State Rail Plan Guidance, 57450-57454 [2013-22679]
Download as PDF
57450
Federal Register / Vol. 78, No. 181 / Wednesday, September 18, 2013 / Notices
technology high-speed ground
transportation system. During the late
1990s, FRA was implementing the
Maglev Deployment Program (Program)
created by Congress in the
Transportation Equity Act for the 21st
Century (Pub. L. 105–178, June 9, 1998).
The purpose of the Program was to
demonstrate the feasibility of maglev
technology. In addition to a number of
feasibility studies, FRA prepared a PEIS
addressing the potential for significant
environmental impact from the Program
that included a Las Vegas-Primm project
as one of seven projects analyzed in the
PEIS. The notice of availability for the
PEIS was published on May 4, 2001.
The Department of Transportation
and Related Agencies Appropriations
Act, 2003 (Pub. L.108–7), which
provides appropriations for the FRA and
other agencies, included funds
specifically to conduct additional
design, engineering and environmental
studies concerning the CaliforniaNevada Interstate Maglev Project under
the FRA’s Next Generation High Speed
Rail Technology Demonstration
Program. On May 20, 2004, FRA issued
a notice of intent to prepare a PEIS for
the California-Nevada Interstate Maglev
project. FRA intended for this PEIS to
draw on environmental analysis already
completed, including the Las VegasPrimm project.
The only activity completed for the
PEIS was scoping in 2004. No further
work has been completed on the PEIS
since that time. Due to a lack of activity
for more than five years, FRA is issuing
this notice terminating the preparation
of the PEIS.
Renee Cooper,
Staff Director, Office of Passenger and Freight
Programs.
[FR Doc. 2013–22600 Filed 9–17–13; 8:45 am]
BILLING CODE 4910–06–P
DEPARTMENT OF TRANSPORTATION
Federal Railroad Administration
Notice Rescinding a Notice of Intent To
Prepare an Environmental Impact
Statement for the Altamont Corridor
Rail Project From Stockton to San
Jose, California
Federal Railroad
Administration (FRA), U.S. Department
of Transportation (DOT).
ACTION: Notice rescinding intent to
prepare an Environmental Impact
Statement (EIS).
emcdonald on DSK67QTVN1PROD with NOTICES
AGENCY:
The Federal Railroad
Administration (FRA) is issuing this
notice to advise the public that FRA is
SUMMARY:
VerDate Mar<15>2010
16:45 Sep 17, 2013
Jkt 229001
rescinding the Notice of Intent (NOI) to
prepare a programmatic environmental
impact statement (EIS) for the Altamont
Corridor Rail Project from Stockton to
San Jose, California Project in
cooperation with the project sponsor,
the California High Speed Rail
Authority (Authority). FRA published
the original NOI in the Federal Register
on October 29, 2009. This rescission is
due to the transfer of the project from
the Authority to the San Joaquin
Regional Rail Commission (SJRRC) and
a change in the project definition and
purpose and need. An NOI to prepare an
Environmental Impact Statement (EIS)
for the revised Altamont Corridor
Express also known as the ACEforward
project is being published concurrently
with this notice.
FOR FURTHER INFORMATION CONTACT: Ms.
Stephanie Perez-Arrieta, Environmental
Protection Specialist, Federal Railroad
Administration, 1200 New Jersey
Avenue Southeast, (Mail Stop 20),
Washington, DC 20590, telephone (202)
493–0388.
SUPPLEMENTARY INFORMATION: The
Altamont Corridor was studied by the
Authority and identified as a candidate
route to the Bay Area in the Statewide
High Speed Train (HST) System
Program Environmental Impact Report/
Environmental Impact Statement (EIR/
EIS). The Authority and FRA further
examined the corridor in the 2008 Bay
Area to Central Valley HST EIR/EIS and
selected the Pacheco Pass via Gilroy as
the route to connect the main line of the
HST network in the Central Valley with
the Peninsula and San Francisco. The
Authority and SJRRC proposed to
develop a dedicated regional rail
corridor through Altamont Pass and the
Tri Valley area capable of supporting
intercity and commuter rail passenger
services. The project was planned to
improve the existing ACE service
managed by SJRRC by accommodating
more trains per day, reducing travel
times, and eliminating freight railroad
delays by providing separate passenger
tracks. The Altamont Corridor was
planned to serve as a feeder to the
statewide HST System being planned
and developed by the Authority. The
project considered connections between
the Altamont corridor and the HST
mainline between Stockton and
Modesto and HST compatible
infrastructure that would have allowed
trains to run from one rail line to the
other in order to accommodate intercity
travel between stations along the
Altamont Corridor and regional stops on
the greater statewide HST System.
Scoping was completed for the EIR/
EIS in 2009 and the development of
PO 00000
Frm 00100
Fmt 4703
Sfmt 4703
preliminary alternatives in 2010 and
2011. No further work was completed
on the EIS. Due to the proposed change
in leadership and direction of this
project, FRA is issuing this notice
terminating the preparation of the
Altamont Corridor Rail Project EIS.
Issued in Washington, DC, on September
13, 2013.
Renee Cooper,
Staff Director, Office of Passenger and Freight
Programs.
[FR Doc. 2013–22599 Filed 9–17–13; 8:45 am]
BILLING CODE 4910–06–P
DEPARTMENT OF TRANSPORTATION
Federal Railroad Administration
[Docket No. FRA–2012–0066]
State Rail Plan Guidance
Federal Railroad
Administration (FRA), Department of
Transportation (DOT).
ACTION: Notice of Availability of Final
State Rail Plan Guidance.
AGENCY:
FRA is publishing this notice
to announce the availability of final
State Rail Plan Guidance. The purpose
of FRA’s final State Rail Plan Guidance
is to describe the processes for the
development, submission, and
acceptance of State rail plans. State rail
plans are documents that are required
under Section 303 of the Passenger Rail
Investment and Improvement Act of
2008 (PRIIA). Section 303 of PRIIA
provides for enhanced State
involvement in rail policy, planning,
and development efforts, including
requiring States to develop FRAaccepted State rail plans in order to be
eligible for the capital grants authorized
in the Act and available under the HighSpeed Intercity Passenger Rail program.
This guidance provides an explanation
of the process to be followed in
developing State rail plans, FRA’s
process for reviewing and accepting
State rail plans, a standardized format,
and a list of the minimum content
requirements for State rail plans. The
State Rail Plan Guidance is available on
FRA’s Web site at https://
www.fra.dot.gov/Page/P0511.
DATES: The final State Rail Plan
Guidance is effective as of the
publication of this notice on September
18, 2013.
Applicability: Any State rail plan
whose development is begun after
publication of this notice must adhere to
the standardized format and minimum
content requirements defined within the
guidance in order to be accepted by the
FRA.
