Notice of Issuance of Final Air Permit; Architect of the Capitol-Capitol Power Plant, 21938 [2013-08697]
Download as PDF
21938
Federal Register / Vol. 78, No. 71 / Friday, April 12, 2013 / Notices
ENVIRONMENTAL PROTECTION
AGENCY
ENVIRONMENTAL PROTECTION
AGENCY
[ER–FRL–9008–6]
[EPA–R3–PAL–001; FRL–9801–9]
Environmental Impacts Statements;
Notice of Availability
Notice of Issuance of Final Air Permit;
Architect of the Capitol—Capitol Power
Plant
Responsible Agency: Office of Federal
Activities, General Information (202)
564–7146 or https://www.epa.gov/
compliance/nepa/.
Weekly receipt of Environmental Impact
Statements
Filed 04/01/2013 Through 04/05/2013
Pursuant to 40 CFR 1506.9.
mstockstill on DSK6TPTVN1PROD with NOTICES
Notice
Section 309(a) of the Clean Air Act
requires that EPA make public its
comments on EISs issued by other
Federal agencies. EPA’s comment letters
on EISs are available at: https://
www.epa.gov/compliance/nepa/
eisdata.html.
EIS No. 20130086, Revised Final EIS,
USFS, ID, Lower Orogrande, North
Fork Ranger District, Clearwater
National Forest, Review Period Ends:
05/28/2013, Contact: George
Harbaugh 208–935–4260.
EIS No. 20130087, Draft EIS, BLM, NM,
TriCounty Resource Management
Plan, Comment Period Ends: 07/11/
2013, Contact: Jennifer Montoya 575–
525–4316.
EIS No. 20130088, Final Supplement,
BOEM, 00, Gulf of Mexico OCS Oil
and Gas Lease Sales: 2013–2014
Western Planning Area Lease Sale 233
Central Planning Area Lease Sale 231,
Review Period Ends: 05/13/2013,
Contact: Poojan B. Tripathi 703–787–
1738.
Amended Notices
EIS No. 20130041, Draft EIS, USFS, AZ,
Salt River Allotments Vegetative
Management, Comment Period Ends:
05/08/2013, Contact: Debbie Cress
928–467–3220, Revision to FR Notice
Published 02/22/2013; Extending
Comment Period from 04/08/2013 to
05/08/2013.
EIS No. 20130047, Draft EIS, NPS, FL,
Everglades National Park Draft
General Management Plan/East
Everglades Wilderness Study,
Comment Period Ends: 05/13/2013,
Contact: Eric Thuerk 303–987–6852,
Revision to FR Notice Published 03/
01/2013; Extending Comment Period
from 4/15/2013 to 5/13/2013.
Dated: April 9, 2013.
Cliff Rader,
Director, NEPA Compliance Division, Office
of Federal Activities.
[FR Doc. 2013–08661 Filed 4–11–13; 8:45 am]
BILLING CODE 6560–50–P
VerDate Mar<15>2010
16:47 Apr 11, 2013
Jkt 229001
Environmental Protection
Agency (EPA).
ACTION: Notice of final agency action.
AGENCY:
This action is to provide
notice that on January 23, 2013, EPA
issued a final air permit to the Architect
of the Capitol for the Capitol Power
Plant (CPP). This permit became
effective on February 25, 2013.
The CPP permit establishes a
plantwide applicability limit (PAL) for
emissions of oxides of nitrogen as an
indicator for nitrogen dioxide,
particulate matter less than or equal to
ten micrometers in diameter, and
greenhouse gases. This action is being
taken in accordance with EPA’s
procedures for decision making set forth
at 40 CFR part 124 and the Clean Air
Act (CAA).
ADDRESSES: The final permit, EPA’s
response to public comments, and
additional supporting information are
available at https://www.epa.gov/
reg3artd/permitting/capitol_power.html.
Copies of the final permit and EPA’s
response to comments are also available
for review at the EPA Region III office
and upon request in writing. EPA
requests that you contact the person
listed in the FOR FURTHER INFORMATION
CONTACT section to schedule your
inspection. The Regional Office’s
official hours of business are Monday
through Friday, 8:30 to 4:30 excluding
federal holidays.
FOR FURTHER INFORMATION CONTACT:
Mike Gordon, (215) 814–2039, or by
email at gordon.mike@epa.gov.
SUPPLEMENTARY INFORMATION: On August
29, 2012, EPA published a request for
public comment and notice of a public
hearing for the CPP permit in the
Washington Times. EPA received over
200 comments during the public
comment period, which ended on
October 1, 2012. EPA carefully reviewed
each of the comments submitted, and
after consideration of the expressed
view of all interested persons, the
pertinent federal statutes and
regulations, the applications and
additional material relevant to the
applications and contained in the
administrative record, EPA made a
decision in accordance with 40 CFR
52.21 and 40 CFR part 124 to issue the
final PAL permit to CPP. The permit
was signed on January 23, 2013, and
SUMMARY:
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
notice of the final permit decision was
provided in accordance with the
requirements of 40 CFR 124.15. The
District Department of the Environment
(DDOE) is also in the process of issuing
permits to CPP, however, the DDOE’s
permits are not part of this action.
Under 40 CFR 124.19(f)(2), notice of
any final EPA action regarding a permit
issued under the authority of 40 CFR
52.21 must be published in the Federal
Register. Section 307(b)(1) of the CAA
provides for review of any final EPA
action in the United States Court of
Appeals for the appropriate circuit.
