FFP Qualified Hydro 14, LLC; Western Minnesota Municipal Power Agency; Notice Announcing Preliminary Permit Drawing, 62350-62351 [2013-24481]
Download as PDF
62350
Federal Register / Vol. 78, No. 202 / Friday, October 18, 2013 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13567–001]
ehiers on DSK2VPTVN1PROD with NOTICES
City of Guttenberg; Notice of
Successive Preliminary Permit
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Competing Applications
On July 2, 2013, the City of
Guttenberg filed an application for a
successive preliminary permit, pursuant
to section 4(f) of the Federal Power Act
(FPA), proposing to study the feasibility
of the Guttenberg Water Power Project
to be located on the Mississippi River,
near the township of Guttenberg, in
Clayton County, Iowa. The sole purpose
of a preliminary permit, if issued, is to
grant the permit holder priority to file
a license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land-disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed project would consist of
the following: (1) An existing 140-footwide by 280-foot-long auxiliary lock; (2)
a new 110-foot-wide by 250-foot-long
concrete powerhouse containing four
new 5-mega-watt (MW) pit-type
horizontal turbine units for a total
capacity of 20 MW; (3) an existing local
step-up transformer; (4) a new 300-footlong, 69-kilovolt (kV) transmission line
extending from the local transformer to
the local grid (the point of
interconnection) which is owned and
operated by the City of Guttenberg; and
(5) appurtenant facilities. The estimated
annual generation of the Guttenberg
Water Power Project would be 63,400
megawatt-hours.
Applicant Contact: Mr. Barry
Dykhuizen, City of Guttenberg, P.O. Box
580, 502 S. 1st Street, Guttenberg, IA
52052–0580; phone: (563) 252–1161,
extension 109.
FERC Contact: Tyrone Williams;
phone: (202) 502–6331.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
VerDate Mar<15>2010
10:03 Oct 17, 2013
Jkt 232001
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–13567–001.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–13567) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
identified in this notice. The
Commission will select between the two
competing permit applications as
provided in section 4.37 of its
regulations.2 The priority established by
this drawing will be used to determine
which applicant, between those with
identical filing times, will be considered
to have the first-filed application.
The drawing is open to the public and
will be held in room 2C, the
Commission Meeting Room, located at
888 First Street NE., Washington, DC
20426. The Secretary will issue a
subsequent notice announcing the
results of the drawing.
Dated: October 10, 2013.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
Federal Energy Regulatory
Commission
[FR Doc. 2013–24480 Filed 10–17–13; 8:45 am]
Dated: October 10, 2013.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2013–24482 Filed 10–17–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
[Project No. 13579–002; Project No. 14491–
000]
BILLING CODE 6717–01–P
FFP Qualified Hydro 14, LLC; Western
Minnesota Municipal Power Agency;
Notice Announcing Preliminary Permit
Drawing
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14539–000; Project No. 14540–
000]
Lock+ Hydro Friends Fund III, LLC;
Western Minnesota Municipal Power
Agency; Notice Announcing
Preliminary Permit Drawing
The Commission has received two
preliminary permit applications deemed
filed on July 23, 2013 at 8:30 a.m.,1 for
proposed projects to be located at the
U.S. Army Corps of Engineers’ Melvin
Price Locks and Dam on the Mississippi
River, near the city of Alton, in Madison
County, Illinois, and the city of West
Alton, in St. Charles County, Missouri.
The applications were filed by Lock+
Hydro Friends Fund III, LLC for Project
No. 14539–000 and Western Minnesota
Municipal Power Agency for Project No.
14540–000.
On October 21, 2013, at 10:00 a.m.
(Eastern Time), the Secretary of the
Commission, or her designee, will
conduct a random drawing to determine
the filing priority of the applicants
The Commission has received two
preliminary permit applications deemed
filed on February 1, 2013 at 8:30 a.m.,1
for proposed projects to be located at the
U.S. Army Corps of Engineers’
Saylorville Dam and Lake on the Des
Moines River, in the city of Johnston in
Polk County, Iowa. The applications
were filed by FFP Qualified Hydro 14,
LLC for Project No. 13579–002 and
Western Minnesota Municipal Power
Agency for Project No. 14491–000.
