Pelzer Hydro Company, Inc. Consolidated Hydro Southeast, Inc.; Notice of Intent To File License Application, Filing of Pre-Application Document, and Approving Use of the Traditional Licensing Process, 21931 [2013-08590]

Download as PDF Federal Register / Vol. 78, No. 71 / Friday, April 12, 2013 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project Nos. P–10254–023; P–10253–027] mstockstill on DSK6TPTVN1PROD with NOTICES Pelzer Hydro Company, Inc. Consolidated Hydro Southeast, Inc.; Notice of Intent To File License Application, Filing of Pre-Application Document, and Approving Use of the Traditional Licensing Process a. Type of Filing: Notice of Intent to File License Application and Request to Use the Traditional Licensing Process. b. Project Nos.: P–10254–023, and P– 10253–027. c. Date Filed: November 11, 2012. d. Submitted by: Pelzer Hydro Company, Inc. and Consolidated Hydro Southeast, Inc., both fully owned subsidiaries of Enel Green Power North America, Inc. e. Name of Projects: Upper Pelzer Hydroelectric Project (P–10254) and Lower Pelzer Hydroelectric Project (P– 10253). f. Location: On the Saluda River in Anderson and Greenville counties near the town of Pelzer (P–10254), and the town of Williamston (P–10253), South Carolina. No federal lands are occupied by the project works or located within the project boundary of either project. g. Filed Pursuant to: 18 CFR 5.3 of the Commission’s regulations. h. Potential Applicant Contact: Beth E. Harris, P.E., Southeast Regional Manager, Aquenergy Systems, Inc., 11 Anderson St., Piedmont, SC 29674; email—Beth.Harris@Enel.com. i. FERC Contact: Sean Murphy at (202) 502–6145 or via email at sean.murphy@ferc.gov. j. Pelzer Hydro Company, Inc. and Consolidated Hydro Southeast, Inc., filed their request to use the Traditional Licensing Process/Alternative Licensing Procedures on November 11, 2012. Pelzer Hydro Company, Inc. and Consolidated Hydro Southeast, Inc. provided public notice of its request on February 13, 2013. In a letter dated April 5, 2013, the Director of the Division of Hydropower Licensing approved Pelzer Hydro Company, Inc. and Consolidated Hydro Southeast, Inc.’s request to use the Traditional Licensing Process. k. With this notice, we are initiating informal consultation with: (a) the U.S. Fish and Wildlife Service and/or NOAA Fisheries under section 7 of the Endangered Species Act and the joint agency regulations thereunder at 50 CFR, Part 402; and (b) the South Carolina State Historic Preservation Officer, as required by section 106, VerDate Mar<15>2010 16:47 Apr 11, 2013 Jkt 229001 National Historical Preservation Act, and the implementing regulations of the Advisory Council on Historic Preservation at 36 CFR 800.2. l. With this notice, we are designating Pelzer Hydro Company, Inc. and Consolidated Hydro Southeast, Inc., as the Commission’s non-federal representative for carrying out informal consultation, pursuant to section 7 of the Endangered Species Act and section 106 of the National Historic Preservation Act. m. Pelzer Hydro Company, Inc. and Consolidated Hydro Southeast, Inc., filed a Pre-Application Document (PAD; including a proposed process plan and schedule) with the Commission, pursuant to 18 CFR 5.6 of the Commission’s regulations. n. Copies of the PADs are available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site (https:// www.ferc.gov), using the ‘‘eLibrary’’ link. Enter the docket number, excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCONlineSupport@ferc.gov or toll free at 1–866–208–3676, or for TTY, (202) 502–8659. Copies are also available for inspection and reproduction at the address in paragraph h. o. The licensee states its unequivocal intent to submit an application for a new license for Project No. 10254. The licensee states its unequivocal intent to submit an application for a voluntary new license for Project No. 10253. Pursuant to 18 CFR 16.8, 16.9, and 16.10 each application for a new license and any competing license applications must be filed with the Commission at least 24 months prior to the expiration of the existing license. All applications for license for these projects must be filed by November 30, 2015. p. Register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filing and issuances related to this or other pending projects. For assistance, contact FERC Online Support. Dated: April 5, 2013. Kimberly D. Bose, Secretary. [FR Doc. 2013–08590 Filed 4–11–13; 8:45 am] BILLING CODE 6717–01–P PO 00000 Frm 00027 Fmt 4703 Sfmt 4703 21931 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP13–83–000] Arlington Storage Company, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Seneca Lake Storage Facility Gallery 2 Expansion Project, and Request for Comments on Environmental Issues The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Arlington Storage Company, LLC (Arlington Storage) Seneca Lake Storage Facility Gallery 2 Expansion Project (Project). The expansion would be accomplished through the conversion of two existing interconnected bedded salt caverns (collectively known as ‘‘Gallery 2’’), previously used for liquid propane gas (LPG) storage, to natural gas storage. The Project is located in Schuyler County, New York on the west side of Seneca Lake in the Town of Reading (Figure 1). This EA will be used by the Commission in its decision-making process to determine whether the project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies on the Project. Your input will help the Commission staff determine what issues need to be evaluated in the EA. Please note that the project scoping period will close on May 3, 2013. Further details on how to submit written comments are provided in the Public Participation section of this notice. This notice is being sent to the Commission’s current environmental mailing list for this project as described under the Environmental Mailing List Section of this notice. State and local government representatives are asked to notify their constituents of this proposed project and encourage them to comment on their areas of concern. The Project would be constructed on land owned by Arlington Storage or its affiliate U.S. Salt Corporation, within an area used for salt mining and/or natural gas activities. Project work areas have been previously disturbed through historical solution mining operations for salt production and LPG storage. Development of the caverns at Gallery 2 began in 1958 by the International Salt Company. The gallery caverns were used for brine production until 1964 E:\FR\FM\12APN1.SGM 12APN1

