Notice of Request Under Blanket Authorization; Petal Gas Storage, LLC., 63179-63180 [2013-24741]
Download as PDF
Federal Register / Vol. 78, No. 205 / Wednesday, October 23, 2013 / Notices
emcdonald on DSK67QTVN1PROD with NOTICES
conditions for such service must be
pursuant to a rate schedule on file with
the Commission,25 even though the rate
schedule would provide no
compensation for such service.26 The
Commission directs staff to conduct a
workshop, in a generic proceeding, to
explore the mechanics of public utilities
filing reactive power rate schedules for
which there is no compensation.
13. This policy is consistent with the
Commission’s precedent distinguishing
between a changed rate and an initial
rate.27 In Southwestern Electric Power
25 We note that our pro forma large generator
interconnection agreement, in section 9.6, governs
the provision of reactive power by an
interconnection customer, i.e., by a generator,
including the instance where an interconnection
customer, i.e., a generator, may charge for reactive
power outside the deadband. Absent payment to the
transmission provider’s own or affiliated generators,
our longstanding policy has been that a
transmission provider does not have to separately
pay an interconnection customer, i.e., a generator,
for reactive power within the deadband.
26 16 U.S.C. 824d(c) (2006) (requiring that ‘‘every
public utility shall file with the Commission . . .
schedules showing all rates and charges for any
transmission or sale subject to the jurisdiction of
the Commission, and the classification, practices,
and regulations affecting such rates and charges,
together with all contracts which in any manner
affect or relate to such rates, charges, classifications,
and services’’); Prior Notice and Filing
Requirements under Part II of the Federal Power
Act, 64 FERC ¶ 61,139, at 61,987, order on reh’g,
65 FERC ¶ 61,081 (1993) (stating that the
Commission has considerable flexibility in
determining what rates and practices are ‘‘for or in
connection with,’’ ‘‘affecting,’’ ‘‘pertaining’’ or
‘‘relat[ing] to’’ jurisdictional service and,
accordingly, must be filed for Commission review);
Sulphur Springs Valley Elec. Coop., 107 FERC ¶
61,284, at P 7 (2004) (finding that the public utility
was obligated to file two agreements for
jurisdictional services even though there were no
specified charges or revenues associated with the
agreements).
27 See, e.g., WPS Canada Generation, Inc., 103
FERC ¶ 61,193, at P 15 (2003) (finding that a
particular facility had been providing reactive
power service to Maine Public for years, although
under different ownership, and, therefore, the
proposed rates were changed rates rather than
initial rates); Calpine Oneta Power, L.P., 103 FERC
¶ 61,338, at P 11 (2003) (finding that the Oneta
Project had been supplying reactive power to Public
Service Company of Oklahoma, although without
charge); Public Service Co. of Colorado, 74 FERC ¶
61,354, at 62,087 & n.2 (1996) (finding that a power
supply agreement with Glenwood Springs adds a
new customer to an existing service and, therefore,
constitutes a changed rate); Northern States Power
Co., 74 FERC ¶ 61,106, at 61,345 (1996) (finding
that Northern States’s filing was a changed rate
because it unbundled its requirements rates to
provide for separately-stated charges for various
types of transmission); Gulf States Utilities Co., 45
FERC ¶ 61,246, at 61,725 (1988) (finding that a rate
schedule for transmission service was a changed
rate because Gulf States was already providing
service to Lafayette and Plaquemine and the present
filing merely provided for a different service to
existing customers); Florida Power & Light Co. v.
FERC, 617 F.2d 809, 813–17 (D.C. Cir. 1980)
(finding that the Commission had a reasonable basis
for changing its policy so as to treat transmission
agreement schedules as changed rates subject to the
Commission’s suspension and refund powers, in
light of previously existing interchange agreements,
rather than initial rates not subject to such powers).
