Transcontinental Gas Pipe Line Company, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Mobile Bay South III Expansion Project and Request for Comments on Environmental Issues, 55072-55074 [2013-21828]
Download as PDF
55072
Federal Register / Vol. 78, No. 174 / Monday, September 9, 2013 / Notices
‘‘eLibrary’’ link. Follow the directions
for accessing information in paragraph
n. Based on all oral and written
comments, a Scoping Document 2 (SD2)
may be issued. SD2 may include a
revised process plan and schedule, as
well as a list of issues, identified
through the scoping process.
Environmental Site Review
PacifiCorp Energy and Commission
staff will conduct an Environmental Site
Review of the project on Tuesday,
September 24, 2013, starting at 1:00
p.m. (PST). All participants should meet
at the Prospect Warehouse, located at
1111 Mill Creek Drive, Prospect, OR
97536. Please contact Mr. Steve
Albertelli at (541) 776–6676 or
steve.albertelli@pacificorp.com by
September 23, 2013, if you plan to
attend the environmental site review.
Meeting Objectives
At the scoping meetings, staff will: (1)
Initiate scoping of the issues; (2) review
and discuss existing conditions and
resource management objectives; (3)
review and discuss existing information
and identify preliminary information
and study needs; (4) review and discuss
the process plan and schedule for prefiling activity that incorporates the time
frames provided for in Part 5 of the
Commission’s regulations and, to the
extent possible, maximizes coordination
of federal, state, and tribal permitting
and certification processes; and (5)
discuss the appropriateness of any
federal or state agency or Indian tribe
acting as a cooperating agency for
development of an environmental
document.
Meeting participants should come
prepared to discuss their issues and/or
concerns. Please review the PAD in
preparation for the scoping meetings.
Directions on how to obtain a copy of
the PAD and SD1 are included in item
n. of this document.
Meeting Procedures
tkelley on DSK3SPTVN1PROD with NOTICES
The meetings will be recorded by a
stenographer and will be placed in the
public records of the project.
Dated: August 30, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–21829 Filed 9–6–13; 8:45 am]
BILLING CODE 6717–01–P
VerDate Mar<15>2010
15:01 Sep 06, 2013
Jkt 229001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12693–003]
Sutton Hydroelectric Company, LLC;
Notice of Preliminary Permit
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Competing Applications
On March 1, 2013, Sutton
Hydroelectric Company, LLC filed an
application for a successive preliminary
permit, pursuant to section 4(f) of the
Federal Power Act (FPA), proposing to
study the feasibility of the Sutton
Hydroelectric Project (project) to be
located at the U.S. Army Corps of
Engineers Sutton Dam, on the Elk River,
in Sutton, Braxton County, West
Virginia. The sole purpose of a
preliminary permit, if issued, is to grant
the permit holder priority to file a
license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land-disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed project would utilize
the existing U.S. Army Corps of
Engineers’ Sutton Dam and would
consist of: (1) A proposed powerhouse
containing three generating units with a
total generating capacity of 9.2
megawatts; (2) a 12-foot-diameter
penstock; (3) a proposed 4,000-footlong, 138-kilovolt transmission line; (4)
a tailrace, and (5) appurtenant facilities.
The project would have an estimated
average annual generation of 36.0
gigawatt-hours.
Applicant Contact: Mr. David C.
Sinclair, President, Advanced Hydro
Solutions, LLC, 3000 Auburn Drive,
Suite 430, Beachwood, OH 4122–4340;
phone: (216) 472–5581.
FERC Contact: Tim Looney; phone:
(202) 502–6096.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36.
The Commission strongly encourages
electronic filing. Please file comments,
motions to intervene, notices of intent,
and competing applications using the
Commission’s eFiling system at https://
www.ferc.gov/docs-filing/efiling.asp.
