Entergy Nuclear Operations, Inc.; Big Rock Point; Independent Spent Fuel Storage Installation, 61401-61403 [2013-24302]

Download as PDF tkelley on DSK3SPTVN1PROD with NOTICES Federal Register / Vol. 78, No. 192 / Thursday, October 3, 2013 / Notices Petitioner also asked that the NRC commit to verifying, during the license renewal period, Entergy’s implementation through routine baseline inspections and to a timely upgrade of the regulatory guidance for maintaining cable qualification and the verification that the cables can perform their design functions. As the basis of the request, the Petitioner asserted, in part, the following concerns: • The NRC regulations require that plant owners ensure that electrical wiring is qualified to perform in the environmental conditions experienced during normal operation and during accidents. Pilgrim has no program today, as required by NRC regulations, to ensure operability of the submerged and/or wetted wires. • Most electrical cables at Pilgrim have been exposed to significant moisture over the 40 years since their initial construction. The wires, and possibly the connections and splices inside conduits, are designed to operate properly only in a dry environment and are not designed to operate in a moist or wet environment. Thus, there is no assurance that these electrical cables will not fail if they are wet, submerged, or previously exposed to moisture. • Wires degrade with age, and the oldest wires are most susceptible to degradation. Pilgrim is one of the oldest operating commercial reactors in the country, and the majority of the conduits and wires at Pilgrim were installed during the initial construction. There are no existing methods to ensure operability, short of visual inspection or replacing cables with ones designed to operate in a wet or submerged environment. • As identified in several pertinent sections of Pilgrim’s license renewal application and safety evaluation report, Pilgrim’s aging management program, for the period 2012–2032, is insufficient and does not provide reasonable assurance to the public. The Petitioner further stated that compliance with the NRC’s regulations is intended to provide reasonable assurance that an electrical wire failure will neither initiate an accident nor make an accident more severe. The Petitioner also noted that Pilgrim has a long history of cables being submerged and/or wetted with no verification of the long-term operability that provides reasonable assurance of continued operation of these cables. The NRC sent a copy of the proposed Director’s Decision to the petitioner and the licensee for comment on March 20, 2013. The Petitioner and the licensee were asked to provide comments within 30 days on any part of the proposed VerDate Mar<15>2010 18:29 Oct 02, 2013 Jkt 232001 Director’s Decision that was considered to be erroneous or any issues in the petition that were not addressed. Comments were received from the Petitioner and are addressed in an attachment to the final Director’s Decision. The Director of the Office of Nuclear Reactor Regulation denied the petitioner’s request to issue a Demand for Information to require Entergy to demonstrate that all inaccessible cables at Pilgrim are capable of performing their functions. The Office has also denied the Petitioner’s request for the NRC to take certain actions to demonstrate that accessible and inaccessible cables can perform their design functions. These actions included requests for NRC to certify that (1) All cables have been identified as to their location, age, and repair history, (2) all cables are monitored by the Licensee prior to continued operation, and (3) the Licensee’s monitoring program incorporates at a minimum, recommendations for certain aging management guidelines and NRC generic guidance. The NRC staff has determined that the Licensee’s programs for cable condition monitoring and managing aging effects of inaccessible power cables have been adequately implemented, to the extent that there is reasonable assurance that cables subject to moisture will be adequately managed during the period of extended operation. The Director’s Decision (DD–13–02) under part 2.206 of Title 10 of the Code of Federal Regulations, ‘‘Requests for Action under This Subpart,’’ explains the reasons for this decision. The complete text is available in ADAMS under Accession No. ML13255A189 for inspection at the Commission’s Public Document Room located at One White Flint North, Public File Area 01 F21, 11555 Rockville Pike (first floor), Rockville, Maryland, and online in the NRC library at https://www.nrc.gov/ reading-rm.html. The NRC will file a copy of the Director’s Decision with the Secretary of the Commission for the Commission’s review in accordance with 10 CFR 2.206. As a provision of this regulation, the Director’s Decision will constitute the final action of the Commission 25 days after the date of the Decision unless the Commission, on its own motion, institutes a review of the Director’s Decision in that time. Dated at Rockville, Maryland, this 26th day of September 2013. PO 00000 Frm 00081 Fmt 4703 Sfmt 4703 61401 For the Nuclear Regulatory Commission. Eric J. Leeds, Director, Office of Nuclear Reactor Regulation. [FR Doc. 2013–24272 Filed 10–2–13; 8:45 am] BILLING CODE 7590–01–P NUCLEAR REGULATORY COMMISSION [Docket Nos. 50–155; 72–43 and NRC–2013– 0218] Entergy Nuclear Operations, Inc.; Big