Eastern Shore Natural Gas Company; Notice of Intent To Prepare an Environmental Assessment for the Proposed White Oak Lateral Project; Request for Comments on Environmental Issues, 49743-49747 [2013-19824]

Download as PDF Federal Register / Vol. 78, No. 158 / Thursday, August 15, 2013 / Notices Comments Due: 5 p.m. ET 8/29/13. Docket Numbers: ER13–2132–000. Applicants: Nevada Power Company. Description: Rate Schedule No. 135 SCE Eldorado Interim Interconnection Agmt Concurrence to be effective 6/25/ 2013. Filed Date: 8/8/13. Accession Number: 20130808–5117. Comments Due: 5 p.m. ET 8/29/13. Docket Numbers: ER13–2133–000. Applicants: Granite State Electric Company. Description: Borderline Sales—Rate Update to be effective 5/1/2013. Filed Date: 8/8/13. Accession Number: 20130808–5134. Comments Due: 5 p.m. ET 8/29/13. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: August 8, 2013. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2013–19798 Filed 8–14–13; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP13–498–000] emcdonald on DSK67QTVN1PROD with NOTICES Eastern Shore Natural Gas Company; Notice of Intent To Prepare an Environmental Assessment for the Proposed White Oak Lateral Project; Request for Comments on Environmental Issues The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the White Oak Lateral Project involving construction and operation of facilities by Eastern Shore Natural Gas Company VerDate Mar<15>2010 17:43 Aug 14, 2013 Jkt 229001 (Eastern Shore) in Kent County, Delaware. The Commission will use this EA in its decision-making process to determine whether the project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies on the project. Your input will help the Commission staff determine what issues they need to evaluate in the EA. Please note that the scoping period will close on September 9, 2013. You may submit comments in written form or verbally. Further details on how to submit written comments are in the Public Participation section of this notice This notice is being sent to the Commission’s current environmental mailing list for this project. State and local government representatives should notify their constituents of this proposed project and encourage them to comment on their areas of concern. If you are a landowner receiving this notice, a pipeline company representative may contact you about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The company would seek to negotiate a mutually acceptable agreement. However, if the Commission approves the project, that approval conveys with it the right of eminent domain. Therefore, if easement negotiations fail to produce an agreement, the pipeline company could initiate condemnation proceedings where compensation would be determined in accordance with state law. Eastern Shore provided landowners with a fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility On My Land? What Do I Need To Know?’’. This fact sheet addresses a number of typically-asked questions, including the use of eminent domain and how to participate in the Commission’s proceedings. It is also available for viewing on the FERC Web site (www.ferc.gov). Summary of the Proposed Project Eastern Shore proposes to construct, own, operate, new natural gas facilities in the Dover area of Kent County, Delaware. The White Oak Lateral Project would provide about 55,200 dekatherms of natural gas per day to Calpine Energy Services, L.P. to fuel the Garrison Energy Center, a proposed 309megawatt combined cycle natural gas fueled power plant under development in Kent County, Delaware. The White Oak Lateral Project would consist of the following facilities: PO 00000 Frm 00022 Fmt 4703 Sfmt 4703 49743 • Approximately 5.5 miles of 16-inchdiameter natural gas pipeline; • one mainline valves assembly; and • metering and regulating facility. The general location of the project facilities is shown in appendix 1.1 Land Requirements for Construction Construction of the proposed facilities would disturb approximately 118 acres of land for the aboveground facilities and the pipeline. Following construction, Eastern Shore would maintain about 10 acres for permanent operation of the project’s facilities; the remaining acreage would be restored and revert to former uses. Approximately 63 percent of the proposed pipeline route parallels existing pipeline, utility, or road rightsof-way. The EA Process The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires us 2 to discover and address concerns the public may have about proposals. This process is referred to as ‘‘scoping.’’ The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of the issues to address in the EA. We will consider all filed comments during the preparation of the EA. In the EA we will discuss impacts that could occur as a result of the construction and operation of the proposed project under these general headings: • Geology and soils; • land use; • water resources, fisheries, and wetlands; • cultural resources; • vegetation and wildlife; • air quality and noise; • endangered and threatened species; and • public safety. We will also evaluate reasonable alternatives to the proposed project or 1 The appendices referenced in this notice will not appear in the Federal Register. Copies of appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called ‘‘eLibrary’’ or from the Commission’s Public Reference Room, 888 First Street NE., Washington, DC 20426, or call (202) 502–8371. For instructions on connecting to eLibrary, refer to the last page of this notice. 