Such a petition for review of final EPA
action must be filed within 60 days from
the date of notice of such action in the
Federal Register. For purposes of
judicial review under the CAA, final
EPA action occurs when a final
Prevention of Significant Deterioration
permit is issued or denied by EPA, and
EPA review procedures are exhausted
under 40 CFR 124.19(f)(1).
Any person who filed comments on
the draft CPP permit was provided the
opportunity to petition the
Environmental Appeals Board by
February 25, 2013. No petitions were
submitted; therefore the CPP permit
became effective on February 25, 2013.
Dated: March 28, 2013.
Diana Esher,
Director, Air Protection Division, Region III.
[FR Doc. 2013–08697 Filed 4–11–13; 8:45 am]
BILLING CODE 6560–50–P
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–HQ–OW–2011–0141; FRL–9733–7]
Final National Pollutant Discharge
Elimination System (NPDES) General
Permit for Discharges Incidental to the
Normal Operation of a Vessel
Environmental Protection
Agency (EPA).
ACTION: Notice of final permit issuance.
AGENCY:
EPA Regions 1, 2, 3, 4, 5, 6,
7, 8, 9, and 10 are finalizing the NPDES
Vessel General Permit (VGP) to
authorize discharges incidental to the
normal operation of non-military and
non-recreational vessels greater than or
equal to 79 feet in length. This VGP,
which has an effective date of December
19, 2013, will replace the current VGP,
which was issued in December 2008
and expires on December 19, 2013. EPA
provided notice of the availability of the
draft permit and accompanying fact
sheet for public comment in the Federal
Register on December 8, 2011. At that
time, EPA also provided notice of
SUMMARY:
E:\FR\FM\12APN1.SGM
12APN1
Agencies
[Federal Register Volume 78, Number 71 (Friday, April 12, 2013)]
[Notices]
[Page 21938]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-08697]
-----------------------------------------------------------------------
ENVIRONMENTAL PROTECTION AGENCY
[EPA-R3-PAL-001; FRL-9801-9]
Notice of Issuance of Final Air Permit; Architect of the
Capitol--Capitol Power Plant
AGENCY: Environmental Protection Agency (EPA).
ACTION: Notice of final agency action.
-----------------------------------------------------------------------
SUMMARY: This action is to provide notice that on January 23, 2013, EPA
issued a final air permit to the Architect of the Capitol for the
Capitol Power Plant (CPP). This permit became effective on February 25,
2013.
The CPP permit establishes a plantwide applicability limit (PAL)
for emissions of oxides of nitrogen as an indicator for nitrogen
dioxide, particulate matter less than or equal to ten micrometers in
diameter, and greenhouse gases. This action is being taken in
accordance with EPA's procedures for decision making set forth at 40
CFR part 124 and the Clean Air Act (CAA).
ADDRESSES: The final permit, EPA's response to public comments, and
additional supporting information are available at https://www.epa.gov/reg3artd/permitting/capitol_power.html. Copies of the final permit and
EPA's response to comments are also available for review at the EPA
Region III office and upon request in writing. EPA requests that you
contact the person listed in the FOR FURTHER INFORMATION CONTACT
section to schedule your inspection. The Regional Office's official
hours of business are Monday through Friday, 8:30 to 4:30 excluding
federal holidays.
FOR FURTHER INFORMATION CONTACT: Mike Gordon, (215) 814-2039, or by
email at gordon.mike@epa.gov.
SUPPLEMENTARY INFORMATION: On August 29, 2012, EPA published a request
for public comment and notice of a public hearing for the CPP permit in
the Washington Times. EPA received over 200 comments during the public
comment period, which ended on October 1, 2012. EPA carefully reviewed
each of the comments submitted, and after consideration of the
expressed view of all interested persons, the pertinent federal
statutes and regulations, the applications and additional material
relevant to the applications and contained in the administrative
record, EPA made a decision in accordance with 40 CFR 52.21 and 40 CFR
part 124 to issue the final PAL permit to CPP. The permit was signed on
January 23, 2013, and notice of the final permit decision was provided
in accordance with the requirements of 40 CFR 124.15. The District
Department of the Environment (DDOE) is also in the process of issuing
permits to CPP, however, the DDOE's permits are not part of this
action.
Under 40 CFR 124.19(f)(2), notice of any final EPA action regarding
a permit issued under the authority of 40 CFR 52.21 must be published
in the Federal Register. Section 307(b)(1) of the CAA provides for
review of any final EPA action in the United States Court of Appeals
for the appropriate circuit. Such a petition for review of final EPA
action must be filed within 60 days from the date of notice of such
action in the Federal Register. For purposes of judicial review under
the CAA, final EPA action occurs when a final Prevention of Significant
Deterioration permit is issued or denied by EPA, and EPA review
procedures are exhausted under 40 CFR 124.19(f)(1).
Any person who filed comments on the draft CPP permit was provided
the opportunity to petition the Environmental Appeals Board by February
25, 2013. No petitions were submitted; therefore the CPP permit became
effective on February 25, 2013.
Dated: March 28, 2013.
Diana Esher,
Director, Air Protection Division, Region III.
[FR Doc. 2013-08697 Filed 4-11-13; 8:45 am]