Proposed Revision 0 to Fitness-for-Duty Standard Review Plan, 42558-42560 [2013-16985]
Download as PDF
42558
5.0
Federal Register / Vol. 78, No. 136 / Tuesday, July 16, 2013 / Notices
Environmental Assessment (EA)
Identification of Proposed Action
By letter dated June 8, 2012, MYAPC
submitted an exemption request in
accordance with 10 CFR 50.12 from
specific EP requirements of 10 CFR
50.47 and Appendix E to 10 CFR part
50 for MY. Specifically, the exemption
would eliminate unnecessary
requirements associated with offsite
consequences, protective actions,
hostile action and emergency facilities
due to the current status of MY.
emcdonald on DSK67QTVN1PROD with NOTICES
Need for the Proposed Action
In accordance with 10 CFR 50.82, the
10 CFR part 50 licensed area for MY has
been reduced to a small area
surrounding the ISFSI. In this condition,
MY poses a significantly reduced risk to
public health and safety from design
basis accidents or credible beyond
design basis accidents since these
cannot result in radioactive releases
which exceed EPA PAGS at the site
boundary. Because of this reduced risk,
compliance with all the requirements in
10 CFR 50.47 and 10 CFR part 50,
Appendix E is not appropriate. The
requested exemption from portions of
10 CFR 50.47 and 10 CFR part 50,
Appendix E is needed to continue
implementation of the MY ISFSI
emergency plan that is appropriate for a
stand-alone ISFSI and is commensurate
with the reduced risk posed by the
facility. The requested exemption will
allow spent fuel to continue to be stored
safely without imposing burdensome
and costly new requirements that
provide no increased safety benefit.
Environmental Impacts of the Proposed
Action
The NRC has determined that, given
the continued implementation of the
MY ISFSI emergency plan, with the
exemptions noted in its SE, no credible
events would result in doses to the
public beyond the owner controlled area
boundary that would exceed the EPA
PAGs. Additionally, the staff has
concluded that the MY ISFSI emergency
plan, with the exemptions described in
its SE, provides for an acceptable level
of emergency preparedness at the
MYAPC facility in its shutdown and
defueled condition, and also provides
reasonable assurance that adequate
protective measures can and will be
taken in the event of a radiological
emergency at the MYAPC facility. Based
on these findings, the NRC concludes
that there are no radiological
environmental impacts due to granting
the approval of the exemptions, the
proposed action will not increase the
probability or consequences of
VerDate Mar<15>2010
18:49 Jul 15, 2013
Jkt 229001
accidents, no changes are being made in
the types or quantities of effluents that
may be released offsite, and there is no
significant increase in occupational or
public radiation exposure. Therefore,
there are no significant radiological
environmental impacts associated with
the proposed action. The proposed
action does not affect non-radiological
plant effluents and has no other
environmental impact. Therefore, there
are no significant non-radiological
impacts associated with the proposed
action. Based on the assessment above,
the proposed action will not have a
significant effect on the quality of the
human environment.
Alternative to the Proposed Action
Since there is no significant
environmental impact associated with
the proposed action, any alternatives
with equal or greater environmental
impact are not evaluated. The
alternative to the proposed action would
be to deny approval of the exemption.
This alternative would have the same
environmental impact.
Finding of No Significant Impact
The environmental impacts of the
proposed action have been reviewed in
accordance with the requirements set
forth in 10 CFR part 51. Based upon the
EA, the Commission finds that the
proposed action of granting an
exemption will not significantly impact
the quality of the human environment.
Accordingly, the Commission has
determined not to prepare an
environmental impact statement for the
proposed exemption.
6.0 Conclusion
The NRC concludes that the licensee’s
request for an exemption from certain
requirements of 10 CFR 50.47(b) and 10
CFR part 50, Appendix E, Section IV as
specified in the SE are acceptable in
view of the greatly reduced offsite
radiological consequences associated
with the ISFSI.
The exemption request has been
reviewed against the acceptance criteria
included in 10 CFR 50.47, Appendix E
to 10 CFR part 50, 10 CFR 72.32 and
Interim Staff Guidance—16. The review
considered the ISFSI and the low
likelihood of any credible accident
resulting in radiological releases
requiring offsite protective measures.
