Entergy Nuclear Operations, Inc.; Big Rock Point; Independent Spent Fuel Storage Installation, 61401-61403 [2013-24302]
Download as PDF
tkelley on DSK3SPTVN1PROD with NOTICES
Federal Register / Vol. 78, No. 192 / Thursday, October 3, 2013 / Notices
Petitioner also asked that the NRC
commit to verifying, during the license
renewal period, Entergy’s
implementation through routine
baseline inspections and to a timely
upgrade of the regulatory guidance for
maintaining cable qualification and the
verification that the cables can perform
their design functions.
As the basis of the request, the
Petitioner asserted, in part, the
following concerns:
• The NRC regulations require that
plant owners ensure that electrical
wiring is qualified to perform in the
environmental conditions experienced
during normal operation and during
accidents. Pilgrim has no program
today, as required by NRC regulations,
to ensure operability of the submerged
and/or wetted wires.
• Most electrical cables at Pilgrim
have been exposed to significant
moisture over the 40 years since their
initial construction. The wires, and
possibly the connections and splices
inside conduits, are designed to operate
properly only in a dry environment and
are not designed to operate in a moist
or wet environment. Thus, there is no
assurance that these electrical cables
will not fail if they are wet, submerged,
or previously exposed to moisture.
• Wires degrade with age, and the
oldest wires are most susceptible to
degradation. Pilgrim is one of the oldest
operating commercial reactors in the
country, and the majority of the
conduits and wires at Pilgrim were
installed during the initial construction.
There are no existing methods to ensure
operability, short of visual inspection or
replacing cables with ones designed to
operate in a wet or submerged
environment.
• As identified in several pertinent
sections of Pilgrim’s license renewal
application and safety evaluation report,
Pilgrim’s aging management program,
for the period 2012–2032, is insufficient
and does not provide reasonable
assurance to the public. The Petitioner
further stated that compliance with the
NRC’s regulations is intended to provide
reasonable assurance that an electrical
wire failure will neither initiate an
accident nor make an accident more
severe. The Petitioner also noted that
Pilgrim has a long history of cables
being submerged and/or wetted with no
verification of the long-term operability
that provides reasonable assurance of
continued operation of these cables.
The NRC sent a copy of the proposed
Director’s Decision to the petitioner and
the licensee for comment on March 20,
2013. The Petitioner and the licensee
were asked to provide comments within
30 days on any part of the proposed
VerDate Mar<15>2010
18:29 Oct 02, 2013
Jkt 232001
Director’s Decision that was considered
to be erroneous or any issues in the
petition that were not addressed.
Comments were received from the
Petitioner and are addressed in an
attachment to the final Director’s
Decision.
The Director of the Office of Nuclear
Reactor Regulation denied the
petitioner’s request to issue a Demand
for Information to require Entergy to
demonstrate that all inaccessible cables
at Pilgrim are capable of performing
their functions. The Office has also
denied the Petitioner’s request for the
NRC to take certain actions to
demonstrate that accessible and
inaccessible cables can perform their
design functions. These actions
included requests for NRC to certify that
(1) All cables have been identified as to
their location, age, and repair history,
(2) all cables are monitored by the
Licensee prior to continued operation,
and (3) the Licensee’s monitoring
program incorporates at a minimum,
recommendations for certain aging
management guidelines and NRC
generic guidance. The NRC staff has
determined that the Licensee’s programs
for cable condition monitoring and
managing aging effects of inaccessible
power cables have been adequately
implemented, to the extent that there is
reasonable assurance that cables subject
to moisture will be adequately managed
during the period of extended operation.
The Director’s Decision (DD–13–02)
under part 2.206 of Title 10 of the Code
of Federal Regulations, ‘‘Requests for
Action under This Subpart,’’ explains
the reasons for this decision. The
complete text is available in ADAMS
under Accession No. ML13255A189 for
inspection at the Commission’s Public
Document Room located at One White
Flint North, Public File Area 01 F21,
11555 Rockville Pike (first floor),
Rockville, Maryland, and online in the
NRC library at https://www.nrc.gov/
reading-rm.html.
The NRC will file a copy of the
Director’s Decision with the Secretary of
the Commission for the Commission’s
review in accordance with 10 CFR
2.206. As a provision of this regulation,
the Director’s Decision will constitute
the final action of the Commission 25
days after the date of the Decision
unless the Commission, on its own
motion, institutes a review of the
Director’s Decision in that time.
