Cleveland National Forest, California, SDG&E Master Special Use Permit and Permit To Construct Power Line Replacement Projects EIR/EIS, 58270-58272 [2013-22904]

Download as PDF emcdonald on DSK67QTVN1PROD with NOTICES 58270 Federal Register / Vol. 78, No. 184 / Monday, September 23, 2013 / Notices about the livestock population and to provide a foundation for possible future studies. The objectives of the study are to: • Provide a baseline description of the U.S. bison industry, including general characteristics of operations, such as inventory, size, and type; • Describe current U.S. bison industry production practices and challenges, including animal identification, confinement and handling, care, and disease testing; • Describe health management and biosecurity practices important for the productivity and health of ranched bison; and • Describe producer-reported occurrence of select health problems and evaluate potentially associated risk factors. The study will consist of a selfadministered questionnaire. APHIS will analyze and organize the information collected into one or more reports. The information collected will be used by APHIS to describe current bison health and management practices, help policymakers and industry make informed decisions, help researchers and private enterprise identify and focus on vital issues related to bison health and productivity, facilitate the education of future producers and veterinarians, and conduct economic analyses of the health and production of the U.S. bison industry. On March 20, 2012, NAHMS was recognized by the Office of Management and Budget (OMB) as a statistical unit under the Confidential Information Protection and Statistical Efficiency Act of 2002 (CIPSEA). All information acquired under the Bison 2014 Study will be used for statistical purposes only and will be treated as confidential in accordance with CIPSEA guidelines. Only NAHMS staff and designated agents will be permitted access to individual-level data. We are asking OMB to approve our use of this information collection activity for 3 years. The purpose of this notice is to solicit comments from the public (as well as affected agencies) concerning our information collection. These comments will help us: (1) Evaluate whether the collection of information is necessary for the proper performance of the functions of the Agency, including whether the information will have practical utility; (2) Evaluate the accuracy of our estimate of the burden of the collection of information, including the validity of the methodology and assumptions used; VerDate Mar<15>2010 20:16 Sep 20, 2013 Jkt 229001 (3) Enhance the quality, utility, and clarity of the information to be collected; and (4) Minimize the burden of the collection of information on those who are to respond, through use, as appropriate, of automated, electronic, mechanical, and other collection technologies, such as electronic submission of responses. Estimate of burden: The public reporting burden for this collection of information is estimated to average 0.33 hours per response. Respondents: Bison owners and operators. Estimated annual number of respondents: 1,200. Estimated annual number of responses per respondent: 1. Estimated annual number of responses: 1,200. Estimated total annual burden on respondents: 396 hours. (Due to averaging, the total annual burden hours may not equal the product of the annual number of responses multiplied by the reporting burden per response.) All responses to this notice will be summarized and included in the request for OMB approval. All comments will also become a matter of public record. Done in Washington, DC, this 17th day of September 2013. Michael C. Gregoire, Acting Administrator, Animal and Plant Health Inspection Service. [FR Doc. 2013–23038 Filed 9–20–13; 8:45 am] BILLING CODE 3410–34–P DEPARTMENT OF AGRICULTURE Forest Service Cleveland National Forest, California, SDG&E Master Special Use Permit and Permit To Construct Power Line Replacement Projects EIR/EIS Forest Service, USDA. Notice of intent to prepare a joint Environmental Impact Report/ Environmental Impact Statement. AGENCY: ACTION: Pursuant to section 102(2)(C) of the National Environmental Policy Act of 1969 (NEPA), as amended, notice is hereby given that the Cleveland National Forest (CNF), together with the California Public Utilities Commission (CPUC), intends to prepare a joint Environmental Impact Report and Environmental Impact Statement (EIR/ EIS), for the San Diego Gas & Electric Company (SDG&E) Master Special Use Permit and Permit to Construct Power Line Replacement Projects. The Master Special Use Permit would authorize SUMMARY: PO 00000 Frm 00004 Fmt 4703 Sfmt 4703 SDG&E to upgrade and/or relocate certain electric powerlines on National Forest System lands, while providing for the operation and maintenance of the SDG&E electric powerline system. The project area is located in multiple locations within the Trabuco, Palomar, and Descanso Ranger Districts, Cleveland National Forest, Orange and San Diego Counties, California. This action is needed because the existing authorizations are expired, and the existing powerlines are needed to supply power to local communities, residents, businesses, and