Notice of Intent To Rule on Change in Use of Aeronautical Property at Bowman Field Airport, Louisville, KY, 64591-64592 [2013-25585]
Download as PDF
Federal Register / Vol. 78, No. 209 / Tuesday, October 29, 2013 / Notices
application, or a change of a person
assigned to a key project staff position
(see section VI.A.2.).
8. A change in or temporary absence
of the person responsible for managing
and reporting on the grant’s finances.
9. A change in the name of the grantee
organization.
10. A transfer or contracting out of
grant-supported activities (see
subsection H. below).
11. A transfer of the grant to another
recipient.
12. Pre-agreement costs (see section
VII.I.2.a.).
13. The purchase of automated data
processing equipment and software (see
section VII.I.2.b.).
14. Consultant rates (see section
VII.I.2.c.).
15. A change in the nature or number
of the products to be prepared or the
manner in which a product would be
distributed.
B. Requests for Grant Adjustments
All grantees must promptly notify SJI,
in writing, of events or proposed
changes that may require adjustments to
the approved project design. In
requesting an adjustment, the grantee
must set forth the reasons and basis for
the proposed adjustment and any other
information the program manager
determines would help SJI’s review.
C. Notification of Approval/Disapproval
If the request is approved, the grantee
will be sent a Grant Adjustment signed
by the SJI Executive Director. If the
request is denied, the grantee will be
sent a written explanation of the reasons
for the denial.
D. Changes in the Scope of the Grant
Major changes in scope, duration,
training methodology, or other
significant areas must be approved in
advance by SJI. A grantee may make
minor changes in methodology,
approach, or other aspects of the grant
to expedite achievement of the grant’s
objectives with subsequent notification
to SJI.
mstockstill on DSK4VPTVN1PROD with NOTICES
E. Date Changes
A request to change or extend the
grant period must be made at least 30
days in advance of the end date of the
grant. A revised task plan should
accompany a request for an extension of
the grant period, along with a revised
budget if shifts among budget categories
will be needed. A request to change or
extend the deadline for the final
financial report or final progress report
must be made at least 14 days in
advance of the report deadline (see
section VII.L.2.).
VerDate Mar<15>2010
18:15 Oct 28, 2013
Jkt 232001
F. Temporary Absence of the Project
Director
Whenever an absence of the project
director is expected to exceed a
continuous period of one month, the
plans for the conduct of the project
director’s duties during such absence
must be approved in advance by the
Institute. This information must be
provided in a letter signed by an
authorized representative of the grantee/
sub-grantee at least 30 days before the
departure of the project director, or as
soon as it is known that the project
director will be absent. The grant may
be terminated if arrangements are not
approved in advance by SJI.
G. Withdrawal of/Change in Project
Director
If the project director relinquishes or
expects to relinquish active direction of
the project, SJI must be notified
immediately. In such cases, if the
grantee/sub-grantee wishes to terminate
the project, SJI will forward procedural
instructions upon notification of such
intent. If the grantee wishes to continue
the project under the direction of
another individual, a statement of the
candidate’s qualifications should be
sent to SJI for review and approval. The
grant may be terminated if the
qualifications of the proposed
individual are not approved in advance
by SJI.
H. Transferring or Contracting Out of
Grant-Supported Activities
No principal activity of a grantsupported project may be transferred or
contracted out to another organization
without specific prior approval by SJI.
All such arrangements must be
formalized in a contract or other written
agreement between the parties involved.
Copies of the proposed contract or
agreement must be submitted for prior
approval of SJI at the earliest possible
time. The contract or agreement must
state, at a minimum, the activities to be
performed, the time schedule, the
policies and procedures to be followed,
the dollar limitation of the agreement,
and the cost principles to be followed in
determining what costs, both direct and
indirect, will be allowed. The contract
or other written agreement must not
affect the grantee’s overall responsibility
for the direction of the project and
accountability to SJI.
