Carlsbad Municipal Water District; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, Protests, Recommendations, and Terms and Conditions, 36179-36180 [2013-14273]
Download as PDF
Federal Register / Vol. 78, No. 116 / Monday, June 17, 2013 / Notices
Dated: June 11, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–14276 Filed 6–14–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[ Project No. 14501–000]
mstockstill on DSK4VPTVN1PROD with NOTICES
Carlsbad Municipal Water District;
Notice of Application Accepted for
Filing and Soliciting Comments,
Motions To Intervene, Protests,
Recommendations, and Terms and
Conditions
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Conduit
Exemption.
b. Project No.: 14501–000.
c. Date filed: February 21, 2013, and
supplemented on May 13, 2013.
d. Applicant: Carlsbad Municipal
Water District.
e. Name of Project: Pressure Control
Hydroelectric Facility at Maerkle
Reservoir Project.
f. Location: The proposed Pressure
Control Hydroelectric Facility at
Maerkle Reservoir Project would be
located on a water supply pipeline
entering the Maerkle Reservoir in San
Diego County, California. The land on
which all the project structures are
located is owned by the applicant.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791a–825r.
h. Applicant Contact: Mr. William
Plummer, Engineering Manager,
Carlsbad Municipal Water District, 5950
El Camino Real, Carlsbad, CA 92008;
phone (760) 602–2768.
i. FERC Contact: Robert Bell, (202)
502–6062, robert.bell@ferc.gov.
j. Status of Environmental Analysis:
This application is ready for
environmental analysis at this time, and
the Commission is requesting
comments, reply comments,
recommendations, terms and
conditions, and prescriptions.
k. Deadline for filing responsive
documents: Due to the small size of the
proposed project, as well as the resource
agency consultation letters filed with
the application, the 60-day timeframe
specified in 18 CFR 4.34(b) for filing all
comments, motions to intervene,
protests, recommendations, terms and
conditions, and prescriptions is
shortened to 30 days from the issuance
date of this notice. All reply comments
VerDate Mar<15>2010
20:38 Jun 14, 2013
Jkt 229001
filed in response to comments
submitted by any resource agency,
Indian tribe, or person, must be filed
with the Commission within 45 days
from the issuance date of this notice.
Comments, protests, and
interventions may be filed electronically
via the Internet in lieu of paper; see 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site at https://www.ferc.gov/docs-filing/
efiling.asp. The Commission strongly
encourages electronic filings.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person on the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
l. Description of the project: The
proposed Pressure Control
Hydroelectric Facility at Maerkle
Reservoir Project would consist of: (1) A
proposed 30-inch-diameter by 16-inchdiameter reducer; (2) a proposed 80foot-long, 16-inch-diameter intake pipe;
(3) a proposed 18-foot by 18-foot
powerhouse containing one generating
unit with an installed capacity of 135
kilowatts; (4) a proposed 16-inch
diameter, 50-foot discharge pipe,
connecting to existing 42-inch diameter
and 10-inch diameter pipes conveying
the water to the Maerkle Tank and
Maerkle Dam Reservoir; and (5)
appurtenant facilities. The applicant
estimates the project would have an
average annual generation of 0.833
gigawatt-hours.
m. This filing is available for review
and reproduction at the Commission in
the Public Reference Room, Room 2A,
888 First Street NE., Washington, DC
20426. The filing may also be viewed on
the web at https://www.ferc.gov/docsfiling/elibrary.asp using the ‘‘eLibrary’’
link. Enter the docket number, P–14501,
in the docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or email
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for review and reproduction at
the address in item h above.
n. Development Application—Any
qualified applicant desiring to file a
competing application must submit to
the Commission, on or before the
specified deadline date for the
particular application, a competing
development application, or a notice of
intent to file such an application.
