City of Crystal Falls, MI; Notice of Application for Temporary Variance of License and Soliciting Comments, Motions To Intervene, and Protests, 21923-21924 [2013-08595]
Download as PDF
Federal Register / Vol. 78, No. 71 / Friday, April 12, 2013 / Notices
Each filing must be accompanied by
proof of service on all persons listed on
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b), and
385.2010.
p. Public notice of the filing of the
initial development application was
made under P–12970–001 and
established the due date for filing
competing applications or notices of
intent. Under the Commission’s
regulations, any competing
development application must be filed
in response to and in compliance with
public notice of the initial development
application. No competing applications
or notices of intent may be filed in
response to this notice.
q. The license applicant must file no
later than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
r. Procedural schedule: The
application will be processed according
to the following procedural schedule.
Revisions to the schedule may be made
as appropriate.
Milestone
Target date
Notice of the availability of the
EA.
August 2013.
Dated: April 8, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–08584 Filed 4–11–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 11402–074]
mstockstill on DSK6TPTVN1PROD with NOTICES
City of Crystal Falls, MI; Notice of
Application for Temporary Variance of
License and Soliciting Comments,
Motions To Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Temporary
variance of license.
b. Project No: 11402–074.
c. Date Filed: March 11, 2013.
d. Applicant: City of Crystal Falls, MI.
e. Name of Project: Crystal Falls
Project.
VerDate Mar<15>2010
16:47 Apr 11, 2013
Jkt 229001
f. Location: The project is located on
the Paint River in the City of Crystal
Falls, Iron County, Michigan.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contact: Dave Graff, City
of Crystal Falls, 401 Superior Avenue,
Crystal Falls, Mi 49920, (906) 875–6650.
i. FERC Contact: Rebecca Martin,
(202) 502–6012,
Rebecca.martin@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests: May
3, 2013.
All documents may be filed
electronically via the Internet. See, 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site at https://www.ferc.gov/docs-filing/
efiling.asp. If unable to be filed
electronically, documents may be paperfiled. To paper-file, an original and
seven copies should be mailed to:
Secretary, Federal Energy Regulatory
Commission, 888 First Street NE.,
Washington, DC 20426. Commenters
can submit brief comments up to 6,000
characters, without prior registration,
using the eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. Please include the
project number (P–11402–074) on any
comments or motions filed.
k. Description of Application: The
City of Crystal Falls is requesting a
variance of articles 401, 402, and 405 of
its license. The City of Crystal Falls
intends to complete non-safety related
maintenance at its low hazard
hydroelectric dam in the summer of
2013. In order to complete the project,
drawdown of the impoundment would
begin on June 27, 2013 at a rate of 1.0
foot per day for the first four days then
the drawdown rate would switch to 1.5
feet per day until a 20 foot drawdown
is reached. The impoundment would be
filled as the inflow allows, while
maintaining 150 cubic feet per second
outflow. The reservoir would be filled
no later than November 1, 2013. During
the drawdown the City will conduct
surveys for stranded mussels and fish.
Additionally, recreational access will be
limited to canoes, kayaks, and small
boats during the drawdown.
l. Locations of the Application: A
copy of the application is available for
inspection and reproduction at the
Commission’s Public Reference Room,
located at 888 First Street NE., Room
2A, Washington, DC 20426, or by calling
(202) 502–8371. This filing may also be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
21923
the docket number field (P–11402) to
access the document. You may also
register online at https://www.ferc.gov/
docs-filing/esubscription.asp to be
notified via email of new filings and
issuances related to this or other
pending projects. For assistance, call 1–
866–208–3676 or email
FERCOnlineSupport@ferc.gov, for TTY,
call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item (h)
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
o. Filing and Service of Responsive
Documents: Any filing must (1) bear in
all capital letters the title
‘‘COMMENTS’’, ‘‘PROTEST’’, or
‘‘MOTION TO INTERVENE’’ as
applicable; (2) set forth in the heading
the name of the applicant and the
project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, motions to intervene, or
protests must set forth their evidentiary
basis and otherwise comply with the
requirements of 18 CFR 4.34(b). All
comments, motions to intervene, or
protests should relate to project works
which are the subject of the amendment
application. Agencies may obtain copies
of the application directly from the
applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. If an intervener files
comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency. A copy of all
other filings in reference to this
E:\FR\FM\12APN1.SGM
12APN1
21924
Federal Register / Vol. 78, No. 71 / Friday, April 12, 2013 / Notices
application must be accompanied by
proof of service on all persons listed in
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
Dated: April 3, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–08595 Filed 4–11–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 618–195]
mstockstill on DSK6TPTVN1PROD with NOTICES
Alabama Power Company; Notice of
Application for Amendment of License
and Soliciting Comments, Motions To
Intervene, and Protests
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Amendment of
License.
b. Project No.: 618–195.
c. Date Filed: March 21, 2013.
d. Applicant: Alabama Power
Company.
e. Name of Project: Jordan Dam
Project.
f. Location: The project is located on
the Coosa River in Chilton, Coosa, and
Elmore Counties, Alabama.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. James F.
Crew, Alabama Power Company, 600
North 18th Street, P.O. Box 2641,
Birmingham, AL 35291–8180, (205)
257–4265.
i. FERC Contact: Christopher Chaney,
(202) 502–6778,
christopher.chaney@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests: April
18, 2013.
All documents may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support.