2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the environmental staff of the Commission’s Office of Energy Projects. E:\FR\FM\15AUN1.SGM 15AUN1 49744 Federal Register / Vol. 78, No. 158 / Thursday, August 15, 2013 / Notices portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas. The EA will present our independent analysis of the issues. The EA will be available in the public record through eLibrary. Depending on the comments received during the scoping process, we may also publish and distribute the EA to the public for an allotted comment period. We will consider all comments on the EA before making our recommendations to the Commission. To ensure we have the opportunity to consider and address your comments, please carefully follow the instructions in the Public Participation section beginning on page 4. With this notice, we are asking agencies with jurisdiction by law and/ or special expertise with respect to the environmental issues of this project to formally cooperate with us in the preparation of the EA.3 Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. Consultations Under Section 106 of the National Historic Preservation Act emcdonald on DSK67QTVN1PROD with NOTICES In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, we are using this notice to initiate consultation with applicable State Historic Preservation Office (SHPO), and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project’s potential effects on historic properties.4 We will define the project-specific Area of Potential Effects (APE) in consultation with the SHPO as the project develops. On natural gas facility projects, the APE at a minimum encompasses all areas subject to ground disturbance (examples include construction right-of-way, contractor/ pipe storage yards, compressor stations, and access roads). Our EA for this project will document our findings on the impacts on historic properties and summarize the status of consultations under section 106. 3 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, § 1501.6. 4 The Advisory Council on Historic Preservation’s regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places. VerDate Mar<15>2010 17:43 Aug 14, 2013 Jkt 229001 Public Participation You can make a difference by providing us with your specific comments or concerns about the project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure that your comments are timely and properly recorded, please send your comments so that the Commission receives them in Washington, DC on or before September 9, 2013. For your convenience, there are three methods you can use to submit your comments to the Commission. In all instances please reference the project docket number (CP13–498–000) with your submission. The Commission encourages electronic filing of comments and has expert staff available to assist you at (202) 502–8258 or efiling@ferc.gov. (1) You can file your comments electronically using the eComment feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. This is an easy method for interested persons to submit brief, text-only comments on a project; (2) You can file your comments electronically using the eFiling feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You must select the type of filing you are making. If you are filing a comment on a particular project, please select ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments by mailing them to the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 20426. Environmental Mailing List The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground PO 00000 Frm 00023 Fmt 4703 Sfmt 4703 facilities, and anyone who submits comments on the project. We will update the environmental mailing list as the analysis proceeds to ensure that we send the information related to this environmental review to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. If we publish and distribute the EA, copies will be sent to the environmental mailing list for public review and comment. If you would prefer to receive a paper copy of the document instead of the CD version or would like to remove your name from the mailing list, please return the attached Information Request (appendix 2). Becoming an Intervenor In addition to involvement in the EA scoping process, you may want to become an ‘‘intervenor’’ which is an official party to the Commission’s proceeding. Intervenors play a more formal role in the process and are able to file briefs, appear at hearings, and be heard by the courts if they choose to appeal the Commission’s final ruling. An intervenor formally participates in the proceeding by filing a request to intervene. Instructions for becoming an intervenor are in the User’s Guide under the ‘‘e-filing’’ link on the Commission’s Web site. Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC Web site at www.ferc.gov using the ‘‘eLibrary’’ link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number, excluding the last three digits in the Docket Number field (i.e., CP13–498). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/ esubscribenow.htm. Finally, public meetings or site visits will be posted on the Commission’s E:\FR\FM\15AUN1.SGM 15AUN1 Federal Register / Vol. 78, No. 158 / Thursday, August 15, 2013 / Notices calendar located at www.ferc.gov/ EventCalendar/EventsList.aspx along with other related information. Dated: August 9, 2013. Kimberly D. Bose, Secretary. 49745 Appendix 1 VerDate Mar<15>2010 17:43 Aug 14, 2013 Jkt 229001 PO 00000 Frm 00024 Fmt 4703 Sfmt 4725 E:\FR\FM\15AUN1.SGM 15AUN1 EN15AU13.002</GPH> emcdonald on DSK67QTVN1PROD with NOTICES BILLING CODE 6717–01–P VerDate Mar<15>2010 Federal Register / Vol. 78, No. 158 / Thursday, August 15, 2013 / Notices 17:43 Aug 14, 2013 Jkt 229001 PO 00000 Frm 00025 Fmt 4703 Sfmt 4725 E:\FR\FM\15AUN1.SGM 15AUN1 EN15AU13.003</GPH> emcdonald on DSK67QTVN1PROD with NOTICES 49746 49747 [FR Doc. 2013–19824 Filed 8–14–13; 8:45 am] BILLING CODE 6717–01–C VerDate Mar<15>2010 17:43 Aug 14, 2013 Jkt 229001 PO 00000 Frm 00026 Fmt 4703 Sfmt 9990 E:\FR\FM\15AUN1.SGM 15AUN1 EN15AU13.004</GPH> emcdonald on DSK67QTVN1PROD with NOTICES Federal Register / Vol. 78, No. 158 / Thursday, August 15, 2013 / Notices

