Entergy Nuclear Operations, Inc., James A. Fitzpatrick Nuclear Power Plant, Vermont Yankee Nuclear Power Station, Pilgrim Nuclear Power Station, Request for Action, 50458 [2013-20145]
Download as PDF
50458
Federal Register / Vol. 78, No. 160 / Monday, August 19, 2013 / Notices
and participation in ACRS meetings
were published in the Federal Register
on October 18, 2012, (77 FR 64146–
64147).
Detailed meeting agendas and meeting
transcripts are available on the NRC
Web site at https://www.nrc.gov/readingrm/doc-collections/acrs. Information
regarding topics to be discussed,
changes to the agenda, whether the
meeting has been canceled or
rescheduled, and the time allotted to
present oral statements can be obtained
from the Web site cited above or by
contacting the identified DFO.
Moreover, in view of the possibility that
the schedule for ACRS meetings may be
adjusted by the Chairman as necessary
to facilitate the conduct of the meeting,
persons planning to attend should check
with these references if such
rescheduling would result in a major
inconvenience.
If attending this meeting, please enter
through the One White Flint North
building, 11555 Rockville Pike,
Rockville, MD. After registering with
security, please contact Mr. Theron
Brown (Telephone 240–888–9835) to be
escorted to the meeting room.
Dated: August 5, 2013.
Cayetano Santos,
Chief, Technical Support Branch, Advisory
Committee on Reactor Safeguards.
[FR Doc. 2013–20138 Filed 8–16–13; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 50–333, 50–271, and 50–293;
NRC–2013–0192]
Entergy Nuclear Operations, Inc.,
James A. Fitzpatrick Nuclear Power
Plant, Vermont Yankee Nuclear Power
Station, Pilgrim Nuclear Power Station,
Request for Action
Nuclear Regulatory
Commission.
ACTION: Request for action; receipt.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is giving notice that
by petition dated March 18, 2013, as
supplemented on April 23, June 28, and
July 22, 2013, Timothy Judson, the
petitioner, on behalf of Alliance for a
Green Economy, Citizens Awareness
Network, Vermont Citizens Action
Network, Pilgrim Watch, and Beyond
Nuclear (hereafter referred to as ‘‘the
petitioners’’) has requested that the NRC
take action with regard to James A.
Fitzpatrick Nuclear Power Plant,
Vermont Yankee Nuclear Power Station,
and Pilgrim Nuclear Power Station. The
TKELLEY on DSK3SPTVN1PROD with NOTICES
SUMMARY:
VerDate Mar<15>2010
17:51 Aug 16, 2013
Jkt 229001
petitioners’ requests are included in the
section of
this document.
ADDRESSES: Please refer to Docket ID
NRC–2013–0192 when contacting the
NRC about the availability of
information regarding this document.
You may access publicly-available
information related to this action by the
following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2013–0192. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–287–3422;
email: Carol.Gallagher@nrc.gov.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may access publicly
available documents online in the NRC
Library at https://www.nrc.gov/readingrm/adams.html. To begin the search,
select ‘‘ADAMS Public Documents’’ and
then select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to PDR.Resource@nrc.gov. The
ADAMS accession number for each
document referenced in this notice (if
that document is available in ADAMS)
is provided the first time that a
document is referenced.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
SUPPLEMENTARY INFORMATION: On March
18, 2013 (ADAMS Accession No.
ML13079A022), the petitioners
requested that the NRC take action with
regard to James A. Fitzpatrick Nuclear
Power Plant (Fitzpatrick), Vermont
Yankee Nuclear Power Station (Vermont
Yankee), and Pilgrim Nuclear Power
Station (Pilgrim). The petitioners
supplemented the petition on April 23,
June 28, and July 22, 2013 (ADAMS
Accession Nos. ML13133A161,
ML13184A109, and ML13205A251,
respectively). The petitioners met with
the Petition Review Board (PRB) on May
7, 2013, to discuss the petition; the
transcript of that meeting is an
additional supplement to the petition
(ADAMS Accession No. ML13135A001).
The petitioners request that the NRC
take enforcement action against Entergy
Nuclear Operations, Inc. (Entergy) to: (1)
Suspend operations at Fitzpatrick and
Vermont Yankee; (2) investigate
whether Entergy possesses sufficient
funds to cease operations and to
decommission the Fitzpatrick reactor
and Vermont Yankee reactor, per Title
10 of the Code of Federal Regulations
SUPPLEMENTARY INFORMATION
PO 00000
Frm 00086
Fmt 4703
Sfmt 9990
(10 CFR), Part 50, Section 75 (10 CFR
50.75); and (3) investigate Entergy’s
current financial qualifications per 10
CFR 50.33(f)(5) for Pilgrim to determine
whether the licensee remains qualified
to continue safe operation of the facility.
As the basis for this request, the
petitioners state that Entergy no longer
meets the financial qualifications
requirements to possess the licenses and
operate Fitzpatrick and Vermont
Yankee, pursuant to 10 CFR
50.80(b)(1)(i) and 10 CFR 50.33(f)(2) and
that Entergy may no longer meet the
same licensing requirements for Pilgrim.
The request is being treated pursuant
to 10 CFR 2.206 of the Commission’s
regulations. The request has been
referred to the Director of the Office of
Nuclear Reactor Regulation. As
provided by 10 CFR 2.206, appropriate
action will be taken on this petition
within a reasonable time.
Dated at Rockville, Maryland, this 7th day
of August 2013.
For the Nuclear Regulatory Commission.