VerDate Mar<15>2010
18:13 Oct 22, 2013
Jkt 232001
Co., the Commission defined an initial
rate as one that provides for a new
service to a new customer.28 The
Commission explained: ‘‘We believe
that our broadened definition of a
change in rate is consistent with and
serves to further the policies which
underlie the FPA. The primary purpose
of the legislation is the protection of
customers from excessive rates and
charges.’’ 29 The Commission
emphasized that this definition of a
changed rate allowed the Commission to
give customers refund protection and,
therefore, shield them from the ability of
utilities to exploit any sort of regulatory
lag by filing unjust and unreasonable
rates.30 Stressing this policy of
protecting customers, the Commission
stated: ‘‘Taking a broad view as to what
constitutes a change in rate clearly
serves, by making filings subject to the
Commission’s suspension and refund
authority under section 205(e) of the
FPA, to protect customers of electricity
from excessive or exploitative rates.’’ 31
14. As we explain below, because our
policy is being clarified and we are
prospectively providing for the filing of
rates, terms and conditions for the
provision of reactive power service
(even within-the-deadband reactive
power service) for which there is no
compensation, we find that it would be
appropriate for Chehalis to recover the
amounts it previously refunded to BPA,
with interest calculated in accordance
with 18 CFR 35.19a (2013).32 The DC
Circuit has recognized the
Commission’s authority to order
recoupment of funds previously paid if
the Commission provides adequate
28 39 FERC ¶ 61,099, at 61,293 (1987)
(Southwestern).
29 Id. (citing Town of Alexandria v. FPC, 555 F.2d
1020, 1028 (D.C. Cir. 1977); Municipal Light Boards
v. FPC, 450 F.2d 1341, 1348 (D.C. Cir. 1971);
Atlantic Refining Co. v. Public Service Commission
of New York, 360 U.S. 378, 388 (1959); FPC v. Hope
Natural Gas Co., 320 U.S. 591, 610 (1944)).
30 The Commission recognizes that section 206 of
the FPA has been modified since the issuance of
Southwestern. While the new section 206 has
eliminated some of the differences underlying the
finding in Southwestern, a fundamental difference
still exists between the refund protection provided
under section 205 of the FPA (suspension and
refund protection for the entire period the filed rate
is collected prior to issuance of a final Commission
order) and section 206 (refund protection limited to
a 15-month period). Thus, the Commission
reaffirms its definitions of initial and changed rates
in order to carry out the primary purpose of the
statute, i.e., to protect customers from excessive
rates and charges. See, e.g., Southwestern, 39 FERC
¶ 61,099.
31 Id.
32 Niagara Mohawk Power Corp. v. FPC, 379 F.2d
153, 159 (D.C. Cir. 1967) (breadth of Commission
discretion is at its zenith when fashioning
remedies).
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
63179
explanation.33 In the instant case, we
find the recoupment of funds would be
appropriate.34 The Commission is
clarifying its policy and, as explained
above, finding that, with regard to
jurisdictional reactive power service
(even within-the-deadband reactive
power service) for which there is no
compensation, on a prospective basis
rate schedules governing the rates,
terms, and conditions for such service
must be on file with the Commission.35
Therefore, given that we are applying
this policy on a prospective basis, we
find that it would be appropriate for
Chehalis to recover the amounts
previously refunded to BPA, with
interest.
The Commission orders:
The Secretary is hereby directed to
promptly publish a copy of this order in
the Federal Register.
By the Commission.
Issued October 17, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–24756 Filed 10–22–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP14–3–000]
Notice of Request Under Blanket
Authorization; Petal Gas Storage, LLC.
Take notice that on October 9, 2013,
Petal Gas Storage, L.L.C. (Petal), 9
Greenway Plaza, Suite 2800, Houston,
Texas 77046, filed in Docket No. CP14–
3–000, a prior notice request pursuant to
sections 157.205 and 157.214 of the
Commission’s Regulations under the
Natural Gas Act (NGA) as amended,
requesting authorization to increase its
maximum storage capacity in the Petal
Salt Dome’s Cavern 12A, located in
Forrest County, Mississippi, from 8.2
Bcf to 9.26 Bcf, all as more fully set
forth in the application which is on file
with the Commission and open to
public inspection. The filing may also
be viewed on the web at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
33 Black Oak Energy, LLC v. FERC, 725 F.3d 230
(D.C. Cir. 2013).
34 Cf. Transmission Agency of Northern California
v. FERC, 495 F.3d 663 (2007).
35 The Commission also clarifies that it does not
intend to exercise its authority to impose
enforcement sanctions for a jurisdictional entity’s
failure, prior to this order, to have a rate schedule
on file for the provision of reactive power service
without compensation. However, jurisdictional
entities are reminded that they must submit filings
on a timely basis in the future or face possible
sanctions by the Commission.
