Lakeport Hydroelectric Associates, Lakeport Hydroelectric Corporation, Lakeport Hydroelectric One, LLC; Notice of Application for Transfer of License, and Soliciting Comments and Motions To Intervene, 28826 [2013-11658]

Download as PDF 28826 Federal Register / Vol. 78, No. 95 / Thursday, May 16, 2013 / Notices Dated: May 9, 2013. Kimberly D. Bose, Secretary. document. For assistance, call toll-free 1–866–208–3372. Dated: May 10, 2013. Kimberly D. Bose, Secretary. [FR Doc. 2013–11663 Filed 5–15–13; 8:45 am] BILLING CODE 6717–01–P [FR Doc. 2013–11658 Filed 5–15–13; 8:45 am] DEPARTMENT OF ENERGY BILLING CODE 6717–01–P Federal Energy Regulatory Commission DEPARTMENT OF ENERGY [ Project No. 6440–008] tkelley on DSK3SPTVN1PROD with NOTICES Lakeport Hydroelectric Associates, Lakeport Hydroelectric Corporation, Lakeport Hydroelectric One, LLC; Notice of Application for Transfer of License, and Soliciting Comments and Motions To Intervene On April 4, 2013, Lakeport Hydroelectric Associates and Lakeport Hydroelectric Corporation (transferors) and Lakeport Hydroelectric One, LLC (transferee) filed an application for the transfer of license for the Lakeport Project, FERC No. 6440, located on the Winnipesaukee River in Belknap County, New Hampshire. Applicants seek Commission approval to transfer the license for the Lakeport Project from the transferors to the transferee. Applicants’ Contact: Shannon P. Coleman, Director, Legal Regulatory Strategy, Algonquin-Liberty Business Services, 2865 Bristol Circle, Oakville, ON, Canada L6H 6X5, telephone (905) 465–4462. FERC Contact: Patricia W. Gillis (202) 502–8735, patricia.gillis@ferc.gov. Deadline for filing comments and motions to intervene: 30 days from the issuance date of this notice by the Commission. Comments and motions to intervene may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1) and the instructions on the Commission’s Web site under https:// www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original plus seven copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. More information about this project can be viewed or printed on the eLibrary link of Commission’s Web site at https:// www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number (P–6440) in the docket number field to access the VerDate Mar<15>2010 18:13 May 15, 2013 Jkt 229001 Federal Energy Regulatory Commission [Project 2629–014] Village of Morrisville, Vermont; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: New Major License. b. Project No.: 2629–014. c. Date Filed: April 25, 2013. d. Applicant: Village of Morrisville, Vermont (Morrisville). e. Name of Project: Morrisville Hydroelectric Project. f. Location: On the Green River, Elmore Pond Brook, and Lamoille River, in Lamoille County, Vermont. The project does not occupy any federal lands. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)–825(r). h. Applicant Contact: Craig Myotte, Village of Morrisville, Water & Light Department, P.O. Box 460—857 Elmore Street, Morrisville, Vermont, 05661– 0460; (802) 888–6521 or cmyotte@mwlvt.com. i. FERC Contact: Steve Kartalia, (202) 502–6131 or stephen.kartalia@ferc.gov. j. This application is not ready for environmental analysis at this time. k. The Project Description: The existing Morrisville Hydroelectric Project consists of four developments with a total installed capacity of 4,990 kilowatts (kW). The project’s average annual generation is 9,032,221 kilowatthours. The power generated by the Morrisville Project is used by Morrisville to meet the power needs of its regional retail customers within the Village of Morrisville and surrounding communities. Green River Development The existing Green River Development is located on the Green River and consists of: (1) A 360-foot- PO 00000 Frm 00031 Fmt 4703 Sfmt 4703 long, 105-foot-high concrete arch dam that includes, near its center, a 60-footlong ungated spillway with a crest elevation of 1,220 feet above mean sea level (msl); (2) a 45-foot-long, 15-foothigh concrete gravity weir that creates a 180-foot-long, 11-foot-deep stilling pool downstream of the concrete arch dam; (3) a 200-foot-long, 16-foot-high earthen embankment with 2-foot-high wooden wave barriers approximately 1.25 miles southeast of the concrete arch dam; (4) a 690-acre impoundment with a storage capacity of 17,400-acre-feet and a normal maximum elevation of 1,220 feet msl; (5) a 16-foot-long, 12-foot-high gated intake structure; (6) a 22-foot-long, 16-foot-wide intake-valve house and a 14-foot-long, 13-foot-wide outlet-valve house; (7) a 116-foot-long penstock, that includes a 6-foot-diameter, 94.5-footlong buried, steel section that bifurcates into two 3-foot-diameter, 21.5-foot-long steel sections; (8) a 32-foot-long, 37-footwide concrete powerhouse containing two 945-kW turbine-generator units for a total installed capacity of 1,890 kW; (9) a 14.5-foot-long, concrete tailrace; (10) a 5-mile-long, 34.5-kilovolt (kV) transmission line connecting the powerhouse to the regional grid; and (11) appurtenant facilities. The Green River Development bypasses approximately 180 feet of the Green River, including the stilling pool. Lake Elmore Development The existing Lake Elmore Development is located on Elmore Pond Brook and consists of: (1) A 26-footlong, 10-foot-high concrete gravity dam and spillway with a crest elevation of 1,139 feet msl; (2) a 300-acre impoundment (Lake Elmore) with a 1,000-acre-foot storage capacity and a normal maximum water surface elevation of 1,139 feet msl; (3) a 8.5foot-long, 7.5-foot-wide gatehouse; (4) a 8.3-foot-long, 3.5-foot-high gated intake structure; (5) a 2.5-foot-long concretelined tailrace; and (6) appurtenant facilities. Morrisville Development The existing Morrisville Development is located on the Lamoille River and consists of: (1) A 384-foot-long, 37-foothigh concrete gravity dam comprised of a 138-foot-long concrete retaining wall, a 30-foot-long intake and gatehouse section, and a 216-foot-long spillway with two 108-foot-long, 4-foot-high Obermeyer inflatable crest gates and a crest elevation of 627.79 feet msl; (2) a 141-foot-long, 8-foot-high concrete wall approximately 260 feet northwest of the dam that includes a 60-foot-long overflow section (back spillway) with 2foot-high wooden flashboards ; (3) a 15- E:\FR\FM\16MYN1.SGM 16MYN1

