640-kilowatt (kW)
turbine-generating units for a total installed capacity 1,920 kW; (8)
three 11.5-foot-long turbine draft tubes; (9) three 265-foot-long, 600-
volt transmission lines; and (10) appurtenant facilities.
The existing project also includes a downstream fish passage
facility that consists of: (1) A 3-foot-wide, 23-foot-long concrete
intake with a 4-foot-wide, 8-foot-high entrance gate; (2) a collection
channel with a 2-foot-high, 2-foot-wide overflow stoplog notch; and (3)
a 5-foot-deep plunge pool.
The existing project bypasses approximately 700 feet of the Nashua
River.
Pepperell Hydro Company, LLC proposes to increase the capacities of
two turbine-generating units to 764 kW and 735 kW and install a new
67.5-kW low flow turbine-generating unit at the dam for a total
installed capacity of 2,206.5 kW. Pepperell Hydro Company, LLC proposes
to operate the project in a run-of-river mode and release: (1) 46 cubic
feet per second (cfs) or inflow to the bypassed reach from April 1
through November 30, which would include 17 cfs or inflow through the
existing downstream fish passage facility from June 15 through October
30; and (2) 15 cfs or inflow to the bypassed reach from December 1
through March 31. The project would have an estimated average annual
generation of 7,997 megawatt-hours.
o. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
p. With this notice, we are initiating consultation with the
Massachusetts Historical Commission, as required by section 106 of the
National Historic Preservation Act and the regulations of the Advisory
Council on Historic Preservation, 36 CFR 800.4.
q. Procedural schedule: The application will be processed according
to the following preliminary Hydro Licensing Schedule. Revisions to the
schedule will be made as appropriate.
Issue Deficiency Letter--December 2013
Issue Notice of Acceptance--February 2014
Issue Scoping Document--March 2014
Issue Notice of Ready for Environmental Analysis--May 2014
Issue Notice of the Availability of the EA--October 2014
Dated: October 23, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-25700 Filed 10-29-13; 8:45 am]
BILLING CODE 6717-01-P