SUMMARY:
E:\FR\FM\18SEN1.SGM
18SEN1
Federal Register / Vol. 78, No. 181 / Wednesday, September 18, 2013 / Notices
For
questions about this notice, please
contact Kyle Gradinger, Transportation
Industry Analyst, Office of Railroad
Policy and Development, Federal
Railroad Administration, 1200 New
Jersey Ave. SE., W38–202, Washington,
DC 20590; telephone: (202) 493–6191.
FOR FURTHER INFORMATION CONTACT:
Final State
Rail Plan Guidance was prepared
through a notice and comment process
involving publication of draft guidance
announced in the August 28, 2012 issue
of the Federal Register, soliciting public
review and comment over the following
90 day period. FRA received 121
individual comments from 55
respondents. Comments were received
from a diverse group comprised of eight
(8) State departments of transportation,
one (1) metropolitan planning
organization (MPO), eleven (11) trade
organizations, five (5) national
stakeholder organizations, one (1)
private individual, and one (1) public
transportation service provider.
emcdonald on DSK67QTVN1PROD with NOTICES
SUPPLEMENTARY INFORMATION:
Broad support was offered by
commenters for preparing State rail
plans as part of a comprehensive,
coordinated planning framework within
and among States, and for addressing
passenger and freight needs in an
integrated, coordinated way. Almost
unanimous support was offered for
integrating, to the extent possible,
preparation of State rail plans with the
statewide/nonmetropolitan and
metropolitan transportation planning
programs required under the Federal-aid
Highway and Federal Transit titles—23
U.S.C. and Chapter 53 of 49 U.S.C.,
respectively. Similarly, it is within that
expanded transportation planning
context of States and metropolitan
planning organizations (MPOs) that
commenters proposed engagement of an
expansive range of stakeholder interests
in State rail plan development—
spanning industry, government, labor,
local communities, and the private
sector.
However, concerns were expressed by
commenters for several procedural
aspects of State rail plan preparation,
including data collection and the depth
of impact assessment required for the
rail infrastructure, facilities, and service
improvements contained in State rail
plans. Other issues raised by
commenters included the importance of
involving private rail interests in
meaningful ways in State rail plan
development, while respecting the
proprietary nature of their operational
and financial records. These comments
are grouped and summarized below by
topic with FRA responses.
VerDate Mar<15>2010
16:45 Sep 17, 2013
Jkt 229001
Coordination With Statewide/
Nonmetropolitan and Metropolitan
Transportation Planning
Several comments were received
supporting full coordination of State rail
plan development with the statewide/
nonmetropolitan and metropolitan
transportation planning programs
required under 23 U.S.C. and Chapter
53 of 49 U.S.C. Commenters
recommended a range of specific
planning work activities and planning
products that represent the best
opportunities for coordination with
State rail plan development. Following
are the details of comments provided
and FRA responses regarding
coordination between State rail plan
development and the transportation
planning processes carried out by States
and MPOs.
Several commenters proposed that
States prepare State rail plans as part of
metropolitan and statewide/
nonmetropolitan transportation
planning processes in order to eliminate
duplication of effort. Particular concern
was expressed for not establishing a
separate planning process for State rail
plans—apart from those existing
planning processes. It was proposed that
States be able to incorporate visions,
plans, and priorities that consider rail as
one of many transportation modes, in a
single statewide transportation plan,
with the State rail plan incorporated
within the overall plan or as an
addendum. A commenter also requested
clarification of the term ‘‘compatible,’’
as it was used in the draft guidance to
describe the relationship between the
State rail plan and planning processes.
Response: FRA has revised the draft
guidance to emphasize the importance
of preparing State rail plans within the
policy and procedural contexts of the
multimodal transportation planning
processes conducted by states and
MPOs and to integrate the documents as
much as possible. In revising the
guidance, FRA was careful not to
convey the MAP–21 financial constraint
requirements associated with highway
and transit listings to the rail proposals
listed in the State rail plan. Also, to
improve clarity, the term ‘‘compatible’’
was replaced with language calling for
state rail plans to be generally consistent
with other planning documents and
policies.
A commenter recommended that the
guidance stipulate that State rail plans
should be prepared in coordination with
the new freight planning activities
carried out by States in accordance with
MAP–21. The commenter proposed that
the guidance direct States to describe
how their State’s long-term vision for
PO 00000
Frm 00101
Fmt 4703
Sfmt 4703
57451
rail integrates with the State Freight
Plan, as well as the National Freight
Policy, the National Freight Strategic
Plan, and the National Export Initiative.
Another commenter recommended that
State rail plans include in depth
discussion of the changing freight
market. Response: FRA agrees that State
rail plans should be prepared with full
understanding of the current and
emerging freight, as well as passenger,
markets and has revised the guidance
accordingly. Language also has been
added to the guidance recommending
that States coordinate preparation of
State freight plans and State rail plans.
A commenter proposed closer
coordination between FRA and FHWA
and State highway offices, suggesting
that States be required to consider the
cross-effects of investment in rail and
highway improvements, including
consideration of rail when planning
future highway investments. Another
commenter recommends that the
guidance specifically require State rail
plans to identify the potential impacts
of individual projects, as well as the
combined impact of all projects in the
State rail plan. Specifically, they
recommended that local transit modes
be added to the list of ‘‘highway,
aviation and maritime modes’’ included
in the draft guidance. Response: FRA
added ‘‘local transit’’ to the list of
modes for which potential impacts of
State rail plan implementation should
be analyzed and added emphasis about
the need to assess potential project
impacts on an individual, as well as
combined, basis.
A commenter recommended revising
the guidance to promote consistency
between the performance measures used
in preparing State rail plans and those
used in the statewide/nonmetropolitan
and metropolitan transportation
planning process, including use of easyto-read tables. Response: FRA agrees
that using consistent performance
measures is preferable and has revised
the guidance to include reference to
using performance measures in
coordination with those used in broader
transportation planning processes,
including promoting consistency with
transit asset management plans required
under MAP–21.
A commenter recommended changing
the 5-year state rail plan update cycle
included in the draft guidance to a 4year cycle, for consistency with the
document update cycles prescribed in
MAP–21 for planning documents.
Another commenter proposed annual
updates. Response: The 5-year update
provision is set forth in PRIIA and
cannot be changed. However, FRA
agrees that the update cycles of State
E:\FR\FM\18SEN1.SGM
18SEN1
emcdonald on DSK67QTVN1PROD with NOTICES
57452
Federal Register / Vol. 78, No. 181 / Wednesday, September 18, 2013 / Notices
rail plans should be aligned, to the
extent possible, with other planning
documents. Accordingly, the guidance
has been revised to encourage States to
update State rail plans on a consistent
cycle with other planning documents, at
least every 5 years.
A commenter suggested that the
guidance be revised to allow States the
flexibility to align the planning horizons
of State rail plans with those used in
their other planning and programming
documents. Response: FRA has revised
the guidance to allow States to use
longer horizon time periods for the Rail
Service and Investment Program as long
as it identifies specific projects for the
4-year short-term and 20-year vision
components.