Rock Point; Independent Spent Fuel Storage Installation Nuclear Regulatory Commission. ACTION: Exemption; issuance. AGENCY: The U.S. Nuclear Regulatory Commission (NRC) is issuing an exemption in response to a request submitted by Entergy Nuclear Operations, Inc. (ENO) on June 20, 2012, for the Big Rock Point (BRP) Independent Spent Fuel Storage Installation (ISFSI). ADDRESSES: Please refer to Docket ID NRC–2013–0218 when contacting the NRC about the availability of information regarding this document. You may access publicly-available information related to this action by the following methods: • Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC–2013–0218. Address question about NRC dockets to Carol Gallagher; telephone: 301–287–3422; email: Carol.Gallagher@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document. • NRC’s Agencywide Documents Access and Management System (ADAMS): You may access publicly available documents online in the NRC Library at https://www.nrc.gov/readingrm/adams.html. To begin the search, select ‘‘ADAMS Public Documents’’ and then select ‘‘Begin Web-based ADAMS Search.’’ For problems with ADAMS, please contact the NRC’s Public Document Room (PDR) reference staff at 1–800–397–4209, 301–415–4737, or by email to pdr.resource@nrc.gov. The ADAMS accession number for each document referenced in this document (if that document is available in ADAMS) is provided the first time that a document is referenced. • NRC’s PDC: You may examine and purchase copies of public documents at the NRC’s PDR, Room O1–F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852. SUMMARY: E:\FR\FM\03OCN1.SGM 03OCN1 61402 Federal Register / Vol. 78, No. 192 / Thursday, October 3, 2013 / Notices Dr. Pamela Longmire, Office of Nuclear Material Safety and Safeguards, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001; telephone: 301–287–0829; email: Pamela.Longmire@nrc.gov. tkelley on DSK3SPTVN1PROD with NOTICES FOR FURTHER INFORMATION CONTACT: 1.0 Introduction On November 23, 2011 (76 FR 72560), the NRC issued a final rule (EP Final Rule) modifying or adding certain emergency planning (EP) requirements in §§ 50.47, 50.54, and appendix E of Title 10 of the Code of Federal Regulations (10 CFR). The EP Final Rule was effective on December 23, 2011, with specific implementation dates for each of the rule changes. Entergy Nuclear Operations, Inc. (ENO) is the holder of Facility Operating License DPR–6 for the BRP facility. The license, issued pursuant to the Atomic Energy Act of 1954, as amended, and 10 CFR part 50, allows ENO to possess and store spent nuclear fuel at the permanently shutdown and decommissioned facility under the provision of 10 CFR part 72, subpart K, ‘‘General License for Storage of Spent Fuel at Power Reactor Sites.’’ In a letter dated June 26, 1997 (ADAMS Legacy Accession No. 9707030167), Consumers Energy Company (CEC) informed the NRC that the BRP facility had permanently ceased power operations. In a letter dated September 23, 1997 (ADAMS Legacy Accession No. 9709300363), CEC informed the NRC that it had permanently moved the fuel from the reactor to the spent fuel pool. After ceasing operations at the reactor, CEC began transferring spent nuclear fuel from the spent fuel pool to the BRP ISFSI for long term dry storage. As discussed in letters dated September 8, 2005, and November 16, 2006 (ADAMS Accession Nos. ML052550366 and ML063260085, respectively), these activities were completed in 2003, and final decommissioning of the reactor site was completed in 2006. The BRP ISFSI is a stand-alone ISFSI located on approximately 30 acres in Charlevoix County, on the northern shore of Michigan’s Lower Peninsula. In a letter dated July 30, 2007 (ADAMS Accession No. ML072220219), ENO applied for an order approving indirect transfer of control of licenses for BRP. By letter dated July 28, 2008 (ADAMS Accession No. ML080940528), the NRC consented to the proposal. On June 20, 2012, ENO submitted a letter, ‘‘Request for Exemption from Emergency Planning and Preparedness Requirements’’ (ADAMS Accession No. ML12173A066), requesting exemption from specific emergency planning VerDate Mar<15>2010 18:29 Oct 02, 2013 Jkt 232001 requirements of 10 CFR 50.47 and appendix E to 10 CFR part 50 for the BRP ISFSI. ENO states that this exemption request and its impact on the corresponding emergency plan: (1) Is authorized by law; (2) will not present an undue risk to the public health and safety; and (3) is consistent with the common defense and security in accordance with 10 CFR 50.12. ENO states that its intent in submitting this exemption request is to maintain the regulatory structure in place prior to the issuance of the EP Final Rule and, therefore, does not propose any changes to its emergency plan or implementing procedures other than simple regulatory reference changes that can be implemented under 10 CFR 50.54(q). 