Alabama Power Company; Notice of Application Accepted for Filing, Soliciting Comments, Motions to Intervene, And Protests, 35015-35016 [2013-13812]
Download as PDF
Federal Register / Vol. 78, No. 112 / Tuesday, June 11, 2013 / Notices
Order No.
Date issued
FE Docket No.
Authorization holder
Description of action
Nexen Energy Marketing
Services U.S.A. Inc.
APS-American Power Supply,
LLC.
Order granting blanket authority to import/export natural
gas from/to Canada/Mexico.
Order granting blanket authority to import natural gas from
Canada and to import LNG from various international
sources by vessel.
Order granting blanket authority to import/export natural
gas from/to Canada.
Order granting blanket authority to import LNG from Canada by truck.
Order granting blanket authority to import/export natural
gas from/to Canada.
Order granting blanket authority to import natural gas from
Canada.
Order granting blanket authority to import/export natural
gas from/to Canada/Mexico.
Order granting blanket authority to import LNG from various
international sources by vessel.
Order granting blanket authority to import/export natural
gas from/to Canada.
3265 .............
04/12/13
13–35–NG
3266 .............
04/12/13
13–38–LNG
3267 .............
04/12/13
13–39–NG
3268 .............
04/12/13
13–40–LNG
3269 .............
04/12/13
13–41–NG
3270 .............
04/12/13
13–43–NG
3271 .............
04/12/13
13–44–NG
Cascade Natural Gas Corporation.
Encana Marketing (USA) Inc.
3272 .............
04/12/13
13–45–LNG
Citigroup Energy Inc. .............
3273 .............
04/12/13
11–46–NG
Centra Gas Manitoba Inc. .....
[FR Doc. 2013–13789 Filed 6–10–13; 8:45 am]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2146–140]
wreier-aviles on DSK5TPTVN1PROD with NOTICES
Alabama Power Company; Notice of
Application Accepted for Filing,
Soliciting Comments, Motions to
Intervene, And Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Non-project use
of project lands and waters.
b. Project No: 2146–140.
c. Date Filed: April 16, 2013.
d. Applicant: Alabama Power
Company.
e. Name of Project: Coosa River
Hydroelectric Project.
f. Location: Coosa River near the city
of Gadsden, in Etowah County, in
northeastern Alabama.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C .791a–825r.
h. Applicant Contact: Ms. Amy J.
Stewart, PE, Team Leader, Alabama
Power Company, 600 18th Street North,
Birmingham, AL 35203–8180, (205)
257–1000.
i. FERC Contact: Mary Karwoski,
(202) 502–6543, or email:
mary.karwoski@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests: July
8, 2013.
All documents may be filed
electronically via the Internet. See, 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site at https://www.ferc.gov/docs-filing/
VerDate Mar<15>2010
15:13 Jun 10, 2013
Jkt 229001
CP Energy Marketing (US)
Inc.
Gaz Metro Solutions Transport.
Mieco Inc. ..............................
efiling.asp. If unable to be filed
electronically, documents may be paperfiled. To paper-file, an original and
seven copies should be mailed to:
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE.,
Washington, DC 20426. Commenters
can submit brief comments up to 6,000
characters, without prior registration,
using the eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. Please include the
project number (P–2146–140) on any
comments or motions filed.
k. Description of Application:
Alabama Power Company requests
Commission approval to grant River
Country Campground a permit to use
project lands and waters to construct
two forty-foot fishing piers with no
cleats and a pier with twelve boat slips
accommodating up to fifty watercraft.
The proposed boat slips are each 22 feet
wide by 24 feet long and can
accommodate up to four personal
watercraft (including but not limited to
jet-skis), plus two watercraft on the end.
River Country Campground operates an
existing RV Campground on the NeelyHenry Development in Gadsden,
Alabama. The facility currently includes
a single lane boat ramp, a courtesy dock
accommodating up to six watercraft,
three wooden docks with no cleats, riprap along the shoreline, and two water
intake structures for irrigation.
l. Locations of the Application: A
copy of the application is available for
inspection and reproduction at the
Commission’s Public Reference Room,
located at 888 First Street, NE., Room
2A, Washington, DC 20426, or by calling
(202) 502–8371. This filing may also be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
PO 00000
35015
Frm 00042
Fmt 4703
Sfmt 4703
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field (P–2146) to
access the document. You may also
register online at https://www.ferc.gov/
docs-filing/esubscription.asp to be
notified via email of new filings and
issuances related to this or other
pending projects. For assistance, call 1–
866–208–3676 or email
FERCOnlineSupport@ferc.gov, for TTY,
call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item (h)
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214,
respectively. In determining the
appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
for the particular application.
