The City of Holyoke Gas & Electric Department; Notice of Intent To File License Application, Filing of Pre-Application Document, and Approving Use of the Traditional Licensing Process, 62347-62348 [2013-24505]
Download as PDF
ehiers on DSK2VPTVN1PROD with NOTICES
Federal Register / Vol. 78, No. 202 / Friday, October 18, 2013 / Notices
Accession Number: 20131001–5164.
Comments Due: 5 p.m. ET 10/22/13.
Docket Numbers: ER13–2308–000.
Applicants: Sapphire Power
Marketing LLC.
Description: Supplement to
September 3, 2013 Sapphire Power
Marketing LLC tariff filing.
Filed Date: 10/8/13.
Accession Number: 20131008–5126.
Comments Due: 5 p.m. ET 10/22/13.
Docket Numbers: ER14–55–000.
Applicants: Arizona Public Service
Company.
Description: Cancellation of Service
Agreement No. 315—Boquillas LGIA to
be effective 12/8/2013.
Filed Date: 10/8/13.
Accession Number: 20131008–5068.
Comments Due: 5 p.m. ET 10/29/13.
Docket Numbers: ER14–56–000.
Applicants: California Independent
System Operator Corporation.
Description: 2013–10–08_
NextEraDesertCenter to be effective
11/1/2013.
Filed Date: 10/8/13.
Accession Number: 20131008–5075.
Comments Due: 5 p.m. ET 10/29/13.
Docket Numbers: ER14–57–000.
Applicants: CES Placerita,
Incorporated.
Description: Amended Change in
Status Filing to be effective 9/30/2013.
Filed Date: 10/8/13.
Accession Number: 20131008–5087.
Comments Due: 5 p.m. ET 10/29/13.
Docket Numbers: ER14–58–000.
Applicants: The Potomac Edison
Company, PJM Interconnection, L.L.C.
Description: FirstEnergy and Potomac
Edison Co submit PJM Service
Agreement No. 3649 to be effective
10/4/2013.
Filed Date: 10/8/13.
Accession Number: 20131008–5098.
Comments Due: 5 p.m. ET 10/29/13.
Docket Numbers: ER14–59–000.
Applicants: The Potomac Edison
Company, PJM Interconnection, L.L.C.
Description: FirstEnergy and Potomac
Edison Co submit Service Agreement
No. 3650 to be effective 10/4/2013.
Filed Date: 10/8/13.
Accession Number: 20131008–5099.
Comments Due: 5 p.m. ET 10/29/13.
Docket Numbers: ER14–60–000.
Applicants: Southwest Power Pool,
Inc.
Description: 2299R2 Rattlesnake
Creek Wind Project, LLC GIA to be
effective 9/26/2013.
Filed Date: 10/8/13.
Accession Number: 20131008–5100.
Comments Due: 5 p.m. ET 10/29/13.
Docket Numbers: ER14–61–000.
Applicants: Chestnut Flats Wind,
LLC.
VerDate Mar<15>2010
10:03 Oct 17, 2013
Jkt 232001
Description: Notice of Cancellation of
Market-Based Rate Tariff for Chestnut
Flats Wind to be effective 10/9/2013.
Filed Date: 10/8/13.
Accession Number: 20131008–5122.
Comments Due: 5 p.m. ET 10/29/13.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: October 9, 2013.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2013–24484 Filed 10–17–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2387–002]
The City of Holyoke Gas & Electric
Department; Notice of Intent To File
License Application, Filing of PreApplication Document, and Approving
Use of the Traditional Licensing
Process
a. Type of Filing: Notice of Intent to
File License Application and Request to
Use the Traditional Licensing Process.
b. Project No.: 2387–002.
c. Date Filed: August 26, 2013.
d. Submitted By: City of Holyoke Gas
& Electric Department.
e. Name of Project: Holyoke No. 2
Hydroelectric Project.
f. Location: Between the first and
second level canals on the Holyoke
Canal System adjacent to the
Connecticut River, in the City of
Holyoke in Hampden County,
Massachusetts. The project does not
occupy federal land.
g. Filed Pursuant to: 18 CFR 5.3 of the
Commission’s regulations.
h. Potential Applicant Contact: Paul
Ducheney, Superintendent, Holyoke Gas
PO 00000
Frm 00005
Fmt 4703
Sfmt 4703
62347
& Electric, 99 Suffolk Street, Holyoke,
MA 01040; (413) 536–9340; email—
ducheney@hged.com.
i. FERC Contact: Adam Beeco at (202)
502–8655; or email at adam.beeco@
ferc.gov.
j. Holyoke Gas and Electric filed its
request to use the Traditional Licensing
Process on August 26, 2013. Holyoke
Gas and Electric provided public notice
of its request on September 1, 2013. In
a letter dated October 9, 2013, the
Director of the Division of Hydropower
Licensing approved Holyoke Gas and
Electric’s request to use the Traditional
Licensing Process.
k. With this notice, we are initiating
informal consultation with: (a) The U.S.