2.0 Discussion On September 19, 1997 (ADAMS Legacy Accession No. 9709240386), CEC requested an exemption from the provisions of 10 CFR 50.54(q) that required emergency plans to meet all of the standards of 10 CFR 50.47(b) and all of the requirements of appendix E to 10 CFR part 50 so that the licensee would have to meet only certain EP standards and requirements. Additionally, in a letter dated September 19, 1997 (ADAMS Legacy Accession No. 9709240383), CEC requested approval of a proposed BRP Defueled Emergency Plan (DEP) that proposed to meet those limited standards and requirements. The NRC approved the requested exemption and the BRP DEP on September 30, 1998 (ADAMS Legacy Accession No. 9810080019). The safety evaluation report (SER) established EP requirements for BRP as documented in the DEP. The NRC staff (staff) concluded that the licensee’s emergency plan was acceptable in view of the greatly reduced offsite radiological consequences associated with the decommissioning plant status. The staff found that the postulated dose to the general public from any reasonably conceivable accident would not exceed the U.S. Environmental Protection Agency (EPA) Protective Action Guides (PAGs), and for the bounding accident, the length of time available to respond to a loss of spent fuel cooling or reduction in water level gave confidence that offsite measures for the public could be taken without preparation. CEC completed moving spent nuclear fuel and Greater-Than-Class-C (GTCC) waste into dry storage at the BRP ISFSI in March of 2003. On September 9, 2004, CEC submitted a request for approval of the BPR Emergency Plan to reflect that only an ISFSI remained at the site (ADAMS Accession No. PO 00000 Frm 00082 Fmt 4703 Sfmt 4703 ML042530611). The NRC approved the BRP ISFSI Emergency Plan on October 13, 2005 (ADAMS Accession No. ML052690042). The NRC staff concluded that the BRP ISFSI Emergency Plan met the emergency planning requirements contained in 10 CFR part 72 for an ISFSI not located on the site of an operating nuclear power reactor, and thus provided for an acceptable level of emergency preparedness. Since this approval, BRP has not requested nor received substantive exemptions from emergency planning requirements. Revision 4 of the BRP ISFSI Emergency Plan, dated September 9, 2008 (Reference 13), reflects the current conditions, where only the ISFSI and its related support systems, structures, and components remain. With the EP Final Rule, several requirements in 10 CFR part 50 were modified or added, including changes in §§ 50.47, 50.54, and appendix E. The EP Final Rule codified certain voluntary protective measures contained in NRC Bulletin 2005–02, ‘‘Emergency Preparedness and Response Actions for Security-Based Events,’’ and generically applicable requirements similar to those previously imposed by NRC Order EA– 02–026, ‘‘Order for Interim Safeguards and Security Compensatory Measures,’’ dated February 25, 2002. In addition, the EP Final Rule amended other licensee emergency plan requirements to: (1) Enhance the ability of licensees in preparing for and in taking certain protective actions in the event of a radiological emergency; (2) address, in part, security issues identified after the terrorist events of September 11, 2001; (3) clarify regulations to effect consistent emergency plan implementation among licensees; and (4) modify certain EP requirements to be more effective and efficient. However, the EP Final Rule was only an enhancement to the NRC’s regulations and was not necessary for adequate protection. On page 72563 of the Federal Register notice for the EP Final Rule, the Commission ‘‘determined that the existing regulatory structure ensures adequate protection of public health and safety and common defense and security.’’ 3.0 Regulatory Evaluation In the Final Rule for Storage of Spent Fuel in NRC-Approved Storage Casks at Power Reactor Sites (55 FR 29181; July 18, 1990), the NRC amended its regulations to provide for the storage of spent nuclear fuel under a general license on the site of any nuclear power reactor. In its Statement of Considerations (SOC) for the Final Rule E:\FR\FM\03OCN1.SGM 03OCN1 Federal Register / Vol. 78, No. 192 / Thursday, October 3, 2013 / Notices tkelley on DSK3SPTVN1PROD with NOTICES (55 FR 29185), the Commission responded to comments related to emergency preparedness for spent fuel dry storage, stating, ‘‘The new 10 CFR 72.32(c) . . . states that, ‘For an ISFSI that is located on the site of a nuclear power reactor licensed for operation by the Commission, the emergency plan required by 10 CFR 50.47 shall be deemed to satisfy the requirements of this Section.’ One condition of the general license is that the reactor licensee must review the reactor emergency plan and modify it as necessary to cover dry cask storage and related activities. If the emergency plan is in compliance with 10 CFR 50.47, then it is in compliance with the Commission’s regulations with respect to dry cask storage.’’ In the SOC for the Final Rule for EP requirements for ISFSIs and Monitored Retrievable Storage Installation (MRS) (60 FR 32430; June 22, 1995), the Commission stated, in part, that ‘‘current reactor emergency plans cover all at-or near reactor ISFSI’s. An ISFSI that is to be licensed for a stand-alone operation will need an emergency plan established in accordance with the requirements in this rulemaking’’ (60 FR 32431). The Commission responded to comments (60 FR 32435) concerning offsite emergency planning for ISFSIs or an MRS and concluded that ‘‘the offsite consequences of potential accidents at an ISFSI or a MRS would not warrant establishing Emergency Planning Zones.’’ As part of the review for ENO’s current exemption request, the staff also used the EP regulations in 10 CFR 72.32 and Spent Fuel Project Office Interim Staff Guidance (ISG)—16, ‘‘Emergency Planning,’’ (ADAMS Accession No. ML003724570) as references to ensure consistency between specific-licensed and general-licensed ISFSIs. 