government owned facilities located within and adjacent to the National Forest. The project study area not only traverses National Forest System lands, but due to the patchwork of land ownership in the project study area, also traverses the National System of Public Lands managed by the Bureau of Land Management (BLM); tribal lands of the La Jolla, Campo, Inaja, and Viejas Indian Reservations managed by the respective tribes and held in trust by the Bureau of Indian Affairs (BIA); Cuyamaca Rancho State Park lands managed by California State Parks (CSP); and private holdings within unincorporated San Diego County amongst others. DATES: All scoping comments must be received by November 7, 2013. ADDRESSES: You may submit comments to Lisa Orsaba, California Public Utilities Commission, and Will Metz, Forest Supervisor, Cleveland National Forest by either of the following methods: Email: cnfmsup@dudek.com. Mail: c/o Dudek, 605 Third Street, Encinitas, California 92024. FOR FURTHER INFORMATION CONTACT: Information can be requested by leaving a voice message at 866–467–4727 or by checking the project Web site at https://www.cpuc.ca.gov/environment/ info/dudek/CNF/CNF.htm. Individuals who use telecommunication devices for the deaf (TDD) may call the Federal Information Relay Service (FIRS) at 1–800–877–8339 between 8 a.m. and 8 p.m., Eastern Time, Monday through Friday. SUPPLEMENTARY INFORMATION: In 2005, in consultation with the Forest Service, SDG&E submitted an initial application to obtain a Master Special Use Permit (MSUP). The purpose of the MSUP was to consolidate SDG&E’s rights and responsibilities in connection with the continued operation of its electric lines and other existing facilities located within the CNF. As part of the NEPA review process, the Forest Service circulated an Environmental Assessment (EA) for public comment in E:\FR\FM\23SEN1.SGM 23SEN1 Federal Register / Vol. 78, No. 184 / Monday, September 23, 2013 / Notices emcdonald on DSK67QTVN1PROD with NOTICES 2009. In response to public comments received on that EA, the Forest Service determined that additional fire risk reduction measures within the CNF (including fire hardening) and additional undergrounding should be evaluated as part of the MSUP review process and that, as a result, an environmental impact statement (EIS) was required. SDG&E has expanded the scope of the proposed MSUP to include fire hardening, undergrounding and relocation as proposed in the power line replacement projects discussed in their application to the CPUC. The proposed power line replacement projects will require approval from the CPUC. The CPUC, Forest Service, BLM, BIA, and CSP have independent jurisdiction and approval authority for the project segments within their areas of jurisdiction. The CPUC is the lead agency under California law and the Forest Service is the lead federal agency. As joint lead agencies, the CPUC and Forest Service have developed and signed a Memorandum of Understanding (January 2012) that will direct the preparation of a joint Environmental Impact Report (EIR) to comply with the California Environmental Quality Act (CEQA) and an Environmental Impact Statement (EIS) to comply with the National Environmental Policy Act (NEPA). The joint document will be called the ‘‘SDG&E Master Special Use Permit and Permit to Construct Power Line Replacement Projects EIR/EIS. The BLM and BIA are joining the Forest Service as federal cooperating agencies under NEPA, and the CSP is participating as a responsible agency under CEQA. Purpose and Need for Action The Forest Service purpose is to authorize the powerlines and associated facilities needed to continue electric service to a variety of users within and adjacent to the CNF through a Master Special Use Permit in a manner that is consistent with the CNF Land Management Plan (LMP). This action is needed because the 70 individual permits or easements for the existing facilities have expired, and a permit is required for the continued occupancy and use of National Forest System lands. Permits issued by the Forest Service are required by law to be consistent with the LMP. The LMP identifies suitable uses within various land use zones, describes desired conditions based on the LMP goals and objectives, and sets resource management standards. The Forest Service proposed action is designed to be consistent with VerDate Mar<15>2010 20:16 Sep 20, 2013 Jkt 229001 the LMP requirements. The Forest Service purpose and need will guide the development of alternatives considered on National Forest System lands. The BLM purpose is to authorize the powerlines and associated facilities needed to continue electric service to a variety of users within and adjacent to the National System of Public Lands in a manner that is consistent with the South Coast Resource Area Plan. This action is needed because the Right-ofWay (ROW) grants for the existing facilities have expired or were never issued, and a ROW grant is required for the continued occupancy and use of Public Lands. The BIA purpose is to authorize the powerlines and associated upgrades needed to continue electric service to a variety of users within and adjacent to the Indian trust lands in a manner that is consistent with tribal land use