National Fuel Gas Supply Corporation; Notice of Request Under Blanket Authorization, 55250-55251 [2013-21971]
Download as PDF
55250
Federal Register / Vol. 78, No. 175 / Tuesday, September 10, 2013 / Notices
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern
Time on September 20, 2013.
Dated: September 4, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–21973 Filed 9–9–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER13–2304–000]
sroberts on DSK5SPTVN1PROD with NOTICES
TEC Energy Inc.; Supplemental Notice
That Initial Market-Based Rate Filing
Includes Request for Blanket Section
204 Authorization
This is a supplemental notice in the
above-referenced proceeding, of TEC
Energy Inc.’s application for marketbased rate authority, with an
accompanying rate schedule, noting that
such application includes a request for
blanket authorization, under 18 CFR
part 34, of future issuances of securities
and assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability is September
23, 2013.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
VerDate Mar<15>2010
16:10 Sep 09, 2013
Jkt 229001
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 5 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
The filings in the above-referenced
proceeding(s) are accessible in the
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an eSubscription link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov. or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Dated: September 3, 2013
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2013–21959 Filed 9–9–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP13–536–000]
National Fuel Gas Supply Corporation;
Notice of Request Under Blanket
Authorization
Take notice that on August 23, 2013,
National Fuel Gas Supply Corporation
(National Fuel), 6363 Main Street,
Williamsville, New York, 14221, filed in
Docket No. CP13–536–000, an
application pursuant to sections 157.205
and 157.216 of the Commission’s
Regulations under the Natural Gas Act
(NGA) as amended, to convert one
injection/withdrawal well to an
observation well and to abandon the
associated well line in Colden Storage
Field located in Erie County, New York,
all as more fully set forth in the
application which is on file with the
Commission and open to public
inspection. The filing may also be
viewed on the web at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, please contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or toll
free at (866) 208–3676, or TTY, contact
(202) 502–8659.
PO 00000
Frm 00014
Fmt 4703
Sfmt 4703
Any questions concerning this
application may be directed to David W.
Reitz, Deputy General Counsel, National
Fuel Gas Supply Corporation, 6363
Main Street, Williamsville, New York,
14221, or phone (716) 857–7949.
Any person or the Commission’s staff
may, within 60 days after issuance of
the instant notice by the Commission,
file pursuant to Rule 214 of the
Commission’s Procedural Rules (18 CFR
385.214) a motion to intervene or notice
of intervention and pursuant to Section
157.205 of the regulations under the
NGA (18 CFR 157.205), a protest to the
request. If no protest is filed within the
time allowed therefore, the proposed
activity shall be deemed to be
authorized effective the day after the
time allowed for filing a protest. If a
protest is filed and not withdrawn
within 30 days after the allowed time
for filing a protest, the instant request
shall be treated as an application for
authorization pursuant to Section 7 of
the NGA.
Pursuant to Section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: Complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding, or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenter’s will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenter’s will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentary,
will not receive copies of all documents
filed by other parties or issued by the
E:\FR\FM\10SEN1.SGM
10SEN1
Federal Register / Vol. 78, No. 175 / Tuesday, September 10, 2013 / Notices
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
www.ferc.gov. Persons unable to file
electronically should submit an original
and 5 copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
Dated: September 3, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–21971 Filed 9–9–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP13–537–000]
sroberts on DSK5SPTVN1PROD with NOTICES
Southeast Supply Header, LLC; Notice
of Request Under Blanket
Authorization
Take notice that on August 23, 2013,
Southeast Supply Header, LLC (SESH),
P.O. Box 1642, Houston, Texas 77251–
1642, filed in Docket No. CP13–537–
000, an application pursuant to sections
157.205 and 157.216(b) of the
Commission’s Regulations under the
Natural Gas Act (NGA) as amended,
requesting authorization to offset and
replace approximately 5,700 feet of the
42-inch Line 100 pipeline in Claiborne
County, Mississippi. The authorizations
are requested under SESH’s blanket
certificate issued in Docket No. CP07–
46–000 1, all as more fully set forth in
the application which is on file with the
Commission and open to public
inspection.
SESH proposes to offset and replace
approximately 5,700 feet of the 42-inch
Line 100 pipeline via horizontal
directional drilling (HDD). Once the
new segment of Line 100 is installed,
SESH will abandon by removal an
approximate 4,000 foot section of the
existing Line 100 and abandon in place
the remainder. The estimated cost of the
project is approximately $14,000,000.
The Project will have no impact on
the certificated parameters of the SESH
pipeline. In addition, there will be no
abandonment or decrease in service to
SESH customers as a result of the
proposed Project. As described in the
1 See Southeast Supply Header, LLC et al, 119
FERC ¶ 61,153 (2007).
VerDate Mar<15>2010
16:10 Sep 09, 2013
Jkt 229001
application, ground-disturbing activities
necessary to construct the project will
result in minimal environmental
impacts.
The filing may also be viewed on the
web at https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, please contact
FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at (866) 208–3676, or TTY, contact
(202) 502–8659.
Any questions concerning this
application should be directed to P.
Martin Teague, Associate General
Counsel, Southeast Supply Header, LLC,
P.O. Box 1642, Houston, Texas 77251–
1642, phone (813) 282–6605, fax (813)
289–4438, or Email pmteague@
spectraenergy.com.