A commenter recommended adding a
requirement that statewide/
nonmetropolitan and metropolitan
transportation planning processes
consider the rail transportation needs of
military and federal facilities where
appropriate and where regional
transportation has an impact on
‘‘military readiness.’’ Response: FRA
has revised the guidance to require
States to identify Strategic Rail Corridor
Network (STRACNET) facilities in the
State rail plans. In addition, revisions
also were made to encourage States to
include the rail transportation needs of
military and federal facilities in their
statewide/nonmetropolitan planning
processes, as well as in development of
State rail plans, as appropriate.
A commenter recommended that the
FRA Regional Manager be included as a
non-voting member on MPO policy
boards. Response: While FRA staff can
provide technical assistance to States
during State rail plan development and
MPOs have broad latitude to include
non-voting members from Federal and
non-Federal agencies, recommending
such action is beyond the scope of
PRIIA and this guidance.
A commenter questioned the focus
directed to ‘‘megaregions,’’ in that the
concept does not apply to rural States as
they seek to accommodate their product
shipment needs, as well as serving as
through-movement ‘‘bridge states’’ for
transporting goods to market. Response:
FRA has revised the guidance to
reference rail service needs within and
between mega-regions, as well as to
passenger service and freight movement
needs in all other appropriate sections
of the country.
Public and Stakeholder Involvement
Several comments were received that
recommended linking public
involvement processes during State rail
plan development with the statewide/
nonmetropolitan and metropolitan
VerDate Mar<15>2010
16:45 Sep 17, 2013
Jkt 229001
transportation planning programs
required under 23 U.S.C. and Chapter
53 of 49 U.S.C. Following are the
detailed comments provided and FRA
responses regarding coordination of
public and stakeholder involvement
between State rail plan development
and the transportation planning
processes carried out by States and
MPOs.
Commenters recommended that the
guidance explicitly require that draft
State rail plans be presented for public
comment for at least 30 days prior to
being submitted to the FRA for
acceptance, as well as identify
milestones and minimum standards for
stakeholder and public involvement that
emphasize collaborative partnerships.
Response: The guidance has been
revised to encourage States to conduct
stakeholder involvement in full
coordination with, or incorporated
within, the public involvement
activities conducted by States and
MPOs in their respective transportation
planning processes. Federal
requirements for transportation
planning (23 CFR part 450) call for those
public involvement processes to be
developed by State and local officials,
not the Federal government, and to be
prepared in collaboration with the
public and stakeholders. The agreed
upon public involvement processes
must then be documented and
periodically evaluated for effectiveness.
Several commenters called for greater
clarity of the role of freight rail, noting
the unique position, perspectives, and
interests of privately owned freight rail
lines—as owners, operators, investors,
and private sector partners in rail
development. Comments particularly
focused on the need for States to respect
the proprietary nature of inventory and
operations data held by private freight
rail operators and to protect the
confidentiality of such data if obtained
for use in State rail plan development.
Concern was expressed for including
privately funded rail improvements in
the State rail plan, as privately funded
improvements typically are not
included in the plans of States and
MPOs. Response: FRA recognizes
limitations to imposing requirements on
and requesting data from private
operators and the guidance has been
revised to stress the importance of
obtaining private freight rail
perspectives in State rail plan
development while respecting their
private business status and the
proprietary nature of their market and
operating data. Language requesting
States to include privately funded rail
facility improvements in State and MPO
PO 00000
Frm 00102
Fmt 4703
Sfmt 4703
plans, TIPs, and STIPs was retained for
information and coordination purposes.
Several commenters noted how rail
unions both influence, and are
influenced by, the contents of State rail
plans, and recommended that those
organizations be explicitly mentioned
among the stakeholder interests.
Response: FRA has added ‘‘Rail Labor
Organizations’’ to the list of stakeholder
interests for which an opportunity to
contribute to and comment on the
development of the State rail plan
should be provided.
A commenter recommended
including MPOs among the list of
stakeholders with whom State rail plan
development should be coordinated.
Response: FRA has added focus on
engaging MPOs in the development of
State rail plans in the revised guidance.
Content and Format of State Rail Plans
Several comments were received
recommending a relaxation of the level
of detail required of the proposed
improvements in the 20-year State rail
plan, as well as potential sources of
funding and analysis of impacts. Other
topics were proposed for more detailed
discussion, including the role and
planning implication of public-private
partnerships, integrated planning for
passenger and freight rail, and reference
to Service Development Plans (SDPs) in
the State rail plan documents.
A commenter suggested requiring less
detailed information on commuter rail
activities because the State rail plan
qualifies States to receive grants for
high-speed rail only. Response:
Operational information about all
relevant services, including intercity
and commuter rail, is needed for
coordinated planning. Such information
should be readily available from the
public operators of commuter rail.
Accordingly, the guidance was not
changed.
A commenter expressed concern for
requiring inclusion of a detailed list of
rail capital projects in the State rail plan
due to the cost and administrative
burden, as well as the separate MAP–21
requirements for highway and transit
project listings in the STIP. Several
other commenters questioned the need
to identify the distribution of benefits
from rail service implementation to
regions. Response: PRIIA requires State
rail plans to include a list of proposed
rail improvements, as well as an
analysis of the distribution of benefits to
regions. Accordingly, FRA has not
modified those provisions in the
guidance. However, inclusion of rail
improvements in the TIPs/STIPs
prepared by MPOs and States, while
encouraged by the guidance, is not
E:\FR\FM\18SEN1.SGM
18SEN1
emcdonald on DSK67QTVN1PROD with NOTICES
Federal Register / Vol. 78, No. 181 / Wednesday, September 18, 2013 / Notices
required. The guidance has been revised
to clarify that inclusion of rail
improvements in TIPs/STIPs is for
information and coordination purposes
only.
Several commenters expressed
concern for the level and detail of
analysis of rail’s impact on the range of
factors published in the guidance,
including congestion mitigation, safety,
economic development, air quality, land
use, and energy use. A commenter
proposed that the impact analyses for
the 20-year plan be conducted on a
corridor-basis, rather than at the project
level. Another commenter expressed
concern that specific financing
strategies and the level of detail
requested for data associated with the
passenger and freight rail proposals are
too detailed for projects in the early
stages of planning over a 20-year period.
Response: FRA agrees that the
descriptive detail of individual rail
proposals and discussion of their
potential impacts should be most
detailed for the immediate 4-year phase
of the Rail Service Investment Program,
with a more aggregate, general
description of impacts and financial
information that is ‘‘reasonably
expected’’ for the outer years of the full
20-year plan. The guidance was revised
accordingly, with distinction between
the information that is expected of the
4-year phase vs. the outer years of the
20-year plan.