Agencies

[Federal Register Volume 78, Number 158 (Thursday, August 15, 2013)]
[Notices]
[Pages 49743-49747]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-19824]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP13-498-000]


Eastern Shore Natural Gas Company; Notice of Intent To Prepare an 
Environmental Assessment for the Proposed White Oak Lateral Project; 
Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the White Oak Lateral Project 
involving construction and operation of facilities by Eastern Shore 
Natural Gas Company (Eastern Shore) in Kent County, Delaware. The 
Commission will use this EA in its decision-making process to determine 
whether the project is in the public convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the project. Your input will help the Commission staff 
determine what issues they need to evaluate in the EA. Please note that 
the scoping period will close on September 9, 2013.
    You may submit comments in written form or verbally. Further 
details on how to submit written comments are in the Public 
Participation section of this notice
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    Eastern Shore provided landowners with a fact sheet prepared by the 
FERC entitled ``An Interstate Natural Gas Facility On My Land? What Do 
I Need To Know?''. This fact sheet addresses a number of typically-
asked questions, including the use of eminent domain and how to 
participate in the Commission's proceedings. It is also available for 
viewing on the FERC Web site (www.ferc.gov).

Summary of the Proposed Project

    Eastern Shore proposes to construct, own, operate, new natural gas 
facilities in the Dover area of Kent County, Delaware. The White Oak 
Lateral Project would provide about 55,200 dekatherms of natural gas 
per day to Calpine Energy Services, L.P. to fuel the Garrison Energy 
Center, a proposed 309-megawatt combined cycle natural gas fueled power 
plant under development in Kent County, Delaware.
    The White Oak Lateral Project would consist of the following 
facilities:
     Approximately 5.5 miles of 16-inch-diameter natural gas 
pipeline;
     one mainline valves assembly; and
     metering and regulating facility.
    The general location of the project facilities is shown in appendix 
1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called ``eLibrary'' or from the Commission's Public 
Reference Room, 888 First Street NE., Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the proposed facilities would disturb approximately 
118 acres of land for the aboveground facilities and the pipeline. 
Following construction, Eastern Shore would maintain about 10 acres for 
permanent operation of the project's facilities; the remaining acreage 
would be restored and revert to former uses. Approximately 63 percent 
of the proposed pipeline route parallels existing pipeline, utility, or 
road rights-of-way.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\2\ to discover and address concerns the public may have about 
proposals. This process is referred to as ``scoping.'' The main goal of 
the scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed project under these 
general headings:
     Geology and soils;
     land use;
     water resources, fisheries, and wetlands;
     cultural resources;
     vegetation and wildlife;
     air quality and noise;
     endangered and threatened species; and
     public safety.
    We will also evaluate reasonable alternatives to the proposed 
project or

[[Page 49744]]

portions of the project, and make recommendations on how to lessen or 
avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary. Depending on 
the comments received during the scoping process, we may also publish 
and distribute the EA to the public for an allotted comment period. We 
will consider all comments on the EA before making our recommendations 
to the Commission. To ensure we have the opportunity to consider and 
address your comments, please carefully follow the instructions in the 
Public Participation section beginning on page 4.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues of 
this project to formally cooperate with us in the preparation of the 
EA.\3\ Agencies that would like to request cooperating agency status 
should follow the instructions for filing comments provided under the 
Public Participation section of this notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Sec.  1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with applicable State Historic Preservation Office (SHPO), and to 
solicit their views and those of other government agencies, interested 
Indian tribes, and the public on the project's potential effects on 
historic properties.\4\ We will define the project-specific Area of 
Potential Effects (APE) in consultation with the SHPO as the project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EA for this project will document our 
findings on the impacts on historic properties and summarize the status 
of consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Public Participation

    You can make a difference by providing us with your specific 
comments or concerns about the project. Your comments should focus on 
the potential environmental effects, reasonable alternatives, and 
measures to avoid or lessen environmental impacts. The more specific 
your comments, the more useful they will be. To ensure that your 
comments are timely and properly recorded, please send your comments so 
that the Commission receives them in Washington, DC on or before 
September 9, 2013.
    For your convenience, there are three methods you can use to submit 
your comments to the Commission. In all instances please reference the 
project docket number (CP13-498-000) with your submission. The 
Commission encourages electronic filing of comments and has expert 
staff available to assist you at (202) 502-8258 or efiling@ferc.gov.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for interested persons to 
submit brief, text-only comments on a project;
    (2) You can file your comments electronically using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' You must select the type of filing you are making. If 
you are filing a comment on a particular project, please select 
``Comment on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 
20426.

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
proposed project.
    If we publish and distribute the EA, copies will be sent to the 
environmental mailing list for public review and comment. If you would 
prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the User's Guide under the ``e-filing'' link on the Commission's Web 
site.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., CP13-
498). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/esubscribenow.htm.
    Finally, public meetings or site visits will be posted on the 
Commission's

[[Page 49745]]

calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along 
with other related information.

    Dated: August 9, 2013.
Kimberly D. Bose,
 Secretary.
BILLING CODE 6717-01-P

Appendix 1
[GRAPHIC] [TIFF OMITTED] TN15AU13.002


[[Page 49746]]


[GRAPHIC] [TIFF OMITTED] TN15AU13.003


[[Page 49747]]


[GRAPHIC] [TIFF OMITTED] TN15AU13.004

[FR Doc. 2013-19824 Filed 8-14-13; 8:45 am]
BILLING CODE 6717-01-C
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.