Empire Pipeline, Inc.; National Fuel Gas Supply Corporation; Notice of Intent To Prepare an Environmental Assessment for the Planned Tuscarora Expansion Project, Request for Comments on Environmental Issues, and Notice of Public Scoping Meeting, 62010-62012 [2013-24445]

Download as PDF wreier-aviles on DSK5TPTVN1PROD with NOTICES 62010 Federal Register / Vol. 78, No. 198 / Friday, October 11, 2013 / Notices 888 First Street NE., Room 2A, Washington, DC 20426, (202) 502–8371. Any person wishing to comment on the EA may do so. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure that the Commission has the opportunity to consider your comments prior to making its decision on this project, it is important that we receive your comments in Washington, DC on or before November 4, 2013. For your convenience, there are three methods you can use to file your comments to the Commission. In all instances, please reference the project docket number (CP13–498–000) with your submission. The Commission encourages electronic filing of comments and has expert staff available to assist you at (202) 502–8258 or efiling@ferc.gov. (1) You can file your comments electronically using the eComment feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. This is an easy method for submitting brief, text-only comments on a project; (2) You can also file your comments electronically using the eFiling feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You must select the type of filing you are making. If you are filing a comment on a particular project, please select ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments by mailing them to the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 20426. Any person seeking to become a party to the proceeding must file a motion to intervene pursuant to Rule 214 of the Commission’s Rules of Practice and Procedures (18 CFR 385.214).1 Only intervenors have the right to seek rehearing of the Commission’s decision. The Commission grants affected landowners and others with environmental concerns intervenor status upon showing good cause by stating that they have a clear and direct interest in this proceeding which no 1 See the previous discussion on the methods for filing comments. VerDate Mar<15>2010 10:29 Oct 10, 2013 Jkt 232001 other party can adequately represent. Simply filing environmental comments will not give you intervenor status, but you do not need intervenor status to have your comments considered. Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC Web site (www.ferc.gov) using the eLibrary link. Click on the eLibrary link, click on ‘‘General Search,’’ and enter the docket number excluding the last three digits in the Docket Number field (i.e., CP13– 498). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/ esubscribenow.htm. Dated: October 4, 2013. Kimberly D. Bose, Secretary. [FR Doc. 2013–24439 Filed 10–10–13; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. PF13–12–000] Empire Pipeline, Inc.; National Fuel Gas Supply Corporation; Notice of Intent To Prepare an Environmental Assessment for the Planned Tuscarora Expansion Project, Request for Comments on Environmental Issues, and Notice of Public Scoping Meeting The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Tuscarora Expansion Project (Project) involving construction and operation of facilities by Empire Pipeline, Inc. and National Fuel Gas Supply Corporation (Collectively known and National Fuel) in Steuben County, New York and Tioga County, PO 00000 Frm 00005 Fmt 4703 Sfmt 4703 Pennsylvania. The Commission will use this EA in its decision-making process to determine whether the project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies on the project. Your input will help the Commission staff determine what issues they need to evaluate in the EA. Please note that the scoping period will close on November 4, 2013. You may submit comments in written form or verbally. Further details on how to submit written comments are in the Public Participation section of this notice. In lieu of or in addition to sending written comments, the Commission invites you to attend the public scoping meeting scheduled as follows: FERC Public Scoping Meeting Tuscarora Expansion Project 6 p.m., October 16, 2013, Addison American Legion, 85 Maple Street, Addison, NY 14801. This notice is being sent to the Commission’s current environmental mailing list for this project. State and local government representatives should notify their constituents of this planned project and encourage them to comment on their areas of concern. If you are a landowner receiving this notice, a pipeline company representative may contact you about the acquisition of an easement to construct, operate, and maintain the planned facilities. The company would seek to negotiate a mutually acceptable agreement. However, if the Commission approves the project, that approval conveys with it the right of eminent domain. Therefore, if easement negotiations fail to produce an agreement, the pipeline company could initiate condemnation proceedings where compensation would be determined in accordance with state law. A fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility On My Land? What Do I Need To Know?’’ is available for viewing on the FERC Web site (www.ferc.gov). This fact sheet addresses a number of typically-asked questions, including the use of eminent domain and how to participate in the Commission’s proceedings. Summary of the Planned Project National Fuel proposes to construct: • 16.9 miles of 16 or 20 inch diameter natural gas pipeline running from the