Dated at Rockville, Maryland, this 26th day
of September 2013.
PO 00000
Frm 00081
Fmt 4703
Sfmt 4703
61401
For the Nuclear Regulatory Commission.
Eric J. Leeds,
Director, Office of Nuclear Reactor
Regulation.
[FR Doc. 2013–24272 Filed 10–2–13; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 50–155; 72–43 and NRC–2013–
0218]
Entergy Nuclear Operations, Inc.; Big
Rock Point; Independent Spent Fuel
Storage Installation
Nuclear Regulatory
Commission.
ACTION: Exemption; issuance.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is issuing an
exemption in response to a request
submitted by Entergy Nuclear
Operations, Inc. (ENO) on June 20, 2012,
for the Big Rock Point (BRP)
Independent Spent Fuel Storage
Installation (ISFSI).
ADDRESSES: Please refer to Docket ID
NRC–2013–0218 when contacting the
NRC about the availability of
information regarding this document.
You may access publicly-available
information related to this action by the
following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2013–0218. Address
question about NRC dockets to Carol
Gallagher; telephone: 301–287–3422;
email: Carol.Gallagher@nrc.gov. For
technical questions, contact the
individual listed in the FOR FURTHER
INFORMATION CONTACT section of this
document.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may access publicly
available documents online in the NRC
Library at https://www.nrc.gov/readingrm/adams.html. To begin the search,
select ‘‘ADAMS Public Documents’’ and
then select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced in this document
(if that document is available in
ADAMS) is provided the first time that
a document is referenced.
• NRC’s PDC: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
SUMMARY:
E:\FR\FM\03OCN1.SGM
03OCN1
61402
Federal Register / Vol. 78, No. 192 / Thursday, October 3, 2013 / Notices
Dr.
Pamela Longmire, Office of Nuclear
Material Safety and Safeguards, U.S.
Nuclear Regulatory Commission,
Washington, DC 20555–0001; telephone:
301–287–0829; email:
Pamela.Longmire@nrc.gov.
tkelley on DSK3SPTVN1PROD with NOTICES
FOR FURTHER INFORMATION CONTACT:
1.0 Introduction
On November 23, 2011 (76 FR 72560),
the NRC issued a final rule (EP Final
Rule) modifying or adding certain
emergency planning (EP) requirements
in §§ 50.47, 50.54, and appendix E of
Title 10 of the Code of Federal
Regulations (10 CFR). The EP Final Rule
was effective on December 23, 2011,
with specific implementation dates for
each of the rule changes.
Entergy Nuclear Operations, Inc.
(ENO) is the holder of Facility Operating
License DPR–6 for the BRP facility. The
license, issued pursuant to the Atomic
Energy Act of 1954, as amended, and 10
CFR part 50, allows ENO to possess and
store spent nuclear fuel at the
permanently shutdown and
decommissioned facility under the
provision of 10 CFR part 72, subpart K,
‘‘General License for Storage of Spent
Fuel at Power Reactor Sites.’’ In a letter
dated June 26, 1997 (ADAMS Legacy
Accession No. 9707030167), Consumers
Energy Company (CEC) informed the
NRC that the BRP facility had
permanently ceased power operations.
In a letter dated September 23, 1997
(ADAMS Legacy Accession No.
9709300363), CEC informed the NRC
that it had permanently moved the fuel
from the reactor to the spent fuel pool.
After ceasing operations at the reactor,
CEC began transferring spent nuclear
fuel from the spent fuel pool to the BRP
ISFSI for long term dry storage. As
discussed in letters dated September 8,
2005, and November 16, 2006 (ADAMS
Accession Nos. ML052550366 and
ML063260085, respectively), these
activities were completed in 2003, and
final decommissioning of the reactor
site was completed in 2006. The BRP
ISFSI is a stand-alone ISFSI located on
approximately 30 acres in Charlevoix
County, on the northern shore of
Michigan’s Lower Peninsula. In a letter
dated July 30, 2007 (ADAMS Accession
No. ML072220219), ENO applied for an
order approving indirect transfer of
control of licenses for BRP. By letter
dated July 28, 2008 (ADAMS Accession
No. ML080940528), the NRC consented
to the proposal.
On June 20, 2012, ENO submitted a
letter, ‘‘Request for Exemption from
Emergency Planning and Preparedness
Requirements’’ (ADAMS Accession No.
