Notice of Availability; Draft Environmental Impact Statement for the FutureGen 2.0 Project, 26004-26005 [2013-10662]
Download as PDF
26004
Federal Register / Vol. 78, No. 86 / Friday, May 3, 2013 / Notices
consistent with its approved application
and budget. In making a continuation
grant, the Secretary also considers
whether the grantee is operating in
compliance with the assurances in its
approved application, including those
applicable to Federal civil rights laws
that prohibit discrimination in programs
or activities receiving Federal financial
assistance from the Department (34 CFR
100.4, 104.5, 106.4, 108.8, and 110.23).
VII. Agency Contact
FOR FURTHER INFORMATION CONTACT:
Carol Lyons, U.S. Department of
Education, 400 Maryland Avenue SW.,
Room 4W203, Washington, DC 20202–
5930. Telephone: (202) 453–7122. FAX:
(202) 205–5631 or by email: i3@ed.gov.
If you use a TDD or a TTY, call the
FRS, toll free, at 1–800–877–8339.
VIII. Other Information
Accessible Format: Individuals with
disabilities can obtain this document
and a copy of the application package in
an accessible format (e.g., braille, large
print, audiotape, or compact disc) on
request to the program contact person
listed under FOR FURTHER INFORMATION
CONTACT in section VII of this notice.
Electronic Access to This Document:
The official version of this document is
the document published in the Federal
Register. Free Internet access to the
official edition of the Federal Register
and the Code of Federal Regulations is
available via the Federal Digital System
at: www.gpo.gov/fdsys. At this site you
can view this document, as well as all
other documents of this Department
published in the Federal Register, in
text or Adobe Portable Document
Format (PDF). To use PDF you must
have Adobe Acrobat Reader, which is
available free at the site.
You may also access documents of the
Department published in the Federal
Register by using the article search
feature at: www.federalregister.gov.
Specifically, through the advanced
search feature at this site, you can limit
your search to documents published by
the Department.
Dated: April 30, 2013.
James H. Shelton, III,
Assistant Deputy Secretary for Innovation and
Improvement.
[FR Doc. 2013–10466 Filed 5–2–13; 8:45 am]
erowe on DSK2VPTVN1PROD with NOTICES
BILLING CODE 4000–01–P
DEPARTMENT OF ENERGY
Notice of Availability; Draft
Environmental Impact Statement for
the FutureGen 2.0 Project
AGENCY:
U. S. Department of Energy.
VerDate Mar<15>2010
14:52 May 02, 2013
Jkt 229001
Notice of availability and public
hearing.
ACTION:
SUMMARY: The U.S. Department of
Energy (DOE) announces the availability
of the Draft Environmental Impact
Statement for the FutureGen 2.0 Project
(DOE/EIS–0460D) for public review and
comment, as well as the date, location,
and time for a public hearing. The draft
environmental impact statement (EIS)
analyzes the potential impacts
associated with the FutureGen 2.0
Project (FutureGen 2.0), which would be
designed, constructed, operated, and
partially funded by the FutureGen
Industrial Alliance, Inc. (Alliance). In
addition to Alliance funding, FutureGen
2.0 may receive approximately $1
billion in federal financial assistance
under the American Recovery and
Reinvestment Act (ARRA).
DOE prepared this draft EIS in
accordance with the National
Environmental Policy Act of 1969
(NEPA) (42 U.S.C. 4321 et seq.), the
Council on Environmental Quality
regulations that implement the
procedural provisions of NEPA (40 CFR
parts 1500–1508), DOE’s procedures
implementing NEPA (10 CFR part 1021),
and DOE’s procedures for compliance
with floodplain and wetland review
requirements (10 CFR part 1022).
DATES: DOE invites the public to
comment on the draft EIS during the
public comment period, which ends
June 17, 2013. DOE will consider all
comments postmarked or received
during the public comment period when
preparing the final EIS and will
consider late comments to the extent
practicable.