existing Tuscarora Gas Compressor Station near Tuscarora, New York to the E:\FR\FM\11OCN1.SGM 11OCN1 Federal Register / Vol. 78, No. 198 / Friday, October 11, 2013 / Notices existing Tioga Pipeline Extension in Tioga County, Pennsylvania; • pipeline interconnection facilities for the pipeline; and • an expansion of the existing Tuscarora Compressor Station by installing and additional 1,400 to 2,400 horsepower of compression. The purpose of the Project is to enable Empire to offer new no-notice transportation and storage services that have been requested by one of its largest local distribution company customers. The general location of the project facilities is shown in appendix 1.1 Land Requirements for Construction Construction of the planned pipeline and compressor station facilities would disturb about 237.7 acres of land. Following construction, National Fuel would maintain about 113.1 acres for permanent operation of the project’s facilities; the remaining acreage would be restored and revert to former uses. wreier-aviles on DSK5TPTVN1PROD with NOTICES The EA Process The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires us 2 to discover and address concerns the public may have about proposals. This process is referred to as scoping. The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of the issues to address in the EA. We will consider all filed comments during the preparation of the EA. In the EA we will discuss impacts that could occur as a result of the construction and operation of the planned project under these general headings: • Geology and soils; • land use; • water resources, fisheries, and wetlands; • cultural resources; • vegetation and wildlife; • air quality and noise; • endangered and threatened species; and 1 The appendices referenced in this notice will not appear in the Federal Register. Copies of the appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called ‘‘eLibrary’’ or from the Commission’s Public Reference Room, 888 First Street NE., Washington, DC 20426, or call (202) 502–8371. For instructions on connecting to eLibrary, refer to the last page of this notice. 2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the environmental staff of the Commission’s Office of Energy Projects. VerDate Mar<15>2010 10:29 Oct 10, 2013 Jkt 232001 • reliability and safety. We will also evaluate possible alternatives to the planned project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas. Although no formal application has been filed, we have already initiated our NEPA review under the Commission’s pre-filing process. The purpose of the pre-filing process is to encourage early involvement of interested stakeholders and to identify and resolve issues before the FERC receives an application. As part of our pre-filing review, we have begun to contact some federal and state agencies to discuss their involvement in the scoping process and the preparation of the EA. The EA will present our independent analysis of the issues. The EA will be available in the public record through eLibrary. Depending on the comments received during the scoping process, we may also publish and distribute the EA to the public for an allotted comment period. We will consider all comments on the EA before we make our recommendations to the Commission. To ensure we have the opportunity to consider and address your comments, please carefully follow the instructions in the Public Participation section below. With this notice, we are asking agencies with jurisdiction by law and/ or special expertise with respect to the environmental issues related to this project to formally cooperate with us in the preparation of the EA.3 Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. Consultations Under Section 106 of the National Historic Preservation Act In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, we are using this notice to initiate consultation with applicable State Historic Preservation Office(s), and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project’s potential effects on historic properties.4 We will define the 3 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at 40 CFR 1501.6. 4 The Advisory Council on Historic Preservation regulations are at 36 CFR Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places. PO 00000 Frm 00006 Fmt 4703 Sfmt 4703 62011 project-specific Area of Potential Effects (APE) in consultation with the SHPO(s) as the project develops. On natural gas facility projects, the APE at a minimum encompasses all areas subject to ground disturbance (examples include construction right-of-way, contractor/ pipe storage yards, compressor stations, and access roads). Our EA for this project will document our findings on the impacts on historic properties and summarize the status of consultations under section 106. Public Participation You can make a difference by providing us with your specific comments or concerns about the project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure that your comments are timely and properly recorded, please send your comments so that the Commission receives them in Washington, DC on or before November 4, 2013. For your convenience, there are three methods you can use to submit your comments to the Commission. In all instances, please reference the project docket number (PF13–12–000) with your submission. The Commission encourages electronic filing of comments and has expert staff available to assist you at (202) 502–8258 or efiling@ferc.gov. (1) You can file your comments electronically using the eComment feature located on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. This