Although the Commission strongly
encourages electronic filing, documents
VerDate Mar<15>2010
16:47 Apr 11, 2013
Jkt 229001
may also be paper-filed. To paper-file,
mail an original and seven copies to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. Description of Application:
Alabama Power Company seeks
approval to replace the Unit 4 turbine at
the Jordan Dam Project. Specifically, the
licensee proposes the following work:
complete turbine replacement, wicket
gate system rehabilitation or
replacement, gate stem bushing
replacement, turbine and generator
bearing refurbishment, and related
component replacement. The turbine
unit modifications are expected to
increase the turbine rating by
approximately 3 megawatts (MW), as
well as increase efficiency and annual
generation; however, since the unit is
generator-limited, the installed capacity
will not change. The unit replacement
would result in a maximum hydraulic
capacity increase of approximately 4.6
percent for Unit 4, and 1.2 percent for
the Project. No change in project
operations is proposed.
l. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number (P–618–195) excluding the last
three digits in the docket number field
to access the document. For assistance,
contact FERC Online Support. A copy is
also available for inspection and
reproduction at the address in item h
above.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
Any filings must bear in all capital
letters the title ‘‘COMMENTS,’’
‘‘PROTEST,’’ or ‘‘MOTION TO
INTERVENE,’’ as applicable, and the
Project Number of the particular
application to which the filing refers. A
copy of any motion to intervene must
also be served upon each representative
of the Applicant specified in the
particular application.
o. Agency Comments: Federal, state,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
Dated: April 3, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–08594 Filed 4–11–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
Take notice that the Commission
received the following exempt
wholesale generator filings:
Docket Numbers: EG13–23–000.
Applicants: RE Rosamond One LLC.
Description: RE Rosamond One LLC
submits Notice of Self-Certification of
Exempt Wholesale Generator Status.
Filed Date: 4/3/13.
Accession Number: 20130403–5061.
Comments Due: 5 p.m. ET 4/24/13.
Docket Numbers: EG13–24–000.
Applicants: RE Rosamond Two LLC.
Description: RE Rosamond Two LLC
submits Notice of Self-Certification of
Exempt Wholesale Generator Status.
Filed Date: 4/3/13.
Accession Number: 20130403–5062.
Comments Due: 5 p.m. ET 4/24/13.
E:\FR\FM\12APN1.SGM
12APN1
Agencies
[Federal Register Volume 78, Number 71 (Friday, April 12, 2013)]
[Notices]
[Pages 21923-21924]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-08595]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 11402-074]
City of Crystal Falls, MI; Notice of Application for Temporary
Variance of License and Soliciting Comments, Motions To Intervene, and
Protests
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Application Type: Temporary variance of license.
b. Project No: 11402-074.
c. Date Filed: March 11, 2013.
d. Applicant: City of Crystal Falls, MI.
e. Name of Project: Crystal Falls Project.
f. Location: The project is located on the Paint River in the City
of Crystal Falls, Iron County, Michigan.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
h. Applicant Contact: Dave Graff, City of Crystal Falls, 401
Superior Avenue, Crystal Falls, Mi 49920, (906) 875-6650.
i. FERC Contact: Rebecca Martin, (202) 502-6012,
Rebecca.martin@ferc.gov.
j. Deadline for filing comments, motions to intervene, and
protests: May 3, 2013.
All documents may be filed electronically via the Internet. See, 18
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web
site at https://www.ferc.gov/docs-filing/efiling.asp. If unable to be
filed electronically, documents may be paper-filed. To paper-file, an
original and seven copies should be mailed to: Secretary, Federal
Energy Regulatory Commission, 888 First Street NE., Washington, DC
20426. Commenters can submit brief comments up to 6,000 characters,
without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and
contact information at the end of your comments. Please include the
project number (P-11402-074) on any comments or motions filed.
k. Description of Application: The City of Crystal Falls is
requesting a variance of articles 401, 402, and 405 of its license. The
City of Crystal Falls intends to complete non-safety related
maintenance at its low hazard hydroelectric dam in the summer of 2013.
In order to complete the project, drawdown of the impoundment would
begin on June 27, 2013 at a rate of 1.0 foot per day for the first four
days then the drawdown rate would switch to 1.5 feet per day until a 20
foot drawdown is reached. The impoundment would be filled as the inflow
allows, while maintaining 150 cubic feet per second outflow. The
reservoir would be filled no later than November 1, 2013. During the
drawdown the City will conduct surveys for stranded mussels and fish.
Additionally, recreational access will be limited to canoes, kayaks,
and small boats during the drawdown.
l. Locations of the Application: A copy of the application is
available for inspection and reproduction at the Commission's Public
Reference Room, located at 888 First Street NE., Room 2A, Washington,
DC 20426, or by calling (202) 502-8371. This filing may also be viewed
on the Commission's Web site at https://www.ferc.gov using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field (P-11402) to access the document. You
may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, call 1-866-
208-3676 or email FERCOnlineSupport@ferc.gov, for TTY, call (202) 502-
8659. A copy is also available for inspection and reproduction at the
address in item (h) above.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Comments, Protests, or Motions to Intervene: Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
comment date for the particular application.
o. Filing and Service of Responsive Documents: Any filing must (1)
bear in all capital letters the title ``COMMENTS'', ``PROTEST'', or
``MOTION TO INTERVENE'' as applicable; (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person protesting or intervening; and (4) otherwise
comply with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, motions to intervene, or protests must set forth their
evidentiary basis and otherwise comply with the requirements of 18 CFR
4.34(b). All comments, motions to intervene, or protests should relate
to project works which are the subject of the amendment application.
Agencies may obtain copies of the application directly from the
applicant. A copy of any protest or motion to intervene must be served
upon each representative of the applicant specified in the particular
application. If an intervener files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency. A copy of all other
filings in reference to this
[[Page 21924]]
application must be accompanied by proof of service on all persons
listed in the service list prepared by the Commission in this
proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
Dated: April 3, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-08595 Filed 4-11-13; 8:45 am]