o. Filing and Service of Documents:
Any filing must (1) bear in all capital
letters the title ‘‘COMMENTS’’,
‘‘PROTEST’’, or ‘‘MOTION TO
INTERVENE’’ as applicable; (2) set forth
in the heading the name of the applicant
and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
commenting, protesting or intervening;
E:\FR\FM\11JNN1.SGM
11JNN1
35016
Federal Register / Vol. 78, No. 112 / Tuesday, June 11, 2013 / Notices
and (4) otherwise comply with the
requirements of 18 CFR 385.2001
through 385.2005. All comments,
motions to intervene, or protests must
set forth their evidentiary basis. Any
filing made by an intervener must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
385.2010.
Dated: June 4, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–13812 Filed 6–10–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14490–000]
wreier-aviles on DSK5TPTVN1PROD with NOTICES
FFP Project 118, LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions to Intervene, and
Competing Applications
On February 1, 2013, FFP Project 118,
LLC filed an application for a
preliminary permit, pursuant to section
4(f) of the Federal Power Act (FPA),
proposing to study the feasibility of a
hydropower project located at the U.S.
Army Corps of Engineers’ (Corps) Green
River Lock & Dam #1, located on the
Green River near the town of Henderson
in Henderson County, Kentucky. The
sole purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land-disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
The proposed project would consist of
the following: (1) A 650-foot-long, 320foot-wide intake channel with a 150foot-long retaining wall; (2) a 400-footlong crest dam extension connecting the
existing dam to the new powerhouse; (3)
a 160-foot-long, 120-foot-wide
powerhouse containing two generating
units with a total capacity of 5.6
megawatts; (4) a 220-foot-long, 160-footwide tailrace with a 75-foot-long
retaining wall; (5) a 4.16/69 kilo-volt
(kV) substation; (6) a 310-foot-long
access road to the powerhouse and
substation; (7) a 2.0-mile-long, 69kV
transmission line. The proposed project
would have an average annual
generation of 27,000 megawatt-hours,
and operate as directed by the Corps.
VerDate Mar<15>2010
15:13 Jun 10, 2013
Jkt 229001
Applicant Contact: Ms. Ramya
Swaminathan, Free Flow Power
Corporation, 239 Causeway Street, Suite
300, Boston, MA 02114. (978) 283–2822.
FERC Contact: Christiane Casey,
christiane.casey@ferc.gov, (202) 502–
8577.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36. Comments, motions to
intervene, notices of intent, and
competing applications may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and five copies to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–14490) in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
Dated: June 5, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–13807 Filed 6–10–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER12–2159–003.
Applicants: Canadian Hills Wind,
LLC.
PO 00000
Frm 00043
Fmt 4703
Sfmt 4703
Description: Notice of Non-Material
Change in Status of Canadian Hills
Wind, LLC.
Filed Date: 6/3/13.
Accession Number: 20130603–5167.
Comments Due: 5 p.m. ET 6/24/13.
Docket Numbers: ER13–535–003.
Applicants: PJM Interconnection,
L.L.C.
Description: Compliance Filing to 5/2/
2013 MOPR Order in ER13–535–000,
001 to be effective 2/5/2013.
Filed Date: 6/3/13.
Accession Number: 20130603–5162.
Comments Due: 5 p.m. ET 6/24/13.
Docket Numbers: ER13–692–004.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: 06–03–2013 OASIS
Compliance Filing to be effective 6/4/
2013.
Filed Date: 6/4/13.
Accession Number: 20130604–5000.
Comments Due: 5 p.m. ET 6/25/13.
Docket Numbers: ER13–983–000.
Applicants: Arizona Public Service
Company.
Description: Refund Report for MPP
Westwing Substation Interconnection
Construction Agreement to be effective
N/A.
Filed Date: 6/3/13.
Accession Number: 20130603–5147.
Comments Due: 5 p.m. ET 6/24/13.
Docket Numbers: ER13–1346–000.
Applicants: Mesa Wind Power
Corporation.
Description: Supplement to April 26,
2013 Mesa Wind Power Corporation
tariff filing.
Filed Date: 6/3/13.
Accession Number: 20130603–5120.
Comments Due: 5 p.m. ET 6/24/13.
Docket Numbers: ER13–1630–000.
Applicants: California Independent
System Operator Corporation, AES
Huntington Beach, L.L.C.
Description: Amendments to RMR
Agreement to be effective 6/26/2013.