State Justice Institute Board of
Directors
James R. Hannah (Chairman), Chief Justice,
Supreme Court of Arkansas, Little Rock,
AR
PO 00000
Frm 00125
Fmt 4703
Sfmt 4703
64591
Daniel J. Becker (Vice Chairman), State Court
Administrator, Utah Administrative Office
of the Courts, Salt Lake City, UT
Gayle A. Nachtigal (Secretary), Senior Circuit
Court Judge, Washington County Circuit
Court, Hillsboro, OR
Hernan D. Vera (Treasurer), President & CEO,
Public Counsel Law Center, Los Angeles,
CA
Chase T. Rogers, Chief Justice, Supreme
Court of Connecticut, Hartford, CT
Jonathan Lippman, Chief Judge of the State
of New York, New York, NY
David V. Brewer, Justice, Oregon Supreme
Court, Salem, OR
Wilfredo Martinez, County Judge, 9th
Judicial Circuit of Florida, Orlando, FL
Marsha J. Rabiteau, Executive Director, Legal
Policy Strategies Group, Bloomfield, CT
John B. Nalbandian, Partner, Taft Stettinius
& Hollister LLP, Cincinnati, OH
Isabel Framer, President, Language Access
Consultants LLC, Copley, OH
Jonathan D. Mattiello, Executive Director (ex
officio)
Jonathan D. Mattiello,
Executive Director.
[FR Doc. 2013–25461 Filed 10–28–13; 8:45 am]
BILLING CODE P
DEPARTMENT OF TRANSPORTATION
Federal Aviation Administration
Notice of Intent To Rule on Change in
Use of Aeronautical Property at
Bowman Field Airport, Louisville, KY
Federal Aviation
Administration (FAA), DOT.
ACTION: Request for public comment.
AGENCY:
The Federal Aviation
Administration is requesting public
comment on request by the Louisville
Regional Airport Authority to
temporarily change a portion of airport
property from aeronautical to nonaeronautical use at the Bowman Field
Airport, Louisville, Kentucky. The
request consists approximately of 0.41
acres of temporary use. This action is
taken under the provisions of Section
125 of the Wendell H. Ford Aviation
Investment Reform Act for the 21st
Century (AIR 21).
DATES: Comments must be received on
or before November 29, 2013.
ADDRESSES: Documents are available for
review at the Louisville Regional
Airport Authority, 700 Administration
Drive, Louisville, KY 40209; and the
FAA Memphis Airports District Office,
2600 Thousand Oaks Boulevard, Suite
2250, Memphis, TN 38118–2482.
Written comments on the Sponsor’s
request must be delivered or mailed to:
Mr. Phillip J. Braden, Manager,
Memphis Airports District Office, 2600
SUMMARY:
E:\FR\FM\29OCN1.SGM
29OCN1
64592
Federal Register / Vol. 78, No. 209 / Tuesday, October 29, 2013 / Notices
Thousand Oaks Boulevard, Suite 2250,
Memphis, TN 38118–2482.
In addition, a copy of any comments
submitted to the FAA must be mailed or
delivered to Mr. Charles T. Miller,
Executive Director, Louisville Regional
Airport Authority, P.O. Box 9129,
Louisville, KY 40209.
Mr.
Tommy L. Dupree, Team Lead/Civil
Engineer, Federal Aviation
Administration, Memphis Airports
District Office, 2600, Thousand Oaks
Boulevard, Suite 2250, Memphis, TN
38118–2482. The application may be
reviewed in person at this same
location, by appointment.
FOR FURTHER INFORMATION CONTACT:
The FAA
proposes to rule and invites public
comment on the request to lease
property for non-aeronautical purposes
at Bowman Field Airport, Louisville, KY
42103. Under the provisions of AIR 21
(49 U.S.C. 47107(h)(2)).
On September 30, 2013, the FAA
determined that the request to lease
property for non-aeronautical purposes
at Bowman Field Airport meets the
procedural requirements of the Federal
Aviation Administration. The FAA may
approve the request, in whole or in part,
no later than November 29, 2013.
The following is a brief overview of
the request:
The Louisville Regional Airport
Authority is proposing the lease of
approximately 0.41 acres, a partial of
Parcel 48, bounded by Roger E. Schupp
Street to the north, Dutchman’s Lane to
the south, Tucker Boulevard to the east,
and Gast Boulevard to the west. The
non-aeronautical lease is for a period of
5 (five) years, with an option of 5 (five)
years that can be exercised by the
airport authority. The non-aeronautical
lease is for the purpose of leasing said
property to an adjacent land owner, The
Jewish Family & Career Services of
Louisville, Inc., to be used as a parking
lot.
Any person may inspect, by
appointment, the request in person at
the FAA office listed above under FOR
FURTHER INFORMATION CONTACT.
mstockstill on DSK4VPTVN1PROD with NOTICES
SUPPLEMENTARY INFORMATION:
Issued in Memphis, TN on September 30,
2013.