4.0 Technical Evaluation Pursuant to 10 CFR 50.12, the Commission may, upon application by any interested person or upon its own initiative, grant exemptions from the requirements of 10 CFR part 50 when: (1) The exemptions are authorized by law, will not present an undue risk to public health or safety, and are consistent with the common defense and security; and (2) when special circumstances are present. The staff reviewed this request to determine whether the specific exemptions should be granted, and the staff evaluation (SE) is provided in its letter to ENO, dated September 26, 2013 (ADAMS Accession No. ML13268A501). After evaluating the exemption requests, the staff determined that the ENO should be VerDate Mar<15>2010 18:29 Oct 02, 2013 Jkt 232001 granted the exemptions detailed in the SE. The NRC has found that the ENO meets the criteria for an exemption in 10 CFR 50.12. The NRC has determined that granting the exemption will not result in a violation of the Atomic Energy Act of 1954, as amended, or the Commission’s regulations. Therefore, the exemption is authorized by law. As noted in Section 2.0, ‘‘Discussion,’’ above, the ENO’s compliance with the EP requirements that were in effect before the effective date of the EP Final Rule demonstrated reasonable assurance of adequate protection of public health and safety and common defense and security. In its SE, the NRC staff explains that the ENO’s implementation of its Emergency Plan, with the exemptions, will continue to provide this reasonable assurance of adequate protection. Thus, granting the exemptions will not present an undue risk to public health or safety and is not inconsistent with the common defense and security. For the Commission to grant an exemption, special circumstances must exist. Under 10 CFR 50.12(a)(2)(ii), special circumstances are present when ‘‘[a]pplication of the regulation in the particular circumstances would not serve the underlying purpose of the rule or is not necessary to achieve the underlying purpose of the rule.’’ These special circumstances exist here. The NRC has determined that the ENO’s compliance with the regulations that the staff describes in its SE is not necessary for the licensee to demonstrate that, under its emergency plan, there is reasonable assurance that adequate protective measures can and will be taken in the event of a radiological emergency. Consequently, special circumstances are present because requiring the ENO to comply with the regulations that the staff describes in its SE is not necessary to achieve the underlying purpose of the EP regulations. 5.0 Evironmental Assessment (EA) The NRC staff also considered in the review of this exemption request whether there would be any significant environmental impacts associated with the exemption. For this proposed action, the NRC staff performed an environmental assessment pursuant to 10 CFR 51.30. The proposed action is the approval of a request to exempt the applicant from certain requirements of 10 CFR 50.47(b) and portions of 10 CFR part 50, appendix E. The environmental assessment concluded that the proposed action would not significantly impact the PO 00000 Frm 00083 Fmt 4703 Sfmt 9990 61403 quality of the human environment. The NRC staff concludes that the proposed action will not result in any changes in the types or amounts of any radiological effluents that may be released offsite, and there is no significant increase in occupational or public radiation exposure because of the proposed action. The Environmental Assessment and the Finding of No Significant Impact was published on September 24, 2013 (78 FR 58570). 6.0 Conclusion The NRC concludes that the licensee’s request for an exemption from certain requirements of 10 CFR 50.47(b) and 10 CFR part 50, appendix E, section IV as specified in this SE is acceptable in view of the greatly reduced offsite radiological consequences associated with the ISFSI. The BRP ISFSI Emergency Plan has been reviewed against the acceptance criteria included in 10 CFR 50.47, appendix E to 10 CFR part 50, 10 CFR 72.32 and Interim Staff Guidance—16. The review considered the ISFSI and the low likelihood of any credible accident resulting in radiological releases requiring offsite protective measures. These evaluations were supported by the previously documented licensee and staff accident analyses. The staff concludes that: The BRP ISFSI Emergency Plan provides: (1) An adequate basis for an acceptable state of emergency preparedness; and (2) in conjunction with arrangements made with offsite response agencies, reasonable assurance that adequate protective measures can and will be taken in the event of a radiological emergency at the BRP facility. The NRC has determined that pursuant to 10 CFR 50.12, the exemptions described in the SE are authorized by law, will not endanger life or property or the common defense and security, and are otherwise in the public interest, and special circumstances are present. This exemption is effective upon issuance. Dated at Rockville, Maryland, this 26th day of September, 2013. For the Nuclear Regulatory Commission. Anthony H. Hsia, Deputy Director, Division of Spent Fuel Storage and Transportation, Office of Nuclear Material Safety and Safeguards. [FR Doc. 2013–24302 Filed 10–2–13; 8:45 am] BILLING CODE 7590–01–P E:\FR\FM\03OCN1.SGM 03OCN1