ML12173A066), requesting exemption
from specific emergency planning
VerDate Mar<15>2010
18:29 Oct 02, 2013
Jkt 232001
requirements of 10 CFR 50.47 and
appendix E to 10 CFR part 50 for the
BRP ISFSI.
ENO states that this exemption
request and its impact on the
corresponding emergency plan: (1) Is
authorized by law; (2) will not present
an undue risk to the public health and
safety; and (3) is consistent with the
common defense and security in
accordance with 10 CFR 50.12. ENO
states that its intent in submitting this
exemption request is to maintain the
regulatory structure in place prior to the
issuance of the EP Final Rule and,
therefore, does not propose any changes
to its emergency plan or implementing
procedures other than simple regulatory
reference changes that can be
implemented under 10 CFR 50.54(q).
2.0 Discussion
On September 19, 1997 (ADAMS
Legacy Accession No. 9709240386), CEC
requested an exemption from the
provisions of 10 CFR 50.54(q) that
required emergency plans to meet all of
the standards of 10 CFR 50.47(b) and all
of the requirements of appendix E to 10
CFR part 50 so that the licensee would
have to meet only certain EP standards
and requirements. Additionally, in a
letter dated September 19, 1997
(ADAMS Legacy Accession No.
9709240383), CEC requested approval of
a proposed BRP Defueled Emergency
Plan (DEP) that proposed to meet those
limited standards and requirements.
The NRC approved the requested
exemption and the BRP DEP on
September 30, 1998 (ADAMS Legacy
Accession No. 9810080019). The safety
evaluation report (SER) established EP
requirements for BRP as documented in
the DEP. The NRC staff (staff) concluded
that the licensee’s emergency plan was
acceptable in view of the greatly
reduced offsite radiological
consequences associated with the
decommissioning plant status. The staff
found that the postulated dose to the
general public from any reasonably
conceivable accident would not exceed
the U.S. Environmental Protection
Agency (EPA) Protective Action Guides
(PAGs), and for the bounding accident,
the length of time available to respond
to a loss of spent fuel cooling or
reduction in water level gave confidence
that offsite measures for the public
could be taken without preparation.
CEC completed moving spent nuclear
fuel and Greater-Than-Class-C (GTCC)
waste into dry storage at the BRP ISFSI
in March of 2003. On September 9,
2004, CEC submitted a request for
approval of the BPR Emergency Plan to
reflect that only an ISFSI remained at
the site (ADAMS Accession No.
PO 00000
Frm 00082
Fmt 4703
Sfmt 4703
ML042530611). The NRC approved the
BRP ISFSI Emergency Plan on October
13, 2005 (ADAMS Accession No.
ML052690042). The NRC staff
concluded that the BRP ISFSI
Emergency Plan met the emergency
planning requirements contained in 10
CFR part 72 for an ISFSI not located on
the site of an operating nuclear power
reactor, and thus provided for an
acceptable level of emergency
preparedness. Since this approval, BRP
has not requested nor received
substantive exemptions from emergency
planning requirements.
Revision 4 of the BRP ISFSI
Emergency Plan, dated September 9,
2008 (Reference 13), reflects the current
conditions, where only the ISFSI and its
related support systems, structures, and
components remain.
With the EP Final Rule, several
requirements in 10 CFR part 50 were
modified or added, including changes in
§§ 50.47, 50.54, and appendix E. The EP
Final Rule codified certain voluntary
protective measures contained in NRC
Bulletin 2005–02, ‘‘Emergency
Preparedness and Response Actions for
Security-Based Events,’’ and generically
applicable requirements similar to those
previously imposed by NRC Order EA–
02–026, ‘‘Order for Interim Safeguards
and Security Compensatory Measures,’’
dated February 25, 2002.
In addition, the EP Final Rule
amended other licensee emergency plan
requirements to: (1) Enhance the ability
of licensees in preparing for and in
taking certain protective actions in the
event of a radiological emergency; (2)
address, in part, security issues
identified after the terrorist events of
September 11, 2001; (3) clarify
regulations to effect consistent
emergency plan implementation among
licensees; and (4) modify certain EP
requirements to be more effective and
efficient. However, the EP Final Rule
was only an enhancement to the NRC’s
regulations and was not necessary for
adequate protection. On page 72563 of
the Federal Register notice for the EP
Final Rule, the Commission
‘‘determined that the existing regulatory
structure ensures adequate protection of
public health and safety and common
defense and security.’’