A commenter proposed expanding the
discussion of public private
partnerships (PPP) to include a fuller
description of the concept, benefits, and
supportive planning techniques
associated with PPPs. Response: Text
regarding the value of PPPs in rail
development and operation has been
added.
A commenter noted that planning for
passenger and freight rail needs to take
place in a coordinated, non-competitive
fashion. It was recommended that
narrative be added to the guidance to
describe the shared rail synergies and
win-win solutions that are possible with
passenger and freight coordination.
Response: FRA supports coordinated
and integrated rail planning and
operation across passenger and freight
markets and has revised the guidance in
several sections accordingly.
A commenter suggested that States be
required to include discussion of SDPs
in State rail plans. Response: While an
SDP is a vital plan for passenger rail
corridor investment, the time horizon of
each SDP may not always fit within
every State’s long-range rail
improvement framework. States may
optionally choose to include discussion
of SDPs where they exist.
VerDate Mar<15>2010
16:45 Sep 17, 2013
Jkt 229001
Procedures for Preparing and
Submitting State Rail Plans
Several comments were received
regarding the administrative preparation
of State rail plans, as well as review and
acceptance by FRA. Some commenters
proposed increasing the frequency of
State rail plan updates and lengthening
the planning horizon. Other
commenters requested clarification of
when and how FRA would review the
draft documents.
A commenter sought clarification of
the eligibility of States to receive
funding under Section 301, 302, and
501 of PRIIA if their State rail plans
were under development at the time of
publication of final State Rail Plan
Guidance. Another commenter
requested clarification of FRA’s
timetable for reviewing and accepting
State rail plans if a Notice of Funding
Availability (NOFA) should happen to
be issued for capital grants under
Sections 301, 302, and 501 prior to
‘‘acceptance’’ of the plan by FRA.
Response: The guidance has been
revised to clarify that State rail plans
that were in preparation prior to
issuance of this final guidance, and that
substantially meet the requirements of
PRIIA, will be deemed by FRA to meet
program and project eligibility
requirements for grants authorized
under Sections 301, 302, and 501 of
PRIIA. The guidance has been revised to
add that a State rail plan for which
contractor assistance had reached the
‘‘notice-to-proceed’’ stage will be
considered ‘‘underway.’’ Also, FRA will
exercise due diligence in reviewing asyet-unapproved State rail plans in a
timely manner when any future funding
NOFAs may be issued.
A commenter questioned the need for
States to establish two separate
authorities and asked if a single
authority could serve both purposes.
Response: PRIIA calls for States to
designate the two authorities noted
above; however the guidance was
revised to indicate that the same State
entity can serve both purposes.
A commenter suggested that the
guidance outline a clear process and
timeline for FRA review and acceptance
of draft and final State rail plans, as well
as a process for submitting amended
State rail plans. Response: The
published draft guidance described a
formal process for State rail plan
submittal to FRA and notification of
receipt by FRA, upon which FRA has
committed to a 90-day review and
acceptance schedule. Language has been
added clarifying that updates of State
rail plans may be submitted at any time
the State deems necessary, for which
PO 00000
Frm 00103
Fmt 4703
Sfmt 4703
57453
FRA would follow the process described
for all plan submissions—regardless of
their frequency or what triggered the
update.
A commenter noted potentially
conflicting statements in the guidance
regarding submission of State rail plans
in draft form to FRA vs. transmittal of
the final draft. Response: The guidance
was clarified to describe how States are
encouraged to submit preliminary drafts
of their State rail plans to FRA for
review and comment prior to formal
submission of the final draft plan.
Data Requirements for State Rail Plans
Most commenters expressed concern
for the amount of data collection and
analysis required in State rail plans—
particularly for rail concepts that were
more than 20 years in the future.
Commenters expressed concern for the
availability of data, particularly for
privately owned/operated services.
Special attention was proposed for
collecting information around stations
and intermodal transfer points.
A commenter noted that data was not
available for all of the metrics contained
in Section 207 of PRIIA and that States
should be responsible only for accessing
information that is actually available.
Two other commenters proposed that
FRA assemble the required data
inventories and provide them to the
States as a cost-saving measure and to
ensure consistency. Response: FRA has
revised the guidance to indicate that
only available data should be required
for inclusion in State rail plans. The
suggestion that FRA compile the
necessary data resources will be taken
under advisement and considered,
subject to resource availability at the
Federal level.
A commenter noted that the effort
entailed in compiling demographic data
for all station areas could be excessive.
Four other commenters expressed
concern that assembling detailed
information on station facility
improvements and area land use plans
would be excessive and possibly
duplicative of local plans, necessitating
the provision of more detailed guidance
on the methodologies and data inputs.
Response: The guidance has been
revised to remove the request for
detailed demographic data and instead
promotes close integration of State rail
plan development within the statewide/
nonmetropolitan transportation
planning process, which could provide
ready access to land use data for entire
study areas, corridors, and stationspecific information. FRA also agrees
with the concern about collecting
information on improvements to nonmajor station facilities and has revised
E:\FR\FM\18SEN1.SGM
18SEN1
emcdonald on DSK67QTVN1PROD with NOTICES
57454
Federal Register / Vol. 78, No. 181 / Wednesday, September 18, 2013 / Notices
the presentation of that information at a
summary or program level. However,
station information for major passenger
and freight intermodal connections and
facilities is an explicit provision in
PRIIA, and remains a part of the
guidance. Lastly, the guidance was
revised to call for ‘‘a summary level of
discussion’’ on land use impacts.
A commenter expressed concern for
reporting station-to-station intrastate
ridership for any but the top ten city
pairs, proposing that States simply
report boardings and alightings.
Response: A comprehensive profile of
current usage is a critical component to
preparation of a credible State rail plan,
and limiting ridership flows to the top
city pairs will not provide useful
information on growth trends in small
and mid-sized markets. Therefore, no
change has been made.
Several commenters proposed not
collecting information on the owner/
operator status of rail lines, citing the
difficulty, expense, and inconsistency
with PRIIA. Response: Owner/operator
status of rail lines as a key element of
the inventory of the existing rail
services and facilities within the State,
which is an explicit requirement of
PRIIA. The guidance has been revised to
identify the availability of the data in
GIS format from the National
Transportation Atlas Database (NTAD),
which is maintained online by the U.S.
Department of Transportation. In
addition, information on publicly
funded commuter rail operations should
be available through the MPO if in an
urbanized area or State if in a nonurbanized area.
A commenter regarded ‘‘railway
assets currently out of service or rail
banked’’ as abandoned and expressed
concern for the burden of assembling an
inventory of those lines. Response: Railbanked and out of service rail lines have
not been formally abandoned and
therefore remain important rail facilities
to be inventoried.
A commenter recommended adding a
section on passenger station needs and
plans. Response: FRA agrees that station
planning, including consideration of
usage, station area development and
interfaces with other modes, is
important and the topic has been added
to the guidance.