Agencies

[Federal Register Volume 78, Number 192 (Thursday, October 3, 2013)]
[Notices]
[Pages 61401-61403]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-24302]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 50-155; 72-43 and NRC-2013-0218]


Entergy Nuclear Operations, Inc.; Big Rock Point; Independent 
Spent Fuel Storage Installation

AGENCY: Nuclear Regulatory Commission.

ACTION: Exemption; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing an 
exemption in response to a request submitted by Entergy Nuclear 
Operations, Inc. (ENO) on June 20, 2012, for the Big Rock Point (BRP) 
Independent Spent Fuel Storage Installation (ISFSI).

ADDRESSES: Please refer to Docket ID NRC-2013-0218 when contacting the 
NRC about the availability of information regarding this document. You 
may access publicly-available information related to this action by the 
following methods:
     Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2013-0218. Address 
question about NRC dockets to Carol Gallagher; telephone: 301-287-3422; 
email: Carol.Gallagher@nrc.gov. For technical questions, contact the 
individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may access publicly available documents online in the NRC 
Library at https://www.nrc.gov/reading-rm/adams.html. To begin the 
search, select ``ADAMS Public Documents'' and then select ``Begin Web-
based ADAMS Search.'' For problems with ADAMS, please contact the NRC's 
Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-
4737, or by email to pdr.resource@nrc.gov. The ADAMS accession number 
for each document referenced in this document (if that document is 
available in ADAMS) is provided the first time that a document is 
referenced.
     NRC's PDC: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

[[Page 61402]]


FOR FURTHER INFORMATION CONTACT: Dr. Pamela Longmire, Office of Nuclear 
Material Safety and Safeguards, U.S. Nuclear Regulatory Commission, 
Washington, DC 20555-0001; telephone: 301-287-0829; email: 
Pamela.Longmire@nrc.gov.

