EcoEléctrica, L.P.; Notice of Intent To Prepare an Environmental Assessment for the Proposed LNG Supply Pipeline Project and Request for Comments on Environmental Issues, 53750-53751 [2013-21208]

Download as PDF tkelley on DSK3SPTVN1PROD with NOTICES 53750 Federal Register / Vol. 78, No. 169 / Friday, August 30, 2013 / Notices Web site (www.ferc.gov) under the link to Documents and Filings. This is an easy method for submitting brief, textonly comments on a project; (2) You can also file your comments electronically using the eFiling feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You must select the type of filing you are making. If you are filing a comment on a particular project, please select ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments by mailing them to the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 20426. Any person seeking to become a party to the proceeding must file a motion to intervene pursuant to Rule 214 of the Commission’s Rules of Practice and Procedures (18 CFR 385.214).2 Only intervenors have the right to seek rehearing of the Commission’s decision. The Commission grants affected landowners and others with environmental concerns intervenor status upon showing good cause by stating that they have a clear and direct interest in this proceeding which no other party can adequately represent. Simply filing environmental comments will not give you intervenor status, but you do not need intervenor status to have your comments considered. Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC Web site (www.ferc.gov) using the eLibrary link. Click on the eLibrary link, click on ‘‘General Search,’’ and enter the docket number excluding the last three digits in the Docket Number field (i.e., CP13–96). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of 2 See the previous discussion on the methods for filing comments. VerDate Mar<15>2010 18:00 Aug 29, 2013 Jkt 229001 time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/ esubscribenow.htm. Dated: August 23, 2013. Kimberly D. Bose, Secretary. [FR Doc. 2013–21198 Filed 8–29–13; 8:45 am] BILLING CODE 6717–01–P being developed and permitted by Gas Natural Puerto Rico, Inc. The new facilities would consist of an approximately 3,600-foot-long, 4-inchdiameter LNG transfer pipeline; an approximately 3,600-foot-long, 6-inchdiameter boil-off gas return pipeline; an approximately 3,600-foot-long, 1.5-inchdiameter LNG recirculation pipeline; and associated equipment. The general location of the project is shown in appendix 1.1 Federal Energy Regulatory Commission Land Requirements for Construction ´ EcoElectrica plans to construct the facilities using approximately 1 acre of an already disturbed area within its LNG facility. [Docket No. CP13–516–000] The EA Process ´ EcoElectrica, L.P.; Notice of Intent To Prepare an Environmental Assessment for the Proposed LNG Supply Pipeline Project and Request for Comments on Environmental Issues The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from an action whenever it considers an authorization of a project. NEPA also requires us 2 to discover and address concerns the public may have about proposals. This process is referred to as ‘‘scoping.’’ The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of the issues to address in the EA. We will consider all filed comments during the preparation of the EA. In the EA we will discuss impacts that could occur as a result of the construction and operation of the proposed project under the general headings of land use, air quality, noise, and public safety. We do not expect other resource areas to be impacted by the proposed project, which would take place entirely within an existing industrial-use facility. We will also evaluate reasonable alternatives to the proposed project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas. The EA will present our independent analysis of the issues. It will be available in the public record through eLibrary. Depending on the comments DEPARTMENT OF ENERGY The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the LNG Supply Pipeline Project involving construction and operation of ´ facilities by EcoElectrica, L.P. ´ (EcoElectrica) at its liquefied natural gas ˜ (LNG) facility in Penuelas, Puerto Rico. This EA will be used by the Commission in its decision-making process to determine whether the project is in the public interest. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies on the project. Your input will help the Commission staff determine what issues need to be evaluated in the EA. Comments may be submitted in written form or verbally. Further details on how to submit written comments are provided in the Public Participation section of this notice. Please note that the scoping period will close on September 23, 2013. This notice is being sent to the Commission’s current environmental mailing list for this project. State and local government representatives are asked to notify their constituents of this proposed project and encourage them to comment on their areas of concern. Summary of the Proposed Project ´ EcoElectrica plans to construct and operate facilities at its LNG facility in ´ order to enable EcoElectrica to supply LNG to a proposed adjacent LNG truck loading facility that is not under the Commission’s jurisdiction and that is PO 00000 Frm 00025 Fmt 4703 Sfmt 4703 1 The appendices referenced in this notice will not appear in the Federal Register. Copies of appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called ‘‘eLibrary’’ or from the Commission’s Public Reference Room, 888 First Street NE., Washington, DC 20426, or call (202) 502–8371. For instructions on connecting to eLibrary, refer to the ‘‘Additional Information’’ section at the end of this notice. 