Fish and Wildlife Service and/or NOAA
Fisheries under section 7 of the
Endangered Species Act and the joint
agency regulations thereunder at 50
CFR, Part 402; (b) NOAA Fisheries
under section 305(b) of the MagnusonStevens Fishery Conservation and
Management Act and implementing
regulations at 50 CFR 600.920; and (c)
the Massachusetts State Historic
Preservation Officer, as required by
section 106, National Historical
Preservation Act, and the implementing
regulations of the Advisory Council on
Historic Preservation at 36 CFR 800.2.
l. With this notice, we are designating
Holyoke Gas and Electric as the
Commission’s non-federal
representative for carrying out informal
consultation, pursuant to section 7 of
the Endangered Species Act and section
106 of the National Historic
Preservation Act.
m. Holyoke Gas and Electric filed a
Pre-Application Document (PAD) and a
proposed process plan and schedule
with the Commission, pursuant to 18
CFR 5.6 of the Commission’s
regulations.
n. A copy of the PAD is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site (https://
www.ferc.gov), using the ‘‘eLibrary’’
link. Enter the docket number,
excluding the last three digits in the
docket number field to access the
document. For assistance, contact FERC
Online Support at FERCONline
Support@ferc.gov or toll free at 1–866–
208–3676, or for TTY, (202) 502–8659.
A copy is also available for inspection
and reproduction at the address in
paragraph h.
o. Register online at https://www.ferc.
gov/docs-filing/esubscription.asp to be
notified via email of new filing and
issuances related to this or other
pending projects. For assistance, contact
FERC Online Support.
E:\FR\FM\18OCN1.SGM
18OCN1
62348
Federal Register / Vol. 78, No. 202 / Friday, October 18, 2013 / Notices
Dated: October 9, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–24505 Filed 10–17–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 7518–015]
Erie Boulevard Hydropower L.P.;
Notice of Application Tendered for
Filing With the Commission and
Establishing Procedural Schedule for
Licensing and Deadline for
Submission of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
License.
b. Project No.: 7518–015.
c. Date Filed: September 30, 2013.
d. Applicant: Erie Boulevard
Hydropower L.P.
e. Name of Project: Hogansburg
Hydroelectric Project.
f. Location: On the St. Regis River in
Franklin County, New York. The project
does not occupy any federal lands.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Steven Murphy,
Brookfield Renewable Power, 33 West
1st Street South, Fulton, New York (315)
598–6130 or email at steven.murphy@
brookfieldpower.com.
i. FERC Contact: John Mudre at (202)
502–8902 or email at john.mudre@
ferc.gov.
j. This application is not ready for
environmental analysis at this time.
k. Project Description: The existing
Hogansburg Project consists of: (1) A
reservoir having a surface area of about
18.6 acres and a maximum storage
capacity of approximately 112 acre-feet;
(2) a 247-foot-long, 11.5-foot-high
concrete gravity dam with a spillway
crest elevation of 165.2 feet above mean
sea level; (3) a 34-foot-long, 22-foot-high
stoplog gate structure; (4) a 45-foot by
48-foot integrated intake/powerhouse
structure at the dam’s right abutment;
(5) a single S. Morgan Smith vertical
propeller generating unit having a rated
capacity of 485 kilowatts; (6) a 600-footlong tailrace having varying widths
between 24 feet and 100 feet; and (7)
2.4-kilovolt (kV) generator leads
extending about 25 feet to an adjacent
electrical substation containing a 2.4/
4.8-kV, 600-kilovolt-amperes, step-up
transformer bank. A transmission line
owned and operated by National Grid
Corporation connects directly to the
substation. Power generated at the
project interconnects with the electrical
grid at the substation.
At the time the Commission issued
the original license for the Hogansburg
Project (1985), the Commission’s
regulations did not require minor
projects occupying non-federal lands to
have an established project boundary.
Therefore, the boundary for the project
is being established through this
relicensing process.
l. Locations of the Application: A
copy of the application is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at FERCOnlineSupport@
ferc.gov or toll-free at 1–866–208–3676,
or for TTY, (202) 502–8659. A copy is
also available for inspection and
reproduction at the address in item (h)
above.
m. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Procedural Schedule:
The application will be processed
according to the following preliminary
Hydro Licensing Schedule. Revisions to
the schedule may be made as
appropriate.
Milestone
Target date
Notice of Acceptance/Notice of Ready for Environmental Analysis .....................................................................................
Filing of recommendations, preliminary terms and conditions, and fishway prescriptions ...................................................
Commission issues Draft EA .................................................................................................................................................