E:\FR\FM\23OCN1.SGM
23OCN1
emcdonald on DSK67QTVN1PROD with NOTICES
63180
Federal Register / Vol. 78, No. 205 / Wednesday, October 23, 2013 / Notices
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, please contact FERC Online
Support at FERCOnlineSupport@
ferc.gov or toll free at (866) 208–3676, or
TTY, contact (202) 502–8659.
Any questions concerning this
application may be directed to J. Kyle
Stephens, Vice President, Regulatory
Affairs or M.L. Gutierrez, Director,
Regulatory Affairs, by telephone at (713)
479–8252, by facsimile at (713) 479–
1745, or by email at Kyle.Stephens@
bwpmlp.com or Nell.Gutierrez@
bwpmlp.com.
Any person or the Commission’s staff
may, within 60 days after issuance of
the instant notice by the Commission,
file pursuant to Rule 214 of the
Commission’s Procedural Rules (18 CFR
385.214) a motion to intervene or notice
of intervention and pursuant to Section
157.205 of the regulations under the
NGA (18 CFR 157.205), a protest to the
request. If no protest is filed within the
time allowed therefore, the proposed
activity shall be deemed to be
authorized effective the day after the
time allowed for filing a protest. If a
protest is filed and not withdrawn
within 30 days after the allowed time
for filing a protest, the instant request
shall be treated as an application for
authorization pursuant to section 7 of
the NGA.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding, or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenter’s will be
placed on the Commission’s
environmental mailing list, will receive
VerDate Mar<15>2010
18:13 Oct 22, 2013
Jkt 232001
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenter’s will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentary,
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and 5 copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
Dated: October 16, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–24741 Filed 10–22–13; 8:45 am]
BILLING CODE 6717–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[FRL–9901–90–OEI]
Agency Information Collection
Activities OMB Responses
Environmental Protection
Agency (EPA).
ACTION: Notice.
AGENCY:
This document announces the
Office of Management and Budget
(OMB) responses to Agency Clearance
requests, in compliance with the
Paperwork Reduction Act (44 U.S.C.
3501 et. seq.). An agency may not
conduct or sponsor, and a person is not
required to respond to, a collection of
information unless it displays a
currently valid OMB control number.
The OMB control numbers for EPA
regulations are listed in 40 CFR part 9
and 48 CFR chapter 15.
FOR FURTHER INFORMATION CONTACT: Rick
Westlund (202) 566–1682, or email at
westlund.rick@epa.gov and please refer
to the appropriate EPA Information
Collection Request (ICR) Number.
SUPPLEMENTARY INFORMATION:
SUMMARY:
OMB Responses to Agency Clearance
Requests
OMB Approvals
EPA ICR Number 2045.05; NESHAP
for Automobile and Light-duty Truck
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
Surface Coating; 40 CFR part 63
subparts A and IIII; was approved on
09/09/2013; OMB Number 2060–0550;
expires on 09/30/2016; Approved
without change.
EPA ICR Number 1967.05; NESHAP
for Stationary Combustion Turbines; 40
CFR part 63 subparts A and YYYY; was
approved on 09/09/2013; OMB Number
2060–0540; expires on 09/30/2016;
Approved without change.
EPA ICR Number 1759.06; Pesticide
Worker Protection Standard Training
and Notification; 40 CFR part 170; was
approved on 09/12/2013; OMB Number
2070–0148; expires on 09/30/2016;
Approved with change.
EPA ICR Number 1031.10;
Recordkeeping and Reporting
Requirements for Allegations of
Significant Adverse Reactions to Human
Health or the Environment (TSCA
Section 8(c)); 40 CFR part 717; was
approved on 09/12/2013; OMB Number
2070–0017; expires on 09/30/2016;
Approved with change.
EPA ICR Number 2456.01;
Willingness to Pay for Improved Water
Quality in the Chesapeake Bay (New);
was approved on 09/17/2013; OMB
Number 2010–0043; expires on 09/30/
2015; Approved with change.
EPA ICR Number 1664.09; National
Oil and Hazardous Substances Pollution
Contingency Plans (Renewal); 40 CFR
300.900; was approved on 09/23/2013;
OMB Number 2050–0141; expires on
09/30/2016; Approved without change.