3.0 Regulatory Evaluation
In the Final Rule for Storage of Spent
Fuel in NRC-Approved Storage Casks at
Power Reactor Sites (55 FR 29181; July
18, 1990), the NRC amended its
regulations to provide for the storage of
spent nuclear fuel under a general
license on the site of any nuclear power
reactor. In its Statement of
Considerations (SOC) for the Final Rule
E:\FR\FM\03OCN1.SGM
03OCN1
Federal Register / Vol. 78, No. 192 / Thursday, October 3, 2013 / Notices
tkelley on DSK3SPTVN1PROD with NOTICES
(55 FR 29185), the Commission
responded to comments related to
emergency preparedness for spent fuel
dry storage, stating, ‘‘The new 10 CFR
72.32(c) . . . states that, ‘For an ISFSI
that is located on the site of a nuclear
power reactor licensed for operation by
the Commission, the emergency plan
required by 10 CFR 50.47 shall be
deemed to satisfy the requirements of
this Section.’ One condition of the
general license is that the reactor
licensee must review the reactor
emergency plan and modify it as
necessary to cover dry cask storage and
related activities. If the emergency plan
is in compliance with 10 CFR 50.47,
then it is in compliance with the
Commission’s regulations with respect
to dry cask storage.’’
In the SOC for the Final Rule for EP
requirements for ISFSIs and Monitored
Retrievable Storage Installation (MRS)
(60 FR 32430; June 22, 1995), the
Commission stated, in part, that
‘‘current reactor emergency plans cover
all at-or near reactor ISFSI’s. An ISFSI
that is to be licensed for a stand-alone
operation will need an emergency plan
established in accordance with the
requirements in this rulemaking’’ (60 FR
32431). The Commission responded to
comments (60 FR 32435) concerning
offsite emergency planning for ISFSIs or
an MRS and concluded that ‘‘the offsite
consequences of potential accidents at
an ISFSI or a MRS would not warrant
establishing Emergency Planning
Zones.’’
As part of the review for ENO’s
current exemption request, the staff also
used the EP regulations in 10 CFR 72.32
and Spent Fuel Project Office Interim
Staff Guidance (ISG)—16, ‘‘Emergency
Planning,’’ (ADAMS Accession No.
ML003724570) as references to ensure
consistency between specific-licensed
and general-licensed ISFSIs.
4.0 Technical Evaluation
Pursuant to 10 CFR 50.12, the
Commission may, upon application by
any interested person or upon its own
initiative, grant exemptions from the
requirements of 10 CFR part 50 when:
(1) The exemptions are authorized by
law, will not present an undue risk to
public health or safety, and are
consistent with the common defense
and security; and (2) when special
circumstances are present. The staff
reviewed this request to determine
whether the specific exemptions should
be granted, and the staff evaluation (SE)
is provided in its letter to ENO, dated
September 26, 2013 (ADAMS Accession
No. ML13268A501). After evaluating the
exemption requests, the staff
determined that the ENO should be
VerDate Mar<15>2010
18:29 Oct 02, 2013
Jkt 232001
granted the exemptions detailed in the
SE.
The NRC has found that the ENO
meets the criteria for an exemption in 10
CFR 50.12. The NRC has determined
that granting the exemption will not
result in a violation of the Atomic
Energy Act of 1954, as amended, or the
Commission’s regulations. Therefore,
the exemption is authorized by law.
As noted in Section 2.0, ‘‘Discussion,’’
above, the ENO’s compliance with the
EP requirements that were in effect
before the effective date of the EP Final
Rule demonstrated reasonable assurance
of adequate protection of public health
and safety and common defense and
security. In its SE, the NRC staff
explains that the ENO’s implementation
of its Emergency Plan, with the
exemptions, will continue to provide
this reasonable assurance of adequate
protection. Thus, granting the
exemptions will not present an undue
risk to public health or safety and is not
inconsistent with the common defense
and security.
For the Commission to grant an
exemption, special circumstances must
exist. Under 10 CFR 50.12(a)(2)(ii),
special circumstances are present when
‘‘[a]pplication of the regulation in the
particular circumstances would not
serve the underlying purpose of the rule
or is not necessary to achieve the
underlying purpose of the rule.’’ These
special circumstances exist here. The
NRC has determined that the ENO’s
compliance with the regulations that the
staff describes in its SE is not necessary
for the licensee to demonstrate that,
under its emergency plan, there is
reasonable assurance that adequate
protective measures can and will be
taken in the event of a radiological
emergency. Consequently, special
circumstances are present because
requiring the ENO to comply with the
regulations that the staff describes in its
SE is not necessary to achieve the
underlying purpose of the EP
regulations.