Submission of a timely notice of intent
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
36179
allows an interested person to file the
competing development application no
later than 120 days after the specified
deadline date for the particular
application. Applications for
preliminary permits will not be
accepted in response to this notice.
o. Notice of Intent—A notice of intent
must specify the exact name, business,
address, and telephone number of the
prospective applicant, and must include
an unequivocal statement of intent to
submit a competing development
application. A notice of intent must be
served on the applicant named in this
public notice.
p. Protests or Motions to Intervene—
Anyone may submit a protest or a
motion to intervene in accordance with
the requirements of Rules of Practice
and Procedure, 18 CFR 385.210,
385.211, and 385.214. In determining
the appropriate action to take, the
Commission will consider all protests
filed, but only those who file a motion
to intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any protests or
motions to intervene must be received
on or before the specified deadline date
for the particular application.
q. All filings must (1) bear in all
capital letters the title ‘‘PROTEST,’’
‘‘MOTION TO INTERVENE,’’
‘‘COMMENTS,’’ ‘‘REPLY COMMENTS,’’
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or
‘‘PRESCRIPTIONS;’’ (2) set forth in the
heading, the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, recommendations, terms and
conditions or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requirements
of 18 CFR 4.34(b). Agencies may obtain
copies of the application directly from
the applicant. Any of these documents
must be filed by providing the original
and seven copies to: The Secretary,
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426. An additional copy must be sent
to Director, Division of Hydropower
Administration and Compliance, Office
of Energy Projects, Federal Energy
Regulatory Commission, at the above
address. A copy of any protest or motion
to intervene must be served upon each
representative of the applicant specified
in the particular application. A copy of
all other filings in reference to this
application must be accompanied by
proof of service on all persons listed in
E:\FR\FM\17JNN1.SGM
17JNN1
36180
Federal Register / Vol. 78, No. 116 / Monday, June 17, 2013 / Notices
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
r. Waiver of Pre-filing Consultation: In
January 2011, the applicant informed
agencies and affected Indian Tribes of
its request to waive the Commission’s
consultation requirements under 18 CFR
4.38(c). No objections were received.
Therefore, the Commission intends to
accept the consultation that has
occurred on this project during the prefiling period and to waive pre-filing
consultation under section 4.38(c),
which requires, among other things,
conducting studies requested by
resource agencies, and distributing and
consulting on a draft exemption
application.
Dated: June 11, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–14273 Filed 6–14–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
mstockstill on DSK4VPTVN1PROD with NOTICES
Combined Notice of Filings #2
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC13–91–000.
Applicants: Florida Power & Light
Company.
Description: Florida Power & Light
Company submits response to May 15,
2013 letter requesting additional
information on the impact of the
transaction on rates etc.
Filed Date: 5/28/13.
Accession Number: 20130528–5157.
Comments Due: 5 p.m. ET 6/24/13.
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG13–39–000.
Applicants: Osprey Energy Center,
LLC.
Description: Self-Certification of
Exempt Wholesale Generator Status of
Osprey Energy Center, LLC.
Filed Date: 6/10/13.
Accession Number: 20130610–5069.
Comments Due: 5 p.m. ET 7/1/13.
Docket Numbers: EG13–40–000.
Applicants: CCFC Sutter Energy, LLC.
Description: Self-Certification of
Exempt Wholesale Generator Status of
CCFC Sutter Energy, LLC.
Filed Date: 6/10/13.
Accession Number: 20130610–5071.
Comments Due: 5 p.m. ET 7/1/13.
VerDate Mar<15>2010
20:38 Jun 14, 2013
Jkt 229001
Docket Numbers: EG13–41–000.
Applicants: Westbrook Energy Center,
LLC.
Description: Self-Certification of
Exempt Wholesale generator Status of
Westbrook Energy Center, LLC.
Filed Date: 6/10/13.
Accession Number: 20130610–5072.
Comments Due: 5 p.m. ET 7/1/13.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER10–2738–002.
Applicants: The Empire District
Electric Company.
Description: Supplement to June 29,
2012 Triennial Market Power Analysis.
Filed Date: 2/6/13.
Accession Number: 20130206–5043.
Comments Due: 5 p.m. ET 6/24/13.
Docket Numbers: ER13–1649–000.
Applicants: Trademark Merchant
Energy, LLC.
Description: Amendment to MBR
Tariff—Polaris to be effective 8/9/2013.
Filed Date: 6/10/13.
Accession Number: 20130610–5058.
Comments Due: 5 p.m. ET 7/1/13.
Docket Numbers: ER13–1650–000.
Applicants: Tyr Energy LLC.
Description: Amendment to MBR
Tariff—Polaris to be effective 8/9/2013.
Filed Date: 6/10/13.
Accession Number: 20130610–5059.
Comments Due: 5 p.m. ET 7/1/13.
Docket Numbers: ER13–1651–000.
Applicants: PJM Interconnection,
L.L.C.