goals and policies. The action is needed to amend the existing easements to include the proposed fire hardening measures and locations and to extend their term. Proposed Action The Forest Service proposed action would combine over 70 existing use permits for electric line facilities within the CNF into one MSUP. The MSUP would allow the continued maintenance and operation of more than 50 miles of 69 kV power lines and 12 kV distribution lines and ancillary facilities that are required to operate and maintain existing electric facilities located within the administrative boundary of the CNF. The Project would also replace several existing 69 kV power lines and 12 kV distribution lines located within and outside of the CNF. Replacement would include fire hardening (wood to steel pole replacement), along with removal, relocation, undergrounding and single to double circuit conversion along certain segments. Specific components of the Forest Service proposed action include relocating transmission line (TL) number 626 out of the Cedar Creek undeveloped area, relocating distribution line 79 out of the Sill Hill Inventoried Roadless Area, and relocating distribution line 157 out of the Hauser Wilderness Area. A more detailed description of the proposed action is available in the Notice of Preparation posted on the project Web site. The BLM proposed action would authorize one electric line and issue new ROW grants for two electric lines, and authorize the fire hardening upgrades. This action includes portions of TL 629, TL 6923, and TL 625. PO 00000 Frm 00005 Fmt 4703 Sfmt 4703 58271 The BIA proposed action would authorize the fire hardening upgrades and amend the term and location of the existing easements. This action includes portions of TL 629 and TL 682. Possible Alternatives The EIR/EIS will describe and evaluate the comparative merits of a reasonable range of alternatives to the proposed action and associated Powerline Replacement Projects. Alternatives to be analyzed in the EIR/ EIS will be developed during the environmental review process and will consider input received during scoping, and will include the no action alternative as required by law. Responsible Official The Responsible Official for the Forest Service decision is Will Metz, Forest Supervisor, Cleveland National Forest. The Responsible Official for the BLM decision is John Kalish, Field Manager, Palm Springs South Coast Field Office. The Responsible Official for the BIA decision is Amy L. Dutschke, Regional Director, BIA Pacific Region. The Commissioners appointed to the CPUC are the deciding body for the Permit to Construct. The Responsible Official for the CSP decision is Dan Falat, Colorado Desert District Superintendent. Nature of Decision To Be Made Each agency has independent decision authority within their jurisdictional area. The federal responsible officials, as well as the CSP, will decide whether or not to authorize their portions of the project, and if so, under what conditions. The CPUC has independent jurisdiction over power lines and will determine if a Permit to Construct will be issued, and if so, under what conditions. Preliminary Issues The Forest Service and CPUC have identified potential issues and impacts to the existing environment require a detailed analysis in the EIR/EIS. Those issues and impacts include aesthetics, air quality, biological resources, cultural and paleontological resources, greenhouse gas emissions, fire, water quality, land use, noise, public services, recreation, wilderness, and transportation. No determinations have yet been made as to the significance of these potential impacts; such determinations will be made in the environmental analysis conducted in the EIR/EIS after the issues are considered thoroughly. This overview is presented to assist the public and E:\FR\FM\23SEN1.SGM 23SEN1 58272 Federal Register / Vol. 78, No. 184 / Monday, September 23, 2013 / Notices agencies in preparing written scoping comments. DEPARTMENT OF AGRICULTURE Rural Housing Service Invitation to Cooperating Agencies The Forest Service invites other federal agencies or tribes to join as cooperating agencies. Requests for cooperating agency status may be submitted to Forest Supervisor Will Metz, Cleveland National Forest, 10845 Rancho Bernardo Road, Suite 200, San Diego, CA 92127–2107. Scoping Process emcdonald on DSK67QTVN1PROD with NOTICES The CPUC and Forest Service are initiating the joint CEQA/NEPA scoping process with this Notice of Intent and associated Notice of Preparation. The comments received during scoping will help guide the development of the EIR/ EIS. Two public workshops will be held during the scoping process to answer questions about the proposed action. Workshops will be held at the Julian Elementary School, 1704 Cape Horn, Julian, California, on Tuesday, October 22, 2013 at 5:00 p.m., and at the Alpine Community Center, 1830 Alpine Boulevard, Alpine, California, on Wednesday, October 23, 2013 at 5:00 p.m. It is important that reviewers provide their comments at such times and in such a way that they are useful to the CPUC and Forest Service preparation of the EIR/EIS. Therefore, comments should be provided prior to the close of the comment period and should clearly articulate