Pelzer Hydro Company, Inc. Consolidated Hydro Southeast, Inc.; Notice of Intent To File License Application, Filing of Pre-Application Document, and Approving Use of the Traditional Licensing Process, 21931 [2013-08590]
Download as PDF
Federal Register / Vol. 78, No. 71 / Friday, April 12, 2013 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project Nos. P–10254–023; P–10253–027]
mstockstill on DSK6TPTVN1PROD with NOTICES
Pelzer Hydro Company, Inc.
Consolidated Hydro Southeast, Inc.;
Notice of Intent To File License
Application, Filing of Pre-Application
Document, and Approving Use of the
Traditional Licensing Process
a. Type of Filing: Notice of Intent to
File License Application and Request to
Use the Traditional Licensing Process.
b. Project Nos.: P–10254–023, and P–
10253–027.
c. Date Filed: November 11, 2012.
d. Submitted by: Pelzer Hydro
Company, Inc. and Consolidated Hydro
Southeast, Inc., both fully owned
subsidiaries of Enel Green Power North
America, Inc.
e. Name of Projects: Upper Pelzer
Hydroelectric Project (P–10254) and
Lower Pelzer Hydroelectric Project (P–
10253).
f. Location: On the Saluda River in
Anderson and Greenville counties near
the town of Pelzer (P–10254), and the
town of Williamston (P–10253), South
Carolina. No federal lands are occupied
by the project works or located within
the project boundary of either project.
g. Filed Pursuant to: 18 CFR 5.3 of the
Commission’s regulations.
h. Potential Applicant Contact: Beth
E. Harris, P.E., Southeast Regional
Manager, Aquenergy Systems, Inc., 11
Anderson St., Piedmont, SC 29674;
email—Beth.Harris@Enel.com.
i. FERC Contact: Sean Murphy at
(202) 502–6145 or via email at
sean.murphy@ferc.gov.
j. Pelzer Hydro Company, Inc. and
Consolidated Hydro Southeast, Inc.,
filed their request to use the Traditional
Licensing Process/Alternative Licensing
Procedures on November 11, 2012.
Pelzer Hydro Company, Inc. and
Consolidated Hydro Southeast, Inc.
provided public notice of its request on
February 13, 2013. In a letter dated
April 5, 2013, the Director of the
Division of Hydropower Licensing
approved Pelzer Hydro Company, Inc.
and Consolidated Hydro Southeast,
Inc.’s request to use the Traditional
Licensing Process.
k. With this notice, we are initiating
informal consultation with: (a) the U.S.
Fish and Wildlife Service and/or NOAA
Fisheries under section 7 of the
Endangered Species Act and the joint
agency regulations thereunder at 50
CFR, Part 402; and (b) the South
Carolina State Historic Preservation
Officer, as required by section 106,
VerDate Mar<15>2010
16:47 Apr 11, 2013
Jkt 229001
National Historical Preservation Act,
and the implementing regulations of the
Advisory Council on Historic
Preservation at 36 CFR 800.2.
l. With this notice, we are designating
Pelzer Hydro Company, Inc. and
Consolidated Hydro Southeast, Inc., as
the Commission’s non-federal
representative for carrying out informal
consultation, pursuant to section 7 of
the Endangered Species Act and section
106 of the National Historic
Preservation Act.
m. Pelzer Hydro Company, Inc. and
Consolidated Hydro Southeast, Inc.,
filed a Pre-Application Document (PAD;
including a proposed process plan and
schedule) with the Commission,
pursuant to 18 CFR 5.6 of the
Commission’s regulations.
n. Copies of the PADs are available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site (https://
www.ferc.gov), using the ‘‘eLibrary’’
link. Enter the docket number,
excluding the last three digits in the
docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCONlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. Copies are also
available for inspection and
reproduction at the address in
paragraph h.
o. The licensee states its unequivocal
intent to submit an application for a
new license for Project No. 10254. The
licensee states its unequivocal intent to
submit an application for a voluntary
new license for Project No. 10253.
Pursuant to 18 CFR 16.8, 16.9, and 16.10
each application for a new license and
any competing license applications
must be filed with the Commission at
least 24 months prior to the expiration
of the existing license. All applications
for license for these projects must be
filed by November 30, 2015.
p. Register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filing and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
Dated: April 5, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–08590 Filed 4–11–13; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
21931
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP13–83–000]
Arlington Storage Company, LLC;
Notice of Intent To Prepare an
Environmental Assessment for the
Proposed Seneca Lake Storage Facility
Gallery 2 Expansion Project, and
Request for Comments on
Environmental Issues
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Arlington Storage Company, LLC
(Arlington Storage) Seneca Lake Storage
Facility Gallery 2 Expansion Project
(Project). The expansion would be
accomplished through the conversion of
two existing interconnected bedded salt
caverns (collectively known as ‘‘Gallery
2’’), previously used for liquid propane
gas (LPG) storage, to natural gas storage.