1.0 Introduction

    On November 23, 2011 (76 FR 72560), the NRC issued a final rule (EP 
Final Rule) modifying or adding certain emergency planning (EP) 
requirements in Sec. Sec.  50.47, 50.54, and appendix E of Title 10 of 
the Code of Federal Regulations (10 CFR). The EP Final Rule was 
effective on December 23, 2011, with specific implementation dates for 
each of the rule changes.
    Entergy Nuclear Operations, Inc. (ENO) is the holder of Facility 
Operating License DPR-6 for the BRP facility. The license, issued 
pursuant to the Atomic Energy Act of 1954, as amended, and 10 CFR part 
50, allows ENO to possess and store spent nuclear fuel at the 
permanently shutdown and decommissioned facility under the provision of 
10 CFR part 72, subpart K, ``General License for Storage of Spent Fuel 
at Power Reactor Sites.'' In a letter dated June 26, 1997 (ADAMS Legacy 
Accession No. 9707030167), Consumers Energy Company (CEC) informed the 
NRC that the BRP facility had permanently ceased power operations. In a 
letter dated September 23, 1997 (ADAMS Legacy Accession No. 
9709300363), CEC informed the NRC that it had permanently moved the 
fuel from the reactor to the spent fuel pool.
    After ceasing operations at the reactor, CEC began transferring 
spent nuclear fuel from the spent fuel pool to the BRP ISFSI for long 
term dry storage. As discussed in letters dated September 8, 2005, and 
November 16, 2006 (ADAMS Accession Nos. ML052550366 and ML063260085, 
respectively), these activities were completed in 2003, and final 
decommissioning of the reactor site was completed in 2006. The BRP 
ISFSI is a stand-alone ISFSI located on approximately 30 acres in 
Charlevoix County, on the northern shore of Michigan's Lower Peninsula. 
In a letter dated July 30, 2007 (ADAMS Accession No. ML072220219), ENO 
applied for an order approving indirect transfer of control of licenses 
for BRP. By letter dated July 28, 2008 (ADAMS Accession No. 
ML080940528), the NRC consented to the proposal.
    On June 20, 2012, ENO submitted a letter, ``Request for Exemption 
from Emergency Planning and Preparedness Requirements'' (ADAMS 
Accession No. ML12173A066), requesting exemption from specific 
emergency planning requirements of 10 CFR 50.47 and appendix E to 10 
CFR part 50 for the BRP ISFSI.
    ENO states that this exemption request and its impact on the 
corresponding emergency plan: (1) Is authorized by law; (2) will not 
present an undue risk to the public health and safety; and (3) is 
consistent with the common defense and security in accordance with 10 
CFR 50.12. ENO states that its intent in submitting this exemption 
request is to maintain the regulatory structure in place prior to the 
issuance of the EP Final Rule and, therefore, does not propose any 
changes to its emergency plan or implementing procedures other than 
simple regulatory reference changes that can be implemented under 10 
CFR 50.54(q).