the reviewer’s concerns and contentions. Comments received during scoping, including names and addresses of those who comment, will be part of the public record for this proposed project. Comments submitted anonymously will be accepted and considered; however, anonymous comments will not provide the respondent with standing to participate in subsequent administrative review or judicial review of the Forest Service decision. This project will follow the predecisional administrative review process pursuant to 36 CFR 218, Subparts A and B. Dated: September 16, 2013. William Metz, Forest Supervisor. [FR Doc. 2013–22904 Filed 9–20–13; 8:45 am] BILLING CODE 3410–11–P VerDate Mar<15>2010 20:16 Sep 20, 2013 Jkt 229001 Notice of Intent To Review Online Homeownership Education Courses for Nationwide Use in the Single Family Housing Section 502 Direct Loan Program Rural Housing Service, USDA. Notice. AGENCY: ACTION: Effective on May 7, 2007, first-time homebuyers financed under the direct loan program must successfully complete an approved homeownership education course prior to loan closing. 7 CFR Part 3550.11 outlines the order of preference given to courses. First preference is given to classroom, one-on-one counseling, or interactive video conference. These formats are generally extensive and require a significant time and participation commitment from the Agency applicants. Second preference is given to interactive home-study or interactive telephone counseling of at least four hours duration. These formats may only be used if the formats under the first preference are not reasonably available. Third preference, which can only be used if all other formats are not reasonably available, is given to online counseling. It also outlines the requirements an education provider and their course must meet in order to be approved for use by Agency applicants. While approval is generally made by the Agency at the state level, there is currently one nationally approved online education provider. To expand the Agency applicants’ access to and options of approved education providers, the Agency will consider approving other online education providers on a national level. Approval will be subject to meeting course criteria, a recommendation by the Agency-selected panel of housing partners, and signoff by the Administrator. Approval will be given as a third preference format unless the education provider is able to demonstrate and document how their online course along with a required supplemented service provides the same level of training and individualized attention as a first or second preference. A notice of education providers approved through this process will be issued via a memorandum to the Rural Development (RD) state offices. The memorandum will list the format preference assigned to each provider. A copy of the memorandum will be simultaneously emailed to all education providers who applied through this notice. SUMMARY: PO 00000 Frm 00006 Fmt 4703 Sfmt 4703 Approvals are not subject to expiration. However, an approval may be revoked for justifiable cause. DATES: Online homeownership education providers interested in having their courses reviewed should submit a complete package to the Single Family Housing Direct Division within 30 days of this notice. Submissions may be sent electronically to SFHDIRECTPROGRAM@wdc.usda.gov or by mail to 1400 Independence Avenue, Stop 0783, Washington, DC 20250–0783. FOR FURTHER INFORMATION CONTACT: Shantelle Gordon, shantelle.gordon@ wdc.usda.gov or (202) 205–9567. Non-Discrimination Statement USDA prohibits discrimination in all its programs and activities on the basis of race, color, national origin, age, disability, and where applicable, sex, marital status, familial status, parental status, religion, sexual orientation, political beliefs, genetic information, reprisal, or because all or part of an individual’s income is derived from any public assistance program. (Not all prohibited bases apply to all programs.) To file a complaint of discrimination, complete, sign and mail a program discrimination complaint form, (available at any USDA office location or online at www.ascr.usda.gov, or write to: U.S. Department of Agriculture, Office of the Assistant Secretary for Civil Rights, 1400 Independence Avenue SW., STOP 9410, Washington, DC 20250–9410. Or call toll-free (866) 632–9992 (voice) to obtain additional information, the appropriate office or to request documents. Individuals who are deaf, hard of hearing or have speech disabilities may contact USDA through the Federal Relay Service at (800) 877– 8339 or (877) 845–6136 (in Spanish). ‘‘USDA is an equal opportunity provider, employer and lender.’’ Persons with disabilities who require alternative means for communication of program information (e.g. Brail, large print, audiotape, etc.) should contact USDA TARTET Center at (202) 720– 2600 (voice and TDD). SUPPLEMENTARY INFORMATION: At a minimum, courses submitted for consideration must contain the following content: • Preparing for homeownership (evaluate readiness to go from rental to homeownership) • Budgeting (pre and post purchase) • Credit counseling • Shopping for a home • Lender differences (predatory lending) E:\FR\FM\23SEN1.SGM 23SEN1