The Project is located in Schuyler
County, New York on the west side of
Seneca Lake in the Town of Reading
(Figure 1). This EA will be used by the
Commission in its decision-making
process to determine whether the
project is in the public convenience and
necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the Project.
Your input will help the Commission
staff determine what issues need to be
evaluated in the EA. Please note that the
project scoping period will close on
May 3, 2013. Further details on how to
submit written comments are provided
in the Public Participation section of
this notice.
This notice is being sent to the
Commission’s current environmental
mailing list for this project as described
under the Environmental Mailing List
Section of this notice. State and local
government representatives are asked to
notify their constituents of this
proposed project and encourage them to
comment on their areas of concern.
The Project would be constructed on
land owned by Arlington Storage or its
affiliate U.S. Salt Corporation, within an
area used for salt mining and/or natural
gas activities. Project work areas have
been previously disturbed through
historical solution mining operations for
salt production and LPG storage.
Development of the caverns at Gallery 2
began in 1958 by the International Salt
Company. The gallery caverns were
used for brine production until 1964
E:\FR\FM\12APN1.SGM
12APN1
Agencies
[Federal Register Volume 78, Number 71 (Friday, April 12, 2013)]
[Notices]
[Page 21931]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-08590]
[[Page 21931]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project Nos. P-10254-023; P-10253-027]
Pelzer Hydro Company, Inc. Consolidated Hydro Southeast, Inc.;
Notice of Intent To File License Application, Filing of Pre-Application
Document, and Approving Use of the Traditional Licensing Process
a. Type of Filing: Notice of Intent to File License Application and
Request to Use the Traditional Licensing Process.
b. Project Nos.: P-10254-023, and P-10253-027.
c. Date Filed: November 11, 2012.
d. Submitted by: Pelzer Hydro Company, Inc. and Consolidated Hydro
Southeast, Inc., both fully owned subsidiaries of Enel Green Power
North America, Inc.
e. Name of Projects: Upper Pelzer Hydroelectric Project (P-10254)
and Lower Pelzer Hydroelectric Project (P-10253).
f. Location: On the Saluda River in Anderson and Greenville
counties near the town of Pelzer (P-10254), and the town of Williamston
(P-10253), South Carolina. No federal lands are occupied by the project
works or located within the project boundary of either project.
g. Filed Pursuant to: 18 CFR 5.3 of the Commission's regulations.
h. Potential Applicant Contact: Beth E. Harris, P.E., Southeast
Regional Manager, Aquenergy Systems, Inc., 11 Anderson St., Piedmont,
SC 29674; email_Beth.Harris@Enel.com.
i. FERC Contact: Sean Murphy at (202) 502-6145 or via email at
sean.murphy@ferc.gov.
j. Pelzer Hydro Company, Inc. and Consolidated Hydro Southeast,
Inc., filed their request to use the Traditional Licensing Process/
Alternative Licensing Procedures on November 11, 2012. Pelzer Hydro
Company, Inc. and Consolidated Hydro Southeast, Inc. provided public
notice of its request on February 13, 2013. In a letter dated April 5,
2013, the Director of the Division of Hydropower Licensing approved
Pelzer Hydro Company, Inc. and Consolidated Hydro Southeast, Inc.'s
request to use the Traditional Licensing Process.
k. With this notice, we are initiating informal consultation with:
(a) the U.S. Fish and Wildlife Service and/or NOAA Fisheries under
section 7 of the Endangered Species Act and the joint agency
regulations thereunder at 50 CFR, Part 402; and (b) the South Carolina
State Historic Preservation Officer, as required by section 106,
National Historical Preservation Act, and the implementing regulations
of the Advisory Council on Historic Preservation at 36 CFR 800.2.
l. With this notice, we are designating Pelzer Hydro Company, Inc.
and Consolidated Hydro Southeast, Inc., as the Commission's non-federal
representative for carrying out informal consultation, pursuant to
section 7 of the Endangered Species Act and section 106 of the National
Historic Preservation Act.
m. Pelzer Hydro Company, Inc. and Consolidated Hydro Southeast,
Inc., filed a Pre-Application Document (PAD; including a proposed
process plan and schedule) with the Commission, pursuant to 18 CFR 5.6
of the Commission's regulations.
n. Copies of the PADs are available for review at the Commission in
the Public Reference Room or may be viewed on the Commission's Web site
(https://www.ferc.gov), using the ``eLibrary'' link. Enter the docket
number, excluding the last three digits in the docket number field to
access the document. For assistance, contact FERC Online Support at
FERCONlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY,
(202) 502-8659. Copies are also available for inspection and
reproduction at the address in paragraph h.
o. The licensee states its unequivocal intent to submit an
application for a new license for Project No. 10254. The licensee
states its unequivocal intent to submit an application for a voluntary
new license for Project No. 10253. Pursuant to 18 CFR 16.8, 16.9, and
16.10 each application for a new license and any competing license
applications must be filed with the Commission at least 24 months prior
to the expiration of the existing license. All applications for license
for these projects must be filed by November 30, 2015.
p. Register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filing and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
Dated: April 5, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-08590 Filed 4-11-13; 8:45 am]