Drawbridge Operation Regulation; Atlantic Intracoastal Waterway (AIWW), Chesapeake, VA, 48608 [2013-19353]
Download as PDF
48608
Federal Register / Vol. 78, No. 154 / Friday, August 9, 2013 / Rules and Regulations
DEPARTMENT OF HOMELAND
SECURITY
Coast Guard
33 CFR Part 117
[Docket No. USCG–2013–0707]
Drawbridge Operation Regulation;
Atlantic Intracoastal Waterway (AIWW),
Chesapeake, VA
Coast Guard, DHS.
Notice of deviation from
drawbridge regulations.
AGENCY:
ACTION:
The Coast Guard has issued a
temporary deviation from the operating
schedule that governs the operation of
the I64 Bridge across the Atlantic
Intracoastal Waterway, South Branch of
the Elizabeth River, mile 7.1, at
Chesapeake, VA.
This deviation is necessary to
facilitate maintenance work on the
moveable spans. This temporary
deviation allows the drawbridge to
remain in the closed to navigation
position.
SUMMARY:
This deviation is effective from
7 a.m. on Sept 13, 2013 to 5 p.m. Sept
29, 2013.
ADDRESSES: The docket for this
deviation, [USCG–2013–0707] is
available at https://www.regulations.gov.
Type the docket number in the
‘‘SEARCH’’ box and click ‘‘SEARCH.’’
Click on Open Docket Folder on the line
associated with this deviation. You may
also visit the Docket Management
Facility in Room W12–140 on the
ground floor of the Department of
Transportation West Building, 1200
New Jersey Avenue SE., Washington,
DC 20590, between 9 a.m. and 5 p.m.,
Monday through Friday, except Federal
holidays.
FOR FURTHER INFORMATION CONTACT: If
you have questions on this temporary
deviation, call or email Mrs. Kashanda
Booker, Bridge Administration Branch
Fifth District, Coast Guard; telephone
(757) 398–6227, email
Kashanda.l.booker@uscg.mil. If you
have questions on reviewing the docket,
call Barbara Hairston, Program Manager,
Docket Operations, (202) 366–9826.
SUPPLEMENTARY INFORMATION: The
Virginia Department of Transportation,
who owns and operates this bridge, has
requested a temporary deviation from
the current operating regulation set out
in 33 CFR 117.997(e), to facilitate
maintenance of the moveable spans on
the structure.
The current operating schedule for the
bridge is set out in 33 CFR 117.997 (e)
which requires the bridge open on
pmangrum on DSK3VPTVN1PROD with RULES
DATES:
VerDate Mar<15>2010
14:49 Aug 08, 2013
Jkt 229001
signal if at least 24 hours notice is given.
The I64 Bridge has a vertical clearance
in the closed position of 65 feet above
mean high water.
Under this temporary deviation, the
drawbridge will be closed to navigation
each day, from 7 a.m. to 5 p.m., on
Friday September 13, 2013 to Sunday
September 15, 2013; and on Friday
September 20, 2013 to Sunday
September 22, 2013; with inclement
weather dates, from 7 a.m. to 5 p.m., on
Friday September 27, 2013 through
Sunday, September 29, 2013. The bridge
will operate under normal operating
schedule at all other times.
Vessels able to pass under the bridge
in the closed position may do so at
anytime and are advised to proceed
with caution. There is no immediate
alternate route for vessels transiting this
section on the South Branch of the
Elizabeth River; however, vessels
requiring an opening may proceed
before and after the closure periods. The
bridge will not be able to open for
emergencies. The Coast Guard will also
inform additional waterway users
through our Local and Broadcast
Notices to Mariners of the closure
periods for the bridge so that vessels can
arrange their transits to minimize any
impacts caused by the temporary
deviation.
In accordance with 33 CFR 117.35(e),
the drawbridge must return to its regular
operating schedule immediately at the
end of the effective period of this
temporary deviation. This deviation
from the operating regulations is
authorized under 33 CFR 117.35.
Dated: July 31, 2013.
Waverly W. Gregory, Jr.,
Bridge Program Manager, Fifth Coast Guard
District.
[FR Doc. 2013–19353 Filed 8–8–13; 8:45 am]
BILLING CODE 9110–04–P
DEPARTMENT OF HOMELAND
SECURITY
Coast Guard
33 CFR Part 117
[Docket No. USCG–2013–0719]
Drawbridge Operation Regulations;
Townsend Gut, Boothbay Harbor and
Southport, ME
Coast Guard, DHS.
Notice of temporary deviation
from regulations.
AGENCY:
ACTION:
The Commander, First Coast
Guard District, has issued a temporary
deviation from the regulation governing
the operation of the Southport SR27
SUMMARY:
PO 00000
Frm 00010
Fmt 4700
Sfmt 4700
Bridge across Townsend Gut, mile 0.7,
between Boothbay Harbor and
Southport, Maine. The bridge owner,
Maine Department of Transportation
will be performing electrical repairs at
the bridge. This deviation allows the
bridge to remain in the closed position
for four hours to facilitate scheduled
bridge maintenance.
This deviation is effective
between 8 a.m. and 12 p.m. on August
21, 2013 and August 22, 2013.
DATES:
Documents mentioned in
this preamble as being available in the
docket are part of docket USCG–2013–
0719 and are available online at
www.regulations.gov, inserting USCG–
2013–0719 in the ‘‘Keyword’’ and then
clicking ‘‘Search’’. They are also
available for inspection or copying at
the Docket Management Facility (M–30),
U.S. Department of Transportation,
West Building Ground Floor, Room
W12–140, 1200 New Jersey Avenue SE.,
Washington, DC 20590, between 9 a.m.
and 5 p.m., Monday through Friday,
except Federal holidays.