On October 21, 2013, at 10:00 a.m.
(Eastern Time), the Secretary of the
Commission, or her designee, will
conduct a random drawing to determine
the filing priority of the applicants
identified in this notice. The
Commission will select between the two
competing permit applications as
provided in section 4.37 of its
regulations.2 The priority established by
this drawing will be used to determine
which applicant, between those with
identical filing times, will be considered
to have the first-filed application.
2 See
id. 4.37.
the Commission’s Rules of Practice and
Procedure, any document received after regular
business hours is considered filed at 8:30 a.m. on
the next regular business day. See 18 CFR
385.2001(a)(2) (2013).
2 See id. 4.37.
1 Under
1 Under the Commission’s Rules of Practice and
Procedure, any document received after regular
business hours is considered filed at 8:30 a.m. on
the next regular business day. See 18 CFR
385.2001(a)(2) (2013).
PO 00000
Frm 00008
Fmt 4703
Sfmt 4703
E:\FR\FM\18OCN1.SGM
18OCN1
Federal Register / Vol. 78, No. 202 / Friday, October 18, 2013 / Notices
The drawing is open to the public and
will be held in room 2C, the
Commission Meeting Room, located at
888 First Street NE., Washington, DC
20426. The Secretary will issue a
subsequent notice announcing the
results of the drawing.
Dated: October 10, 2013.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2013–24481 Filed 10–17–13; 8:45 am]
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CD14–1–000]
North Side Canal Company; Notice of
Preliminary Determination of a
Qualifying Conduit Hydropower
Facility and Soliciting Comments and
Motions To Intervene
On October 3, 2013, North Side Canal
Company, filed a notice of intent to
construct a qualifying conduit
hydropower facility, pursuant to section
30 of the Federal Power Act, as
amended by section 4 of the
Hydropower Regulatory Efficiency Act
of 2013 (HREA). The U Canal Hydro #2
Project would be located along North
Side Canal Company’s irrigation system
on the U Canal in Jerome County, Idaho.
Applicant Contact: Alan W. Hansten,
Manager, North Side Canal Company,
BILLING CODE 6717–01–P
62351
Ltd., 921 North Lincoln, Jerome, ID
83338, Phone No. (208) 324–2319.
FERC Contact: Christopher Chaney,
Phone No. (202) 502–6778, email:
christopher.chaney@ferc.gov.
Qualifying Conduit Hydropower
Facility Description: The proposed
project would consist of: (1) A proposed
1,500-foot-long, 15-foot- diameter
penstock receiving water from a 1,600foot-long realigned section of the U
Canal; (2) a proposed 48-foot-wide by
105-foot-long powerhouse, containing
one 4,800-kilowatt generating unit; (3) a
proposed tailrace returning flows to the
U Canal; and (4) appurtenant facilities.
The proposed project would have an
estimated annual generating capacity of
16,215 megawatt-hours.
A qualifying conduit hydropower
facility is one that is determined or
deemed to meet all of the criteria shown
in the table below.
TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY
Statutory provision
Description
Satisfies
(Y/N)
FPA 30(a)(3)(A), as amended by HREA ..............
The conduit the facility uses is a tunnel, canal, pipeline, aqueduct, flume, ditch,
or similar manmade water conveyance that is operated for the distribution of
water for agricultural, municipal, or industrial consumption and not primarily for
the generation of electricity.
The facility is constructed, operated, or maintained for the generation of electric
power and uses for such generation only the hydroelectric potential of a nonfederally owned conduit.
The facility has an installed capacity that does not exceed 5 megawatts ..............
On or before August 9, 2013, the facility is not licensed, or exempted from the licensing requirements of Part I of the FPA.
Y
FPA 30(a)(3)(C)(i), as amended by HREA ..........
ehiers on DSK2VPTVN1PROD with NOTICES
FPA 30(a)(3)(C)(ii), as amended by HREA .........
FPA 30(a)(3)(C)(iii), as amended by HREA .........