Any person or the Commission’s staff
may, within 60 days after issuance of
the instant notice by the Commission,
file pursuant to Rule 214 of the
Commission’s Procedural Rules (18 CFR
385.214) a motion to intervene or notice
of intervention and pursuant to Section
157.205 of the regulations under the
NGA (18 CFR 157.205), a protest to the
request. If no protest is filed within the
time allowed therefore, the proposed
activity shall be deemed to be
authorized effective the day after the
time allowed for filing a protest. If a
protest is filed and not withdrawn
within 30 days after the allowed time
for filing a protest, the instant request
shall be treated as an application for
authorization pursuant to Section 7 of
the NGA.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenter’s will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenter’s will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentary,
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://
PO 00000
Frm 00015
Fmt 4703
Sfmt 4703
55251
www.ferc.gov. Persons unable to file
electronically should submit an original
and 7 copies of the protest or
intervention to the Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
Comment Date: 5:00 p.m. Eastern
Time on November 4, 2013
Dated: September 4, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–21972 Filed 9–9–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. AD13–9–000]
Hydropower Regulatory Efficiency Act
of 2013; Notice of Workshop
The Federal Energy Regulatory
Commission (FERC or Commission) staff
will hold a workshop on October 2,
2013, from 12:00 p.m. (EDT) to 4:00
p.m. (EDT) in the Commission Meeting
Room at 888 First Street, NE.,
Washington, DC 20426. The workshop
will be open to the public, and all
interested parties are invited to attend
and participate.
The purpose of the workshop is to
begin investigating the feasibility of a
two-year process for the issuance of a
license for hydropower development at
non-powered dams and closed-loop
pumped storage projects in compliance
with section 6 of the Hydropower
Regulatory Efficiency Act of 2013.
Participants should be prepared to
discuss whether such a process is
feasible, present ideas on the details of
a two-year licensing process, discuss
potential criteria for identifying projects
that may be appropriate for a two-year
licensing process, and recommend
potential pilot projects to test a two-year
licensing process.
This workshop will be transcribed.
Transcripts of the workshop will be
immediately available for a fee from
Ace-Federal Reporters, Inc. at (202)
347–3700. A free webcast of this event
will be available through www.ferc.gov.
Anyone with internet access who wants
to view this event can do so by
navigating to the Calendar of Events at
www.ferc.gov and locating this event in
the Calendar. The event will contain a
link to its webcast. The Capitol
Connection provides technical support
for webcasts and offers the option of
listening to the workshop via phonebridge for a fee. If you have any
questions, visit
E:\FR\FM\10SEN1.SGM
10SEN1
Agencies
[Federal Register Volume 78, Number 175 (Tuesday, September 10, 2013)]
[Notices]
[Pages 55250-55251]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-21971]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP13-536-000]
National Fuel Gas Supply Corporation; Notice of Request Under
Blanket Authorization
Take notice that on August 23, 2013, National Fuel Gas Supply
Corporation (National Fuel), 6363 Main Street, Williamsville, New York,
14221, filed in Docket No. CP13-536-000, an application pursuant to
sections 157.205 and 157.216 of the Commission's Regulations under the
Natural Gas Act (NGA) as amended, to convert one injection/withdrawal
well to an observation well and to abandon the associated well line in
Colden Storage Field located in Erie County, New York, all as more
fully set forth in the application which is on file with the Commission
and open to public inspection. The filing may also be viewed on the web
at https://www.ferc.gov using the ``eLibrary'' link. Enter the docket
number excluding the last three digits in the docket number field to
access the document. For assistance, please contact FERC Online Support
at FERCOnlineSupport@ferc.gov or toll free at (866) 208-3676, or TTY,
contact (202) 502-8659.
Any questions concerning this application may be directed to David
W. Reitz, Deputy General Counsel, National Fuel Gas Supply Corporation,
6363 Main Street, Williamsville, New York, 14221, or phone (716) 857-
7949.
Any person or the Commission's staff may, within 60 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to Section 157.205 of
the regulations under the NGA (18 CFR 157.205), a protest to the
request. If no protest is filed within the time allowed therefore, the
proposed activity shall be deemed to be authorized effective the day
after the time allowed for filing a protest. If a protest is filed and
not withdrawn within 30 days after the allowed time for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to Section 7 of the NGA.
Pursuant to Section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice the Commission staff will either:
Complete its environmental assessment (EA) and place it into the
Commission's public record (eLibrary) for this proceeding, or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or EA for this
proposal. The filing of the EA in the Commission's public record for
this proceeding or the issuance of a Notice of Schedule for
Environmental Review will serve to notify federal and state agencies of
the timing for the completion of all necessary reviews, and the
subsequent need to complete all federal authorizations within 90 days
of the date of issuance of the Commission staff's FEIS or EA.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenter's will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commenter's will not be required to serve copies of filed
documents on all other parties. However, the non-party commentary, will
not receive copies of all documents filed by other parties or issued by
the
[[Page 55251]]
Commission (except for the mailing of environmental documents issued by
the Commission) and will not have the right to seek court review of the
Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at https://www.ferc.gov. Persons unable to file electronically should
submit an original and 5 copies of the protest or intervention to the
Federal Energy Regulatory Commission, 888 First Street NE., Washington,
DC 20426.
Dated: September 3, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-21971 Filed 9-9-13; 8:45 am]
BILLING CODE 6717-01-P