DOE will hold a public hearing on
May 21, 2013, at Jacksonville High
School, 1211 N. Diamond Street,
Jacksonville, Illinois. An informational
session will be held from 5:00 p.m. to
6:00 p.m., preceding the formal
presentations and comment period from
6:00 p.m. to approximately 8:00 p.m.
See the PUBLIC HEARING section for
details on the hearing process.
ADDRESSES: Requests for information
about this draft EIS or for a paper copy
should be directed to: Mr. Cliff Whyte,
M/S: I07, National Energy Technology
Laboratory, 3610 Collins Ferry Road,
P.O. Box 880, Morgantown, WV 26507–
0880.
Additional information about the
draft EIS may also be requested by
electronic mail at
cliff.whyte@netl.doe.gov, by telephone
at (304) 285–2098, or by toll-free
telephone at 1–800–432–8330,
extension 2098. The draft EIS will be
available at https://energy.gov/nepa.
Copies of the draft EIS are also available
PO 00000
Frm 00066
Fmt 4703
Sfmt 4703
for review at the locations listed in the
AVAILABILITY OF THE DRAFT EIS
section of this notice.
Written comments on the draft EIS
can be mailed or sent electronically to
Mr. Whyte at the addresses noted above.
Written comments may also be
submitted by fax to (304) 285–4403.
Oral comments on the draft EIS will be
accepted during the public hearing
scheduled for the date and location
provided in the DATES section of this
notice.
FOR FURTHER INFORMATION CONTACT: For
further information on the proposed
project or the draft EIS, please contact:
Mr. Cliff Whyte (see ADDRESSES). For
general information regarding DOE’s
NEPA process, please contact: Ms. Carol
M. Borgstrom, Director, Office of NEPA
Policy and Compliance (GC–54), U.S.
Department of Energy, 1000
Independence Avenue SW.,
Washington, DC 20585; Telephone:
(202) 586–4600; Fax: (202) 586–7031.
You may also call Ms. Borgstrom at
(800) 472–2756.
SUPPLEMENTARY INFORMATION: DOE
proposes to provide financial assistance
(approximately $1 billion), through two
cooperative agreements, to the Alliance
for its proposed FutureGen 2.0 Project.
FutureGen 2.0 is a public-private
partnership formed for the purpose of
developing and sharing the cost of the
world’s first commercial-scale oxycombustion electricity generation plant
integrated with carbon dioxide (CO2)
capture and storage. Babcock & Wilcox
Power Generation Group, Inc. and Air
Liquide Process and Construction, Inc.,
among others, would participate in the
project by supplying technology, major
components, and construction services.
The project would use oxycombustion technology to generate
electric power and would capture CO2
for permanent storage underground. The
plant would generate 168 megawatts
(MW) (gross) of electricity. The Alliance
would design and construct the plant to
capture at least 90 percent of the CO2
generated (up to 98 percent could be
captured). Captured CO2 would be
transported through a 30-mile pipeline
to a facility where it would be injected
into the Mount Simon formation for
permanent storage. This saline rock
formation is approximately 4,000–4,500
feet below ground. The project would be
designed to capture, transport, and
inject approximately 1.1 million metric
tons of CO2 annually, or a total of
approximately 33 million metric tons
over 30 years of operation. The Alliance
would also construct and operate a
visitor and research center and training
facilities related to carbon capture and
E:\FR\FM\03MYN1.SGM
03MYN1
erowe on DSK2VPTVN1PROD with NOTICES
Federal Register / Vol. 78, No. 86 / Friday, May 3, 2013 / Notices
storage in the vicinity of Jacksonville,
Illinois. The DOE-funded demonstration
period would last for 56 months, from
the start of operations (July 2017)
through February 2022, but the plant is
expected to continue commercial
operations after this date.
The oxy-combustion plant would be
built on a 263-acre existing power plant
site in Morgan County, Illinois,
approximately one mile south of the
Village of Meredosia. Ameren Energy
Resources (Ameren) has agreed to sell to
the Alliance the assets at the Meredosia
Energy Center that are necessary for the
FutureGen 2.0 Project. These assets
include Unit 4, which was constructed
in 1975. The Unit 4 steam turbine,
material and fuel handling facilities,
process water sources, cooling systems,
high-voltage interconnection lines, and
certain other facilities would be used for
the new plant. Ameren would continue
to own the three other electricity
generation units at the Meredosia
Energy Center. Operation of these units
has been suspended since 2011.
