Download as PDF 22872 Federal Register / Vol. 78, No. 74 / Wednesday, April 17, 2013 / Notices Dated: April 11, 2013. Kimberly D. Bose, Secretary. FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5:00 p.m. Eastern Time on Thursday, April 18, 2013. Dated: April 11, 2013. Kimberly D. Bose, Secretary. [Docket No. PR13–16–001; Docket No. PR13–17–001; Not Consolidated] sroberts on DSK5SPTVN1PROD with NOTICES TexStar Transmission, LP; TEAK Texana Transmission Company, LP; Notice of Filings Take notice that on April 5, 2013, the applicants listed above submitted an amendment to the December 6, 2012, baseline filing of their Statement of Operating Conditions for services provided under Section 311 of the Natural Gas Policy Act of 1978 (‘‘NGPA’’). Any person desiring to participate in this rate filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the date as indicated below. Anyone filing an intervention or protest must serve a copy of that document on the Applicant. Anyone filing an intervention or protest on or before the intervention or protest date need not serve motions to intervene or protests on persons other than the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 7 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email VerDate Mar<15>2010 16:50 Apr 16, 2013 Jkt 229001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Federal Energy Regulatory Commission BILLING CODE 6717–01–P DEPARTMENT OF ENERGY DEPARTMENT OF ENERGY [FR Doc. 2013–09018 Filed 4–16–13; 8:45 am] BILLING CODE 6717–01–P BILLING CODE 6717–01–P Dated: April 11, 2013. Kimberly D. Bose, Secretary. [FR Doc. 2013–09010 Filed 4–16–13; 8:45 am] [FR Doc. 2013–09016 Filed 4–16–13; 8:45 am] should contact W. Doug Foster at (202) 502–6118 (via email at doug.foster@ferc.gov), or Norman Richardson at (202) 502–6219 (via email at norman.richardson@ferc.gov). Federal Energy Regulatory Commission [Docket No. AD13–1–000] [Project No. 14499–000] Review of Cost Submittals by Other Federal Agencies for Administering Part I of the Federal Power Act; Notice Requesting Questions and Comments on Fiscal Year 2012 Other Federal Agency Cost Submissions Hamilton Street Hydro, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications In its Order On Rehearing Consolidating Administrative Annual Charges Bill Appeals And Modifying Annual Charges Billing Procedures, 109 FERC ¶ 61,040 (2004) (October 8 Order) the Commission set forth an annual process for Other Federal Agencies (OFAs) to submit their costs related to Administering Part I of the Federal Power Act. Pursuant to the established process, the Director of the Financial Management Division, Office of the Executive Director, on October 10, 2012, issued a letter requesting the OFAs to submit their costs by January 8, 2013 using the OFA Cost Submission Form. Upon receipt of the agency submissions, the Commission posted the information in eLibrary, and issued, on March 13, 2013, a notice announcing the date for a technical conference to review the submitted costs. On March 28, 2013, the Commission held the technical conference. Technical conference transcripts, submitted cost forms, and detailed supporting documents are all available for review under Docket No. AD13–1. These documents are accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and are available for review in the Commission’s Public Reference Room in Washington, DC. Interested parties may file specific questions and comments on the FY 2012 OFA cost submissions with the Commission under Docket No. AD13–1, no later than April 25, 2013. Once filed, the Commission will forward the questions and comments to the OFAs for response. Anyone with questions pertaining to the technical conference or this notice On February 19, 2013, Hamilton Street Hydro, LLC, filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act (FPA), proposing to study the feasibility of hydropower at the existing Chain Dam located on the Lehigh River in Northampton County, Pennsylvania. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any landdisturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed Chain Dam Hydroelectric Project would consist of the following: (1) An existing 20-foothigh concrete gravity dam with a 690foot-long spillway; (2) an existing impoundment having a surface area of 300 acres and a storage capacity of 1,197 acre-feet at an elevation of 190 feet mean sea level (msl); (3) a new 70-footlong by 40-foot-wide by 35-foot-high powerhouse with three new identical turbine-generator units with an installed capacity of 1,368 kilowatts each, and three identical 20-foot-wide, 10-foothigh, 5-foot-long direct intakes; (4) a new tailrace consisting of a 300-footlong, 5-foot-high concrete wing wall; (5) a new 4,160-kilovolt transmission line extending 245 feet from the powerhouse to an existing distribution line; and (6) appurtenant facilities. The proposed project would have an annual generation of 18.3 gigawatt-hours. Applicant Contact: Mark Boumansour, Hamilton Street Hydro, LLC, 1401 Walnut Street, Suite 301, PO 00000 Frm 00031 Fmt 4703 Sfmt 4703 E:\FR\FM\17APN1.SGM 17APN1 Federal Register / Vol. 78, No. 74 / Wednesday, April 17, 2013 / Notices Boulder, CO 80302; phone: (303) 440– 3378. FERC Contact: Monir Chowdhury; phone: (202) 502–6736. