Drawbridge Operation Regulation; Lake Washington Ship Canal, Seattle, WA, 45056 [2013-18029]

Download as PDF 45056 Federal Register / Vol. 78, No. 144 / Friday, July 26, 2013 / Rules and Regulations Monday, July 15, 2013, make the following correction: On page 42326, in Table 1, the table section beneath the heading ‘‘Scenario: (3) Serve as an SIC (first officer) in part 121 operations’’ should read as follows: Scenario: (3) Serve as an SIC (first officer) in part 121 operations Previous requirements Requirements in final rule Hold: (1) At least a commercial pilot certificate with an appropriate category and class rating; (2) An instrument rating; and (3) At least a second-class medical certificate. Hold: (1) An ATP certificate with appropriate aircraft type rating OR—An ATP certificate with restricted privileges and an appropriate aircraft type rating; and (2) At least a second-class medical certificate. (Ref. §§ 121.436 and 61.23). [FR Doc. C1–2013–16849 Filed 7–25–13; 8:45 am] BILLING CODE 1505–01–D DEPARTMENT OF HOMELAND SECURITY Coast Guard 33 CFR Part 117 [Docket No. USCG–2013–0620] Drawbridge Operation Regulation; Lake Washington Ship Canal, Seattle, WA Coast Guard, DHS. Notice of deviation from drawbridge regulation. AGENCY: ACTION: The Coast Guard has issued a temporary deviation from the operating schedule that governs the Montlake Bridge across the Lake Washington Ship Canal, mile 5.2, at Seattle, WA. The deviation is necessary to accommodate vehicular traffic attending football games at Husky Stadium at the University of Washington, Seattle, Washington. This deviation allows the bridge to remain in the closed position two hours before and two hours after each game. Please note that the game times for five of the seven games scheduled for Husky Stadium have not yet been determined due to NCAA television scheduling. DATES: This deviation is effective from 5 p.m. to 7 p.m. and 10 p.m. to 11:59 p.m. on August 31, 2013; 12:01 a.m. to 11:59 p.m. on September 21, 2013; 12:01 a.m. to 11:59 p.m. on September 28, 2013; 12:01 a.m. to 11:59 p.m. on October 12, 2013; 12:01 a.m. to 11:59 p.m. on October 26, 2013; 12:01 a.m. to 11:59 p.m. on November 9, 2013; 10:30 a.m. to 12:30 p.m. and 3:30 p.m. to 5:30 p.m. on November 29, 2013. ADDRESSES: The docket for this deviation, [USCG–2013–0620] is available at https://www.regulations.gov. Type the docket number in the ‘‘SEARCH’’ box and click ‘‘SEARCH.’’ Click on Open Docket Folder on the line tkelley on DSK3SPTVN1PROD with RULES SUMMARY: VerDate Mar<15>2010 17:30 Jul 25, 2013 Jkt 229001 associated with this deviation. You may also visit the Docket Management Facility in Room W12–140 on the ground floor of the Department of Transportation West Building, 1200 New Jersey Avenue SE., Washington, DC 20590, between 9 a.m. and 5 p.m., Monday through Friday, except Federal holidays. FOR FURTHER INFORMATION CONTACT: If you have questions on this temporary deviation, call or email Steven M. Fischer, Lieutenant Commander, Bridge Specialist, Thirteenth District, Coast Guard; telephone 206–220–7277, email Steven.M.Fischer2@uscg.mil. If you have questions on viewing the docket, call Barbara Hairston, Program Manager, Docket Operations, telephone 202–366– 9826. SUPPLEMENTARY INFORMATION: The Washington State Department of Transportation, on behalf of the University of Washington Police Department, has requested that the Montlake Bridge bascule span remain closed and need not open to vessel traffic to facilitate timely movement of pre-game and post game football traffic. The Montlake Bridge crosses the Lake Washington Ship Canal at mile 5.2 and while in the closed position provides 30 feet of vertical clearance throughout the navigation channel and 46 feet of vertical clearance throughout the center 60-feet of the bridge. These vertical clearance measurements are made in reference to the Mean Water Level of Lake Washington. Vessels which do not require a bridge opening may continue to transit beneath the bridges during this closure period. Under normal conditions this bridge opens on signal, subject to the list of exceptions provided in 33 CFR 117.1051(e). This deviation period will cover the dates August 31, 2013 to November 29, 2013 as follows. From 5:00 p.m. to 7:00 p.m. and from 10:00 p.m. to 11:59 p.m. on August 31, 2013; from 10:30 a.m. to 12:30 p.m. and from 3:30 p.m. to 5:30 p.m. on November 29, 2013. The times for the closures on September 21, 2013, September 28, 2013, October 12, 2013, PO 00000 Frm 00006 Fmt 4700 Sfmt 9990 October 26, 2013, and November 09, 2013 will be determined and announced in the Coast Guard’s Local Notice to Mariners and Broadcast Notice to Mariners as they become available. Due to NCAA television scheduling, the times for the games are not currently available. The deviation allows the bascule span of the Montlake Bridge to remain in the closed position and need not open for maritime traffic from 5:00 p.m. to 7:00 p.m. and 10:00 p.m. to 11:59 p.m. on August 31, 2013, and from 10:30 a.m. to 12:30 p.m. and 3:30 p.m. to 5:30 p.m. on November 29, 2013, for times to be determined on September 21, 2013, September 28, 2013, October 12, 2013, October 26, 2013, and November 09, 2013. The bridge shall operate in accordance with 33 CFR 117.1051(e) at all other times. Waterway usage on the Lake Washington Ship Canal ranges from commercial tug and barge to small pleasure craft. Mariners will be notified and kept informed of the bridge’s operational status via the Coast Guard Notice to Mariners publication and Broadcast Notice to Mariners as appropriate. The draw span will be required to open, if needed, for vessels engaged in emergency response operations during this closure period. In accordance with 33 CFR 117.35(e), the drawbridges must return to its regular operating schedule immediately at the end of the designated time period. This deviation from the operating regulations is authorized under 33 CFR 117.35. Dated: July 16, 2013. Daryl R. Peloquin, Acting Bridge Administrator, Thirteenth Coast Guard District. [FR Doc. 2013–18029 Filed 7–25–13; 8:45 am] BILLING CODE 9110–04–P E:\FR\FM\26JYR1.SGM 26JYR1