Description: PJM Interconnection,
L.L.C. submits tariff filing per
35.13(a)(2)(iii: Original Service
Agreement No. 3570; Queue No. NQ81
to be effective 5/9/2013.
Filed Date: 6/10/13.
Accession Number: 20130610–5078.
Comments Due: 5 p.m. ET 7/1/13.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
Dated: June 10, 2013.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2013–14317 Filed 6–14–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC13–107–000.
Applicants: Beech Ridge Energy LLC,
Bishop Hill Energy LLC, Bishop Hill
Energy III LLC, Bishop Hill
Interconnection LLC, California Ridge
Wind Energy LLC, Forward Energy LLC,
Grand Ridge Energy LLC, Grand Ridge
Energy II LLC, Grand Ridge Energy III
LLC, Grand Ridge Energy IV LLC, Grand
Ridge Energy V LLC, Gratiot County
Wind LLC, Gratiot County Wind II LLC,
Invenergy TN LLC, Judith Gap Energy
LLC, Sheldon Energy LLC, Spring
Canyon Energy LLC, Stony Creek Energy
LLC, Vantage Wind Energy LLC, Willow
Creek Energy LLC, Wolverine Creek
Energy LLC, Wolverine Creek Goshen
Interconnection LLC, Prairie Breeze
Wind Energy LLC.
Description: Supplement to May 22,
2013 Section 203 Filing of Beech Ridge
Energy LLC, et al.
Filed Date: 6/10/13.
Accession Number: 20130610–5033.
Comments Due: 5 p.m. ET 6/20/13.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER13–1139–002.
Applicants: Imperial Valley Solar 1,
LLC.
Description: Imperial Valley Solar 1,
LLC submit a revised horizontal market
power analysis that relies on the
analysis of the CASIO market submitted
by Agua Caliente Solar, LLC.
Filed Date: 6/7/13.
Accession Number: 20130607–5145.
Comments Due: 5 p.m. ET 6/21/13.
Docket Numbers: ER13–1394–000.
Applicants: Indiana Michigan Power
Company, American Electric Power
Service Corporation, PJM
Interconnection, L.L.C.
Description: AEP (I&M) submits
supplemental information to clarify
effective date to be effective N/A.
Filed Date: 6/7/13.
Accession Number: 20130607–5055.
Comments Due: 5 p.m. ET 6/28/13.
Docket Numbers: ER13–1647–000.
Applicants: Pacific Gas and Electric
Company.
E:\FR\FM\17JNN1.SGM
17JNN1
Agencies
[Federal Register Volume 78, Number 116 (Monday, June 17, 2013)]
[Notices]
[Pages 36179-36180]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-14273]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[ Project No. 14501-000]
Carlsbad Municipal Water District; Notice of Application Accepted
for Filing and Soliciting Comments, Motions To Intervene, Protests,
Recommendations, and Terms and Conditions
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Conduit Exemption.
b. Project No.: 14501-000.
c. Date filed: February 21, 2013, and supplemented on May 13, 2013.
d. Applicant: Carlsbad Municipal Water District.
e. Name of Project: Pressure Control Hydroelectric Facility at
Maerkle Reservoir Project.
f. Location: The proposed Pressure Control Hydroelectric Facility
at Maerkle Reservoir Project would be located on a water supply
pipeline entering the Maerkle Reservoir in San Diego County,
California. The land on which all the project structures are located is
owned by the applicant.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791a-825r.
h. Applicant Contact: Mr. William Plummer, Engineering Manager,
Carlsbad Municipal Water District, 5950 El Camino Real, Carlsbad, CA
92008; phone (760) 602-2768.
i. FERC Contact: Robert Bell, (202) 502-6062, robert.bell@ferc.gov.
j. Status of Environmental Analysis: This application is ready for
environmental analysis at this time, and the Commission is requesting
comments, reply comments, recommendations, terms and conditions, and
prescriptions.
k. Deadline for filing responsive documents: Due to the small size
of the proposed project, as well as the resource agency consultation
letters filed with the application, the 60-day timeframe specified in
18 CFR 4.34(b) for filing all comments, motions to intervene, protests,
recommendations, terms and conditions, and prescriptions is shortened
to 30 days from the issuance date of this notice. All reply comments
filed in response to comments submitted by any resource agency, Indian
tribe, or person, must be filed with the Commission within 45 days from
the issuance date of this notice.
Comments, protests, and interventions may be filed electronically
via the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and
the instructions on the Commission's Web site at https://www.ferc.gov/docs-filing/efiling.asp. The Commission strongly encourages electronic
filings.