Agencies

[Federal Register Volume 78, Number 184 (Monday, September 23, 2013)]
[Notices]
[Pages 58270-58272]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-22904]


-----------------------------------------------------------------------

DEPARTMENT OF AGRICULTURE

Forest Service


Cleveland National Forest, California, SDG&E Master Special Use 
Permit and Permit To Construct Power Line Replacement Projects EIR/EIS

AGENCY: Forest Service, USDA.

ACTION: Notice of intent to prepare a joint Environmental Impact 
Report/Environmental Impact Statement.

-----------------------------------------------------------------------

SUMMARY: Pursuant to section 102(2)(C) of the National Environmental 
Policy Act of 1969 (NEPA), as amended, notice is hereby given that the 
Cleveland National Forest (CNF), together with the California Public 
Utilities Commission (CPUC), intends to prepare a joint Environmental 
Impact Report and Environmental Impact Statement (EIR/EIS), for the San 
Diego Gas & Electric Company (SDG&E) Master Special Use Permit and 
Permit to Construct Power Line Replacement Projects. The Master Special 
Use Permit would authorize SDG&E to upgrade and/or relocate certain 
electric powerlines on National Forest System lands, while providing 
for the operation and maintenance of the SDG&E electric powerline 
system. The project area is located in multiple locations within the 
Trabuco, Palomar, and Descanso Ranger Districts, Cleveland National 
Forest, Orange and San Diego Counties, California. This action is 
needed because the existing authorizations are expired, and the 
existing powerlines are needed to supply power to local communities, 
residents, businesses, and government owned facilities located within 
and adjacent to the National Forest. The project study area not only 
traverses National Forest System lands, but due to the patchwork of 
land ownership in the project study area, also traverses the National 
System of Public Lands managed by the Bureau of Land Management (BLM); 
tribal lands of the La Jolla, Campo, Inaja, and Viejas Indian 
Reservations managed by the respective tribes and held in trust by the 
Bureau of Indian Affairs (BIA); Cuyamaca Rancho State Park lands 
managed by California State Parks (CSP); and private holdings within 
unincorporated San Diego County amongst others.

DATES: All scoping comments must be received by November 7, 2013.

ADDRESSES: You may submit comments to Lisa Orsaba, California Public 
Utilities Commission, and Will Metz, Forest Supervisor, Cleveland 
National Forest by either of the following methods:
    Email: cnfmsup@dudek.com.
    Mail: c/o Dudek, 605 Third Street, Encinitas, California 92024.

FOR FURTHER INFORMATION CONTACT: Information can be requested by 
leaving a voice message at 866-467-4727 or by checking the project Web 
site at https://www.cpuc.ca.gov/environment/info/dudek/CNF/CNF.htm.
    Individuals who use telecommunication devices for the deaf (TDD) 
may call the Federal Information Relay Service (FIRS) at 1-800-877-8339 
between 8 a.m. and 8 p.m., Eastern Time, Monday through Friday.