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Competing applications and notices of intent must meet the requirements of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at 1–866–208–3676, or for TTY, (202) 502–8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and five copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of the Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–14499–000) in the docket number field to access the document. For assistance, contact FERC Online Support. Dated: April 11, 2013. Kimberly D. Bose, Secretary. [FR Doc. 2013–09012 Filed 4–16–13; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission sroberts on DSK5SPTVN1PROD with NOTICES [Project No. 14500–000] Hamilton Street Hydro, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications On February 19, 2013, Hamilton Street Hydro, LLC, filed an application VerDate Mar<15>2010 16:50 Apr 16, 2013 Jkt 229001 for a preliminary permit, pursuant to section 4(f) of the Federal Power Act (FPA), proposing to study the feasibility of hydropower at the existing Hamilton Street Dam located on the Lehigh River in Lehigh County, Pennsylvania. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land-disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed Hamilton Street Dam Hydroelectric Project would consist of the following: (1) An existing 14-foothigh concrete gravity dam with a 480foot-long spillway; (2) an existing impoundment having a surface area of 50 acres and a storage capacity of 371 acre-feet at an elevation of 240 feet mean sea level (msl); (3) a new 60-footlong by 30-foot-wide by 30-foot-high powerhouse with two turbine-generator units having a combined capacity of 2,028 kilowatts and two identical 20foot-wide, 10-foot-high, 5-foot-long direct intakes; (4) a 500-foot-long section of the existing canal to direct flows to the intakes; (5) a new 40-footwide, 100-foot-long tailrace; (6) a new 1,500-foot-long, 4,160-kilovolt transmission line extending from the powerhouse to an existing substation; and (7) appurtenant facilities. The proposed project would have an annual generation of 9.635 gigawatt-hours. Applicant Contact: Mark Boumansour, Hamilton Street Hydro, LLC, 1401 Walnut Street, Suite 301, Boulder, CO 80302; phone: (303) 440– 3378. FERC Contact: Monir Chowdhury; phone: (202) 502–6736. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Competing applications and notices of intent must meet the requirements of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at PO 00000 Frm 00032 Fmt 4703 Sfmt 4703 22873 FERCOnlineSupport@ferc.gov or toll free at 1–866–208–3676, or for TTY, (202) 502–8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and five copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of the Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–14500–000) in the docket number field to access the document. For assistance, contact FERC Online Support. Dated: April 11, 2013. Kimberly D. Bose, Secretary. [FR Doc. 2013–09013 Filed 4–16–13; 8:45 am] BILLING CODE 6717–01–P ENVIRONMENTAL PROTECTION AGENCY [EPA–HQ–OPP–2013–0230; FRL–9384–1] FIFRA Scientific Advisory Panel; Notice of Public Meeting Environmental Protection Agency (EPA). ACTION: Notice. AGENCY: There will be a 4-day meeting of the Federal Insecticide, Fungicide, and Rodenticide Act Scientific Advisory Panel (FIFRA SAP) to consider and review Weight-of-Evidence: Evaluating Results of EDSP Tier 1 Screening. DATES: The meeting will be held July 30, 2013–August 2, 2013, from approximately 8:30 a.m. to 5 p.m. Comments. The Agency encourages that written comments be submitted by July 16, 2013, and requests for oral comments be submitted by July 23, 2013. However, written comments and requests to make oral comments may be submitted until the date of the meeting, but anyone submitting written comments after July 16, 2013, should contact the Designated Federal Official (DFO) listed under FOR FURTHER INFORMATION CONTACT. For additional instructions, see Unit I.C. of the SUPPLEMENTARY INFORMATION. Nominations. Nominations of candidates to serve as ad hoc members of FIFRA SAP for this meeting should be provided on or before May 2, 2013. Webcast. This meeting may be webcast. Please refer to the FIFRA SAP’s Web site at https://www.epa.gov/scipoly/ SUMMARY: E:\FR\FM\17APN1.SGM 17APN1