5.0 Evironmental Assessment (EA)
The NRC staff also considered in the
review of this exemption request
whether there would be any significant
environmental impacts associated with
the exemption. For this proposed action,
the NRC staff performed an
environmental assessment pursuant to
10 CFR 51.30. The proposed action is
the approval of a request to exempt the
applicant from certain requirements of
10 CFR 50.47(b) and portions of 10 CFR
part 50, appendix E.
The environmental assessment
concluded that the proposed action
would not significantly impact the
PO 00000
Frm 00083
Fmt 4703
Sfmt 9990
61403
quality of the human environment. The
NRC staff concludes that the proposed
action will not result in any changes in
the types or amounts of any radiological
effluents that may be released offsite,
and there is no significant increase in
occupational or public radiation
exposure because of the proposed
action. The Environmental Assessment
and the Finding of No Significant
Impact was published on September 24,
2013 (78 FR 58570).
6.0
Conclusion
The NRC concludes that the licensee’s
request for an exemption from certain
requirements of 10 CFR 50.47(b) and 10
CFR part 50, appendix E, section IV as
specified in this SE is acceptable in
view of the greatly reduced offsite
radiological consequences associated
with the ISFSI.
The BRP ISFSI Emergency Plan has
been reviewed against the acceptance
criteria included in 10 CFR 50.47,
appendix E to 10 CFR part 50, 10 CFR
72.32 and Interim Staff Guidance—16.
The review considered the ISFSI and
the low likelihood of any credible
accident resulting in radiological
releases requiring offsite protective
measures. These evaluations were
supported by the previously
documented licensee and staff accident
analyses. The staff concludes that: The
BRP ISFSI Emergency Plan provides: (1)
An adequate basis for an acceptable
state of emergency preparedness; and (2)
in conjunction with arrangements made
with offsite response agencies,
reasonable assurance that adequate
protective measures can and will be
taken in the event of a radiological
emergency at the BRP facility.
The NRC has determined that
pursuant to 10 CFR 50.12, the
exemptions described in the SE are
authorized by law, will not endanger
life or property or the common defense
and security, and are otherwise in the
public interest, and special
circumstances are present.
This exemption is effective upon
issuance.
Dated at Rockville, Maryland, this 26th day
of September, 2013.
For the Nuclear Regulatory Commission.
Anthony H. Hsia,
Deputy Director, Division of Spent Fuel
Storage and Transportation, Office of Nuclear
Material Safety and Safeguards.
[FR Doc. 2013–24302 Filed 10–2–13; 8:45 am]
BILLING CODE 7590–01–P
E:\FR\FM\03OCN1.SGM
03OCN1
Agencies
[Federal Register Volume 78, Number 192 (Thursday, October 3, 2013)]
[Notices]
[Pages 61401-61403]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-24302]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-155; 72-43 and NRC-2013-0218]
Entergy Nuclear Operations, Inc.; Big Rock Point; Independent
Spent Fuel Storage Installation
AGENCY: Nuclear Regulatory Commission.
ACTION: Exemption; issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing an
exemption in response to a request submitted by Entergy Nuclear
Operations, Inc. (ENO) on June 20, 2012, for the Big Rock Point (BRP)
Independent Spent Fuel Storage Installation (ISFSI).
ADDRESSES: Please refer to Docket ID NRC-2013-0218 when contacting the
NRC about the availability of information regarding this document. You
may access publicly-available information related to this action by the
following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2013-0218. Address
question about NRC dockets to Carol Gallagher; telephone: 301-287-3422;
email: Carol.Gallagher@nrc.gov. For technical questions, contact the
individual listed in the FOR FURTHER INFORMATION CONTACT section of
this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may access publicly available documents online in the NRC
Library at https://www.nrc.gov/reading-rm/adams.html. To begin the
search, select ``ADAMS Public Documents'' and then select ``Begin Web-
based ADAMS Search.'' For problems with ADAMS, please contact the NRC's
Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-
4737, or by email to pdr.resource@nrc.gov. The ADAMS accession number
for each document referenced in this document (if that document is
available in ADAMS) is provided the first time that a document is
referenced.