A commenter suggested that
evaluation of passenger rail projects for
impact on livability, land use, and
walkability would be too detailed for a
statewide level document describing
projects at the systems planning stage of
development. Response: FRA has
revised the guidance to call for analysis
of land use impacts only for those
projects that have reached the
VerDate Mar<15>2010
16:45 Sep 17, 2013
Jkt 229001
environmental analysis phase, with a
summary discussion of land use impacts
required elsewhere.
A commenter requested that FRA
provide benefit-cost formulas for use by
States. Response: Currently, FRA does
not have specific guidance on benefitcost analyses but may be able to provide
technical assistance upon request.
However, the DOT Office of Inspector
General recently released a report
highlighting best practices in
conducting rail benefits assessments,
available at: https://www.oig.dot.gov/
sites/dot/files/OIG–HSR-Best-PracticePublic-Benefits-Report.pdf.
Additionally, benefit-cost guidance used
for the TIGER grant program can be used
to structure a rail analysis: https://
www.dot.gov/sites/dot.dev/files/docs/
TIGER%202013%20NOFA_
BCA%20Guidance_0.pdf.
A commenter requested more
information on the list of performance
measures proposed in Appendix 1 for
possible inclusion in Section 2.1.
Response: The guidance was not revised
because the measures were listed as
optional information items offered for
consideration, subject to their
availability.
A commenter suggested that ridership
information may not be available from
more than 5 years prior and proposed
modifying the request to apply to only
the previous five years. Another
commenter noted that passenger train
miles (adjusted for cancellations/
terminations) is typically available only
from Amtrak. Another commenter
proposed that passenger mile data be
provided on a route basis. Response:
FRA has revised the guidance to request
data only for only the past 5 years, with
States encouraged to use data from
earlier years if they have it. The
guidance also was revised to advise that
‘‘general estimates’’ of passenger mile
data are acceptable for state-supported
services, with route-level data
acceptable for long-distance trains.
A commenter expressed concern for
the lack of intercity rail mode share
data, as required by the draft guidance
for State rail plans. Response: FRA has
revised the guidance to require
inclusion of mode share data only if it
is available, or able to be calculated,
through the use of existing information.
A commenter suggested that
commuter rail mode share be calculated
as commuter rail trips per total public
transit trips. Response: FRA has
retained the definition given in the draft
guidance in order to provide a
consistent measurement standard for all
State rail plans. Individual States may
optionally choose additional measures
PO 00000
Frm 00104
Fmt 4703
Sfmt 4703
and alternative definitions of mode
share if they wish.
Availability of Final Guidance
Notice is hereby given that FRA has
released final State Rail Plan Guidance,
which is available at: https://
www.fra.dot.gov/Page/P0511. The
purpose of FRA’s final State Rail Plan
Guidance is to describe the processes for
the development, submission, and
acceptance of State rail plans. State rail
plans are documents that are required
under Section 303 of the Passenger Rail
Investment and Improvement Act of
2008.
Paul Nissenbaum,
Associate Administrator for Railroad Policy
and Development.
[FR Doc. 2013–22679 Filed 9–17–13; 8:45 am]
BILLING CODE 4910–06–P
DEPARTMENT OF TRANSPORTATION
Maritime Administration
Marine Transportation System National
Advisory Council
Maritime Administration, DOT.
Notice of request for
applications.
AGENCY:
ACTION:
The Maritime Administration
(MarAd) is seeking applications for
membership on the Marine
Transportation System National
Advisory Council (MTSNAC). The
Council advises and makes
recommendations to the Secretary of
Transportation (Secretary) via the
Maritime Administrator on
impediments to the effective use and
expansion of America’s Marine
Highways; waterways and ports, and
their intermodal, road, rail, and marine
highway connections; shipbuilding
capacity; and guidelines for the
development of a national freight policy
from a marine transportation
perspective.
SUMMARY:
MTSNAC applications should be
received on or before October 18, 2013.
ADDRESSES: Submit your application by
mail, email, or facsimile to MarAdMTSNAC Designated Federal Officer,
Room W21–310, U.S. Department of
Transportation, 1200 New Jersey
Avenue SE., Washington, DC 20590.
Email: nac.marad@dot.gov. Fax: (202)
366–6988.
FOR FURTHER INFORMATION CONTACT: Mr.
Richard Lolich, MTSNAC Designated
Federal Officer, Maritime
Administration, 1200 New Jersey
Avenue SE., Room W21–310,
Washington, DC 20590, Richard.Lolich@
DATES:
E:\FR\FM\18SEN1.SGM
18SEN1
Agencies
[Federal Register Volume 78, Number 181 (Wednesday, September 18, 2013)]
[Notices]
[Pages 57450-57454]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-22679]
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Federal Railroad Administration
[Docket No. FRA-2012-0066]
State Rail Plan Guidance
AGENCY: Federal Railroad Administration (FRA), Department of
Transportation (DOT).
ACTION: Notice of Availability of Final State Rail Plan Guidance.
-----------------------------------------------------------------------
SUMMARY: FRA is publishing this notice to announce the availability of
final State Rail Plan Guidance. The purpose of FRA's final State Rail
Plan Guidance is to describe the processes for the development,
submission, and acceptance of State rail plans. State rail plans are
documents that are required under Section 303 of the Passenger Rail
Investment and Improvement Act of 2008 (PRIIA). Section 303 of PRIIA
provides for enhanced State involvement in rail policy, planning, and
development efforts, including requiring States to develop FRA-accepted
State rail plans in order to be eligible for the capital grants
authorized in the Act and available under the High-Speed Intercity
Passenger Rail program. This guidance provides an explanation of the
process to be followed in developing State rail plans, FRA's process
for reviewing and accepting State rail plans, a standardized format,
and a list of the minimum content requirements for State rail plans.
The State Rail Plan Guidance is available on FRA's Web site at https://www.fra.dot.gov/Page/P0511.
DATES: The final State Rail Plan Guidance is effective as of the
publication of this notice on September 18, 2013.
Applicability: Any State rail plan whose development is begun after
publication of this notice must adhere to the standardized format and
minimum content requirements defined within the guidance in order to be
accepted by the FRA.
[[Page 57451]]
FOR FURTHER INFORMATION CONTACT: For questions about this notice,
please contact Kyle Gradinger, Transportation Industry Analyst, Office
of Railroad Policy and Development, Federal Railroad Administration,
1200 New Jersey Ave. SE., W38-202, Washington, DC 20590; telephone:
(202) 493-6191.
SUPPLEMENTARY INFORMATION: Final State Rail Plan Guidance was prepared
through a notice and comment process involving publication of draft
guidance announced in the August 28, 2012 issue of the Federal
Register, soliciting public review and comment over the following 90
day period. FRA received 121 individual comments from 55 respondents.
Comments were received from a diverse group comprised of eight (8)
State departments of transportation, one (1) metropolitan planning
organization (MPO), eleven (11) trade organizations, five (5) national
stakeholder organizations, one (1) private individual, and one (1)
public transportation service provider.