Phillip J. Braden,
Manager, Memphis Airports District Office,
Southern Region.
[FR Doc. 2013–25585 Filed 10–28–13; 8:45 am]
BILLING CODE 4910–13–P
VerDate Mar<15>2010
18:15 Oct 28, 2013
Jkt 232001
DEPARTMENT OF TRANSPORTATION
Federal Highway Administration
Notice of Final Federal Agency Actions
on the Stehekin Valley Road
Improvement Project From the
Stehekin River Corridor
Implementation Plan: Chelan County,
Washington
Federal Highway
Administration (FHWA), Department of
Transportation (DOT) and other Federal
agencies.
ACTION: Notice of Limitations on Claims
for Judicial Review of Actions by FHWA
and other Federal agencies.
AGENCY:
This notice announces final
environmental actions taken by the
FHWA, the National Park Service (NPS),
the United States Fish and Wildlife
Service (USF&WS), and other Federal
agencies that are final within the
meaning of 23 U.S.C. § 139(l)(1). The
actions relate to the Stehekin Valley
Road Improvement project from the
Stehekin River Corridor Implementation
Plan in Chelan County, Washington.
This action grants approval for the road
improvement project element of the
plan.
DATES: By this notice, the FHWA is
advising the public of final agency
actions subject to 23 U.S.C. 139(l)(1). A
claim seeking judicial review of the
Federal agency actions on the roadway
project will be barred unless the claim
is filed on or before March 28, 2014. If
the Federal law that authorizes judicial
review of a claim provides a time period
of less than 150 days for filing such
claim, then that shorter time period still
applies.
FOR FURTHER INFORMATION CONTACT:
Michelle Eraut, Acting Environmental
Program Manager, FHWA, 610 East 5th
Street, Vancouver, WA, Telephone:
(360) 619–7967. For the NPS: Roy M.
Zipp, Environmental Protection
Specialist, North Cascades National
Park, 810 State Route 20, Sedro-Wolley,
WA 98284, Telephone: 360–854–7313.
For the USF&WS, Greg Kurz, Central
Washington Field Office, 215 Melody
Lane, Suite 119, Wenatchee, WA 98801,
Telephone: (509) 665–3508. The FHWA
Stehekin Valley Road Improvement
Project Record of Decision, NPS
Stehekin River Corridor Implementation
Plan Environmental Impact Statement
(EIS) and Record of Decision (ROD), is
available upon written request from the
Federal Highway Administration at the
address shown above. Comments or
questions concerning this proposed
action should be directed to the FHWA
at the address provided above.
SUMMARY:
PO 00000
Frm 00126
Fmt 4703
Sfmt 4703
Notice is
hereby given that the FHWA, has taken
final agency action subject to 23 U.S.C.
§ 139(l)(1) by issuing approval for the
following highway project in the State
of Washington: Stehekin Valley Road
Improvement Project. The project is a
component of the Stehekin River
Corridor Implementation Plan (Plan) in
the Lake Chelan National Recreation
Area for which the U.S. Department of
Interior National Park Service issued a
Record of Decision dated March 13,
2013. FHWA served as a cooperating
agency in the development of the EIS,
and issued a FHWA Record of Decision,
dated September 27, 2013. FHWAadministered funds will be used for the
project and FHWA will administer the
construction contact. The project will
realign 1.8 miles of the existing 10 mile
alignment, moving this section outside
of the Stehekin River’s channel
migration zone to reduce flooding by the
river and, consequently, the threat to
public safety and access and
maintenance costs. Another 7.4 miles of
the road will undergo minor
improvements including resurfacing
and culvert replacement within the
existing roadway prism. In addition, a
1200-foot long connector road will be
built to provide access between the
realigned portion of the road and the
existing alignment. The actions by the
Federal agencies and the laws under
which such actions were taken are
described in the Record of Decision
issued on September 27, 2013. The NPS
EIS, NPS ROD, and the FHWA ROD, are
available by contacting the FHWA at the
address provided above. This notice
applies to all Federal agency decisions
as of the issuance date of this notice and
all laws under which such actions were
taken, including but not limited to:
1. General: National Environmental
Policy Act (NEPA) [42 U.S.C 4321–
4347]; Federal-Aid Highway Act [23
U.S.C. 109 and 23 U.S.C. 128].
2. Air: Clean Air Act [42 U.S.C. 7401–
7671(q)].