The CO2 storage site would be located
30 miles east of the plant site, on the
eastern side of Morgan County. A new
12-inch diameter pipeline would be
sited and constructed using an 80-foot
construction right-of-way and a 50-foot
permanent right-of-way. The Alliance
has identified two possible routes for
the pipeline and has proposed to use the
route that would minimize impacts to
landowners and the environment. The
Alliance has not identified a final
location for the proposed injection
wells, but has identified an
approximately 5,300-acre site in which
the wells would be located and under
which the CO2 would be permanently
stored. Up to 25 acres of land would be
used for the injection facilities,
associated infrastructure and buildings,
and access roads.
The draft EIS evaluates the potential
impacts of the proposed project,
connected actions, and reasonable
alternatives. Because the proposed
project may affect wetlands, the draft
EIS includes an assessment of impacts
to wetlands in accordance with DOE’s
regulations under Compliance with
Floodplains and Wetlands
Environmental Review Requirements
(10 CFR part 1022).
DOE analyzed two alternatives in the
draft EIS: the proposed action and the
no action alternative. Under the
proposed action, DOE would provide
approximately $1 billion in cost-shared
ARRA funding to the proposed project.
Under the no action alternative, DOE
would not provide continued funding.
Without DOE funding, it is unlikely that
the Alliance, or the industry in general,
VerDate Mar<15>2010
14:52 May 02, 2013
Jkt 229001
would undertake the utility-scale
integration of CO2 capture and geologic
storage with a coal-fueled power plant
using oxy-combustion. Therefore, the no
action alternative also represents a ‘‘nobuild’’ alternative. Without DOE’s
investment in a utility-scale facility, the
development of oxy-combustion
repowered plants integrated with CO2
capture and geologic storage would
occur more slowly or not at all.
The draft EIS considers the
environmental consequences that may
result from the proposed project and
describes additional mitigation that
might be used to reduce various
impacts.
Availability of the Draft EIS: Copies of
the draft EIS have been distributed to
members of Congress; Native American
tribal governments; federal, state, and
local officials; and agencies,
organizations, and individuals who may
be interested or affected. The draft EIS
will be available on the Internet at:
https://energy.gov/nepa/nepadocuments. Copies of the draft EIS are
available for public review at the
following locations: M–C River Public
Library District, 304 Main Street,
Meredosia, Illinois; Jacksonville Public
Library, 201 West College Avenue,
Jacksonville, Illinois; Taylorville Public
Library, 121 West Vine Street,
Taylorville, Illinois; Arcola Public
Library, 407 East Main Street, Arcola,
Illinois; and Tuscola Public Library, 112
Sale Street, Tuscola, Illinois. Additional
copies also can be requested (see
ADDRESSES).
Public Hearing: DOE will conduct a
public hearing on May 21, 2013 at the
Jacksonville High School, Jacksonville,
Illinois to obtain comments on the draft
EIS. Requests to speak at the public
hearing can be made by calling or
writing to Mr. Whyte (see ADDRESSES).
Requests to speak not submitted prior to
the hearing will be accepted in the order
in which they are received during the
hearing. Speakers are encouraged to
provide a written version of their oral
comments or supplementary materials
for the record. Each speaker will be
allowed approximately five minutes to
present comments. Those speakers who
want more than five minutes should
indicate the length of time desired in
their request. Depending on the number
of speakers, DOE may need to limit all
speakers to five minutes initially and
provide additional opportunities as time
permits. Comments will be recorded by
a court reporter and will become part of
the public record. Oral and written
comments will be given equal
consideration.
The public hearing will begin at 5:00
p.m. with an informational session.