Jennifer L. Uhle,
Deputy Director, Reactor Safety Programs,
Office of Nuclear Reactor Regulation.
[FR Doc. 2013–20145 Filed 8–16–13; 8:45 am]
BILLING CODE 7590–01–P
POSTAL SERVICE
Board of Governors; Sunshine Act
Meeting
September 24, 2013, at
4:30 p.m., and September 25, 2013, at
9:00 a.m.
PLACE: Kansas City, Missouri.
STATUS: Closed.
MATTERS TO BE CONSIDERED:
DATES AND TIMES:
Tuesday, September 24, 2013, at 4:30
p.m.
1. Strategic Issues.
Wednesday, September 25, 2013, at 9:00
a.m.
1. Strategic Issues continued.
2. Financial Matters.
3. Pricing.
4. Personnel Matters and Compensation
Issues.
5. Governors’ Executive Session—
Discussion of prior agenda items and
Board Governance.
CONTACT PERSON FOR MORE INFORMATION:
Julie S. Moore, Secretary of the Board,
U.S. Postal Service, 475 L’Enfant Plaza
SW., Washington, DC 20260–1000.
Telephone (202) 268–4800.
Julie S. Moore,
Secretary.
[FR Doc. 2013–20301 Filed 8–15–13; 4:15 pm]
BILLING CODE 7710–12–P
E:\FR\FM\19AUN1.SGM
19AUN1
Agencies
[Federal Register Volume 78, Number 160 (Monday, August 19, 2013)]
[Notices]
[Page 50458]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-20145]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-333, 50-271, and 50-293; NRC-2013-0192]
Entergy Nuclear Operations, Inc., James A. Fitzpatrick Nuclear
Power Plant, Vermont Yankee Nuclear Power Station, Pilgrim Nuclear
Power Station, Request for Action
AGENCY: Nuclear Regulatory Commission.
ACTION: Request for action; receipt.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is giving notice
that by petition dated March 18, 2013, as supplemented on April 23,
June 28, and July 22, 2013, Timothy Judson, the petitioner, on behalf
of Alliance for a Green Economy, Citizens Awareness Network, Vermont
Citizens Action Network, Pilgrim Watch, and Beyond Nuclear (hereafter
referred to as ``the petitioners'') has requested that the NRC take
action with regard to James A. Fitzpatrick Nuclear Power Plant, Vermont
Yankee Nuclear Power Station, and Pilgrim Nuclear Power Station. The
petitioners' requests are included in the SUPPLEMENTARY INFORMATION
section of this document.
ADDRESSES: Please refer to Docket ID NRC-2013-0192 when contacting the
NRC about the availability of information regarding this document. You
may access publicly-available information related to this action by the
following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2013-0192. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-287-
3422; email: Carol.Gallagher@nrc.gov.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may access publicly available documents online in the NRC
Library at https://www.nrc.gov/reading-rm/adams.html. To begin the
search, select ``ADAMS Public Documents'' and then select ``Begin Web-
based ADAMS Search.'' For problems with ADAMS, please contact the NRC's
Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-
4737, or by email to PDR.Resource@nrc.gov. The ADAMS accession number
for each document referenced in this notice (if that document is
available in ADAMS) is provided the first time that a document is
referenced.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
SUPPLEMENTARY INFORMATION: On March 18, 2013 (ADAMS Accession No.
ML13079A022), the petitioners requested that the NRC take action with
regard to James A. Fitzpatrick Nuclear Power Plant (Fitzpatrick),
Vermont Yankee Nuclear Power Station (Vermont Yankee), and Pilgrim
Nuclear Power Station (Pilgrim). The petitioners supplemented the
petition on April 23, June 28, and July 22, 2013 (ADAMS Accession Nos.
ML13133A161, ML13184A109, and ML13205A251, respectively). The
petitioners met with the Petition Review Board (PRB) on May 7, 2013, to
discuss the petition; the transcript of that meeting is an additional
supplement to the petition (ADAMS Accession No. ML13135A001). The
petitioners request that the NRC take enforcement action against
Entergy Nuclear Operations, Inc. (Entergy) to: (1) Suspend operations
at Fitzpatrick and Vermont Yankee; (2) investigate whether Entergy
possesses sufficient funds to cease operations and to decommission the
Fitzpatrick reactor and Vermont Yankee reactor, per Title 10 of the
Code of Federal Regulations (10 CFR), Part 50, Section 75 (10 CFR
50.75); and (3) investigate Entergy's current financial qualifications
per 10 CFR 50.33(f)(5) for Pilgrim to determine whether the licensee
remains qualified to continue safe operation of the facility.
As the basis for this request, the petitioners state that Entergy
no longer meets the financial qualifications requirements to possess
the licenses and operate Fitzpatrick and Vermont Yankee, pursuant to 10
CFR 50.80(b)(1)(i) and 10 CFR 50.33(f)(2) and that Entergy may no
longer meet the same licensing requirements for Pilgrim.
The request is being treated pursuant to 10 CFR 2.206 of the
Commission's regulations. The request has been referred to the Director
of the Office of Nuclear Reactor Regulation. As provided by 10 CFR
2.206, appropriate action will be taken on this petition within a
reasonable time.
Dated at Rockville, Maryland, this 7th day of August 2013.
For the Nuclear Regulatory Commission.
Jennifer L. Uhle,
Deputy Director, Reactor Safety Programs, Office of Nuclear Reactor
Regulation.
[FR Doc. 2013-20145 Filed 8-16-13; 8:45 am]