Demand Response Coalition v. PJM Interconnection, L.L.C.; Notice of Complaint, 21928 [2013-08601]
Download as PDF
21928
Federal Register / Vol. 78, No. 71 / Friday, April 12, 2013 / Notices
transmission planning activities of the
Southern Company Services, Inc.:
mstockstill on DSK6TPTVN1PROD with NOTICES
Southeastern Regional Transmission
Planning (SERTP) Process Interim
Stakeholder Meeting on Order No. 1000
April 10, 2013, 10:00 a.m.–3:00 p.m.,
Local Time
The above-referenced meeting will be
held at:
Georgia Transmission Corporation
(GTC) Headquarters—Tucker, Georgia
The above-referenced meeting is open
to stakeholders.
Further information may be found at:
www.southeasternrtp.com.
The discussions at the meeting
described above may address matters at
issue in the following proceedings:
Docket No. ER13–908, Alabama Power
Company et al.
Docket No. ER13–913, Ohio Valley
Electric Corporation
Docket No. ER13–897, Louisville Gas
and Electric Company and Kentucky
Utilities Company
Docket No. ER12–337, Mississippi
Power Company
Docket No. ER13–1221, Mississippi
Power Company
Docket No. EL05–121, PJM
Interconnection, L.L.C.
Docket No. EL10–52, Central
Transmission, L.L.C. v. PJM
Interconnection, L.L.C.
Docket No. ER09–1256, PotomacAppalachian Transmission Highline,
L.L.C.
Docket Nos. ER10–253 and EL10–14,
Primary Power, L.L.C.
Docket Nos. ER11–2814 and ER11–2815,
PJM Interconnection, L.L.C. and
American Transmission Systems, Inc.
Docket No. EL12–69, Primary Power
LLC v. PJM Interconnection, L.L.C.
Docket No. ER12–91, PJM
Interconnection, L.L.C.
Docket No. ER12–92, PJM
Interconnection, L.L.C., et al.
Docket No. ER12–1178, PJM
Interconnection, L.L.C.
Docket No. ER12–2399, PJM
Interconnection, L.L.C.
Docket No. ER12–2708, PJM
Interconnection, L.L.C.
Docket No. ER13–90, Public Service
Electric and Gas Company and PJM
Interconnection, L.L.C.
Docket No. ER13–195, Indicated PJM
Transmission Owners
Docket No. ER13–198, PJM
Interconnection, L.L.C.
Docket No. ER13–887, PJM
Interconnection, L.L.C.
Docket No. ER13–1033, Linden VFT,
LLC and PJM Interconnection, L.L.C.
Docket Nos. ER13–1177, 1178 and 1179,
PJM Interconnection, L.L.C. and
VerDate Mar<15>2010
16:47 Apr 11, 2013
Jkt 229001
Eastern Kentucky Power Cooperative,
Inc.
Docket No. ER13–186, Midwest
Independent Transmission System
Operator, Inc. and the MISO
Transmission Owners
Docket No. ER13–187, Midwest
Independent Transmission System
Operator, Inc. and the MISO
Transmission Owners
Docket No. ER13–89, MidAmerican
Energy Company and Midwest
Independent Transmission System
Operator, Inc.
Docket No. ER13–101, American
Transmission Company LLC and the
Midwest Independent Transmission
System Operator, Inc.
Docket No. ER13–84, Cleco Power LLC
Docket No. ER13–95, Entergy Arkansas,
Inc.
Docket No. ER13–80, Tampa Electric
Company
Docket No. ER13–86, Florida Power
Corporation
Docket No. ER13–104, Florida Power &
Light Company
Docket No. NJ13–2, Orlando Utilities
Commission
Docket Nos. ER13–366 and ER13–367,
Southwest Power Pool, Inc.
Docket No. ER13–83, Duke Energy
Carolinas LLC and Carolina Power &
Light Company
Docket No. ER13–88, Alcoa Power
Generating, Inc.
Docket No. ER13–107, South Carolina
Electric & Gas Company
For more information, contact Valerie
Martin, Office of Energy Market
Regulation, Federal Energy Regulatory
Commission at (202) 502–6139 or
Valerie.Martin@ferc.gov.