NRC's PDC: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
[[Page 61402]]
FOR FURTHER INFORMATION CONTACT: Dr. Pamela Longmire, Office of Nuclear
Material Safety and Safeguards, U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001; telephone: 301-287-0829; email:
Pamela.Longmire@nrc.gov.
1.0 Introduction
On November 23, 2011 (76 FR 72560), the NRC issued a final rule (EP
Final Rule) modifying or adding certain emergency planning (EP)
requirements in Sec. Sec. 50.47, 50.54, and appendix E of Title 10 of
the Code of Federal Regulations (10 CFR). The EP Final Rule was
effective on December 23, 2011, with specific implementation dates for
each of the rule changes.
Entergy Nuclear Operations, Inc. (ENO) is the holder of Facility
Operating License DPR-6 for the BRP facility. The license, issued
pursuant to the Atomic Energy Act of 1954, as amended, and 10 CFR part
50, allows ENO to possess and store spent nuclear fuel at the
permanently shutdown and decommissioned facility under the provision of
10 CFR part 72, subpart K, ``General License for Storage of Spent Fuel
at Power Reactor Sites.'' In a letter dated June 26, 1997 (ADAMS Legacy
Accession No. 9707030167), Consumers Energy Company (CEC) informed the
NRC that the BRP facility had permanently ceased power operations. In a
letter dated September 23, 1997 (ADAMS Legacy Accession No.
9709300363), CEC informed the NRC that it had permanently moved the
fuel from the reactor to the spent fuel pool.
After ceasing operations at the reactor, CEC began transferring
spent nuclear fuel from the spent fuel pool to the BRP ISFSI for long
term dry storage. As discussed in letters dated September 8, 2005, and
November 16, 2006 (ADAMS Accession Nos. ML052550366 and ML063260085,
respectively), these activities were completed in 2003, and final
decommissioning of the reactor site was completed in 2006. The BRP
ISFSI is a stand-alone ISFSI located on approximately 30 acres in
Charlevoix County, on the northern shore of Michigan's Lower Peninsula.
In a letter dated July 30, 2007 (ADAMS Accession No. ML072220219), ENO
applied for an order approving indirect transfer of control of licenses
for BRP. By letter dated July 28, 2008 (ADAMS Accession No.
ML080940528), the NRC consented to the proposal.
On June 20, 2012, ENO submitted a letter, ``Request for Exemption
from Emergency Planning and Preparedness Requirements'' (ADAMS
Accession No. ML12173A066), requesting exemption from specific
emergency planning requirements of 10 CFR 50.47 and appendix E to 10
CFR part 50 for the BRP ISFSI.
ENO states that this exemption request and its impact on the
corresponding emergency plan: (1) Is authorized by law; (2) will not
present an undue risk to the public health and safety; and (3) is
consistent with the common defense and security in accordance with 10
CFR 50.12. ENO states that its intent in submitting this exemption
request is to maintain the regulatory structure in place prior to the
issuance of the EP Final Rule and, therefore, does not propose any
changes to its emergency plan or implementing procedures other than
simple regulatory reference changes that can be implemented under 10
CFR 50.54(q).
2.0 Discussion
On September 19, 1997 (ADAMS Legacy Accession No. 9709240386), CEC
requested an exemption from the provisions of 10 CFR 50.54(q) that
required emergency plans to meet all of the standards of 10 CFR
50.47(b) and all of the requirements of appendix E to 10 CFR part 50 so
that the licensee would have to meet only certain EP standards and
requirements. Additionally, in a letter dated September 19, 1997 (ADAMS
Legacy Accession No. 9709240383), CEC requested approval of a proposed
BRP Defueled Emergency Plan (DEP) that proposed to meet those limited
standards and requirements.
The NRC approved the requested exemption and the BRP DEP on
September 30, 1998 (ADAMS Legacy Accession No. 9810080019). The safety
evaluation report (SER) established EP requirements for BRP as
documented in the DEP. The NRC staff (staff) concluded that the
licensee's emergency plan was acceptable in view of the greatly reduced
offsite radiological consequences associated with the decommissioning
plant status. The staff found that the postulated dose to the general
public from any reasonably conceivable accident would not exceed the
U.S. Environmental Protection Agency (EPA) Protective Action Guides
(PAGs), and for the bounding accident, the length of time available to
respond to a loss of spent fuel cooling or reduction in water level
gave confidence that offsite measures for the public could be taken
without preparation.