is an easy method for interested persons to submit brief, text-only comments on a project; (2) You can file your comments electronically using the eFiling feature located on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You must select the type of filing you are making. If you are filing a comment on a particular project, please select ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments by mailing them to the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 20426. E:\FR\FM\11OCN1.SGM 11OCN1 62012 Federal Register / Vol. 78, No. 198 / Friday, October 11, 2013 / Notices Environmental Mailing List The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; interested Indian Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project. We will update the environmental mailing list as the analysis proceeds to ensure that we send the information related to this environmental review to all individuals, organizations, and government entities interested in and/or potentially affected by the planned project. If we publish and distribute the EA, copies will be sent to the environmental mailing list for public review and comment. If you would prefer to receive a paper copy of the document instead of the CD version or would like to remove your name from the mailing list, please return the attached Information Request (appendix 2). Once National Fuel files its application with the Commission, you may want to become an ‘‘intervenor’’ which is an official party to the Commission’s proceeding. Intervenors play a more formal role in the process and are able to file briefs, appear at hearings, and be heard by the courts if they choose to appeal the Commission’s final ruling. An intervenor formally participates in the proceeding by filing a request to intervene. Instructions for becoming an intervenor are in the User’s Guide under the ‘‘e-filing’’ link on the Commission’s Web site. Please note that the Commission will not accept requests for intervenor status at this time. You must wait until the Commission receives a formal application for the project. wreier-aviles on DSK5TPTVN1PROD with NOTICES Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC Web site (www.ferc.gov) using the eLibrary link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number, excluding the last three digits in the Docket Number field (i.e., PF13– 12–000). Be sure you have selected an appropriate date range. For assistance, 10:29 Oct 10, 2013 Dated: October 3, 2013. Kimberly D. Bose, Secretary. [FR Doc. 2013–24445 Filed 10–10–13; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Becoming an Intervenor VerDate Mar<15>2010 please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/ esubscribenow.htm. Finally, public meetings or site visits will be posted on the Commission’s calendar located at www.ferc.gov/Event Calendar/EventsList.aspx along with other related information. Jkt 232001 [Project No. 2351–017–CO] Public Service Company of Colorado; Notice of Availability of Environmental Assessment In accordance with the National Environmental Policy Act of 1969 and the Federal Energy Regulatory Commission’s (Commission or FERC) regulations contained in the Code of Federal Regulations (CFR)(18 CFR Part 380 [FERC Order No. 486, 52 FR 47897]), the Office of Energy Projects has reviewed Public Service Company of Colorado’s application for license for the Cabin Creek Pumped Storage Hydroelectric Project (FERC Project No. 2351), located on South Clear Creek near the town of Georgetown, Clear Creek County, Colorado. The project currently occupies a total of 267 acres of federal lands within the Arapaho National Forest administered by the U.S. Forest Service. Staff prepared an environmental assessment (EA), which analyzes the potential environmental effects of relicensing the project, and concludes that licensing the project, with appropriate environmental protective measures, would not constitute a major federal action that would significantly PO 00000 Frm 00007 Fmt 4703 Sfmt 4703 affect the quality of the human environment. A copy of the EA is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCOnlineSupport@ ferc.gov or toll-free at 1–866–208–3676, or for TTY, 202–502–8659. You may also register online at www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. Any comments should be filed within 30 days from the date of this notice. The Commission strongly encourages electronic filing. Please file the requested information using the Commission’s eFiling system at https:// www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support at FERCOnlineSupport@ ferc.gov, (866) 208–3676 (toll free), or (202) 502–8659 (TTY). In lieu of electronic filing, please send a paper copy to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The first page of any filing should include docket number P–2351–017. For further information, contact Ryan Hansen by telephone at (202) 502–8074 or by email at ryan.hansen@ferc.gov. Dated: October 4, 2013. Kimberly D. Bose, Secretary. [FR Doc. 2013–24437 Filed 10–10–13; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket Nos. CP13–36–000; CP13–132–000] Transcontinental Gas Pipeline Company; Notice of Availability of the Draft Environmental Impact Statement for the Proposed Rockaway Delivery Lateral and Northeast Connector Projects and Notice of Public Comment Meetings The staff of the Federal Energy Regulatory Commission (FERC or Commission) has prepared this draft environmental impact statement (EIS) for the Rockaway Delivery Lateral Project and Northeast Connector Project E:\FR\FM\11OCN1.SGM 11OCN1