2.0 Discussion

    On September 19, 1997 (ADAMS Legacy Accession No. 9709240386), CEC 
requested an exemption from the provisions of 10 CFR 50.54(q) that 
required emergency plans to meet all of the standards of 10 CFR 
50.47(b) and all of the requirements of appendix E to 10 CFR part 50 so 
that the licensee would have to meet only certain EP standards and 
requirements. Additionally, in a letter dated September 19, 1997 (ADAMS 
Legacy Accession No. 9709240383), CEC requested approval of a proposed 
BRP Defueled Emergency Plan (DEP) that proposed to meet those limited 
standards and requirements.
    The NRC approved the requested exemption and the BRP DEP on 
September 30, 1998 (ADAMS Legacy Accession No. 9810080019). The safety 
evaluation report (SER) established EP requirements for BRP as 
documented in the DEP. The NRC staff (staff) concluded that the 
licensee's emergency plan was acceptable in view of the greatly reduced 
offsite radiological consequences associated with the decommissioning 
plant status. The staff found that the postulated dose to the general 
public from any reasonably conceivable accident would not exceed the 
U.S. Environmental Protection Agency (EPA) Protective Action Guides 
(PAGs), and for the bounding accident, the length of time available to 
respond to a loss of spent fuel cooling or reduction in water level 
gave confidence that offsite measures for the public could be taken 
without preparation.
    CEC completed moving spent nuclear fuel and Greater-Than-Class-C 
(GTCC) waste into dry storage at the BRP ISFSI in March of 2003. On 
September 9, 2004, CEC submitted a request for approval of the BPR 
Emergency Plan to reflect that only an ISFSI remained at the site 
(ADAMS Accession No. ML042530611). The NRC approved the BRP ISFSI 
Emergency Plan on October 13, 2005 (ADAMS Accession No. ML052690042). 
The NRC staff concluded that the BRP ISFSI Emergency Plan met the 
emergency planning requirements contained in 10 CFR part 72 for an 
ISFSI not located on the site of an operating nuclear power reactor, 
and thus provided for an acceptable level of emergency preparedness. 
Since this approval, BRP has not requested nor received substantive 
exemptions from emergency planning requirements.
    Revision 4 of the BRP ISFSI Emergency Plan, dated September 9, 2008 
(Reference 13), reflects the current conditions, where only the ISFSI 
and its related support systems, structures, and components remain.
    With the EP Final Rule, several requirements in 10 CFR part 50 were 
modified or added, including changes in Sec. Sec.  50.47, 50.54, and 
appendix E. The EP Final Rule codified certain voluntary protective 
measures contained in NRC Bulletin 2005-02, ``Emergency Preparedness 
and Response Actions for Security-Based Events,'' and generically 
applicable requirements similar to those previously imposed by NRC 
Order EA-02-026, ``Order for Interim Safeguards and Security 
Compensatory Measures,'' dated February 25, 2002.
    In addition, the EP Final Rule amended other licensee emergency 
plan requirements to: (1) Enhance the ability of licensees in preparing 
for and in taking certain protective actions in the event of a 
radiological emergency; (2) address, in part, security issues 
identified after the terrorist events of September 11, 2001; (3) 
clarify regulations to effect consistent emergency plan implementation 
among licensees; and (4) modify certain EP requirements to be more 
effective and efficient. However, the EP Final Rule was only an 
enhancement to the NRC's regulations and was not necessary for adequate 
protection. On page 72563 of the Federal Register notice for the EP 
Final Rule, the Commission ``determined that the existing regulatory 
structure ensures adequate protection of public health and safety and 
common defense and security.''

3.0 Regulatory Evaluation

    In the Final Rule for Storage of Spent Fuel in NRC-Approved Storage 
Casks at Power Reactor Sites (55 FR 29181; July 18, 1990), the NRC 
amended its regulations to provide for the storage of spent nuclear 
fuel under a general license on the site of any nuclear power reactor. 
In its Statement of Considerations (SOC) for the Final Rule

[[Page 61403]]

(55 FR 29185), the Commission responded to comments related to 
emergency preparedness for spent fuel dry storage, stating, ``The new 
10 CFR 72.32(c) . . . states that, `For an ISFSI that is located on the 
site of a nuclear power reactor licensed for operation by the 
Commission, the emergency plan required by 10 CFR 50.47 shall be deemed 
to satisfy the requirements of this Section.' One condition of the 
general license is that the reactor licensee must review the reactor 
emergency plan and modify it as necessary to cover dry cask storage and 
related activities. If the emergency plan is in compliance with 10 CFR 
50.47, then it is in compliance with the Commission's regulations with 
respect to dry cask storage.''
    In the SOC for the Final Rule for EP requirements for ISFSIs and 
Monitored Retrievable Storage Installation (MRS) (60 FR 32430; June 22, 
1995), the Commission stated, in part, that ``current reactor emergency 
plans cover all at-or near reactor ISFSI's. An ISFSI that is to be 
licensed for a stand-alone operation will need an emergency plan 
established in accordance with the requirements in this rulemaking'' 
(60 FR 32431). The Commission responded to comments (60 FR 32435) 
concerning offsite emergency planning for ISFSIs or an MRS and 
concluded that ``the offsite consequences of potential accidents at an 
ISFSI or a MRS would not warrant establishing Emergency Planning 
Zones.''
    As part of the review for ENO's current exemption request, the 
staff also used the EP regulations in 10 CFR 72.32 and Spent Fuel 
Project Office Interim Staff Guidance (ISG)--16, ``Emergency 
Planning,'' (ADAMS Accession No. ML003724570) as references to ensure 
consistency between specific-licensed and general-licensed ISFSIs.