These evaluations were supported by
the previously documented licensee and
staff accident analyses. The staff
concludes that: the MY ISFSI
Emergency Plan provides: (1) An
adequate basis for an acceptable state of
emergency preparedness; and (2) the
emergency plan, in conjunction with
PO 00000
Frm 00073
Fmt 4703
Sfmt 4703
arrangements made with offsite
response agencies, provides reasonable
assurance that adequate protective
measures can and will be taken in the
event of a radiological emergency at the
MYAPC facility.
The NRC has determined that
pursuant to 10 CFR 50.12, the
exemptions described in the SE are
authorized by law, will not endanger
life or property or the common defense
and security, and are otherwise in the
public interest, and special
circumstances are present.
7.0 Further Information
Documents related to this action,
including the application for renewal
and supporting documentation, are
available online in the NRC library at
https://www.nrc.gov/reading-rm/
adams.html. From this site, you can
access the NRC’s ADAMS, which
provides text and image files of NRC’s
public documents. If you do not have
access to ADAMS or if there are
problems in accessing the documents
located in ADAMS, contact the NRC
Public Document Room (PDR) Reference
staff at 1–800–397–4209, 301–415–4737
or by email to pdr.resource@nrc.gov.
These documents may also be viewed
electronically on the public computers
located at the NRC’s PDR, O 1 F21, One
White Flint North, 11555 Rockville
Pike, Rockville, MD 20852. The PDR
reproduction contractor will copy
documents for a fee.
Dated at Rockville, Maryland, this 28th day
of June, 2013.
For the Nuclear Regulatory Commission.
Michele M. Sampson,
Acting Chief, Licensing Branch, Division of
Spent Fuel Storage and Transportation, Office
of Nuclear Material Safety and Safeguards.
[FR Doc. 2013–16988 Filed 7–15–13; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2013–0149]
Proposed Revision 0 to Fitness-forDuty Standard Review Plan
Nuclear Regulatory
Commission.
ACTION: Notice of availability and
request for comment.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is soliciting public
comment on draft NUREG–0800,
‘‘Standard Review Plan for the Review
of Safety Analysis Reports for Nuclear
Power Plants,’’ LWR Edition: Section
13.7 ‘‘Fitness-for-Duty,’’ and Section
13.7.1 ‘‘Fitness-for-Duty—Operational
SUMMARY:
E:\FR\FM\16JYN1.SGM
16JYN1
Federal Register / Vol. 78, No. 136 / Tuesday, July 16, 2013 / Notices
Program.’’ The NRC seeks comments on
the proposed new sections of the
Standard Review Plan (SRP), concerning
implementation of a Fitness-for-Duty
(FFD) program. The current SRP does
not contain guidance on the review of
an applicant’s proposed FFD program.
DATES: Comments must be filed no later
than August 15, 2013. Comments
received after this date will be
considered, if it is practical to do so, but
the Commission is able to ensure
consideration only for comments
received on or before this date.
ADDRESSES: You may access information
and comment submissions related to
this document, which the NRC
possesses and are publically available,
by searching on https://
www.regulations.gov under Docket ID
NRC–2013–0149. You may submit
comments by any of the following
methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2013–0149. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–492–3668;
email: Carol.Gallagher@nrc.gov.
• Mail comments to: Cindy Bladey,
Chief, Rules, Announcements, and
Directives Branch (RADB), Office of
Administration, Mail Stop: 3WFN 6–
A56, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001.
For additional direction on accessing
information and submitting comments,
see ‘‘Accessing Information and
Submitting Comments’’ in the
SUPPLEMENTARY INFORMATION.
FOR FURTHER INFORMATION CONTACT:
Wesley Held, Office of New Reactors,
U.S. Nuclear Regulatory Commission,
Washington, DC 20555–0001; telephone:
301–415–1583 or email:
Wesley.Held@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Accessing Information and
Submitting Comments
emcdonald on DSK67QTVN1PROD with NOTICES
A. Accessing Information
Please refer to Docket ID NRC–2013–
0149 when contacting the NRC about
the availability of information regarding
this document. You may access
information related to this document,
which the NRC possesses and are
publicly available, by any of the
following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2013–0149.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may access publicly
available documents online in the NRC
VerDate Mar<15>2010
18:49 Jul 15, 2013
Jkt 229001
Library at https://www.nrc.gov/readingrm/adams.html. To begin the search,
select ‘‘ADAMS Public Documents’’ and
then select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS Accession numbers for the
proposed new sections of the SRP are
available in ADAMS under Accession
Nos.: ML113250516 (Section 13.7,
‘‘Fitness for Duty—Introduction’’), and
ML113250541 (Section 13.7.1, ‘‘Fitness
for Duty—Operational Program’’).