2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the environmental staff of the Commission’s Office of Energy Projects. E:\FR\FM\30AUN1.SGM 30AUN1 Federal Register / Vol. 78, No. 169 / Friday, August 30, 2013 / Notices received during the scoping process, we may also publish and distribute the EA to the public for an allotted comment period. We will consider all comments on the EA before making our recommendations to the Commission. To ensure we have the opportunity to consider and address your comments, please carefully follow the instructions in the Public Participation section below. With this notice, we are asking agencies with jurisdiction by law and/ or special expertise with respect to the environmental issues of this project to formally cooperate with us in the preparation of the EA.3 Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. tkelley on DSK3SPTVN1PROD with NOTICES Public Participation You can make a difference by providing us with your specific comments or concerns about the project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure that your comments are timely and properly recorded, please send your comments so that the Commission receives them in Washington, DC on or before September 23, 2013. For your convenience, there are three methods you can use to submit your comments to the Commission. In all instances, please reference the project docket number (CP13–516–000) with your submission. The Commission encourages electronic filing of comments and has expert eFiling staff available to assist you at (202) 502–8258 or efiling@ferc.gov. (1) You can file your comments electronically using the eComment feature on the Commission’s Web site at www.ferc.gov under the link to Documents and Filings. This is an easy method for interested persons to submit brief, text-only comments on a project; (2) You can file your comments electronically by using the eFiling feature on the Commission’s Web site at www.ferc.gov under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by 3 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Part 1501.6. VerDate Mar<15>2010 18:00 Aug 29, 2013 Jkt 229001 clicking on ‘‘eRegister.’’ You must select the type of filing you are making. If you are filing a comment on a particular project, please select ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments by mailing them to the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 20426. Environmental Mailing List The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project. We will update the environmental mailing list as the analysis proceeds to ensure that we send the information related to this environmental review to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. If we publish and distribute the EA, copies of it will be sent to the environmental mailing list for public review and comment. If you would prefer to receive a paper copy of the document instead of the CD version or would like to remove your name from the mailing list, please return the attached Information Request (appendix 2). Becoming an Intervenor In addition to involvement in the EA scoping process, you may want to become an ‘‘intervenor’’ which is an official party to the Commission’s proceeding. Intervenors play a more formal role in the process and are able to file briefs, appear at hearings, and be heard by the courts if they choose to appeal the Commission’s final ruling. An intervenor formally participates in the proceeding by filing a request to intervene. Instructions for becoming an intervenor are in the User’s Guide under the ‘‘e-filing’’ link on the Commission’s Web site. Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC Web site (www.ferc.gov) using the eLibrary link. Click on the eLibrary link, click on PO 00000 Frm 00026 Fmt 4703 Sfmt 4703 53751 ‘‘General Search’’ and enter the project docket number, excluding the last three digits in the Docket Number field (i.e., CP13–516). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/ esubscribenow.htm. Finally, public meetings or site visits will be posted on the Commission’s calendar located at www.ferc.gov/ EventCalendar/EventsList.aspx along with other related information. Dated: August 22, 2013. Kimberly D. Bose, Secretary. [FR Doc. 2013–21208 Filed 8–29–13; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. OR13–32–000] Dominion NGL Pipelines, LLC; Notice of Petition for Declaratory Order Take notice that on August 21, 2013, pursuant to Rule 207 of the Commission’s Rules of Practices and Procedure, 18 CFR 385.207, Dominion NGL Pipelines, LLC filed a petition requesting a declaratory order approving, (1) the general rate structure for its new ethane pipeline (Natrium Ethane Pipeline) extending from a new natural gas processing and fractionation plant operating in Marshall County, West Virginia, to an interconnection near Follansbee, West Virginia with Enterprise Products Partners, L.P.’s Appalachia to Texas Express (ATEX) pipeline; (2) the rate and terms agreed upon by Dominion NGL with a shipper that has made a long-term commitment to utilize, or pay for, significant capacity on the Natrium Ethane Pipeline (Committed Shipper); and (3) the rate design utilizing revenue crediting to E:\FR\FM\30AUN1.SGM 30AUN1