Commenters can submit brief comments
up to 6,000 characters, without prior
registration, using the eComment system
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
at https://www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–12693–003.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–12693) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
Dated: August 30, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–21830 Filed 9–6–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP13–523–000]
Transcontinental Gas Pipe Line
Company, LLC; Notice of Intent To
Prepare an Environmental Assessment
for the Proposed Mobile Bay South III
Expansion Project and Request for
Comments on Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Mobile Bay South III Expansion
Project involving construction and
operation of facilities by
Transcontinental Gas Pipe Line
Company, LLC (Transco) in Mobile
County, Alabama. The Commission will
use this EA in its decision-making
process to determine whether the
project is in the public convenience and
necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
Your input will help the Commission
staff determine what issues they need to
evaluate in the EA. Please note that the
scoping period will close on September
30, 2013.
This notice is being sent to the
Commission’s current environmental
E:\FR\FM\09SEN1.SGM
09SEN1
Federal Register / Vol. 78, No. 174 / Monday, September 9, 2013 / Notices
mailing list for this project. State and
local government representatives should
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, a pipeline company
representative may contact you about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the Commission
approves the project, that approval
conveys with it the right of eminent
domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings
where compensation would be
determined in accordance with state
law.
Transco provided landowners with a
fact sheet prepared by the FERC entitled
‘‘An Interstate Natural Gas Facility On
My Land? What Do I Need To Know?’’
This fact sheet addresses a number of
typically-asked questions, including the
use of eminent domain and how to
participate in the Commission’s
proceedings. It is also available for
viewing on the FERC Web site
(www.ferc.gov).
tkelley on DSK3SPTVN1PROD with NOTICES
Summary of the Proposed Project
Transco proposes to add a new
compressor unit to its existing
Compressor Station 85 in Choctaw
County, Alabama and up-rate an
existing compressor unit at its existing
Compressor Station 83 in Mobile
County, Alabama. The Mobile Bay
South III Expansion Project would
enable firm transportation service of
225,000 dekatherms per day (dth/d)
from Compressor Station 85 Receipt
Points southward to the Citronelle and
Bay Gas Storage Interconnections while
preserving Transco’s capability to
provide its existing certificated levels of
northbound and southbound firm
transportation service on the Mobile Bay
Lateral.
The Mobile Bay South III Expansion
Project would consist of the following
facilities:
• Adding 20,500-horsepower (hp) of
compression at Transco’s existing
Compressor Station 85 located at the
interconnection of the Mobile Bay
Lateral and Transco’s main line in
Choctaw County, Alabama;
• Constructing approximately 2,500
feet of 30-inch-diameter pipeline to
connect high pressure supply from the
interconnection between the suction
header of the new unit and existing
units at Compressor Station 85;
VerDate Mar<15>2010
15:01 Sep 06, 2013
Jkt 229001
• Modifying existing compressors 1, 2
and 3 at Compressor Station 85 to allow
for operation at higher suction and
discharge pressures; and
• Rewheeling, installing associated
inlet air cooling for and up-rating an
existing 15,000-hp compressor to
16,000-hp at Transco’s existing
Compressor Station 83 in Mobile
County, Alabama.
The general location of the project
facilities is shown in appendix 1.1
Land Requirements for Construction
Construction of the proposed facilities
would disturb about 38.18 acres of land,
including the aboveground facilities and
associated pipeline construction.
Following construction, the Project
would permanently impact
approximately 2.20 acres for operation
of the facilities; the remaining acreage
would revert to former uses.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us2 to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. We will consider all
filed comments during the preparation
of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
proposed project under these general
headings:
• Geology and soils;
• Land use;
• Water resources and wetlands;
• Cultural resources;
• Vegetation and wildlife;
• Endangered and threatened species;
• Air quality and noise;
• Public safety; and
• Cumulative impacts.
We will also evaluate reasonable
alternatives to the proposed project or
1 The appendices referenced in this notice will
not appear in the Federal Register. Copies of
appendices were sent to all those receiving this
notice in the mail and are available at www.ferc.gov
using the link called ‘‘eLibrary’’ or from the
Commission’s Public Reference Room, 888 First
Street NE., Washington, DC 20426, or call (202)
502–8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the
environmental staff of the Commission’s Office of
Energy Projects.
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
55073
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
The EA will present our independent
analysis of the issues. The EA will be
available in the public record through
eLibrary. Depending on the comments
received during the scoping process, we
may also publish and distribute the EA
to the public for an allotted comment
period. We will consider all comments
on the EA before making our
recommendations to the Commission.