Agencies

[Federal Register Volume 78, Number 198 (Friday, October 11, 2013)]
[Notices]
[Pages 62010-62012]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-24445]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. PF13-12-000]


Empire Pipeline, Inc.; National Fuel Gas Supply Corporation; 
Notice of Intent To Prepare an Environmental Assessment for the Planned 
Tuscarora Expansion Project, Request for Comments on Environmental 
Issues, and Notice of Public Scoping Meeting

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Tuscarora Expansion Project 
(Project) involving construction and operation of facilities by Empire 
Pipeline, Inc. and National Fuel Gas Supply Corporation (Collectively 
known and National Fuel) in Steuben County, New York and Tioga County, 
Pennsylvania. The Commission will use this EA in its decision-making 
process to determine whether the project is in the public convenience 
and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the project. Your input will help the Commission staff 
determine what issues they need to evaluate in the EA. Please note that 
the scoping period will close on November 4, 2013.
    You may submit comments in written form or verbally. Further 
details on how to submit written comments are in the Public 
Participation section of this notice. In lieu of or in addition to 
sending written comments, the Commission invites you to attend the 
public scoping meeting scheduled as follows:

FERC Public Scoping Meeting Tuscarora Expansion Project

6 p.m., October 16, 2013, Addison American Legion, 85 Maple Street, 
Addison, NY 14801.

    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this planned 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the planned facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    A fact sheet prepared by the FERC entitled ``An Interstate Natural 
Gas Facility On My Land? What Do I Need To Know?'' is available for 
viewing on the FERC Web site (www.ferc.gov). This fact sheet addresses 
a number of typically-asked questions, including the use of eminent 
domain and how to participate in the Commission's proceedings.

Summary of the Planned Project

    National Fuel proposes to construct:
     16.9 miles of 16 or 20 inch diameter natural gas pipeline 
running from the existing Tuscarora Gas Compressor Station near 
Tuscarora, New York to the

[[Page 62011]]