PO 00000
Frm 00067
Fmt 4703
Sfmt 4703
26005
Formal presentations and a formal
comment session will begin at
approximately 6:00 p.m. DOE will begin
the hearing’s formal session with
overviews of its clean coal program,
proposed FutureGen 2.0 Project, and the
NEPA process, followed by oral
statements by pre-registered speakers.
Speakers may be asked questions to
help ensure that DOE fully understands
their comments. A presiding officer will
establish the order of speakers and
provide any additional procedures
necessary to conduct the hearing.
The public hearing will be accessible
to people with disabilities. In addition,
any individual needing specific
assistance, such as a sign language
interpreter or a translator, should
contact Mr. Whyte (See ADDRESSES) at
least 48 hours in advance of the hearing
so that arrangements can be made.
Dated: May 1, 2013.
Mark J. Matarrese,
Director, Office of Environment, Security,
Safety and Health, Office of Fossil Energy.
[FR Doc. 2013–10662 Filed 5–1–13; 4:15 pm]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
Environmental Management SiteSpecific Advisory Board, Savannah
River Site
AGENCY:
ACTION:
Department of Energy.
Notice of Open Meeting.
SUMMARY: This notice announces a
meeting of the Environmental
Management Site-Specific Advisory
Board (EM SSAB), Savannah River Site.
The Federal Advisory Committee Act
(Pub. L. 92–463, 86 Stat. 770) requires
that public notice of this meeting be
announced in the Federal Register.
Monday, May 20, 2013, 1:00
p.m.–5:15 p.m.; Tuesday, May 21, 2013,
8:30 a.m.–5:00 p.m.
DATES:
North Augusta Community
Center, 495 Brookside Avenue, North
Augusta, SC 29841.
ADDRESSES:
FOR FURTHER INFORMATION CONTACT:
Gerri Flemming, Office of External
Affairs, Department of Energy,
Savannah River Operations Office, P.O.
Box A, Aiken, SC, 29802; Phone: (803)
952–7886.
SUPPLEMENTARY INFORMATION:
Purpose of the Board: The purpose of
the Board is to make recommendations
to DOE–EM and site management in the
areas of environmental restoration,
waste management, and related
activities.
E:\FR\FM\03MYN1.SGM
03MYN1
Agencies
[Federal Register Volume 78, Number 86 (Friday, May 3, 2013)]
[Notices]
[Pages 26004-26005]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-10662]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Notice of Availability; Draft Environmental Impact Statement for
the FutureGen 2.0 Project
AGENCY: U. S. Department of Energy.
ACTION: Notice of availability and public hearing.
-----------------------------------------------------------------------
SUMMARY: The U.S. Department of Energy (DOE) announces the availability
of the Draft Environmental Impact Statement for the FutureGen 2.0
Project (DOE/EIS-0460D) for public review and comment, as well as the
date, location, and time for a public hearing. The draft environmental
impact statement (EIS) analyzes the potential impacts associated with
the FutureGen 2.0 Project (FutureGen 2.0), which would be designed,
constructed, operated, and partially funded by the FutureGen Industrial
Alliance, Inc. (Alliance). In addition to Alliance funding, FutureGen
2.0 may receive approximately $1 billion in federal financial
assistance under the American Recovery and Reinvestment Act (ARRA).
DOE prepared this draft EIS in accordance with the National
Environmental Policy Act of 1969 (NEPA) (42 U.S.C. 4321 et seq.), the
Council on Environmental Quality regulations that implement the
procedural provisions of NEPA (40 CFR parts 1500-1508), DOE's
procedures implementing NEPA (10 CFR part 1021), and DOE's procedures
for compliance with floodplain and wetland review requirements (10 CFR
part 1022).
DATES: DOE invites the public to comment on the draft EIS during the
public comment period, which ends June 17, 2013. DOE will consider all
comments postmarked or received during the public comment period when
preparing the final EIS and will consider late comments to the extent
practicable.
DOE will hold a public hearing on May 21, 2013, at Jacksonville
High School, 1211 N. Diamond Street, Jacksonville, Illinois. An
informational session will be held from 5:00 p.m. to 6:00 p.m.,
preceding the formal presentations and comment period from 6:00 p.m. to
approximately 8:00 p.m. See the PUBLIC HEARING section for details on
the hearing process.