To ensure we have the opportunity to
consider and address your comments,
please carefully follow the instructions
in the Public Participation section
beginning on page 5.
With this notice, we are asking
agencies with jurisdiction by law and/
or special expertise with respect to the
environmental issues of this project to
formally cooperate with us in the
preparation of the EA.3 Agencies that
would like to request cooperating
agency status should follow the
instructions for filing comments
provided under the Public Participation
section of this notice.
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultation with
applicable State Historic Preservation
Office (SHPO), and to solicit their views
and those of other government agencies,
interested Indian tribes, and the public
on the project’s potential effects on
historic properties.4 We will define the
project-specific Area of Potential Effects
(APE) in consultation with the SHPO as
the project develops. On natural gas
facility projects, the APE at a minimum
encompasses all areas subject to ground
disturbance (examples include
construction right-of-way, contractor/
pipe storage yards, compressor stations,
and access roads). Our EA for this
project will document our findings on
the impacts on historic properties and
summarize the status of consultations
under section 106.
3 The Council on Environmental Quality
regulations addressing cooperating agency
responsibilities are at Title 40, Code of Federal
Regulations, § 1501.6.
4 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Those regulations define
historic properties as any prehistoric or historic
district, site, building, structure, or object included
in or eligible for inclusion in the National Register
of Historic Places.
E:\FR\FM\09SEN1.SGM
09SEN1
55074
Federal Register / Vol. 78, No. 174 / Monday, September 9, 2013 / Notices
Environmental Mailing List
Currently Identified Environmental
Issues
We have already identified several
issues that we think deserve attention
based on a preliminary review of the
proposed facilities and the
environmental information provided by
Transco. This preliminary list of issues
may be changed based on your
comments and our analysis.
• Cumulative noise impacts on the
communities in the vicinity of
Compressor Station 85
tkelley on DSK3SPTVN1PROD with NOTICES
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the project.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
The more specific your comments, the
more useful they will be. To ensure that
your comments are timely and properly
recorded, please send your comments so
that the Commission receives them in
Washington, DC on or before September
30, 2013.
For your convenience, there are three
methods which you can use to submit
your comments to the Commission. In
all instances please reference the project
docket number (CP13–523–000) with
your submission. The Commission
encourages electronic filing of
comments and has expert staff available
to assist you at (202) 502–8258 or
efiling@ferc.gov.
(1) You can file your comments
electronically using the eComment
feature on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. This is an easy
method for interested persons to submit
brief, text-only comments on a project;
(2) You can file your comments
electronically using the eFiling feature
on the Commission’s Web site
(www.ferc.gov) under the link to
Documents and Filings. With eFiling,
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ You must select
the type of filing you are making. If you
are filing a comment on a particular
project, please select ‘‘Comment on a
Filing’’; or
(3) You can file a paper copy of your
comments by mailing them to the
following address: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE., Room
1A, Washington, DC 20426.
VerDate Mar<15>2010
15:01 Sep 06, 2013
Jkt 229001
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project. We will
update the environmental mailing list as
the analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the proposed project.
If we publish and distribute the EA,
copies will be sent to the environmental
mailing list for public review and
comment. If you would prefer to receive
a paper copy of the document instead of
the CD version or would like to remove
your name from the mailing list, please
return the attached Information Request
(appendix 2).
In addition to involvement in the EA
scoping process, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are in the User’s Guide under
the ‘‘e-filing’’ link on the Commission’s
Web site.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site at www.ferc.gov using the
‘‘eLibrary’’ link. Click on the eLibrary
link, click on ‘‘General Search’’ and
enter the docket number, excluding the
last three digits in the Docket Number
field (i.e., CP13–523). Be sure you have
selected an appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at (866) 208–3676, or for
TTY, contact (202) 502–8659. The
eLibrary link also provides access to the
Frm 00023
Fmt 4703
Sfmt 4703
Dated: August 30, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–21828 Filed 9–6–13; 8:45 am]
BILLING CODE 6717–01–P
FARM CREDIT SYSTEM INSURANCE
CORPORATION
Farm Credit System Insurance
Corporation Board; Regular Meeting
Farm Credit System Insurance
Corporation.