Dated: April 4, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–08586 Filed 4–11–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL13–57–000]
Demand Response Coalition v. PJM
Interconnection, L.L.C.; Notice of
Complaint
Take notice that on April 3, 2013,
pursuant to sections 206 and 306 of the
Federal Power Act (FPA), 16 U.S.C.
824e and 825e and Rule 206 of the Rules
of Practice and Procedures of the
Federal Energy Regulatory Commission
(Commission), 18 CFR 385.206, the
PO 00000
Frm 00024
Fmt 4703
Sfmt 9990
Demand Response Coalition 1
(Complainant) filed a formal complaint
against the PJM Interconnection, L.L.C.
(Respondent or PJM), alleging that
certain newly adopted provisions of
PJM’s Manual 18 (the ‘‘DR Plan
Enhancements’’) violate section 205 of
the FPA and are therefore
unenforceable.
The Complainant certifies that copies
of the Complaint were served on the
contacts for the Respondent as listed on
the Commission’s list of Corporate
Officials.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. The Respondent’s answer
and all interventions, or protests must
be filed on or before the comment date.
The Respondent’s answer, motions to
intervene, and protests must be served
on the Complainants.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 5 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5:00 p.m. Eastern
Time on April 15, 2013.
Dated: April 3, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–08601 Filed 4–11–13; 8:45 am]
BILLING CODE 6717–01–P
1 The Demand Response Coalition includes
Comverge, Inc., Viridity Energy, and Energy
Curtailment Specialists (ECS).
E:\FR\FM\12APN1.SGM
12APN1
Agencies
[Federal Register Volume 78, Number 71 (Friday, April 12, 2013)]
[Notices]
[Page 21928]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-08601]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. EL13-57-000]
Demand Response Coalition v. PJM Interconnection, L.L.C.; Notice
of Complaint
Take notice that on April 3, 2013, pursuant to sections 206 and 306
of the Federal Power Act (FPA), 16 U.S.C. 824e and 825e and Rule 206 of
the Rules of Practice and Procedures of the Federal Energy Regulatory
Commission (Commission), 18 CFR 385.206, the Demand Response Coalition
\1\ (Complainant) filed a formal complaint against the PJM
Interconnection, L.L.C. (Respondent or PJM), alleging that certain
newly adopted provisions of PJM's Manual 18 (the ``DR Plan
Enhancements'') violate section 205 of the FPA and are therefore
unenforceable.
---------------------------------------------------------------------------
\1\ The Demand Response Coalition includes Comverge, Inc.,
Viridity Energy, and Energy Curtailment Specialists (ECS).
---------------------------------------------------------------------------
The Complainant certifies that copies of the Complaint were served
on the contacts for the Respondent as listed on the Commission's list
of Corporate Officials.
Any person desiring to intervene or to protest this filing must
file in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211, 385.214). Protests will be
considered by the Commission in determining the appropriate action to
be taken, but will not serve to make protestants parties to the
proceeding. Any person wishing to become a party must file a notice of
intervention or motion to intervene, as appropriate. The Respondent's
answer and all interventions, or protests must be filed on or before
the comment date. The Respondent's answer, motions to intervene, and
protests must be served on the Complainants.
The Commission encourages electronic submission of protests and
interventions in lieu of paper using the ``eFiling'' link at https://www.ferc.gov. Persons unable to file electronically should submit an
original and 5 copies of the protest or intervention to the Federal
Energy Regulatory Commission, 888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at https://www.ferc.gov, using the
``eLibrary'' link and is available for review in the Commission's
Public Reference Room in Washington, DC. There is an ``eSubscription''
link on the Web site that enables subscribers to receive email
notification when a document is added to a subscribed docket(s). For
assistance with any FERC Online service, please email
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For
TTY, call (202) 502-8659.
Comment Date: 5:00 p.m. Eastern Time on April 15, 2013.
Dated: April 3, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-08601 Filed 4-11-13; 8:45 am]