Broad support was offered by commenters for preparing State rail
plans as part of a comprehensive, coordinated planning framework within
and among States, and for addressing passenger and freight needs in an
integrated, coordinated way. Almost unanimous support was offered for
integrating, to the extent possible, preparation of State rail plans
with the statewide/nonmetropolitan and metropolitan transportation
planning programs required under the Federal-aid Highway and Federal
Transit titles--23 U.S.C. and Chapter 53 of 49 U.S.C., respectively.
Similarly, it is within that expanded transportation planning context
of States and metropolitan planning organizations (MPOs) that
commenters proposed engagement of an expansive range of stakeholder
interests in State rail plan development--spanning industry,
government, labor, local communities, and the private sector.
However, concerns were expressed by commenters for several
procedural aspects of State rail plan preparation, including data
collection and the depth of impact assessment required for the rail
infrastructure, facilities, and service improvements contained in State
rail plans. Other issues raised by commenters included the importance
of involving private rail interests in meaningful ways in State rail
plan development, while respecting the proprietary nature of their
operational and financial records. These comments are grouped and
summarized below by topic with FRA responses.
Coordination With Statewide/Nonmetropolitan and Metropolitan
Transportation Planning
Several comments were received supporting full coordination of
State rail plan development with the statewide/nonmetropolitan and
metropolitan transportation planning programs required under 23 U.S.C.
and Chapter 53 of 49 U.S.C. Commenters recommended a range of specific
planning work activities and planning products that represent the best
opportunities for coordination with State rail plan development.
Following are the details of comments provided and FRA responses
regarding coordination between State rail plan development and the
transportation planning processes carried out by States and MPOs.
Several commenters proposed that States prepare State rail plans as
part of metropolitan and statewide/nonmetropolitan transportation
planning processes in order to eliminate duplication of effort.
Particular concern was expressed for not establishing a separate
planning process for State rail plans--apart from those existing
planning processes. It was proposed that States be able to incorporate
visions, plans, and priorities that consider rail as one of many
transportation modes, in a single statewide transportation plan, with
the State rail plan incorporated within the overall plan or as an
addendum. A commenter also requested clarification of the term
``compatible,'' as it was used in the draft guidance to describe the
relationship between the State rail plan and planning processes.
Response: FRA has revised the draft guidance to emphasize the
importance of preparing State rail plans within the policy and
procedural contexts of the multimodal transportation planning processes
conducted by states and MPOs and to integrate the documents as much as
possible. In revising the guidance, FRA was careful not to convey the
MAP-21 financial constraint requirements associated with highway and
transit listings to the rail proposals listed in the State rail plan.
Also, to improve clarity, the term ``compatible'' was replaced with
language calling for state rail plans to be generally consistent with
other planning documents and policies.
A commenter recommended that the guidance stipulate that State rail
plans should be prepared in coordination with the new freight planning
activities carried out by States in accordance with MAP-21. The
commenter proposed that the guidance direct States to describe how
their State's long-term vision for rail integrates with the State
Freight Plan, as well as the National Freight Policy, the National
Freight Strategic Plan, and the National Export Initiative. Another
commenter recommended that State rail plans include in depth discussion
of the changing freight market. Response: FRA agrees that State rail
plans should be prepared with full understanding of the current and
emerging freight, as well as passenger, markets and has revised the
guidance accordingly. Language also has been added to the guidance
recommending that States coordinate preparation of State freight plans
and State rail plans.
A commenter proposed closer coordination between FRA and FHWA and
State highway offices, suggesting that States be required to consider
the cross-effects of investment in rail and highway improvements,
including consideration of rail when planning future highway
investments. Another commenter recommends that the guidance
specifically require State rail plans to identify the potential impacts
of individual projects, as well as the combined impact of all projects
in the State rail plan. Specifically, they recommended that local
transit modes be added to the list of ``highway, aviation and maritime
modes'' included in the draft guidance. Response: FRA added ``local
transit'' to the list of modes for which potential impacts of State
rail plan implementation should be analyzed and added emphasis about
the need to assess potential project impacts on an individual, as well
as combined, basis.
A commenter recommended revising the guidance to promote
consistency between the performance measures used in preparing State
rail plans and those used in the statewide/nonmetropolitan and
metropolitan transportation planning process, including use of easy-to-
read tables. Response: FRA agrees that using consistent performance
measures is preferable and has revised the guidance to include
reference to using performance measures in coordination with those used
in broader transportation planning processes, including promoting
consistency with transit asset management plans required under MAP-21.
A commenter recommended changing the 5-year state rail plan update
cycle included in the draft guidance to a 4-year cycle, for consistency
with the document update cycles prescribed in MAP-21 for planning
documents. Another commenter proposed annual updates. Response: The 5-
year update provision is set forth in PRIIA and cannot be changed.
However, FRA agrees that the update cycles of State
[[Page 57452]]
rail plans should be aligned, to the extent possible, with other
planning documents. Accordingly, the guidance has been revised to
encourage States to update State rail plans on a consistent cycle with
other planning documents, at least every 5 years.
A commenter suggested that the guidance be revised to allow States
the flexibility to align the planning horizons of State rail plans with
those used in their other planning and programming documents. Response:
FRA has revised the guidance to allow States to use longer horizon time
periods for the Rail Service and Investment Program as long as it
identifies specific projects for the 4-year short-term and 20-year
vision components.
A commenter recommended adding a requirement that statewide/
nonmetropolitan and metropolitan transportation planning processes
consider the rail transportation needs of military and federal
facilities where appropriate and where regional transportation has an
impact on ``military readiness.'' Response: FRA has revised the
guidance to require States to identify Strategic Rail Corridor Network
(STRACNET) facilities in the State rail plans. In addition, revisions
also were made to encourage States to include the rail transportation
needs of military and federal facilities in their statewide/
nonmetropolitan planning processes, as well as in development of State
rail plans, as appropriate.
A commenter recommended that the FRA Regional Manager be included
as a non-voting member on MPO policy boards. Response: While FRA staff
can provide technical assistance to States during State rail plan
development and MPOs have broad latitude to include non-voting members
from Federal and non-Federal agencies, recommending such action is
beyond the scope of PRIIA and this guidance.
A commenter questioned the focus directed to ``megaregions,'' in
that the concept does not apply to rural States as they seek to
accommodate their product shipment needs, as well as serving as
through-movement ``bridge states'' for transporting goods to market.
Response: FRA has revised the guidance to reference rail service needs
within and between mega-regions, as well as to passenger service and
freight movement needs in all other appropriate sections of the
country.