ADDRESSES: Requests for information about this draft EIS or for a paper
copy should be directed to: Mr. Cliff Whyte, M/S: I07, National Energy
Technology Laboratory, 3610 Collins Ferry Road, P.O. Box 880,
Morgantown, WV 26507-0880.
Additional information about the draft EIS may also be requested by
electronic mail at cliff.whyte@netl.doe.gov, by telephone at (304) 285-
2098, or by toll-free telephone at 1-800-432-8330, extension 2098. The
draft EIS will be available at https://energy.gov/nepa. Copies of the
draft EIS are also available for review at the locations listed in the
AVAILABILITY OF THE DRAFT EIS section of this notice.
Written comments on the draft EIS can be mailed or sent
electronically to Mr. Whyte at the addresses noted above. Written
comments may also be submitted by fax to (304) 285-4403. Oral comments
on the draft EIS will be accepted during the public hearing scheduled
for the date and location provided in the DATES section of this notice.
FOR FURTHER INFORMATION CONTACT: For further information on the
proposed project or the draft EIS, please contact: Mr. Cliff Whyte (see
ADDRESSES). For general information regarding DOE's NEPA process,
please contact: Ms. Carol M. Borgstrom, Director, Office of NEPA Policy
and Compliance (GC-54), U.S. Department of Energy, 1000 Independence
Avenue SW., Washington, DC 20585; Telephone: (202) 586-4600; Fax: (202)
586-7031. You may also call Ms. Borgstrom at (800) 472-2756.
SUPPLEMENTARY INFORMATION: DOE proposes to provide financial assistance
(approximately $1 billion), through two cooperative agreements, to the
Alliance for its proposed FutureGen 2.0 Project. FutureGen 2.0 is a
public-private partnership formed for the purpose of developing and
sharing the cost of the world's first commercial-scale oxy-combustion
electricity generation plant integrated with carbon dioxide
(CO2) capture and storage. Babcock & Wilcox Power Generation
Group, Inc. and Air Liquide Process and Construction, Inc., among
others, would participate in the project by supplying technology, major
components, and construction services.
The project would use oxy-combustion technology to generate
electric power and would capture CO2 for permanent storage
underground. The plant would generate 168 megawatts (MW) (gross) of
electricity. The Alliance would design and construct the plant to
capture at least 90 percent of the CO2 generated (up to 98
percent could be captured). Captured CO2 would be
transported through a 30-mile pipeline to a facility where it would be
injected into the Mount Simon formation for permanent storage. This
saline rock formation is approximately 4,000-4,500 feet below ground.
The project would be designed to capture, transport, and inject
approximately 1.1 million metric tons of CO2 annually, or a
total of approximately 33 million metric tons over 30 years of
operation. The Alliance would also construct and operate a visitor and
research center and training facilities related to carbon capture and
[[Page 26005]]
storage in the vicinity of Jacksonville, Illinois. The DOE-funded
demonstration period would last for 56 months, from the start of
operations (July 2017) through February 2022, but the plant is expected
to continue commercial operations after this date.
The oxy-combustion plant would be built on a 263-acre existing
power plant site in Morgan County, Illinois, approximately one mile
south of the Village of Meredosia. Ameren Energy Resources (Ameren) has
agreed to sell to the Alliance the assets at the Meredosia Energy
Center that are necessary for the FutureGen 2.0 Project. These assets
include Unit 4, which was constructed in 1975. The Unit 4 steam
turbine, material and fuel handling facilities, process water sources,
cooling systems, high-voltage interconnection lines, and certain other
facilities would be used for the new plant. Ameren would continue to
own the three other electricity generation units at the Meredosia
Energy Center. Operation of these units has been suspended since 2011.