SUPPLEMENTARY INFORMATION: In 2005, in consultation with the Forest 
Service, SDG&E submitted an initial application to obtain a Master 
Special Use Permit (MSUP). The purpose of the MSUP was to consolidate 
SDG&E's rights and responsibilities in connection with the continued 
operation of its electric lines and other existing facilities located 
within the CNF. As part of the NEPA review process, the Forest Service 
circulated an Environmental Assessment (EA) for public comment in

[[Page 58271]]

2009. In response to public comments received on that EA, the Forest 
Service determined that additional fire risk reduction measures within 
the CNF (including fire hardening) and additional undergrounding should 
be evaluated as part of the MSUP review process and that, as a result, 
an environmental impact statement (EIS) was required.
    SDG&E has expanded the scope of the proposed MSUP to include fire 
hardening, undergrounding and relocation as proposed in the power line 
replacement projects discussed in their application to the CPUC. The 
proposed power line replacement projects will require approval from the 
CPUC.
    The CPUC, Forest Service, BLM, BIA, and CSP have independent 
jurisdiction and approval authority for the project segments within 
their areas of jurisdiction. The CPUC is the lead agency under 
California law and the Forest Service is the lead federal agency. As 
joint lead agencies, the CPUC and Forest Service have developed and 
signed a Memorandum of Understanding (January 2012) that will direct 
the preparation of a joint Environmental Impact Report (EIR) to comply 
with the California Environmental Quality Act (CEQA) and an 
Environmental Impact Statement (EIS) to comply with the National 
Environmental Policy Act (NEPA). The joint document will be called the 
``SDG&E Master Special Use Permit and Permit to Construct Power Line 
Replacement Projects EIR/EIS. The BLM and BIA are joining the Forest 
Service as federal cooperating agencies under NEPA, and the CSP is 
participating as a responsible agency under CEQA.

Purpose and Need for Action

    The Forest Service purpose is to authorize the powerlines and 
associated facilities needed to continue electric service to a variety 
of users within and adjacent to the CNF through a Master Special Use 
Permit in a manner that is consistent with the CNF Land Management Plan 
(LMP). This action is needed because the 70 individual permits or 
easements for the existing facilities have expired, and a permit is 
required for the continued occupancy and use of National Forest System 
lands.
    Permits issued by the Forest Service are required by law to be 
consistent with the LMP. The LMP identifies suitable uses within 
various land use zones, describes desired conditions based on the LMP 
goals and objectives, and sets resource management standards. The 
Forest Service proposed action is designed to be consistent with the 
LMP requirements. The Forest Service purpose and need will guide the 
development of alternatives considered on National Forest System lands.
    The BLM purpose is to authorize the powerlines and associated 
facilities needed to continue electric service to a variety of users 
within and adjacent to the National System of Public Lands in a manner 
that is consistent with the South Coast Resource Area Plan. This action 
is needed because the Right-of-Way (ROW) grants for the existing 
facilities have expired or were never issued, and a ROW grant is 
required for the continued occupancy and use of Public Lands.
    The BIA purpose is to authorize the powerlines and associated 
upgrades needed to continue electric service to a variety of users 
within and adjacent to the Indian trust lands in a manner that is 
consistent with tribal land use goals and policies. The action is 
needed to amend the existing easements to include the proposed fire 
hardening measures and locations and to extend their term.

Proposed Action

    The Forest Service proposed action would combine over 70 existing 
use permits for electric line facilities within the CNF into one MSUP. 
The MSUP would allow the continued maintenance and operation of more 
than 50 miles of 69 kV power lines and 12 kV distribution lines and 
ancillary facilities that are required to operate and maintain existing 
electric facilities located within the administrative boundary of the 
CNF. The Project would also replace several existing 69 kV power lines 
and 12 kV distribution lines located within and outside of the CNF. 
Replacement would include fire hardening (wood to steel pole 
replacement), along with removal, relocation, undergrounding and single 
to double circuit conversion along certain segments. Specific 
components of the Forest Service proposed action include relocating 
transmission line (TL) number 626 out of the Cedar Creek undeveloped 
area, relocating distribution line 79 out of the Sill Hill Inventoried 
Roadless Area, and relocating distribution line 157 out of the Hauser 
Wilderness Area. A more detailed description of the proposed action is 
available in the Notice of Preparation posted on the project Web site.
    The BLM proposed action would authorize one electric line and issue 
new ROW grants for two electric lines, and authorize the fire hardening 
upgrades. This action includes portions of TL 629, TL 6923, and TL 625.
    The BIA proposed action would authorize the fire hardening upgrades 
and amend the term and location of the existing easements. This action 
includes portions of TL 629 and TL 682.