Public and Stakeholder Involvement
Several comments were received that recommended linking public
involvement processes during State rail plan development with the
statewide/nonmetropolitan and metropolitan transportation planning
programs required under 23 U.S.C. and Chapter 53 of 49 U.S.C. Following
are the detailed comments provided and FRA responses regarding
coordination of public and stakeholder involvement between State rail
plan development and the transportation planning processes carried out
by States and MPOs.
Commenters recommended that the guidance explicitly require that
draft State rail plans be presented for public comment for at least 30
days prior to being submitted to the FRA for acceptance, as well as
identify milestones and minimum standards for stakeholder and public
involvement that emphasize collaborative partnerships. Response: The
guidance has been revised to encourage States to conduct stakeholder
involvement in full coordination with, or incorporated within, the
public involvement activities conducted by States and MPOs in their
respective transportation planning processes. Federal requirements for
transportation planning (23 CFR part 450) call for those public
involvement processes to be developed by State and local officials, not
the Federal government, and to be prepared in collaboration with the
public and stakeholders. The agreed upon public involvement processes
must then be documented and periodically evaluated for effectiveness.
Several commenters called for greater clarity of the role of
freight rail, noting the unique position, perspectives, and interests
of privately owned freight rail lines--as owners, operators, investors,
and private sector partners in rail development. Comments particularly
focused on the need for States to respect the proprietary nature of
inventory and operations data held by private freight rail operators
and to protect the confidentiality of such data if obtained for use in
State rail plan development. Concern was expressed for including
privately funded rail improvements in the State rail plan, as privately
funded improvements typically are not included in the plans of States
and MPOs. Response: FRA recognizes limitations to imposing requirements
on and requesting data from private operators and the guidance has been
revised to stress the importance of obtaining private freight rail
perspectives in State rail plan development while respecting their
private business status and the proprietary nature of their market and
operating data. Language requesting States to include privately funded
rail facility improvements in State and MPO plans, TIPs, and STIPs was
retained for information and coordination purposes.
Several commenters noted how rail unions both influence, and are
influenced by, the contents of State rail plans, and recommended that
those organizations be explicitly mentioned among the stakeholder
interests. Response: FRA has added ``Rail Labor Organizations'' to the
list of stakeholder interests for which an opportunity to contribute to
and comment on the development of the State rail plan should be
provided.
A commenter recommended including MPOs among the list of
stakeholders with whom State rail plan development should be
coordinated. Response: FRA has added focus on engaging MPOs in the
development of State rail plans in the revised guidance.
Content and Format of State Rail Plans
Several comments were received recommending a relaxation of the
level of detail required of the proposed improvements in the 20-year
State rail plan, as well as potential sources of funding and analysis
of impacts. Other topics were proposed for more detailed discussion,
including the role and planning implication of public-private
partnerships, integrated planning for passenger and freight rail, and
reference to Service Development Plans (SDPs) in the State rail plan
documents.
A commenter suggested requiring less detailed information on
commuter rail activities because the State rail plan qualifies States
to receive grants for high-speed rail only. Response: Operational
information about all relevant services, including intercity and
commuter rail, is needed for coordinated planning. Such information
should be readily available from the public operators of commuter rail.
Accordingly, the guidance was not changed.
A commenter expressed concern for requiring inclusion of a detailed
list of rail capital projects in the State rail plan due to the cost
and administrative burden, as well as the separate MAP-21 requirements
for highway and transit project listings in the STIP. Several other
commenters questioned the need to identify the distribution of benefits
from rail service implementation to regions. Response: PRIIA requires
State rail plans to include a list of proposed rail improvements, as
well as an analysis of the distribution of benefits to regions.
Accordingly, FRA has not modified those provisions in the guidance.
However, inclusion of rail improvements in the TIPs/STIPs prepared by
MPOs and States, while encouraged by the guidance, is not
[[Page 57453]]
required. The guidance has been revised to clarify that inclusion of
rail improvements in TIPs/STIPs is for information and coordination
purposes only.
Several commenters expressed concern for the level and detail of
analysis of rail's impact on the range of factors published in the
guidance, including congestion mitigation, safety, economic
development, air quality, land use, and energy use. A commenter
proposed that the impact analyses for the 20-year plan be conducted on
a corridor-basis, rather than at the project level. Another commenter
expressed concern that specific financing strategies and the level of
detail requested for data associated with the passenger and freight
rail proposals are too detailed for projects in the early stages of
planning over a 20-year period. Response: FRA agrees that the
descriptive detail of individual rail proposals and discussion of their
potential impacts should be most detailed for the immediate 4-year
phase of the Rail Service Investment Program, with a more aggregate,
general description of impacts and financial information that is
``reasonably expected'' for the outer years of the full 20-year plan.
The guidance was revised accordingly, with distinction between the
information that is expected of the 4-year phase vs. the outer years of
the 20-year plan.
A commenter proposed expanding the discussion of public private
partnerships (PPP) to include a fuller description of the concept,
benefits, and supportive planning techniques associated with PPPs.
Response: Text regarding the value of PPPs in rail development and
operation has been added.
A commenter noted that planning for passenger and freight rail
needs to take place in a coordinated, non-competitive fashion. It was
recommended that narrative be added to the guidance to describe the
shared rail synergies and win-win solutions that are possible with
passenger and freight coordination. Response: FRA supports coordinated
and integrated rail planning and operation across passenger and freight
markets and has revised the guidance in several sections accordingly.
A commenter suggested that States be required to include discussion
of SDPs in State rail plans. Response: While an SDP is a vital plan for
passenger rail corridor investment, the time horizon of each SDP may
not always fit within every State's long-range rail improvement
framework. States may optionally choose to include discussion of SDPs
where they exist.
Procedures for Preparing and Submitting State Rail Plans
Several comments were received regarding the administrative
preparation of State rail plans, as well as review and acceptance by
FRA. Some commenters proposed increasing the frequency of State rail
plan updates and lengthening the planning horizon. Other commenters
requested clarification of when and how FRA would review the draft
documents.
A commenter sought clarification of the eligibility of States to
receive funding under Section 301, 302, and 501 of PRIIA if their State
rail plans were under development at the time of publication of final
State Rail Plan Guidance. Another commenter requested clarification of
FRA's timetable for reviewing and accepting State rail plans if a
Notice of Funding Availability (NOFA) should happen to be issued for
capital grants under Sections 301, 302, and 501 prior to ``acceptance''
of the plan by FRA. Response: The guidance has been revised to clarify
that State rail plans that were in preparation prior to issuance of
this final guidance, and that substantially meet the requirements of
PRIIA, will be deemed by FRA to meet program and project eligibility
requirements for grants authorized under Sections 301, 302, and 501 of
PRIIA. The guidance has been revised to add that a State rail plan for
which contractor assistance had reached the ``notice-to-proceed'' stage
will be considered ``underway.'' Also, FRA will exercise due diligence
in reviewing as-yet-unapproved State rail plans in a timely manner when
any future funding NOFAs may be issued.