The Commission's Rules of Practice and Procedure require all
intervenors filing documents with the Commission to serve a copy of
that document on each person on the official service list for the
project. Further, if an intervenor files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency.
l. Description of the project: The proposed Pressure Control
Hydroelectric Facility at Maerkle Reservoir Project would consist of:
(1) A proposed 30-inch-diameter by 16-inch-diameter reducer; (2) a
proposed 80-foot-long, 16-inch-diameter intake pipe; (3) a proposed 18-
foot by 18-foot powerhouse containing one generating unit with an
installed capacity of 135 kilowatts; (4) a proposed 16-inch diameter,
50-foot discharge pipe, connecting to existing 42-inch diameter and 10-
inch diameter pipes conveying the water to the Maerkle Tank and Maerkle
Dam Reservoir; and (5) appurtenant facilities. The applicant estimates
the project would have an average annual generation of 0.833 gigawatt-
hours.
m. This filing is available for review and reproduction at the
Commission in the Public Reference Room, Room 2A, 888 First Street NE.,
Washington, DC 20426. The filing may also be viewed on the web at
https://www.ferc.gov/docs-filing/elibrary.asp using the ``eLibrary''
link. Enter the docket number, P-14501, in the docket number field to
access the document. For assistance, call toll-free 1-866-208-3676 or
email FERCOnlineSupport@ferc.gov. For TTY, call (202) 502-8659. A copy
is also available for review and reproduction at the address in item h
above.
n. Development Application--Any qualified applicant desiring to
file a competing application must submit to the Commission, on or
before the specified deadline date for the particular application, a
competing development application, or a notice of intent to file such
an application. Submission of a timely notice of intent allows an
interested person to file the competing development application no
later than 120 days after the specified deadline date for the
particular application. Applications for preliminary permits will not
be accepted in response to this notice.
o. Notice of Intent--A notice of intent must specify the exact
name, business, address, and telephone number of the prospective
applicant, and must include an unequivocal statement of intent to
submit a competing development application. A notice of intent must be
served on the applicant named in this public notice.
p. Protests or Motions to Intervene--Anyone may submit a protest or
a motion to intervene in accordance with the requirements of Rules of
Practice and Procedure, 18 CFR 385.210, 385.211, and 385.214. In
determining the appropriate action to take, the Commission will
consider all protests filed, but only those who file a motion to
intervene in accordance with the Commission's Rules may become a party
to the proceeding. Any protests or motions to intervene must be
received on or before the specified deadline date for the particular
application.
q. All filings must (1) bear in all capital letters the title
``PROTEST,'' ``MOTION TO INTERVENE,'' ``COMMENTS,'' ``REPLY COMMENTS,''
``RECOMMENDATIONS,'' ``TERMS AND CONDITIONS,'' or ``PRESCRIPTIONS;''
(2) set forth in the heading, the name of the applicant and the project
number of the application to which the filing responds; (3) furnish the
name, address, and telephone number of the person protesting or
intervening; and (4) otherwise comply with the requirements of 18 CFR
385.2001 through 385.2005. All comments, recommendations, terms and
conditions or prescriptions must set forth their evidentiary basis and
otherwise comply with the requirements of 18 CFR 4.34(b). Agencies may
obtain copies of the application directly from the applicant. Any of
these documents must be filed by providing the original and seven
copies to: The Secretary, Federal Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426. An additional copy must be sent
to Director, Division of Hydropower Administration and Compliance,
Office of Energy Projects, Federal Energy Regulatory Commission, at the
above address. A copy of any protest or motion to intervene must be
served upon each representative of the applicant specified in the
particular application. A copy of all other filings in reference to
this application must be accompanied by proof of service on all persons
listed in
[[Page 36180]]
the service list prepared by the Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and 385.2010.
r. Waiver of Pre-filing Consultation: In January 2011, the
applicant informed agencies and affected Indian Tribes of its request
to waive the Commission's consultation requirements under 18 CFR
4.38(c). No objections were received. Therefore, the Commission intends
to accept the consultation that has occurred on this project during the
pre-filing period and to waive pre-filing consultation under section
4.38(c), which requires, among other things, conducting studies
requested by resource agencies, and distributing and consulting on a
draft exemption application.
Dated: June 11, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-14273 Filed 6-14-13; 8:45 am]