3. Land: Section 4(f) of the
Department of Transportation Act of
1966 [23 U.S.C. 138 and 49 U.S.C. 303];
Section 6(f) of the Land and Water
Conservation Fund Act (LWCF) [16
U.S.C. 460l–4—460l–11.].
4. Wildlife: Section 7 of the
Endangered Species Act [16 U.S.C.
1531–1544]; Fish and Wildlife
Coordination Act [16 U.S.C. 661–667
(e)]; Migratory Bird Treaty Act [16
U.S.C. 703–712].
5. Historic and Cultural Resources:
Section 106 of the National Historic
Preservation Act of 1966, as amended
[16 U.S.C. 470(f) et seq.]; Archeological
Resources Protection Act of 1977 [16
SUPPLEMENTARY INFORMATION:
E:\FR\FM\29OCN1.SGM
29OCN1
Agencies
[Federal Register Volume 78, Number 209 (Tuesday, October 29, 2013)]
[Notices]
[Pages 64591-64592]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-25585]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Federal Aviation Administration
Notice of Intent To Rule on Change in Use of Aeronautical
Property at Bowman Field Airport, Louisville, KY
AGENCY: Federal Aviation Administration (FAA), DOT.
ACTION: Request for public comment.
-----------------------------------------------------------------------
SUMMARY: The Federal Aviation Administration is requesting public
comment on request by the Louisville Regional Airport Authority to
temporarily change a portion of airport property from aeronautical to
non-aeronautical use at the Bowman Field Airport, Louisville, Kentucky.
The request consists approximately of 0.41 acres of temporary use. This
action is taken under the provisions of Section 125 of the Wendell H.
Ford Aviation Investment Reform Act for the 21st Century (AIR 21).
DATES: Comments must be received on or before November 29, 2013.
ADDRESSES: Documents are available for review at the Louisville
Regional Airport Authority, 700 Administration Drive, Louisville, KY
40209; and the FAA Memphis Airports District Office, 2600 Thousand Oaks
Boulevard, Suite 2250, Memphis, TN 38118-2482. Written comments on the
Sponsor's request must be delivered or mailed to: Mr. Phillip J.
Braden, Manager, Memphis Airports District Office, 2600
[[Page 64592]]
Thousand Oaks Boulevard, Suite 2250, Memphis, TN 38118-2482.
In addition, a copy of any comments submitted to the FAA must be
mailed or delivered to Mr. Charles T. Miller, Executive Director,
Louisville Regional Airport Authority, P.O. Box 9129, Louisville, KY
40209.
FOR FURTHER INFORMATION CONTACT: Mr. Tommy L. Dupree, Team Lead/Civil
Engineer, Federal Aviation Administration, Memphis Airports District
Office, 2600, Thousand Oaks Boulevard, Suite 2250, Memphis, TN 38118-
2482. The application may be reviewed in person at this same location,
by appointment.
SUPPLEMENTARY INFORMATION: The FAA proposes to rule and invites public
comment on the request to lease property for non-aeronautical purposes
at Bowman Field Airport, Louisville, KY 42103. Under the provisions of
AIR 21 (49 U.S.C. 47107(h)(2)).
On September 30, 2013, the FAA determined that the request to lease
property for non-aeronautical purposes at Bowman Field Airport meets
the procedural requirements of the Federal Aviation Administration. The
FAA may approve the request, in whole or in part, no later than
November 29, 2013.
The following is a brief overview of the request:
The Louisville Regional Airport Authority is proposing the lease of
approximately 0.41 acres, a partial of Parcel 48, bounded by Roger E.
Schupp Street to the north, Dutchman's Lane to the south, Tucker
Boulevard to the east, and Gast Boulevard to the west. The non-
aeronautical lease is for a period of 5 (five) years, with an option of
5 (five) years that can be exercised by the airport authority. The non-
aeronautical lease is for the purpose of leasing said property to an
adjacent land owner, The Jewish Family & Career Services of Louisville,
Inc., to be used as a parking lot.
Any person may inspect, by appointment, the request in person at
the FAA office listed above under FOR FURTHER INFORMATION CONTACT.
Issued in Memphis, TN on September 30, 2013.
Phillip J. Braden,
Manager, Memphis Airports District Office, Southern Region.
[FR Doc. 2013-25585 Filed 10-28-13; 8:45 am]
BILLING CODE 4910-13-P