AGENCY:
Becoming an Intervenor
PO 00000
texts of formal documents issued by the
Commission, such as orders, notices,
and rulemakings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries, and direct links
to the documents. Go to www.ferc.gov/
esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Notice is hereby given of the
regular meeting of the Farm Credit
System Insurance Corporation Board
(Board).
DATE AND TIME: The meeting of the Board
will be held at the offices of the Farm
Credit Administration in McLean,
Virginia, on September 12, 2013, from
1:00 p.m. until such time as the Board
concludes its business.
SUMMARY:
Dale
L. Aultman, Secretary to the Farm
Credit System Insurance Corporation
Board, (703) 883–4009, TTY (703) 883–
4056.
FOR FURTHER INFORMATION CONTACT:
Farm Credit System
Insurance Corporation, 1501 Farm
Credit Drive, McLean, Virginia 22102.
ADDRESSES:
Parts of
this meeting of the Board will be open
to the public (limited space available)
and parts will be closed to the public.
In order to increase the accessibility to
Board meetings, persons requiring
assistance should make arrangements in
advance. The matters to be considered
at the meeting are:
SUPPLEMENTARY INFORMATION:
Closed Session
• Confidential Report on Farm Credit
System Performance
E:\FR\FM\09SEN1.SGM
09SEN1
Agencies
[Federal Register Volume 78, Number 174 (Monday, September 9, 2013)]
[Notices]
[Pages 55072-55074]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-21828]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP13-523-000]
Transcontinental Gas Pipe Line Company, LLC; Notice of Intent To
Prepare an Environmental Assessment for the Proposed Mobile Bay South
III Expansion Project and Request for Comments on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Mobile Bay South III Expansion
Project involving construction and operation of facilities by
Transcontinental Gas Pipe Line Company, LLC (Transco) in Mobile County,
Alabama. The Commission will use this EA in its decision-making process
to determine whether the project is in the public convenience and
necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. Your input will help the Commission staff
determine what issues they need to evaluate in the EA. Please note that
the scoping period will close on September 30, 2013.
This notice is being sent to the Commission's current environmental
[[Page 55073]]
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the proposed facilities. The company
would seek to negotiate a mutually acceptable agreement. However, if
the Commission approves the project, that approval conveys with it the
right of eminent domain. Therefore, if easement negotiations fail to
produce an agreement, the pipeline company could initiate condemnation
proceedings where compensation would be determined in accordance with
state law.
Transco provided landowners with a fact sheet prepared by the FERC
entitled ``An Interstate Natural Gas Facility On My Land? What Do I
Need To Know?'' This fact sheet addresses a number of typically-asked
questions, including the use of eminent domain and how to participate
in the Commission's proceedings. It is also available for viewing on
the FERC Web site (www.ferc.gov).
Summary of the Proposed Project
Transco proposes to add a new compressor unit to its existing
Compressor Station 85 in Choctaw County, Alabama and up-rate an
existing compressor unit at its existing Compressor Station 83 in
Mobile County, Alabama. The Mobile Bay South III Expansion Project
would enable firm transportation service of 225,000 dekatherms per day
(dth/d) from Compressor Station 85 Receipt Points southward to the
Citronelle and Bay Gas Storage Interconnections while preserving
Transco's capability to provide its existing certificated levels of
northbound and southbound firm transportation service on the Mobile Bay
Lateral.