Agencies

[Federal Register Volume 78, Number 144 (Friday, July 26, 2013)]
[Rules and Regulations]
[Page 45056]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-18029]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF HOMELAND SECURITY

Coast Guard

33 CFR Part 117

[Docket No. USCG-2013-0620]


Drawbridge Operation Regulation; Lake Washington Ship Canal, 
Seattle, WA

AGENCY: Coast Guard, DHS.

ACTION: Notice of deviation from drawbridge regulation.

-----------------------------------------------------------------------

SUMMARY: The Coast Guard has issued a temporary deviation from the 
operating schedule that governs the Montlake Bridge across the Lake 
Washington Ship Canal, mile 5.2, at Seattle, WA. The deviation is 
necessary to accommodate vehicular traffic attending football games at 
Husky Stadium at the University of Washington, Seattle, Washington. 
This deviation allows the bridge to remain in the closed position two 
hours before and two hours after each game. Please note that the game 
times for five of the seven games scheduled for Husky Stadium have not 
yet been determined due to NCAA television scheduling.

DATES: This deviation is effective from 5 p.m. to 7 p.m. and 10 p.m. to 
11:59 p.m. on August 31, 2013; 12:01 a.m. to 11:59 p.m. on September 
21, 2013; 12:01 a.m. to 11:59 p.m. on September 28, 2013; 12:01 a.m. to 
11:59 p.m. on October 12, 2013; 12:01 a.m. to 11:59 p.m. on October 26, 
2013; 12:01 a.m. to 11:59 p.m. on November 9, 2013; 10:30 a.m. to 12:30 
p.m. and 3:30 p.m. to 5:30 p.m. on November 29, 2013.