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
B. Submitting Comments
Please include Docket ID NRC–2013–
0149 in the subject line of your
comment submission, in order to ensure
that the NRC is able to make your
comment submission available to the
public in this docket.
The NRC cautions you not to include
identifying or contact information in
comment submissions that you do not
want to be publicly disclosed. The NRC
posts all comment submissions at https://
www.regulations.gov as well as enters
the comment submissions into ADAMS.
The NRC does not routinely edit
comment submissions to remove
identifying or contact information.
If you are requesting or aggregating
comments from other persons for
submission to the NRC, then you should
inform those persons not to include
identifying or contact information in
their comment submissions that they do
not want to be publicly disclosed. Your
request should state that the NRC does
not routinely edit comment submissions
to remove such information before
making the comment submissions
available to the public or entering the
comment submissions into ADAMS.
II. Further Information
The NRC seeks public comment on
the proposed new sections of the SRP.
These sections have been developed to
assist NRC staff with the review of
applications for certain construction
permits, early site permits, licenses,
license amendments, and combined
licenses and to inform new reactor
applicants and other affected entities of
proposed SRP guidance regarding an
acceptable method by which to evaluate
a proposed Fitness-for-Duty program for
compliance with part 26 of Title 10 of
the Code of Federal Regulations (10
CFR).
PO 00000
Frm 00074
Fmt 4703
Sfmt 4703
42559
Following NRC staff evaluation of
public comments, the NRC intends to
incorporate the final approved guidance
into the next revision of NUREG–0800.
The SRP is guidance for the NRC staff.
The SRP is not a substitute for the NRC
regulations, and compliance with the
SRP is not required.
Backfitting and Issue Finality
Issuance of this draft SRP, if finalized,
would not constitute backfitting as
defined in section 50.109 of Title 10 of
the Code of Federal Regulations (10
CFR) (the Backfit Rule) or otherwise be
inconsistent with the issue finality
provisions in part 50 of Title 10 of the
Code of Federal Regulations (10 CFR).
The NRC’s position is based upon the
following considerations.
1. The draft SRP positions, if
finalized, would not constitute
backfitting, inasmuch as the SRP is
internal guidance to NRC staff.
The SRP provides internal guidance
to the NRC staff on how to review an
application for NRC regulatory approval
in the form of licensing. Changes in
internal staff guidance are not matters
for which either nuclear power plant
applicants or licensees are protected
under either the Backfit Rule or the
issue finality provisions of 10 CFR part
52.
2. The NRC staff has no intention to
impose the SRP positions on existing
licensees either now or in the future.
The NRC staff does not intend to
impose or apply the positions described
in the draft SRP to existing licenses and
regulatory approvals. Hence, the
issuance of a final SRP—even if
considered guidance within the purview
of the issue finality provisions in 10
CFR part 52— would not need to be
evaluated as if it were a backfit or as
being inconsistent with issue finality
provisions. If, in the future, the NRC
staff seeks to impose a position in the
SRP on holders of already issued
licenses in a manner that does not
provide issue finality as described in the
applicable issue finality provision, then
the staff must make the showing as set
forth in the Backfit Rule or address the
criteria for avoiding issue finality as
described in the applicable issue finality
provision.
3. #Backfitting and issue finality do
not—with limited exceptions not
applicable here—protect current or
future applicants.
Applicants and potential applicants
are not, with certain exceptions,
protected by either the Backfit Rule or
any issue finality provisions under 10
CFR part 52. Neither the Backfit Rule
nor the issue finality provisions under
10 CFR part 52—with certain
E:\FR\FM\16JYN1.SGM
16JYN1
42560
Federal Register / Vol. 78, No. 136 / Tuesday, July 16, 2013 / Notices
exclusions—were intended to apply to
every NRC action that substantially
changes the expectations of current and
future applicants. The exceptions to the
general principle are applicable
whenever an applicant references a 10
CFR part 52 license (e.g., an early site
permit) and/or NRC regulatory approval
(e.g., a design certification rule) with
specified issue finality provisions. The
NRC staff does not, at this time, intend
to impose the positions represented in
the draft SRP in a manner that is
inconsistent with any issue finality
provisions. If, in the future, the staff
seeks to impose a position in the draft
SRP in a manner that does not provide
issue finality as described in the
applicable issue finality provision, then
the staff must address the criteria for
avoiding issue finality as described in
the applicable issue finality provision.