The Mobile Bay South III Expansion Project would consist of the
following facilities:
Adding 20,500-horsepower (hp) of compression at Transco's
existing Compressor Station 85 located at the interconnection of the
Mobile Bay Lateral and Transco's main line in Choctaw County, Alabama;
Constructing approximately 2,500 feet of 30-inch-diameter
pipeline to connect high pressure supply from the interconnection
between the suction header of the new unit and existing units at
Compressor Station 85;
Modifying existing compressors 1, 2 and 3 at Compressor
Station 85 to allow for operation at higher suction and discharge
pressures; and
Rewheeling, installing associated inlet air cooling for
and up-rating an existing 15,000-hp compressor to 16,000-hp at
Transco's existing Compressor Station 83 in Mobile County, Alabama.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of appendices were sent to all those
receiving this notice in the mail and are available at www.ferc.gov
using the link called ``eLibrary'' or from the Commission's Public
Reference Room, 888 First Street NE., Washington, DC 20426, or call
(202) 502-8371. For instructions on connecting to eLibrary, refer to
the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the proposed facilities would disturb about 38.18
acres of land, including the aboveground facilities and associated
pipeline construction. Following construction, the Project would
permanently impact approximately 2.20 acres for operation of the
facilities; the remaining acreage would revert to former uses.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires
us\2\ to discover and address concerns the public may have about
proposals. This process is referred to as ``scoping.'' The main goal of
the scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. We will
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------
\2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the proposed project under these
general headings:
Geology and soils;
Land use;
Water resources and wetlands;
Cultural resources;
Vegetation and wildlife;
Endangered and threatened species;
Air quality and noise;
Public safety; and
Cumulative impacts.
We will also evaluate reasonable alternatives to the proposed
project or portions of the project, and make recommendations on how to
lessen or avoid impacts on the various resource areas.
The EA will present our independent analysis of the issues. The EA
will be available in the public record through eLibrary. Depending on
the comments received during the scoping process, we may also publish
and distribute the EA to the public for an allotted comment period. We
will consider all comments on the EA before making our recommendations
to the Commission. To ensure we have the opportunity to consider and
address your comments, please carefully follow the instructions in the
Public Participation section beginning on page 5.
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues of
this project to formally cooperate with us in the preparation of the
EA.\3\ Agencies that would like to request cooperating agency status
should follow the instructions for filing comments provided under the
Public Participation section of this notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Sec. 1501.6.
---------------------------------------------------------------------------
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with applicable State Historic Preservation Office (SHPO), and to
solicit their views and those of other government agencies, interested
Indian tribes, and the public on the project's potential effects on
historic properties.\4\ We will define the project-specific Area of
Potential Effects (APE) in consultation with the SHPO as the project
develops. On natural gas facility projects, the APE at a minimum
encompasses all areas subject to ground disturbance (examples include
construction right-of-way, contractor/pipe storage yards, compressor
stations, and access roads). Our EA for this project will document our
findings on the impacts on historic properties and summarize the status
of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
[[Page 55074]]
Currently Identified Environmental Issues
We have already identified several issues that we think deserve
attention based on a preliminary review of the proposed facilities and
the environmental information provided by Transco. This preliminary
list of issues may be changed based on your comments and our analysis.
Cumulative noise impacts on the communities in the
vicinity of Compressor Station 85
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the project. Your comments should focus on
the potential environmental effects, reasonable alternatives, and
measures to avoid or lessen environmental impacts. The more specific
your comments, the more useful they will be. To ensure that your
comments are timely and properly recorded, please send your comments so
that the Commission receives them in Washington, DC on or before
September 30, 2013.
For your convenience, there are three methods which you can use to
submit your comments to the Commission. In all instances please
reference the project docket number (CP13-523-000) with your
submission. The Commission encourages electronic filing of comments and
has expert staff available to assist you at (202) 502-8258 or
efiling@ferc.gov.
(1) You can file your comments electronically using the eComment
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. This is an easy method for interested persons to
submit brief, text-only comments on a project;
(2) You can file your comments electronically using the eFiling
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
``eRegister.'' You must select the type of filing you are making. If
you are filing a comment on a particular project, please select
``Comment on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the following address: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC
20426.
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project. We will update the environmental mailing list
as the analysis proceeds to ensure that we send the information related
to this environmental review to all individuals, organizations, and
government entities interested in and/or potentially affected by the
proposed project.
If we publish and distribute the EA, copies will be sent to the
environmental mailing list for public review and comment. If you would
prefer to receive a paper copy of the document instead of the CD
version or would like to remove your name from the mailing list, please
return the attached Information Request (appendix 2).
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Instructions for becoming an intervenor are in
the User's Guide under the ``e-filing'' link on the Commission's Web
site.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., CP13-
523). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: August 30, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-21828 Filed 9-6-13; 8:45 am]