existing Tioga Pipeline Extension in Tioga County, Pennsylvania;
     pipeline interconnection facilities for the pipeline; and
     an expansion of the existing Tuscarora Compressor Station 
by installing and additional 1,400 to 2,400 horsepower of compression.
    The purpose of the Project is to enable Empire to offer new no-
notice transportation and storage services that have been requested by 
one of its largest local distribution company customers.
    The general location of the project facilities is shown in appendix 
1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of the appendices were sent to all 
those receiving this notice in the mail and are available at 
www.ferc.gov using the link called ``eLibrary'' or from the 
Commission's Public Reference Room, 888 First Street NE., 
Washington, DC 20426, or call (202) 502-8371. For instructions on 
connecting to eLibrary, refer to the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the planned pipeline and compressor station 
facilities would disturb about 237.7 acres of land. Following 
construction, National Fuel would maintain about 113.1 acres for 
permanent operation of the project's facilities; the remaining acreage 
would be restored and revert to former uses.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\2\ to discover and address concerns the public may have about 
proposals. This process is referred to as scoping. The main goal of the 
scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the planned project under these 
general headings:
     Geology and soils;
     land use;
     water resources, fisheries, and wetlands;
     cultural resources;
     vegetation and wildlife;
     air quality and noise;
     endangered and threatened species; and
     reliability and safety.
    We will also evaluate possible alternatives to the planned project 
or portions of the project, and make recommendations on how to lessen 
or avoid impacts on the various resource areas.
    Although no formal application has been filed, we have already 
initiated our NEPA review under the Commission's pre-filing process. 
The purpose of the pre-filing process is to encourage early involvement 
of interested stakeholders and to identify and resolve issues before 
the FERC receives an application. As part of our pre-filing review, we 
have begun to contact some federal and state agencies to discuss their 
involvement in the scoping process and the preparation of the EA.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary. Depending on 
the comments received during the scoping process, we may also publish 
and distribute the EA to the public for an allotted comment period. We 
will consider all comments on the EA before we make our recommendations 
to the Commission. To ensure we have the opportunity to consider and 
address your comments, please carefully follow the instructions in the 
Public Participation section below.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues 
related to this project to formally cooperate with us in the 
preparation of the EA.\3\ Agencies that would like to request 
cooperating agency status should follow the instructions for filing 
comments provided under the Public Participation section of this 
notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at 40 CFR 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with applicable State Historic Preservation Office(s), and to solicit 
their views and those of other government agencies, interested Indian 
tribes, and the public on the project's potential effects on historic 
properties.\4\ We will define the project-specific Area of Potential 
Effects (APE) in consultation with the SHPO(s) as the project develops. 
On natural gas facility projects, the APE at a minimum encompasses all 
areas subject to ground disturbance (examples include construction 
right-of-way, contractor/pipe storage yards, compressor stations, and 
access roads). Our EA for this project will document our findings on 
the impacts on historic properties and summarize the status of 
consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation regulations 
are at 36 CFR Part 800. Those regulations define historic properties 
as any prehistoric or historic district, site, building, structure, 
or object included in or eligible for inclusion in the National 
Register of Historic Places.
---------------------------------------------------------------------------

Public Participation

    You can make a difference by providing us with your specific 
comments or concerns about the project. Your comments should focus on 
the potential environmental effects, reasonable alternatives, and 
measures to avoid or lessen environmental impacts. The more specific 
your comments, the more useful they will be. To ensure that your 
comments are timely and properly recorded, please send your comments so 
that the Commission receives them in Washington, DC on or before 
November 4, 2013.
    For your convenience, there are three methods you can use to submit 
your comments to the Commission. In all instances, please reference the 
project docket number (PF13-12-000) with your submission. The 
Commission encourages electronic filing of comments and has expert 
staff available to assist you at (202) 502-8258 or efiling@ferc.gov.
    (1) You can file your comments electronically using the eComment 
feature located on the Commission's Web site (www.ferc.gov) under the 
link to Documents and Filings. This is an easy method for interested 
persons to submit brief, text-only comments on a project;
    (2) You can file your comments electronically using the eFiling 
feature located on the Commission's Web site (www.ferc.gov) under the 
link to Documents and Filings. With eFiling, you can provide comments 
in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You must select the type of filing you are making. If 
you are filing a comment on a particular project, please select 
``Comment on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 
20426.

[[Page 62012]]

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; interested Indian Tribes; 
other interested parties; and local libraries and newspapers. This list 
also includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
planned project.
    If we publish and distribute the EA, copies will be sent to the 
environmental mailing list for public review and comment. If you would 
prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (appendix 2).

Becoming an Intervenor

    Once National Fuel files its application with the Commission, you 
may want to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the User's Guide under the ``e-filing'' link on the Commission's Web 
site. Please note that the Commission will not accept requests for 
intervenor status at this time. You must wait until the Commission 
receives a formal application for the project.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., PF13-
12-000). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/esubscribenow.htm.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: October 3, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-24445 Filed 10-10-13; 8:45 am]