EPA ICR Number 1086.11; NSPS for
Onshore Natural Gas Processing Plants;
40 CFR part 60 subparts A, KKK, LLL;
was approved on 09/23/2013; OMB
Number 2060–0120; expires on 03/31/
2014; Approved without change.
EPA ICR Number 2127.03;
Conditional Exclusions from Solid
Waste and Hazardous Waste for SolventContaminated Wipes (Final Rule); 40
CFR 261.4(a)(26) and 261.4(b)(18); was
approved on 09/23/2013; OMB Number
2050–0209; expires on 09/30/2016;
Approved without change.
EPA ICR Number 2358.04; Nitrogen
Oxides Ambient Air Monitoring
(Renewal); 40 CFR part 58; was
approved on 09/25/2013; OMB Number
2060–0638; expires on 09/30/2016;
Approved without change.
EPA ICR Number 1659.08; NESHAP
for Gasoline Distribution Facilities; 40
CFR part 63 subparts A and R; was
approved on 09/25/2013; OMB Number
2060–0325; expires on 09/30/2016;
Approved without change.
EPA ICR Number 1696.08; Fuels and
Fuel Additives: Health-Effects Research
Requirements for Manufacturers; 40
CFR part 79 subpart F; was approved on
09/30/2013; OMB Number 2060–0297;
E:\FR\FM\23OCN1.SGM
23OCN1
Agencies
[Federal Register Volume 78, Number 205 (Wednesday, October 23, 2013)]
[Notices]
[Pages 63179-63180]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-24741]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP14-3-000]
Notice of Request Under Blanket Authorization; Petal Gas
Storage, LLC.
Take notice that on October 9, 2013, Petal Gas Storage, L.L.C.
(Petal), 9 Greenway Plaza, Suite 2800, Houston, Texas 77046, filed in
Docket No. CP14-3-000, a prior notice request pursuant to sections
157.205 and 157.214 of the Commission's Regulations under the Natural
Gas Act (NGA) as amended, requesting authorization to increase its
maximum storage capacity in the Petal Salt Dome's Cavern 12A, located
in Forrest County, Mississippi, from 8.2 Bcf to 9.26 Bcf, all as more
fully set forth in the application which is on file with the Commission
and open to public inspection. The filing may also be viewed on the web
at https://www.ferc.gov using the ``eLibrary'' link.
[[Page 63180]]
Enter the docket number excluding the last three digits in the docket
number field to access the document. For assistance, please contact
FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at (866)
208-3676, or TTY, contact (202) 502-8659.
Any questions concerning this application may be directed to J.
Kyle Stephens, Vice President, Regulatory Affairs or M.L. Gutierrez,
Director, Regulatory Affairs, by telephone at (713) 479-8252, by
facsimile at (713) 479-1745, or by email at Kyle.Stephens@bwpmlp.com or
Nell.Gutierrez@bwpmlp.com.
Any person or the Commission's staff may, within 60 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to Section 157.205 of
the regulations under the NGA (18 CFR 157.205), a protest to the
request. If no protest is filed within the time allowed therefore, the
proposed activity shall be deemed to be authorized effective the day
after the time allowed for filing a protest. If a protest is filed and
not withdrawn within 30 days after the allowed time for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to section 7 of the NGA.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice the Commission staff will either:
complete its environmental assessment (EA) and place it into the
Commission's public record (eLibrary) for this proceeding, or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or EA for this
proposal. The filing of the EA in the Commission's public record for
this proceeding or the issuance of a Notice of Schedule for
Environmental Review will serve to notify federal and state agencies of
the timing for the completion of all necessary reviews, and the
subsequent need to complete all federal authorizations within 90 days
of the date of issuance of the Commission staff's FEIS or EA.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenter's will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commenter's will not be required to serve copies of filed
documents on all other parties. However, the non-party commentary, will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at https://www.ferc.gov. Persons unable to file electronically should
submit an original and 5 copies of the protest or intervention to the
Federal Energy Regulatory Commission, 888 First Street NE., Washington,
DC 20426.
Dated: October 16, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-24741 Filed 10-22-13; 8:45 am]
BILLING CODE 6717-01-P