CEC completed moving spent nuclear fuel and Greater-Than-Class-C
(GTCC) waste into dry storage at the BRP ISFSI in March of 2003. On
September 9, 2004, CEC submitted a request for approval of the BPR
Emergency Plan to reflect that only an ISFSI remained at the site
(ADAMS Accession No. ML042530611). The NRC approved the BRP ISFSI
Emergency Plan on October 13, 2005 (ADAMS Accession No. ML052690042).
The NRC staff concluded that the BRP ISFSI Emergency Plan met the
emergency planning requirements contained in 10 CFR part 72 for an
ISFSI not located on the site of an operating nuclear power reactor,
and thus provided for an acceptable level of emergency preparedness.
Since this approval, BRP has not requested nor received substantive
exemptions from emergency planning requirements.
Revision 4 of the BRP ISFSI Emergency Plan, dated September 9, 2008
(Reference 13), reflects the current conditions, where only the ISFSI
and its related support systems, structures, and components remain.
With the EP Final Rule, several requirements in 10 CFR part 50 were
modified or added, including changes in Sec. Sec. 50.47, 50.54, and
appendix E. The EP Final Rule codified certain voluntary protective
measures contained in NRC Bulletin 2005-02, ``Emergency Preparedness
and Response Actions for Security-Based Events,'' and generically
applicable requirements similar to those previously imposed by NRC
Order EA-02-026, ``Order for Interim Safeguards and Security
Compensatory Measures,'' dated February 25, 2002.
In addition, the EP Final Rule amended other licensee emergency
plan requirements to: (1) Enhance the ability of licensees in preparing
for and in taking certain protective actions in the event of a
radiological emergency; (2) address, in part, security issues
identified after the terrorist events of September 11, 2001; (3)
clarify regulations to effect consistent emergency plan implementation
among licensees; and (4) modify certain EP requirements to be more
effective and efficient. However, the EP Final Rule was only an
enhancement to the NRC's regulations and was not necessary for adequate
protection. On page 72563 of the Federal Register notice for the EP
Final Rule, the Commission ``determined that the existing regulatory
structure ensures adequate protection of public health and safety and
common defense and security.''
3.0 Regulatory Evaluation
In the Final Rule for Storage of Spent Fuel in NRC-Approved Storage
Casks at Power Reactor Sites (55 FR 29181; July 18, 1990), the NRC
amended its regulations to provide for the storage of spent nuclear
fuel under a general license on the site of any nuclear power reactor.
In its Statement of Considerations (SOC) for the Final Rule
[[Page 61403]]
(55 FR 29185), the Commission responded to comments related to
emergency preparedness for spent fuel dry storage, stating, ``The new
10 CFR 72.32(c) . . . states that, `For an ISFSI that is located on the
site of a nuclear power reactor licensed for operation by the
Commission, the emergency plan required by 10 CFR 50.47 shall be deemed
to satisfy the requirements of this Section.' One condition of the
general license is that the reactor licensee must review the reactor
emergency plan and modify it as necessary to cover dry cask storage and
related activities. If the emergency plan is in compliance with 10 CFR
50.47, then it is in compliance with the Commission's regulations with
respect to dry cask storage.''
In the SOC for the Final Rule for EP requirements for ISFSIs and
Monitored Retrievable Storage Installation (MRS) (60 FR 32430; June 22,
1995), the Commission stated, in part, that ``current reactor emergency
plans cover all at-or near reactor ISFSI's. An ISFSI that is to be
licensed for a stand-alone operation will need an emergency plan
established in accordance with the requirements in this rulemaking''
(60 FR 32431). The Commission responded to comments (60 FR 32435)
concerning offsite emergency planning for ISFSIs or an MRS and
concluded that ``the offsite consequences of potential accidents at an
ISFSI or a MRS would not warrant establishing Emergency Planning
Zones.''
As part of the review for ENO's current exemption request, the
staff also used the EP regulations in 10 CFR 72.32 and Spent Fuel
Project Office Interim Staff Guidance (ISG)--16, ``Emergency
Planning,'' (ADAMS Accession No. ML003724570) as references to ensure
consistency between specific-licensed and general-licensed ISFSIs.