Dated at Rockville, Maryland, this 27th day
of June 2013.
For the Nuclear Regulatory Commission.
Joseph Colaccino,
Chief, Policy Branch, Division of Advanced
Reactors and Rulemaking, Office of New
Reactors.
[FR Doc. 2013–16985 Filed 7–15–13; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2013–0001]
Sunshine Act Meeting
AGENCY HOLDING THE MEETINGS: Nuclear
Regulatory Commission.
DATES: Weeks of July 15, 22, 29, August
5, 12, 19, 2013.
PLACE: Commissioners’ Conference
Room, 11555 Rockville Pike, Rockville,
Maryland.
STATUS: Public and Closed.
Week of July 15, 2013
There are no meetings scheduled for
the week of July 15, 2013.
Week of July 22, 2013—Tentative
There are no meetings scheduled for
the week of July 22, 2013.
emcdonald on DSK67QTVN1PROD with NOTICES
Week of July 29, 2013—Tentative
Week of August 19, 2013—Tentative
There are no meetings scheduled for
the week of August 19, 2013.
*
*
*
*
*
*The schedule for Commission
meetings is subject to change on short
notice. To verify the status of meetings,
call (recording)—301–415–1292.
Contact person for more information:
Rochelle Bavol, 301–415–1651.
*
*
*
*
*
I
Korea Hydro and Nuclear Power, Co.,
Ltd. (KHNP) submitted a letter of intent
to the U.S. Nuclear Regulatory
Commission (NRC) for a design
certification (DC) application in 2013.
In June 2009, the Commission
published a rulemaking in the Federal
Register (FR) (74 FR 28112) requiring
applicants for a variety of licensing
activities, including nuclear power
plant designers, to perform a designspecific assessment of the effects of the
impact of a large, commercial aircraft
and to incorporate design features and
functional capabilities into the nuclear
power plant design to provide
additional inherent protection with
reduced use of operator actions. A
discussion of the specific requirements
for applicants for new nuclear power
reactors can be found in Section V of the
Federal Register notice. To assist
designers in completing this assessment,
the Commission has decided to provide
the detailed aircraft impact
characteristics that should be used as
reasonable inputs for reactor vendors
and architect and engineers who have
the need to know and who meet the
NRC’s requirements for the disclosure of
such information to use in the required
aircraft impact assessments.
The NRC derived the characteristics
from agency analyses performed on
operating reactors to support, in part,
the development of a broadly effective
set of mitigation strategies to combat
fires and explosions from a spectrum of
hypothetical aircraft impacts. Although
the detailed characteristics were not
selected as a basis for designing new
reactors, the staff is suggesting them as
a starting point for aircraft impact
assessments. On August 5, 2011, the
NRC issued Regulatory Guide (RG)
1.217, ‘‘Guidance for the Assessment of
Beyond-Design-Basis Aircraft Impacts,’’
(NRC’s Agencywide Documents Access
and Management System (ADAMS)
Accession No. ML092900004), which
endorses the methodologies described
in the industry guidance document,
Nuclear Energy Institute (NEI) 07–13,
Week of August 5, 2013—Tentative
[FR Doc. 2013–17124 Filed 7–12–13; 4:15 pm]
There are no meetings scheduled for
the week of August 5, 2013.
BILLING CODE 7590–01–P
Week of August 12, 2013—Tentative
There are no meetings scheduled for
the week of August 12, 2013.
Jkt 229001
In the Matter of Korea Hydro and
Nuclear Power, Co., Ltd. and All Other
Persons Who Seek or Obtain Access
to Safeguards Information Described
Herein; Order Imposing Protection
Requirements for Access to
Safeguards Information (Effective
Immediately)
By a vote of 5–0 on July 10, 2013, the
Commission determined pursuant to
U.S.C. 552b(e) and ’9.107(a) of the
Commission’s rules that a Discussion of
Management and Personnel Issues
(Closed—Ex. 2 & 6) be held on July 11,
2013, with less than one week notice to
the public. The meeting was held on
July 11, 2013.