ADDRESSES: The docket for this deviation, [USCG-2013-0620] is available 
at https://www.regulations.gov. Type the docket number in the ``SEARCH'' 
box and click ``SEARCH.'' Click on Open Docket Folder on the line 
associated with this deviation. You may also visit the Docket 
Management Facility in Room W12-140 on the ground floor of the 
Department of Transportation West Building, 1200 New Jersey Avenue SE., 
Washington, DC 20590, between 9 a.m. and 5 p.m., Monday through Friday, 
except Federal holidays.

FOR FURTHER INFORMATION CONTACT: If you have questions on this 
temporary deviation, call or email Steven M. Fischer, Lieutenant 
Commander, Bridge Specialist, Thirteenth District, Coast Guard; 
telephone 206-220-7277, email Steven.M.Fischer2@uscg.mil. If you have 
questions on viewing the docket, call Barbara Hairston, Program 
Manager, Docket Operations, telephone 202-366-9826.

SUPPLEMENTARY INFORMATION: The Washington State Department of 
Transportation, on behalf of the University of Washington Police 
Department, has requested that the Montlake Bridge bascule span remain 
closed and need not open to vessel traffic to facilitate timely 
movement of pre-game and post game football traffic. The Montlake 
Bridge crosses the Lake Washington Ship Canal at mile 5.2 and while in 
the closed position provides 30 feet of vertical clearance throughout 
the navigation channel and 46 feet of vertical clearance throughout the 
center 60-feet of the bridge. These vertical clearance measurements are 
made in reference to the Mean Water Level of Lake Washington. Vessels 
which do not require a bridge opening may continue to transit beneath 
the bridges during this closure period. Under normal conditions this 
bridge opens on signal, subject to the list of exceptions provided in 
33 CFR 117.1051(e).
    This deviation period will cover the dates August 31, 2013 to 
November 29, 2013 as follows. From 5:00 p.m. to 7:00 p.m. and from 
10:00 p.m. to 11:59 p.m. on August 31, 2013; from 10:30 a.m. to 12:30 
p.m. and from 3:30 p.m. to 5:30 p.m. on November 29, 2013. The times 
for the closures on September 21, 2013, September 28, 2013, October 12, 
2013, October 26, 2013, and November 09, 2013 will be determined and 
announced in the Coast Guard's Local Notice to Mariners and Broadcast 
Notice to Mariners as they become available. Due to NCAA television 
scheduling, the times for the games are not currently available.
    The deviation allows the bascule span of the Montlake Bridge to 
remain in the closed position and need not open for maritime traffic 
from 5:00 p.m. to 7:00 p.m. and 10:00 p.m. to 11:59 p.m. on August 31, 
2013, and from 10:30 a.m. to 12:30 p.m. and 3:30 p.m. to 5:30 p.m. on 
November 29, 2013, for times to be determined on September 21, 2013, 
September 28, 2013, October 12, 2013, October 26, 2013, and November 
09, 2013. The bridge shall operate in accordance with 33 CFR 
117.1051(e) at all other times. Waterway usage on the Lake Washington 
Ship Canal ranges from commercial tug and barge to small pleasure 
craft. Mariners will be notified and kept informed of the bridge's 
operational status via the Coast Guard Notice to Mariners publication 
and Broadcast Notice to Mariners as appropriate. The draw span will be 
required to open, if needed, for vessels engaged in emergency response 
operations during this closure period.
    In accordance with 33 CFR 117.35(e), the drawbridges must return to 
its regular operating schedule immediately at the end of the designated 
time period. This deviation from the operating regulations is 
authorized under 33 CFR 117.35.

    Dated: July 16, 2013.
Daryl R. Peloquin,
Acting Bridge Administrator, Thirteenth Coast Guard District.
[FR Doc. 2013-18029 Filed 7-25-13; 8:45 am]
BILLING CODE 9110-04-P