Comments on Draft EA .........................................................................................................................................................
Modified Terms and Conditions ............................................................................................................................................
Commission Issues Final EA ................................................................................................................................................
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
DEPARTMENT OF ENERGY
Dated: October 9, 2013.
Kimberly D. Bose,
Secretary.
[Project No. 7320–042]
[FR Doc. 2013–24504 Filed 10–17–13; 8:45 am]
ehiers on DSK2VPTVN1PROD with NOTICES
BILLING CODE 6717–01–P
Federal Energy Regulatory
Commission
Erie Boulevard Hydropower, L.P.;
Notice of Application Accepted for
Filing and Soliciting Motions To
Intervene and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 7320–042.
c. Date filed: July 1, 2013.
VerDate Mar<15>2010
10:03 Oct 17, 2013
Jkt 232001
PO 00000
Frm 00006
Fmt 4703
Sfmt 4703
December 2013.
February 2014.
August 2014.
September 2014.
November 2014.
February 2015.
d. Applicant: Erie Boulevard
Hydropower, L.P.
e. Name of Project: Chasm
Hydroelectric Project.
f. Location: On the Salmon River, in
Franklin County, New York. No federal
lands are occupied by the project works
or located within the project boundary.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Steven Murphy,
Compliance Specialist, Brookfield
Renewable Power—New York West
Operations, 33 West 1st Street South,
Fulton, NY 13069; (315) 589–6130;
email—steven.murphy@
brookfieldpower.com.
i. FERC Contact: John Mudre at (202)
502–8902; or email at john.mudre@
ferc.gov.
E:\FR\FM\18OCN1.SGM
18OCN1
Agencies
[Federal Register Volume 78, Number 202 (Friday, October 18, 2013)]
[Notices]
[Pages 62347-62348]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-24505]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2387-002]
The City of Holyoke Gas & Electric Department; Notice of Intent
To File License Application, Filing of Pre-Application Document, and
Approving Use of the Traditional Licensing Process
a. Type of Filing: Notice of Intent to File License Application and
Request to Use the Traditional Licensing Process.
b. Project No.: 2387-002.
c. Date Filed: August 26, 2013.
d. Submitted By: City of Holyoke Gas & Electric Department.
e. Name of Project: Holyoke No. 2 Hydroelectric Project.
f. Location: Between the first and second level canals on the
Holyoke Canal System adjacent to the Connecticut River, in the City of
Holyoke in Hampden County, Massachusetts. The project does not occupy
federal land.
g. Filed Pursuant to: 18 CFR 5.3 of the Commission's regulations.
h. Potential Applicant Contact: Paul Ducheney, Superintendent,
Holyoke Gas & Electric, 99 Suffolk Street, Holyoke, MA 01040; (413)
536-9340; email_ducheney@hged.com.
i. FERC Contact: Adam Beeco at (202) 502-8655; or email at
adam.beeco@ferc.gov.
j. Holyoke Gas and Electric filed its request to use the
Traditional Licensing Process on August 26, 2013. Holyoke Gas and
Electric provided public notice of its request on September 1, 2013. In
a letter dated October 9, 2013, the Director of the Division of
Hydropower Licensing approved Holyoke Gas and Electric's request to use
the Traditional Licensing Process.
k. With this notice, we are initiating informal consultation with:
(a) The U.S. Fish and Wildlife Service and/or NOAA Fisheries under
section 7 of the Endangered Species Act and the joint agency
regulations thereunder at 50 CFR, Part 402; (b) NOAA Fisheries under
section 305(b) of the Magnuson-Stevens Fishery Conservation and
Management Act and implementing regulations at 50 CFR 600.920; and (c)
the Massachusetts State Historic Preservation Officer, as required by
section 106, National Historical Preservation Act, and the implementing
regulations of the Advisory Council on Historic Preservation at 36 CFR
800.2.
l. With this notice, we are designating Holyoke Gas and Electric as
the Commission's non-federal representative for carrying out informal
consultation, pursuant to section 7 of the Endangered Species Act and
section 106 of the National Historic Preservation Act.
m. Holyoke Gas and Electric filed a Pre-Application Document (PAD)
and a proposed process plan and schedule with the Commission, pursuant
to 18 CFR 5.6 of the Commission's regulations.
n. A copy of the PAD is available for review at the Commission in
the Public Reference Room or may be viewed on the Commission's Web site
(https://www.ferc.gov), using the ``eLibrary'' link. Enter the docket
number, excluding the last three digits in the docket number field to
access the document. For assistance, contact FERC Online Support at
FERCONlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY,
(202) 502-8659. A copy is also available for inspection and
reproduction at the address in paragraph h.
o. Register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filing and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
[[Page 62348]]
Dated: October 9, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-24505 Filed 10-17-13; 8:45 am]