The CO2 storage site would be located 30 miles east of
the plant site, on the eastern side of Morgan County. A new 12-inch
diameter pipeline would be sited and constructed using an 80-foot
construction right-of-way and a 50-foot permanent right-of-way. The
Alliance has identified two possible routes for the pipeline and has
proposed to use the route that would minimize impacts to landowners and
the environment. The Alliance has not identified a final location for
the proposed injection wells, but has identified an approximately
5,300-acre site in which the wells would be located and under which the
CO2 would be permanently stored. Up to 25 acres of land
would be used for the injection facilities, associated infrastructure
and buildings, and access roads.
The draft EIS evaluates the potential impacts of the proposed
project, connected actions, and reasonable alternatives. Because the
proposed project may affect wetlands, the draft EIS includes an
assessment of impacts to wetlands in accordance with DOE's regulations
under Compliance with Floodplains and Wetlands Environmental Review
Requirements (10 CFR part 1022).
DOE analyzed two alternatives in the draft EIS: the proposed action
and the no action alternative. Under the proposed action, DOE would
provide approximately $1 billion in cost-shared ARRA funding to the
proposed project.
Under the no action alternative, DOE would not provide continued
funding. Without DOE funding, it is unlikely that the Alliance, or the
industry in general, would undertake the utility-scale integration of
CO2 capture and geologic storage with a coal-fueled power
plant using oxy-combustion. Therefore, the no action alternative also
represents a ``no-build'' alternative. Without DOE's investment in a
utility-scale facility, the development of oxy-combustion repowered
plants integrated with CO2 capture and geologic storage
would occur more slowly or not at all.
The draft EIS considers the environmental consequences that may
result from the proposed project and describes additional mitigation
that might be used to reduce various impacts.
Availability of the Draft EIS: Copies of the draft EIS have been
distributed to members of Congress; Native American tribal governments;
federal, state, and local officials; and agencies, organizations, and
individuals who may be interested or affected. The draft EIS will be
available on the Internet at: https://energy.gov/nepa/nepa-documents.
Copies of the draft EIS are available for public review at the
following locations: M-C River Public Library District, 304 Main
Street, Meredosia, Illinois; Jacksonville Public Library, 201 West
College Avenue, Jacksonville, Illinois; Taylorville Public Library, 121
West Vine Street, Taylorville, Illinois; Arcola Public Library, 407
East Main Street, Arcola, Illinois; and Tuscola Public Library, 112
Sale Street, Tuscola, Illinois. Additional copies also can be requested
(see ADDRESSES).
Public Hearing: DOE will conduct a public hearing on May 21, 2013
at the Jacksonville High School, Jacksonville, Illinois to obtain
comments on the draft EIS. Requests to speak at the public hearing can
be made by calling or writing to Mr. Whyte (see ADDRESSES). Requests to
speak not submitted prior to the hearing will be accepted in the order
in which they are received during the hearing. Speakers are encouraged
to provide a written version of their oral comments or supplementary
materials for the record. Each speaker will be allowed approximately
five minutes to present comments. Those speakers who want more than
five minutes should indicate the length of time desired in their
request. Depending on the number of speakers, DOE may need to limit all
speakers to five minutes initially and provide additional opportunities
as time permits. Comments will be recorded by a court reporter and will
become part of the public record. Oral and written comments will be
given equal consideration.
The public hearing will begin at 5:00 p.m. with an informational
session. Formal presentations and a formal comment session will begin
at approximately 6:00 p.m. DOE will begin the hearing's formal session
with overviews of its clean coal program, proposed FutureGen 2.0
Project, and the NEPA process, followed by oral statements by pre-
registered speakers. Speakers may be asked questions to help ensure
that DOE fully understands their comments. A presiding officer will
establish the order of speakers and provide any additional procedures
necessary to conduct the hearing.
The public hearing will be accessible to people with disabilities.
In addition, any individual needing specific assistance, such as a sign
language interpreter or a translator, should contact Mr. Whyte (See
ADDRESSES) at least 48 hours in advance of the hearing so that
arrangements can be made.
Dated: May 1, 2013.
Mark J. Matarrese,
Director, Office of Environment, Security, Safety and Health, Office of
Fossil Energy.
[FR Doc. 2013-10662 Filed 5-1-13; 4:15 pm]