Possible Alternatives

    The EIR/EIS will describe and evaluate the comparative merits of a 
reasonable range of alternatives to the proposed action and associated 
Powerline Replacement Projects. Alternatives to be analyzed in the EIR/
EIS will be developed during the environmental review process and will 
consider input received during scoping, and will include the no action 
alternative as required by law.

Responsible Official

    The Responsible Official for the Forest Service decision is Will 
Metz, Forest Supervisor, Cleveland National Forest.
    The Responsible Official for the BLM decision is John Kalish, Field 
Manager, Palm Springs South Coast Field Office.
    The Responsible Official for the BIA decision is Amy L. Dutschke, 
Regional Director, BIA Pacific Region.
    The Commissioners appointed to the CPUC are the deciding body for 
the Permit to Construct.
    The Responsible Official for the CSP decision is Dan Falat, 
Colorado Desert District Superintendent.

Nature of Decision To Be Made

    Each agency has independent decision authority within their 
jurisdictional area. The federal responsible officials, as well as the 
CSP, will decide whether or not to authorize their portions of the 
project, and if so, under what conditions. The CPUC has independent 
jurisdiction over power lines and will determine if a Permit to 
Construct will be issued, and if so, under what conditions.

Preliminary Issues

    The Forest Service and CPUC have identified potential issues and 
impacts to the existing environment require a detailed analysis in the 
EIR/EIS. Those issues and impacts include aesthetics, air quality, 
biological resources, cultural and paleontological resources, 
greenhouse gas emissions, fire, water quality, land use, noise, public 
services, recreation, wilderness, and transportation. No determinations 
have yet been made as to the significance of these potential impacts; 
such determinations will be made in the environmental analysis 
conducted in the EIR/EIS after the issues are considered thoroughly. 
This overview is presented to assist the public and

[[Page 58272]]

agencies in preparing written scoping comments.

Invitation to Cooperating Agencies

    The Forest Service invites other federal agencies or tribes to join 
as cooperating agencies. Requests for cooperating agency status may be 
submitted to Forest Supervisor Will Metz, Cleveland National Forest, 
10845 Rancho Bernardo Road, Suite 200, San Diego, CA 92127-2107.

Scoping Process

    The CPUC and Forest Service are initiating the joint CEQA/NEPA 
scoping process with this Notice of Intent and associated Notice of 
Preparation. The comments received during scoping will help guide the 
development of the EIR/EIS. Two public workshops will be held during 
the scoping process to answer questions about the proposed action. 
Workshops will be held at the Julian Elementary School, 1704 Cape Horn, 
Julian, California, on Tuesday, October 22, 2013 at 5:00 p.m., and at 
the Alpine Community Center, 1830 Alpine Boulevard, Alpine, California, 
on Wednesday, October 23, 2013 at 5:00 p.m.
    It is important that reviewers provide their comments at such times 
and in such a way that they are useful to the CPUC and Forest Service 
preparation of the EIR/EIS. Therefore, comments should be provided 
prior to the close of the comment period and should clearly articulate 
the reviewer's concerns and contentions.
    Comments received during scoping, including names and addresses of 
those who comment, will be part of the public record for this proposed 
project. Comments submitted anonymously will be accepted and 
considered; however, anonymous comments will not provide the respondent 
with standing to participate in subsequent administrative review or 
judicial review of the Forest Service decision. This project will 
follow the predecisional administrative review process pursuant to 36 
CFR 218, Subparts A and B.

    Dated: September 16, 2013.
William Metz,
Forest Supervisor.
[FR Doc. 2013-22904 Filed 9-20-13; 8:45 am]
BILLING CODE 3410-11-P