Agencies

[Federal Register Volume 78, Number 74 (Wednesday, April 17, 2013)]
[Notices]
[Pages 22872-22873]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-09012]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14499-000]


 Hamilton Street Hydro, LLC; Notice of Preliminary Permit 
Application Accepted for Filing and Soliciting Comments, Motions To 
Intervene, and Competing Applications

    On February 19, 2013, Hamilton Street Hydro, LLC, filed an 
application for a preliminary permit, pursuant to section 4(f) of the 
Federal Power Act (FPA), proposing to study the feasibility of 
hydropower at the existing Chain Dam located on the Lehigh River in 
Northampton County, Pennsylvania. The sole purpose of a preliminary 
permit, if issued, is to grant the permit holder priority to file a 
license application during the permit term. A preliminary permit does 
not authorize the permit holder to perform any land-disturbing 
activities or otherwise enter upon lands or waters owned by others 
without the owners' express permission.
    The proposed Chain Dam Hydroelectric Project would consist of the 
following: (1) An existing 20-foot-high concrete gravity dam with a 
690-foot-long spillway; (2) an existing impoundment having a surface 
area of 300 acres and a storage capacity of 1,197 acre-feet at an 
elevation of 190 feet mean sea level (msl); (3) a new 70-foot-long by 
40-foot-wide by 35-foot-high powerhouse with three new identical 
turbine-generator units with an installed capacity of 1,368 kilowatts 
each, and three identical 20-foot-wide, 10-foot-high, 5-foot-long 
direct intakes; (4) a new tailrace consisting of a 300-foot-long, 5-
foot-high concrete wing wall; (5) a new 4,160-kilovolt transmission 
line extending 245 feet from the powerhouse to an existing distribution 
line; and (6) appurtenant facilities. The proposed project would have 
an annual generation of 18.3 gigawatt-hours.
    Applicant Contact: Mark Boumansour, Hamilton Street Hydro, LLC, 
1401 Walnut Street, Suite 301,

[[Page 22873]]

Boulder, CO 80302; phone: (303) 440-3378.
    FERC Contact: Monir Chowdhury; phone: (202) 502-6736.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and 
competing applications may be filed electronically via the Internet. 
See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's 
Web site https://www.ferc.gov/docs-filing/efiling.asp. Commenters can 
submit brief comments up to 6,000 characters, without prior 
registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information 
at the end of your comments. For assistance, please contact FERC Online 
Support at FERCOnlineSupport@ferc.gov or toll free at 1-866-208-3676, 
or for TTY, (202) 502-8659. Although the Commission strongly encourages 
electronic filing, documents may also be paper-filed. To paper-file, 
mail an original and five copies to: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE., Washington, 
DC 20426.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of the 
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-14499-000) in the docket number field to 
access the document. For assistance, contact FERC Online Support.

    Dated: April 11, 2013.
 Kimberly D. Bose,
 Secretary.
[FR Doc. 2013-09012 Filed 4-16-13; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.