ADDRESSES:
If
you have questions on this rule, call or
email Mr. John McDonald, Project
Officer, First Coast Guard District,
telephone (617) 223–8364,
john.w.mcdonald@uscg.mil. If you have
questions on viewing the docket, call
Barbara Hairston, Program Manager,
Docket Operations, telephone 202–366–
9826.
FOR FURTHER INFORMATION CONTACT:
The
Southport SR27 Bridge, across
Townsend Gut, mile 0.7, between
Boothbay Harbor and Southport, Maine,
has a vertical clearance in the closed
position of 10 feet above mean high
water and 19 feet above mean low
water. The bridge operating regulations
are listed at 33 CFR 117.537.
The waterway is transited by
recreational and commercial fishing
boats. There is an alternate route for
navigation around Southport.
The bridge owner, Maine Department
of Transportation, requested a
temporary deviation from the normal
operating schedule to facilitate deck
repairs at the bridge.
Under this temporary deviation the
Southport SR27 Bridge may remain in
the closed position between 8 a.m. and
12 p.m. on August 21, 2013, with a rain
date of August 22, 2013.
In accordance with 33 CFR 117.35(e),
the bridge must return to its regular
operating schedule immediately at the
end of the designated time period. This
deviation from the operating regulations
is authorized under 33 CFR 117.35.
SUPPLEMENTARY INFORMATION:
E:\FR\FM\09AUR1.SGM
09AUR1
Agencies
[Federal Register Volume 78, Number 154 (Friday, August 9, 2013)]
[Rules and Regulations]
[Page 48608]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-19353]
[[Page 48608]]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF HOMELAND SECURITY
Coast Guard
33 CFR Part 117
[Docket No. USCG-2013-0707]
Drawbridge Operation Regulation; Atlantic Intracoastal Waterway
(AIWW), Chesapeake, VA
AGENCY: Coast Guard, DHS.
ACTION: Notice of deviation from drawbridge regulations.
-----------------------------------------------------------------------
SUMMARY: The Coast Guard has issued a temporary deviation from the
operating schedule that governs the operation of the I64 Bridge across
the Atlantic Intracoastal Waterway, South Branch of the Elizabeth
River, mile 7.1, at Chesapeake, VA.
This deviation is necessary to facilitate maintenance work on the
moveable spans. This temporary deviation allows the drawbridge to
remain in the closed to navigation position.
DATES: This deviation is effective from 7 a.m. on Sept 13, 2013 to 5
p.m. Sept 29, 2013.
ADDRESSES: The docket for this deviation, [USCG-2013-0707] is available
at https://www.regulations.gov. Type the docket number in the ``SEARCH''
box and click ``SEARCH.'' Click on Open Docket Folder on the line
associated with this deviation. You may also visit the Docket
Management Facility in Room W12-140 on the ground floor of the
Department of Transportation West Building, 1200 New Jersey Avenue SE.,
Washington, DC 20590, between 9 a.m. and 5 p.m., Monday through Friday,
except Federal holidays.
FOR FURTHER INFORMATION CONTACT: If you have questions on this
temporary deviation, call or email Mrs. Kashanda Booker, Bridge
Administration Branch Fifth District, Coast Guard; telephone (757) 398-
6227, email Kashanda.l.booker@uscg.mil. If you have questions on
reviewing the docket, call Barbara Hairston, Program Manager, Docket
Operations, (202) 366-9826.
SUPPLEMENTARY INFORMATION: The Virginia Department of Transportation,
who owns and operates this bridge, has requested a temporary deviation
from the current operating regulation set out in 33 CFR 117.997(e), to
facilitate maintenance of the moveable spans on the structure.
The current operating schedule for the bridge is set out in 33 CFR
117.997 (e) which requires the bridge open on signal if at least 24
hours notice is given. The I64 Bridge has a vertical clearance in the
closed position of 65 feet above mean high water.
Under this temporary deviation, the drawbridge will be closed to
navigation each day, from 7 a.m. to 5 p.m., on Friday September 13,
2013 to Sunday September 15, 2013; and on Friday September 20, 2013 to
Sunday September 22, 2013; with inclement weather dates, from 7 a.m. to
5 p.m., on Friday September 27, 2013 through Sunday, September 29,
2013. The bridge will operate under normal operating schedule at all
other times.
Vessels able to pass under the bridge in the closed position may do
so at anytime and are advised to proceed with caution. There is no
immediate alternate route for vessels transiting this section on the
South Branch of the Elizabeth River; however, vessels requiring an
opening may proceed before and after the closure periods. The bridge
will not be able to open for emergencies. The Coast Guard will also
inform additional waterway users through our Local and Broadcast
Notices to Mariners of the closure periods for the bridge so that
vessels can arrange their transits to minimize any impacts caused by
the temporary deviation.
In accordance with 33 CFR 117.35(e), the drawbridge must return to
its regular operating schedule immediately at the end of the effective
period of this temporary deviation. This deviation from the operating
regulations is authorized under 33 CFR 117.35.
Dated: July 31, 2013.
Waverly W. Gregory, Jr.,
Bridge Program Manager, Fifth Coast Guard District.
[FR Doc. 2013-19353 Filed 8-8-13; 8:45 am]