4.0 Technical Evaluation

    Pursuant to 10 CFR 50.12, the Commission may, upon application by 
any interested person or upon its own initiative, grant exemptions from 
the requirements of 10 CFR part 50 when: (1) The exemptions are 
authorized by law, will not present an undue risk to public health or 
safety, and are consistent with the common defense and security; and 
(2) when special circumstances are present. The staff reviewed this 
request to determine whether the specific exemptions should be granted, 
and the staff evaluation (SE) is provided in its letter to ENO, dated 
September 26, 2013 (ADAMS Accession No. ML13268A501). After evaluating 
the exemption requests, the staff determined that the ENO should be 
granted the exemptions detailed in the SE.
    The NRC has found that the ENO meets the criteria for an exemption 
in 10 CFR 50.12. The NRC has determined that granting the exemption 
will not result in a violation of the Atomic Energy Act of 1954, as 
amended, or the Commission's regulations. Therefore, the exemption is 
authorized by law.
    As noted in Section 2.0, ``Discussion,'' above, the ENO's 
compliance with the EP requirements that were in effect before the 
effective date of the EP Final Rule demonstrated reasonable assurance 
of adequate protection of public health and safety and common defense 
and security. In its SE, the NRC staff explains that the ENO's 
implementation of its Emergency Plan, with the exemptions, will 
continue to provide this reasonable assurance of adequate protection. 
Thus, granting the exemptions will not present an undue risk to public 
health or safety and is not inconsistent with the common defense and 
security.
    For the Commission to grant an exemption, special circumstances 
must exist. Under 10 CFR 50.12(a)(2)(ii), special circumstances are 
present when ``[a]pplication of the regulation in the particular 
circumstances would not serve the underlying purpose of the rule or is 
not necessary to achieve the underlying purpose of the rule.'' These 
special circumstances exist here. The NRC has determined that the ENO's 
compliance with the regulations that the staff describes in its SE is 
not necessary for the licensee to demonstrate that, under its emergency 
plan, there is reasonable assurance that adequate protective measures 
can and will be taken in the event of a radiological emergency. 
Consequently, special circumstances are present because requiring the 
ENO to comply with the regulations that the staff describes in its SE 
is not necessary to achieve the underlying purpose of the EP 
regulations.

5.0 Evironmental Assessment (EA)

    The NRC staff also considered in the review of this exemption 
request whether there would be any significant environmental impacts 
associated with the exemption. For this proposed action, the NRC staff 
performed an environmental assessment pursuant to 10 CFR 51.30. The 
proposed action is the approval of a request to exempt the applicant 
from certain requirements of 10 CFR 50.47(b) and portions of 10 CFR 
part 50, appendix E.
    The environmental assessment concluded that the proposed action 
would not significantly impact the quality of the human environment. 
The NRC staff concludes that the proposed action will not result in any 
changes in the types or amounts of any radiological effluents that may 
be released offsite, and there is no significant increase in 
occupational or public radiation exposure because of the proposed 
action. The Environmental Assessment and the Finding of No Significant 
Impact was published on September 24, 2013 (78 FR 58570).

6.0 Conclusion

    The NRC concludes that the licensee's request for an exemption from 
certain requirements of 10 CFR 50.47(b) and 10 CFR part 50, appendix E, 
section IV as specified in this SE is acceptable in view of the greatly 
reduced offsite radiological consequences associated with the ISFSI.
    The BRP ISFSI Emergency Plan has been reviewed against the 
acceptance criteria included in 10 CFR 50.47, appendix E to 10 CFR part 
50, 10 CFR 72.32 and Interim Staff Guidance--16. The review considered 
the ISFSI and the low likelihood of any credible accident resulting in 
radiological releases requiring offsite protective measures. These 
evaluations were supported by the previously documented licensee and 
staff accident analyses. The staff concludes that: The BRP ISFSI 
Emergency Plan provides: (1) An adequate basis for an acceptable state 
of emergency preparedness; and (2) in conjunction with arrangements 
made with offsite response agencies, reasonable assurance that adequate 
protective measures can and will be taken in the event of a 
radiological emergency at the BRP facility.
    The NRC has determined that pursuant to 10 CFR 50.12, the 
exemptions described in the SE are authorized by law, will not endanger 
life or property or the common defense and security, and are otherwise 
in the public interest, and special circumstances are present.
    This exemption is effective upon issuance.

    Dated at Rockville, Maryland, this 26th day of September, 2013.

    For the Nuclear Regulatory Commission.
Anthony H. Hsia,
Deputy Director, Division of Spent Fuel Storage and Transportation, 
Office of Nuclear Material Safety and Safeguards.
[FR Doc. 2013-24302 Filed 10-2-13; 8:45 am]
BILLING CODE 7590-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.