4.0 Technical Evaluation
Pursuant to 10 CFR 50.12, the Commission may, upon application by
any interested person or upon its own initiative, grant exemptions from
the requirements of 10 CFR part 50 when: (1) The exemptions are
authorized by law, will not present an undue risk to public health or
safety, and are consistent with the common defense and security; and
(2) when special circumstances are present. The staff reviewed this
request to determine whether the specific exemptions should be granted,
and the staff evaluation (SE) is provided in its letter to ENO, dated
September 26, 2013 (ADAMS Accession No. ML13268A501). After evaluating
the exemption requests, the staff determined that the ENO should be
granted the exemptions detailed in the SE.
The NRC has found that the ENO meets the criteria for an exemption
in 10 CFR 50.12. The NRC has determined that granting the exemption
will not result in a violation of the Atomic Energy Act of 1954, as
amended, or the Commission's regulations. Therefore, the exemption is
authorized by law.
As noted in Section 2.0, ``Discussion,'' above, the ENO's
compliance with the EP requirements that were in effect before the
effective date of the EP Final Rule demonstrated reasonable assurance
of adequate protection of public health and safety and common defense
and security. In its SE, the NRC staff explains that the ENO's
implementation of its Emergency Plan, with the exemptions, will
continue to provide this reasonable assurance of adequate protection.
Thus, granting the exemptions will not present an undue risk to public
health or safety and is not inconsistent with the common defense and
security.
For the Commission to grant an exemption, special circumstances
must exist. Under 10 CFR 50.12(a)(2)(ii), special circumstances are
present when ``[a]pplication of the regulation in the particular
circumstances would not serve the underlying purpose of the rule or is
not necessary to achieve the underlying purpose of the rule.'' These
special circumstances exist here. The NRC has determined that the ENO's
compliance with the regulations that the staff describes in its SE is
not necessary for the licensee to demonstrate that, under its emergency
plan, there is reasonable assurance that adequate protective measures
can and will be taken in the event of a radiological emergency.
Consequently, special circumstances are present because requiring the
ENO to comply with the regulations that the staff describes in its SE
is not necessary to achieve the underlying purpose of the EP
regulations.
5.0 Evironmental Assessment (EA)
The NRC staff also considered in the review of this exemption
request whether there would be any significant environmental impacts
associated with the exemption. For this proposed action, the NRC staff
performed an environmental assessment pursuant to 10 CFR 51.30. The
proposed action is the approval of a request to exempt the applicant
from certain requirements of 10 CFR 50.47(b) and portions of 10 CFR
part 50, appendix E.
The environmental assessment concluded that the proposed action
would not significantly impact the quality of the human environment.
The NRC staff concludes that the proposed action will not result in any
changes in the types or amounts of any radiological effluents that may
be released offsite, and there is no significant increase in
occupational or public radiation exposure because of the proposed
action. The Environmental Assessment and the Finding of No Significant
Impact was published on September 24, 2013 (78 FR 58570).
6.0 Conclusion
The NRC concludes that the licensee's request for an exemption from
certain requirements of 10 CFR 50.47(b) and 10 CFR part 50, appendix E,
section IV as specified in this SE is acceptable in view of the greatly
reduced offsite radiological consequences associated with the ISFSI.
The BRP ISFSI Emergency Plan has been reviewed against the
acceptance criteria included in 10 CFR 50.47, appendix E to 10 CFR part
50, 10 CFR 72.32 and Interim Staff Guidance--16. The review considered
the ISFSI and the low likelihood of any credible accident resulting in
radiological releases requiring offsite protective measures. These
evaluations were supported by the previously documented licensee and
staff accident analyses. The staff concludes that: The BRP ISFSI
Emergency Plan provides: (1) An adequate basis for an acceptable state
of emergency preparedness; and (2) in conjunction with arrangements
made with offsite response agencies, reasonable assurance that adequate
protective measures can and will be taken in the event of a
radiological emergency at the BRP facility.
The NRC has determined that pursuant to 10 CFR 50.12, the
exemptions described in the SE are authorized by law, will not endanger
life or property or the common defense and security, and are otherwise
in the public interest, and special circumstances are present.
This exemption is effective upon issuance.
Dated at Rockville, Maryland, this 26th day of September, 2013.
For the Nuclear Regulatory Commission.
Anthony H. Hsia,
Deputy Director, Division of Spent Fuel Storage and Transportation,
Office of Nuclear Material Safety and Safeguards.
[FR Doc. 2013-24302 Filed 10-2-13; 8:45 am]
BILLING CODE 7590-01-P