*
*
*
*
*
The NRC Commission Meeting
Schedule can be found on the Internet
at: https://www.nrc.gov/public-involve/
public-meetings/schedule.html.
*
*
*
*
*
The NRC provides reasonable
accommodation to individuals with
disabilities where appropriate. If you
need a reasonable accommodation to
participate in these public meetings, or
need this meeting notice or the
transcript or other information from the
public meetings in another format (e.g.
braille, large print), please notify
Kimberly Meyer, NRC Disability
Program Manager, at 301–287–0727, or
by email at kimberly.meyerchambers@nrc.gov. Determinations on
requests for reasonable accommodation
will be made on a case-by-case basis.
*
*
*
*
*
This notice is distributed
electronically to subscribers. If you no
longer wish to receive it, or would like
to be added to the distribution, please
contact the Office of the Secretary,
Washington, DC 20555 (301–415–1969),
or send an email to
darlene.wright@nrc.gov.
Dated: July 11, 2013.
Rochelle C. Bavol,
Policy Coordinator, Office of the Secretary.
18:49 Jul 15, 2013
[NRC–2013–0152]
[EA–13–033; Project No. 0782]
Additional Information
There are no meetings scheduled for
the week of July 29, 2013.
VerDate Mar<15>2010
NUCLEAR REGULATORY
COMMISSION
PO 00000
Frm 00075
Fmt 4703
Sfmt 4703
E:\FR\FM\16JYN1.SGM
16JYN1
Agencies
[Federal Register Volume 78, Number 136 (Tuesday, July 16, 2013)]
[Notices]
[Pages 42558-42560]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-16985]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[NRC-2013-0149]
Proposed Revision 0 to Fitness-for-Duty Standard Review Plan
AGENCY: Nuclear Regulatory Commission.
ACTION: Notice of availability and request for comment.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is soliciting
public comment on draft NUREG-0800, ``Standard Review Plan for the
Review of Safety Analysis Reports for Nuclear Power Plants,'' LWR
Edition: Section 13.7 ``Fitness-for-Duty,'' and Section 13.7.1
``Fitness-for-Duty--Operational
[[Page 42559]]
Program.'' The NRC seeks comments on the proposed new sections of the
Standard Review Plan (SRP), concerning implementation of a Fitness-for-
Duty (FFD) program. The current SRP does not contain guidance on the
review of an applicant's proposed FFD program.
DATES: Comments must be filed no later than August 15, 2013. Comments
received after this date will be considered, if it is practical to do
so, but the Commission is able to ensure consideration only for
comments received on or before this date.
ADDRESSES: You may access information and comment submissions related
to this document, which the NRC possesses and are publically available,
by searching on https://www.regulations.gov under Docket ID NRC-2013-
0149. You may submit comments by any of the following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2013-0149. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-492-
3668; email: Carol.Gallagher@nrc.gov.
Mail comments to: Cindy Bladey, Chief, Rules,
Announcements, and Directives Branch (RADB), Office of Administration,
Mail Stop: 3WFN 6-A56, U.S. Nuclear Regulatory Commission, Washington,
DC 20555-0001.
For additional direction on accessing information and submitting
comments, see ``Accessing Information and Submitting Comments'' in the
SUPPLEMENTARY INFORMATION.
FOR FURTHER INFORMATION CONTACT: Wesley Held, Office of New Reactors,
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001;
telephone: 301-415-1583 or email: Wesley.Held@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Accessing Information and Submitting Comments
A. Accessing Information
Please refer to Docket ID NRC-2013-0149 when contacting the NRC
about the availability of information regarding this document. You may
access information related to this document, which the NRC possesses
and are publicly available, by any of the following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2013-0149.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may access publicly available documents online in the NRC
Library at https://www.nrc.gov/reading-rm/adams.html. To begin the
search, select ``ADAMS Public Documents'' and then select ``Begin Web-
based ADAMS Search.'' For problems with ADAMS, please contact the NRC's
Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-
4737, or by email to pdr.resource@nrc.gov. The ADAMS Accession numbers
for the proposed new sections of the SRP are available in ADAMS under
Accession Nos.: ML113250516 (Section 13.7, ``Fitness for Duty--
Introduction''), and ML113250541 (Section 13.7.1, ``Fitness for Duty--
Operational Program'').