Agencies

[Federal Register Volume 78, Number 71 (Friday, April 12, 2013)]
[Notices]
[Page 21931]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-08590]



[[Page 21931]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project Nos. P-10254-023; P-10253-027]


Pelzer Hydro Company, Inc. Consolidated Hydro Southeast, Inc.; 
Notice of Intent To File License Application, Filing of Pre-Application 
Document, and Approving Use of the Traditional Licensing Process

    a. Type of Filing: Notice of Intent to File License Application and 
Request to Use the Traditional Licensing Process.
    b. Project Nos.: P-10254-023, and P-10253-027.
    c. Date Filed: November 11, 2012.
    d. Submitted by: Pelzer Hydro Company, Inc. and Consolidated Hydro 
Southeast, Inc., both fully owned subsidiaries of Enel Green Power 
North America, Inc.
    e. Name of Projects: Upper Pelzer Hydroelectric Project (P-10254) 
and Lower Pelzer Hydroelectric Project (P-10253).
    f. Location: On the Saluda River in Anderson and Greenville 
counties near the town of Pelzer (P-10254), and the town of Williamston 
(P-10253), South Carolina. No federal lands are occupied by the project 
works or located within the project boundary of either project.
    g. Filed Pursuant to: 18 CFR 5.3 of the Commission's regulations.
    h. Potential Applicant Contact: Beth E. Harris, P.E., Southeast 
Regional Manager, Aquenergy Systems, Inc., 11 Anderson St., Piedmont, 
SC 29674; email_Beth.Harris@Enel.com.
    i. FERC Contact: Sean Murphy at (202) 502-6145 or via email at 
sean.murphy@ferc.gov.
    j. Pelzer Hydro Company, Inc. and Consolidated Hydro Southeast, 
Inc., filed their request to use the Traditional Licensing Process/
Alternative Licensing Procedures on November 11, 2012. Pelzer Hydro 
Company, Inc. and Consolidated Hydro Southeast, Inc. provided public 
notice of its request on February 13, 2013. In a letter dated April 5, 
2013, the Director of the Division of Hydropower Licensing approved 
Pelzer Hydro Company, Inc. and Consolidated Hydro Southeast, Inc.'s 
request to use the Traditional Licensing Process.
    k. With this notice, we are initiating informal consultation with: 
(a) the U.S. Fish and Wildlife Service and/or NOAA Fisheries under 
section 7 of the Endangered Species Act and the joint agency 
regulations thereunder at 50 CFR, Part 402; and (b) the South Carolina 
State Historic Preservation Officer, as required by section 106, 
National Historical Preservation Act, and the implementing regulations 
of the Advisory Council on Historic Preservation at 36 CFR 800.2.
    l. With this notice, we are designating Pelzer Hydro Company, Inc. 
and Consolidated Hydro Southeast, Inc., as the Commission's non-federal 
representative for carrying out informal consultation, pursuant to 
section 7 of the Endangered Species Act and section 106 of the National 
Historic Preservation Act.
    m. Pelzer Hydro Company, Inc. and Consolidated Hydro Southeast, 
Inc., filed a Pre-Application Document (PAD; including a proposed 
process plan and schedule) with the Commission, pursuant to 18 CFR 5.6 
of the Commission's regulations.
    n. Copies of the PADs are available for review at the Commission in 
the Public Reference Room or may be viewed on the Commission's Web site 
(https://www.ferc.gov), using the ``eLibrary'' link. Enter the docket 
number, excluding the last three digits in the docket number field to 
access the document. For assistance, contact FERC Online Support at 
FERCONlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY, 
(202) 502-8659. Copies are also available for inspection and 
reproduction at the address in paragraph h.
    o. The licensee states its unequivocal intent to submit an 
application for a new license for Project No. 10254. The licensee 
states its unequivocal intent to submit an application for a voluntary 
new license for Project No. 10253. Pursuant to 18 CFR 16.8, 16.9, and 
16.10 each application for a new license and any competing license 
applications must be filed with the Commission at least 24 months prior 
to the expiration of the existing license. All applications for license 
for these projects must be filed by November 30, 2015.
    p. Register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filing and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.

    Dated: April 5, 2013.
Kimberly D. Bose,
 Secretary.
[FR Doc. 2013-08590 Filed 4-11-13; 8:45 am]
BILLING CODE 6717-01-P