Filed Date: 6/3/13.
Accession Number: 20130603–5161.
Comments Due: 5 p.m. ET 6/24/13.
Docket Numbers: ER13–1631–000.
Applicants: Midcontinent
Independent System Operator, Inc.
Description: Request for Waiver of
certain tariff provisions of Midcontinent
Independent System Operator, Inc.
Filed Date: 6/4/13.
Accession Number: 20130604–5039.
Comments Due: 5 p.m. ET 6/25/13.
Docket Numbers: ER13–1632–000.
Applicants: Chandler Wind Partners,
LLC.
Description: Chandler Wind Partners,
LLC submits First Revised MBR to be
effective 6/5/2013.
E:\FR\FM\11JNN1.SGM
11JNN1
Agencies
[Federal Register Volume 78, Number 112 (Tuesday, June 11, 2013)]
[Notices]
[Pages 35015-35016]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-13812]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2146-140]
Alabama Power Company; Notice of Application Accepted for Filing,
Soliciting Comments, Motions to Intervene, And Protests
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Application Type: Non-project use of project lands and waters.
b. Project No: 2146-140.
c. Date Filed: April 16, 2013.
d. Applicant: Alabama Power Company.
e. Name of Project: Coosa River Hydroelectric Project.
f. Location: Coosa River near the city of Gadsden, in Etowah
County, in northeastern Alabama.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C .791a-825r.
h. Applicant Contact: Ms. Amy J. Stewart, PE, Team Leader, Alabama
Power Company, 600 18th Street North, Birmingham, AL 35203-8180, (205)
257-1000.
i. FERC Contact: Mary Karwoski, (202) 502-6543, or email:
mary.karwoski@ferc.gov.
j. Deadline for filing comments, motions to intervene, and
protests: July 8, 2013.
All documents may be filed electronically via the Internet. See, 18
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web
site at https://www.ferc.gov/docs-filing/efiling.asp. If unable to be
filed electronically, documents may be paper-filed. To paper-file, an
original and seven copies should be mailed to: Secretary, Federal
Energy Regulatory Commission, 888 First Street NE., Washington, DC
20426. Commenters can submit brief comments up to 6,000 characters,
without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and
contact information at the end of your comments. Please include the
project number (P-2146-140) on any comments or motions filed.
k. Description of Application: Alabama Power Company requests
Commission approval to grant River Country Campground a permit to use
project lands and waters to construct two forty-foot fishing piers with
no cleats and a pier with twelve boat slips accommodating up to fifty
watercraft. The proposed boat slips are each 22 feet wide by 24 feet
long and can accommodate up to four personal watercraft (including but
not limited to jet-skis), plus two watercraft on the end. River Country
Campground operates an existing RV Campground on the Neely-Henry
Development in Gadsden, Alabama. The facility currently includes a
single lane boat ramp, a courtesy dock accommodating up to six
watercraft, three wooden docks with no cleats, rip-rap along the
shoreline, and two water intake structures for irrigation.
l. Locations of the Application: A copy of the application is
available for inspection and reproduction at the Commission's Public
Reference Room, located at 888 First Street, NE., Room 2A, Washington,
DC 20426, or by calling (202) 502-8371. This filing may also be viewed
on the Commission's Web site at https://www.ferc.gov using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field (P-2146) to access the document. You
may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, call 1-866-
208-3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502-
8659. A copy is also available for inspection and reproduction at the
address in item (h) above.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Comments, Protests, or Motions to Intervene: Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214, respectively. In determining the appropriate action to take, the
Commission will consider all protests or other comments filed, but only
those who file a motion to intervene in accordance with the
Commission's Rules may become a party to the proceeding. Any comments,
protests, or motions to intervene must be received on or before the
specified comment date for the particular application.
o. Filing and Service of Documents: Any filing must (1) bear in all
capital letters the title ``COMMENTS'', ``PROTEST'', or ``MOTION TO
INTERVENE'' as applicable; (2) set forth in the heading the name of the
applicant and the project number of the application to which the filing
responds; (3) furnish the name, address, and telephone number of the
person commenting, protesting or intervening;
[[Page 35016]]
and (4) otherwise comply with the requirements of 18 CFR 385.2001
through 385.2005. All comments, motions to intervene, or protests must
set forth their evidentiary basis. Any filing made by an intervener
must be accompanied by proof of service on all persons listed in the
service list prepared by the Commission in this proceeding, in
accordance with 18 CFR 385.2010.
Dated: June 4, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-13812 Filed 6-10-13; 8:45 am]
BILLING CODE 6717-01-P