Agencies

[Federal Register Volume 78, Number 95 (Thursday, May 16, 2013)]
[Notices]
[Page 28826]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-11658]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[ Project No. 6440-008]


Lakeport Hydroelectric Associates, Lakeport Hydroelectric 
Corporation, Lakeport Hydroelectric One, LLC; Notice of Application for 
Transfer of License, and Soliciting Comments and Motions To Intervene

    On April 4, 2013, Lakeport Hydroelectric Associates and Lakeport 
Hydroelectric Corporation (transferors) and Lakeport Hydroelectric One, 
LLC (transferee) filed an application for the transfer of license for 
the Lakeport Project, FERC No. 6440, located on the Winnipesaukee River 
in Belknap County, New Hampshire.
    Applicants seek Commission approval to transfer the license for the 
Lakeport Project from the transferors to the transferee.
    Applicants' Contact: Shannon P. Coleman, Director, Legal Regulatory 
Strategy, Algonquin-Liberty Business Services, 2865 Bristol Circle, 
Oakville, ON, Canada L6H 6X5, telephone (905) 465-4462.
    FERC Contact: Patricia W. Gillis (202) 502-8735, 
patricia.gillis@ferc.gov.
    Deadline for filing comments and motions to intervene: 30 days from 
the issuance date of this notice by the Commission. Comments and 
motions to intervene may be filed electronically via the Internet. See 
18 CFR 385.2001(a)(1) and the instructions on the Commission's Web site 
under https://www.ferc.gov/docs-filing/efiling.asp. Commenters can 
submit brief comments up to 6,000 characters, without prior 
registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information 
at the end of your comments. If unable to be filed electronically, 
documents may be paper-filed. To paper-file, an original plus seven 
copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426. More 
information about this project can be viewed or printed on the eLibrary 
link of Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number (P-6440) in the docket number 
field to access the document. For assistance, call toll-free 1-866-208-
3372.

    Dated: May 10, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-11658 Filed 5-15-13; 8:45 am]
BILLING CODE 6717-01-P