Agencies

[Federal Register Volume 78, Number 169 (Friday, August 30, 2013)]
[Notices]
[Pages 53750-53751]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-21208]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP13-516-000]


EcoEl[eacute]ctrica, L.P.; Notice of Intent To Prepare an 
Environmental Assessment for the Proposed LNG Supply Pipeline Project 
and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the LNG Supply Pipeline Project 
involving construction and operation of facilities by 
EcoEl[eacute]ctrica, L.P. (EcoEl[eacute]ctrica) at its liquefied 
natural gas (LNG) facility in Pe[ntilde]uelas, Puerto Rico. This EA 
will be used by the Commission in its decision-making process to 
determine whether the project is in the public interest.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the project. Your input will help the Commission staff 
determine what issues need to be evaluated in the EA. Comments may be 
submitted in written form or verbally. Further details on how to submit 
written comments are provided in the Public Participation section of 
this notice. Please note that the scoping period will close on 
September 23, 2013.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives are asked to notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.

Summary of the Proposed Project

    EcoEl[eacute]ctrica plans to construct and operate facilities at 
its LNG facility in order to enable EcoEl[eacute]ctrica to supply LNG 
to a proposed adjacent LNG truck loading facility that is not under the 
Commission's jurisdiction and that is being developed and permitted by 
Gas Natural Puerto Rico, Inc.
    The new facilities would consist of an approximately 3,600-foot-
long, 4-inch-diameter LNG transfer pipeline; an approximately 3,600-
foot-long, 6-inch-diameter boil-off gas return pipeline; an 
approximately 3,600-foot-long, 1.5-inch-diameter LNG recirculation 
pipeline; and associated equipment.
    The general location of the project is shown in appendix 1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called ``eLibrary'' or from the Commission's Public 
Reference Room, 888 First Street NE., Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the ``Additional Information'' section at the end of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    EcoEl[eacute]ctrica plans to construct the facilities using 
approximately 1 acre of an already disturbed area within its LNG 
facility.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers an authorization of a 
project. NEPA also requires us \2\ to discover and address concerns the 
public may have about proposals. This process is referred to as 
``scoping.'' The main goal of the scoping process is to focus the 
analysis in the EA on the important environmental issues. By this 
notice, the Commission requests public comments on the scope of the 
issues to address in the EA. We will consider all filed comments during 
the preparation of the EA.
---------------------------------------------------------------------------

    \2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed project under the 
general headings of land use, air quality, noise, and public safety. We 
do not expect other resource areas to be impacted by the proposed 
project, which would take place entirely within an existing industrial-
use facility.
    We will also evaluate reasonable alternatives to the proposed 
project or portions of the project, and make recommendations on how to 
lessen or avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. It will 
be available in the public record through eLibrary. Depending on the 
comments

[[Page 53751]]

received during the scoping process, we may also publish and distribute 
the EA to the public for an allotted comment period. We will consider 
all comments on the EA before making our recommendations to the 
Commission. To ensure we have the opportunity to consider and address 
your comments, please carefully follow the instructions in the Public 
Participation section below.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues of 
this project to formally cooperate with us in the preparation of the 
EA.\3\ Agencies that would like to request cooperating agency status 
should follow the instructions for filing comments provided under the 
Public Participation section of this notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Public Participation

    You can make a difference by providing us with your specific 
comments or concerns about the project. Your comments should focus on 
the potential environmental effects, reasonable alternatives, and 
measures to avoid or lessen environmental impacts. The more specific 
your comments, the more useful they will be. To ensure that your 
comments are timely and properly recorded, please send your comments so 
that the Commission receives them in Washington, DC on or before 
September 23, 2013.
    For your convenience, there are three methods you can use to submit 
your comments to the Commission. In all instances, please reference the 
project docket number (CP13-516-000) with your submission. The 
Commission encourages electronic filing of comments and has expert 
eFiling staff available to assist you at (202) 502-8258 or 
efiling@ferc.gov.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site at www.ferc.gov under the link to 
Documents and Filings. This is an easy method for interested persons to 
submit brief, text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's Web site at www.ferc.gov under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' You must select the type of filing you are making. If 
you are filing a comment on a particular project, please select 
``Comment on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address:
    Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 
888 First Street NE., Room 1A, Washington, DC 20426.

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; other interested parties; and 
local libraries and newspapers. This list also includes all affected 
landowners (as defined in the Commission's regulations) who own homes 
within certain distances of aboveground facilities, and anyone who 
submits comments on the project. We will update the environmental 
mailing list as the analysis proceeds to ensure that we send the 
information related to this environmental review to all individuals, 
organizations, and government entities interested in and/or potentially 
affected by the proposed project.
    If we publish and distribute the EA, copies of it will be sent to 
the environmental mailing list for public review and comment. If you 
would prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the User's Guide under the ``e-filing'' link on the Commission's Web 
site.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the 
eLibrary link, click on ``General Search'' and enter the project docket 
number, excluding the last three digits in the Docket Number field 
(i.e., CP13-516). Be sure you have selected an appropriate date range. 
For assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/esubscribenow.htm.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: August 22, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-21208 Filed 8-29-13; 8:45 am]
BILLING CODE 6717-01-P