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
B. Submitting Comments
Please include Docket ID NRC-2013-0149 in the subject line of your
comment submission, in order to ensure that the NRC is able to make
your comment submission available to the public in this docket.
The NRC cautions you not to include identifying or contact
information in comment submissions that you do not want to be publicly
disclosed. The NRC posts all comment submissions at https://www.regulations.gov as well as enters the comment submissions into
ADAMS. The NRC does not routinely edit comment submissions to remove
identifying or contact information.
If you are requesting or aggregating comments from other persons
for submission to the NRC, then you should inform those persons not to
include identifying or contact information in their comment submissions
that they do not want to be publicly disclosed. Your request should
state that the NRC does not routinely edit comment submissions to
remove such information before making the comment submissions available
to the public or entering the comment submissions into ADAMS.
II. Further Information
The NRC seeks public comment on the proposed new sections of the
SRP. These sections have been developed to assist NRC staff with the
review of applications for certain construction permits, early site
permits, licenses, license amendments, and combined licenses and to
inform new reactor applicants and other affected entities of proposed
SRP guidance regarding an acceptable method by which to evaluate a
proposed Fitness-for-Duty program for compliance with part 26 of Title
10 of the Code of Federal Regulations (10 CFR).
Following NRC staff evaluation of public comments, the NRC intends
to incorporate the final approved guidance into the next revision of
NUREG-0800. The SRP is guidance for the NRC staff. The SRP is not a
substitute for the NRC regulations, and compliance with the SRP is not
required.
Backfitting and Issue Finality
Issuance of this draft SRP, if finalized, would not constitute
backfitting as defined in section 50.109 of Title 10 of the Code of
Federal Regulations (10 CFR) (the Backfit Rule) or otherwise be
inconsistent with the issue finality provisions in part 50 of Title 10
of the Code of Federal Regulations (10 CFR). The NRC's position is
based upon the following considerations.
1. The draft SRP positions, if finalized, would not constitute
backfitting, inasmuch as the SRP is internal guidance to NRC staff.
The SRP provides internal guidance to the NRC staff on how to
review an application for NRC regulatory approval in the form of
licensing. Changes in internal staff guidance are not matters for which
either nuclear power plant applicants or licensees are protected under
either the Backfit Rule or the issue finality provisions of 10 CFR part
52.
2. The NRC staff has no intention to impose the SRP positions on
existing licensees either now or in the future.
The NRC staff does not intend to impose or apply the positions
described in the draft SRP to existing licenses and regulatory
approvals. Hence, the issuance of a final SRP--even if considered
guidance within the purview of the issue finality provisions in 10 CFR
part 52-- would not need to be evaluated as if it were a backfit or as
being inconsistent with issue finality provisions. If, in the future,
the NRC staff seeks to impose a position in the SRP on holders of
already issued licenses in a manner that does not provide issue
finality as described in the applicable issue finality provision, then
the staff must make the showing as set forth in the Backfit Rule or
address the criteria for avoiding issue finality as described in the
applicable issue finality provision.
3. Backfitting and issue finality do not--with limited
exceptions not applicable here--protect current or future applicants.
Applicants and potential applicants are not, with certain
exceptions, protected by either the Backfit Rule or any issue finality
provisions under 10 CFR part 52. Neither the Backfit Rule nor the issue
finality provisions under 10 CFR part 52--with certain
[[Page 42560]]
exclusions--were intended to apply to every NRC action that
substantially changes the expectations of current and future
applicants. The exceptions to the general principle are applicable
whenever an applicant references a 10 CFR part 52 license (e.g., an
early site permit) and/or NRC regulatory approval (e.g., a design
certification rule) with specified issue finality provisions. The NRC
staff does not, at this time, intend to impose the positions
represented in the draft SRP in a manner that is inconsistent with any
issue finality provisions. If, in the future, the staff seeks to impose
a position in the draft SRP in a manner that does not provide issue
finality as described in the applicable issue finality provision, then
the staff must address the criteria for avoiding issue finality as
described in the applicable issue finality provision.
Dated at Rockville, Maryland, this 27th day of June 2013.
For the Nuclear Regulatory Commission.
Joseph Colaccino,
Chief, Policy Branch, Division of Advanced Reactors and Rulemaking,
Office of New Reactors.
[FR Doc. 2013-16985 Filed 7-15-13; 8:45 am]
BILLING CODE 7590-01-P