Preliminary Determination: Based
upon the above criteria, Commission
staff preliminarily determines that the
proposal satisfies the requirements for a
qualifying conduit hydropower facility
not required to be licensed or exempted
from licensing.
Comments and Motions To Intervene:
Deadline for filing comments contesting
whether the facility meets the qualifying
criteria is 45 days from the issuance
date of this notice.
Deadline for filing motions to
intervene is 30 days from the issuance
date of this notice.
Anyone may submit comments or a
motion to intervene in accordance with
the requirements of Rules of Practice
and Procedure, 18 CFR 385.210 and
385.214. Any motions to intervene must
be received on or before the specified
deadline date for the particular
proceeding.
Filing and Service of Responsive
Documents: All filings must (1) bear in
all capital letters the ‘‘COMMENTS
CONTESTING QUALIFICATION FOR A
VerDate Mar<15>2010
10:03 Oct 17, 2013
Jkt 232001
CONDUIT HYDROPOWER FACILITY’’
or ‘‘MOTION TO INTERVENE,’’ as
applicable; (2) state in the heading the
name of the applicant and the project
number of the application to which the
filing responds; (3) state the name,
address, and telephone number of the
person filing; and (4) otherwise comply
with the requirements of sections
385.2001 through 385.2005 of the
Commission’s regulations.1 All
comments contesting Commission staff’s
preliminary determination that the
facility meets the qualifying criteria
must set forth their evidentiary basis.
The Commission strongly encourages
electronic filing. Please file motions to
intervene and comments using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
1 18
PO 00000
CFR 385.2001–2005 (2013).
Frm 00009
Fmt 4703
Sfmt 4703
Y
Y
Y
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
A copy of all other filings in reference
to this application must be accompanied
by proof of service on all persons listed
in the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
Locations of Notice of Intent: Copies
of the notice of intent can be obtained
directly from the applicant or such
copies can be viewed and reproduced at
the Commission in its Public Reference
Room, Room 2A, 888 First Street NE.,
Washington, DC 20426. The filing may
also be viewed on the web at https://
www.ferc.gov/docs-filing/elibrary.asp
using the ‘‘eLibrary’’ link. Enter the
docket number (e.g., CD14–1) in the
E:\FR\FM\18OCN1.SGM
18OCN1
Agencies
[Federal Register Volume 78, Number 202 (Friday, October 18, 2013)]
[Notices]
[Pages 62350-62351]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-24481]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 13579-002; Project No. 14491-000]
FFP Qualified Hydro 14, LLC; Western Minnesota Municipal Power
Agency; Notice Announcing Preliminary Permit Drawing
The Commission has received two preliminary permit applications
deemed filed on February 1, 2013 at 8:30 a.m.,\1\ for proposed projects
to be located at the U.S. Army Corps of Engineers' Saylorville Dam and
Lake on the Des Moines River, in the city of Johnston in Polk County,
Iowa. The applications were filed by FFP Qualified Hydro 14, LLC for
Project No. 13579-002 and Western Minnesota Municipal Power Agency for
Project No. 14491-000.
---------------------------------------------------------------------------
\1\ Under the Commission's Rules of Practice and Procedure, any
document received after regular business hours is considered filed
at 8:30 a.m. on the next regular business day. See 18 CFR
385.2001(a)(2) (2013).
---------------------------------------------------------------------------
On October 21, 2013, at 10:00 a.m. (Eastern Time), the Secretary of
the Commission, or her designee, will conduct a random drawing to
determine the filing priority of the applicants identified in this
notice. The Commission will select between the two competing permit
applications as provided in section 4.37 of its regulations.\2\ The
priority established by this drawing will be used to determine which
applicant, between those with identical filing times, will be
considered to have the first-filed application.
---------------------------------------------------------------------------
\2\ See id. 4.37.
---------------------------------------------------------------------------
[[Page 62351]]
The drawing is open to the public and will be held in room 2C, the
Commission Meeting Room, located at 888 First Street NE., Washington,
DC 20426. The Secretary will issue a subsequent notice announcing the
---------------------------------------------------------------------------
results of the drawing.
Dated: October 10, 2013.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2013-24481 Filed 10-17-13; 8:45 am]
BILLING CODE 6717-01-P