Green Mountain Power Corporation; Notice of Application Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests, 22537 [2013-08820]

Download as PDF Federal Register / Vol. 78, No. 73 / Tuesday, April 16, 2013 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2558–033] mstockstill on DSK4VPTVN1PROD with NOTICES Green Mountain Power Corporation; Notice of Application Accepted for Filing, Soliciting Comments, Motions To Intervene, and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Types of Application: Non-capacity amendment of license. b. Project No.: 2558–033. c. Date Filed: March 29, 2013. d. Applicant: Green Mountain Power Corporation. e. Name of Project: Otter Creek Hydroelectric Project. f. Location: Otter Creek in Addison and Rutland Counties, Vermont. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a–825r. h. Applicant Contact: Mr. Mike Scarzello, Green Mountain Power Corporation, 77 Grove Street, Rutland, VT 05701–3400, (802) 747–5207. i. FERC Contact: Rebecca Martin, (202) 502–6012, Rebecca.Martin@ferc.gov. j. Deadline for filing comments, motions to intervene, and protests: May 9, 2013. All documents may be filed electronically via the Internet. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site at https://www.ferc.gov/docs-filing/ efiling.asp. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and seven copies should be mailed to: Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. Please include the project number (P–2558–033) on any comments or motions filed. k. Description of Application: Green Mountain Power Corporation is requesting a non-capacity license amendment to realign the intake at the Proctor development. The licensee would also remove inoperable generating equipment from the Proctor powerhouse to facilitate installation of new turbine generator equipment that is proposed under the Project’s application for subsequent license currently being VerDate Mar<15>2010 17:58 Apr 15, 2013 Jkt 229001 processed by the Commission. The proposed intake realignment construction includes demolition of portions of the existing intake, limited removal of bedrock, deepening and widening the intake channel and orienting the opening more directly to river flow. l. Locations of the Application: A copy of the application is available for inspection and reproduction at the Commission’s Public Reference Room, located at 888 First Street NE., Room 2A, Washington, DC 20426, or by calling (202) 502–8371. This filing may also be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field (P–2558) to access the document. You may also register online at https://www.ferc.gov/ docs-filing/esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, call 1– 866–208–3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item (h) above. m. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. n. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. o. Filing and Service of Responsive Documents: Any filing must (1) Bear in all capital letters the title ‘‘COMMENTS’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’ as applicable; (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, motions to intervene, or protests must set forth their evidentiary PO 00000 Frm 00027 Fmt 4703 Sfmt 4703 22537 basis and otherwise comply with the requirements of 18 CFR 4.34(b). All comments, motions to intervene, or protests should relate to project works which are the subject of the amendment application. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. If an intervener files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. A copy of all other filings in reference to this application must be accompanied by proof of service on all persons listed in the service list prepared by the Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010. Dated: April 9, 2013. Kimberly D. Bose, Secretary. [FR Doc. 2013–08820 Filed 4–15–13; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following exempt wholesale generator filings: Docket Numbers: EG13–25–000. Applicants: NRG Energy, Inc. Description: Self-Certification of EG or FC of NRG Energy, Inc for Petra Nova Power I LLC. Filed Date: 4/4/13. Accession Number: 20130404–5131. Comments Due: 5 p.m. ET 4/25/13. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER12–817–002. Applicants: Midwest Independent Transmission System Operator, Inc. Description: 04–08–2013 Resource Adequacy 2013 Comp Filing to be effective 2/27/2013. Filed Date: 4/8/13. Accession Number: 20130408–5126. Comments Due: 5 p.m. ET 4/29/13. Docket Numbers: ER13–5–001. Applicants: ITC Midwest LLC. Description: ITC Midwest LLC submits Compliance Filing of ITC Midwest LLC to be effective 3/11/2013. Filed Date: 4/9/13. E:\FR\FM\16APN1.SGM 16APN1

Agencies

[Federal Register Volume 78, Number 73 (Tuesday, April 16, 2013)]
[Notices]
[Page 22537]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-08820]



[[Page 22537]]

=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2558-033]


 Green Mountain Power Corporation; Notice of Application Accepted 
for Filing, Soliciting Comments, Motions To Intervene, and Protests

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Types of Application: Non-capacity amendment of license.
    b. Project No.: 2558-033.
    c. Date Filed: March 29, 2013.
    d. Applicant: Green Mountain Power Corporation.
    e. Name of Project: Otter Creek Hydroelectric Project.
    f. Location: Otter Creek in Addison and Rutland Counties, Vermont.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
    h. Applicant Contact: Mr. Mike Scarzello, Green Mountain Power 
Corporation, 77 Grove Street, Rutland, VT 05701-3400, (802) 747-5207.
    i. FERC Contact: Rebecca Martin, (202) 502-6012, 
Rebecca.Martin@ferc.gov.
    j. Deadline for filing comments, motions to intervene, and 
protests: May 9, 2013.
    All documents may be filed electronically via the Internet. See, 18 
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web 
site at https://www.ferc.gov/docs-filing/efiling.asp. If unable to be 
filed electronically, documents may be paper-filed. To paper-file, an 
original and seven copies should be mailed to: Secretary, Federal 
Energy Regulatory Commission, 888 First Street NE., Washington, DC 
20426. Commenters can submit brief comments up to 6,000 characters, 
without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and 
contact information at the end of your comments. Please include the 
project number (P-2558-033) on any comments or motions filed.
    k. Description of Application: Green Mountain Power Corporation is 
requesting a non-capacity license amendment to realign the intake at 
the Proctor development. The licensee would also remove inoperable 
generating equipment from the Proctor powerhouse to facilitate 
installation of new turbine generator equipment that is proposed under 
the Project's application for subsequent license currently being 
processed by the Commission. The proposed intake realignment 
construction includes demolition of portions of the existing intake, 
limited removal of bedrock, deepening and widening the intake channel 
and orienting the opening more directly to river flow.
    l. Locations of the Application: A copy of the application is 
available for inspection and reproduction at the Commission's Public 
Reference Room, located at 888 First Street NE., Room 2A, Washington, 
DC 20426, or by calling (202) 502-8371. This filing may also be viewed 
on the Commission's Web site at https://www.ferc.gov using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field (P-2558) to access the document. You 
may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, call 1-866-
208-3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502-
8659. A copy is also available for inspection and reproduction at the 
address in item (h) above.
    m. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    n. Comments, Protests, or Motions to Intervene: Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
comment date for the particular application.
    o. Filing and Service of Responsive Documents: Any filing must (1) 
Bear in all capital letters the title ``COMMENTS'', ``PROTEST'', or 
``MOTION TO INTERVENE'' as applicable; (2) set forth in the heading the 
name of the applicant and the project number of the application to 
which the filing responds; (3) furnish the name, address, and telephone 
number of the person protesting or intervening; and (4) otherwise 
comply with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, motions to intervene, or protests must set forth their 
evidentiary basis and otherwise comply with the requirements of 18 CFR 
4.34(b). All comments, motions to intervene, or protests should relate 
to project works which are the subject of the amendment application. 
Agencies may obtain copies of the application directly from the 
applicant. A copy of any protest or motion to intervene must be served 
upon each representative of the applicant specified in the particular 
application. If an intervener files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency. A copy of all other 
filings in reference to this application must be accompanied by proof 
of service on all persons listed in the service list prepared by the 
Commission in this proceeding, in accordance with 18 CFR 4.34(b) and 
385.2010.

    Dated: April 9, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-08820 Filed 4-15-13; 8:45 am]
BILLING CODE 6717-01-P