A commenter questioned the need for States to establish two
separate authorities and asked if a single authority could serve both
purposes. Response: PRIIA calls for States to designate the two
authorities noted above; however the guidance was revised to indicate
that the same State entity can serve both purposes.
A commenter suggested that the guidance outline a clear process and
timeline for FRA review and acceptance of draft and final State rail
plans, as well as a process for submitting amended State rail plans.
Response: The published draft guidance described a formal process for
State rail plan submittal to FRA and notification of receipt by FRA,
upon which FRA has committed to a 90-day review and acceptance
schedule. Language has been added clarifying that updates of State rail
plans may be submitted at any time the State deems necessary, for which
FRA would follow the process described for all plan submissions--
regardless of their frequency or what triggered the update.
A commenter noted potentially conflicting statements in the
guidance regarding submission of State rail plans in draft form to FRA
vs. transmittal of the final draft. Response: The guidance was
clarified to describe how States are encouraged to submit preliminary
drafts of their State rail plans to FRA for review and comment prior to
formal submission of the final draft plan.
Data Requirements for State Rail Plans
Most commenters expressed concern for the amount of data collection
and analysis required in State rail plans--particularly for rail
concepts that were more than 20 years in the future. Commenters
expressed concern for the availability of data, particularly for
privately owned/operated services. Special attention was proposed for
collecting information around stations and intermodal transfer points.
A commenter noted that data was not available for all of the
metrics contained in Section 207 of PRIIA and that States should be
responsible only for accessing information that is actually available.
Two other commenters proposed that FRA assemble the required data
inventories and provide them to the States as a cost-saving measure and
to ensure consistency. Response: FRA has revised the guidance to
indicate that only available data should be required for inclusion in
State rail plans. The suggestion that FRA compile the necessary data
resources will be taken under advisement and considered, subject to
resource availability at the Federal level.
A commenter noted that the effort entailed in compiling demographic
data for all station areas could be excessive. Four other commenters
expressed concern that assembling detailed information on station
facility improvements and area land use plans would be excessive and
possibly duplicative of local plans, necessitating the provision of
more detailed guidance on the methodologies and data inputs. Response:
The guidance has been revised to remove the request for detailed
demographic data and instead promotes close integration of State rail
plan development within the statewide/nonmetropolitan transportation
planning process, which could provide ready access to land use data for
entire study areas, corridors, and station-specific information. FRA
also agrees with the concern about collecting information on
improvements to non-major station facilities and has revised
[[Page 57454]]
the presentation of that information at a summary or program level.
However, station information for major passenger and freight intermodal
connections and facilities is an explicit provision in PRIIA, and
remains a part of the guidance. Lastly, the guidance was revised to
call for ``a summary level of discussion'' on land use impacts.
A commenter expressed concern for reporting station-to-station
intrastate ridership for any but the top ten city pairs, proposing that
States simply report boardings and alightings. Response: A
comprehensive profile of current usage is a critical component to
preparation of a credible State rail plan, and limiting ridership flows
to the top city pairs will not provide useful information on growth
trends in small and mid-sized markets. Therefore, no change has been
made.
Several commenters proposed not collecting information on the
owner/operator status of rail lines, citing the difficulty, expense,
and inconsistency with PRIIA. Response: Owner/operator status of rail
lines as a key element of the inventory of the existing rail services
and facilities within the State, which is an explicit requirement of
PRIIA. The guidance has been revised to identify the availability of
the data in GIS format from the National Transportation Atlas Database
(NTAD), which is maintained online by the U.S. Department of
Transportation. In addition, information on publicly funded commuter
rail operations should be available through the MPO if in an urbanized
area or State if in a non-urbanized area.
A commenter regarded ``railway assets currently out of service or
rail banked'' as abandoned and expressed concern for the burden of
assembling an inventory of those lines. Response: Rail-banked and out
of service rail lines have not been formally abandoned and therefore
remain important rail facilities to be inventoried.
A commenter recommended adding a section on passenger station needs
and plans. Response: FRA agrees that station planning, including
consideration of usage, station area development and interfaces with
other modes, is important and the topic has been added to the guidance.
A commenter suggested that evaluation of passenger rail projects
for impact on livability, land use, and walkability would be too
detailed for a statewide level document describing projects at the
systems planning stage of development. Response: FRA has revised the
guidance to call for analysis of land use impacts only for those
projects that have reached the environmental analysis phase, with a
summary discussion of land use impacts required elsewhere.
A commenter requested that FRA provide benefit-cost formulas for
use by States. Response: Currently, FRA does not have specific guidance
on benefit-cost analyses but may be able to provide technical
assistance upon request. However, the DOT Office of Inspector General
recently released a report highlighting best practices in conducting
rail benefits assessments, available at: https://www.oig.dot.gov/sites/dot/files/OIG-HSR-Best-Practice-Public-Benefits-Report.pdf.
Additionally, benefit-cost guidance used for the TIGER grant program
can be used to structure a rail analysis: https://www.dot.gov/sites/dot.dev/files/docs/TIGER%202013%20NOFA_BCA%20Guidance_0.pdf.
A commenter requested more information on the list of performance
measures proposed in Appendix 1 for possible inclusion in Section 2.1.
Response: The guidance was not revised because the measures were listed
as optional information items offered for consideration, subject to
their availability.
A commenter suggested that ridership information may not be
available from more than 5 years prior and proposed modifying the
request to apply to only the previous five years. Another commenter
noted that passenger train miles (adjusted for cancellations/
terminations) is typically available only from Amtrak. Another
commenter proposed that passenger mile data be provided on a route
basis. Response: FRA has revised the guidance to request data only for
only the past 5 years, with States encouraged to use data from earlier
years if they have it. The guidance also was revised to advise that
``general estimates'' of passenger mile data are acceptable for state-
supported services, with route-level data acceptable for long-distance
trains.
A commenter expressed concern for the lack of intercity rail mode
share data, as required by the draft guidance for State rail plans.
Response: FRA has revised the guidance to require inclusion of mode
share data only if it is available, or able to be calculated, through
the use of existing information.
A commenter suggested that commuter rail mode share be calculated
as commuter rail trips per total public transit trips. Response: FRA
has retained the definition given in the draft guidance in order to
provide a consistent measurement standard for all State rail plans.
Individual States may optionally choose additional measures and
alternative definitions of mode share if they wish.
Availability of Final Guidance
Notice is hereby given that FRA has released final State Rail Plan
Guidance, which is available at: https://www.fra.dot.gov/Page/P0511. The
purpose of FRA's final State Rail Plan Guidance is to describe the
processes for the development, submission, and acceptance of State rail
plans. State rail plans are documents that are required under Section
303 of the Passenger Rail Investment and Improvement Act of 2008.
Paul Nissenbaum,
Associate Administrator for Railroad Policy and Development.
[FR Doc. 2013-22679 Filed 9-17-13; 8:45 am]
BILLING CODE 4910-06-P