Download as PDF Federal Register / Vol. 78, No. 53 / Tuesday, March 19, 2013 / Notices who are to respond, including the use of automated collection techniques or other forms of information technology. Dated: March 12, 2013. Kimberly D. Bose, Secretary. [FR Doc. 2013–06201 Filed 3–18–13; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP13–92–000] tkelley on DSK3SPTVN1PROD with NOTICES Gulf South Pipeline Company, LP; Notice of Application Take notice that on March 1, 2013, Gulf South Pipeline Company, LP (Gulf South), filed in Docket No. CP13–92– 000, an application pursuant to section 7(b) of the Natural Gas Act (NGA) and Part 157 of the Commission’s regulations, requesting authorization to abandon by sale to an affiliated company, Boardwalk Mississippi Intrastate Pipeline Company, LLC, approximately 511 miles of low/lowerpressure pipeline, consisting of 479 miles of transmission pipeline and 32 miles of gathering pipeline, associated meters, and appurtenant and auxiliary facilities located in Mississippi, all as more fully set forth in the application which is on file with the Commission and open to public inspection. This filing may also be viewed on the Commission’s Web site at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number, excluding the last three digits, in the docket number field to access the document. For assistance, call (866) 208–3676 or TTY, (202) 502–8659. Any questions regarding this application should be directed to Mr. J. Kyle Stephens, Vice-President, Regulatory Affairs, Gulf South Pipeline Company, LP, 9 Greenway Plaza, Suite 2800, Houston, Texas, 77046, or by calling (713) 479–8033 (telephone) or (713) 479–1846 (fax) Kyle.Stephens@bwpmlp.com. Pursuant to Section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding, or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final VerDate Mar<15>2010 17:00 Mar 18, 2013 Jkt 229001 environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below, file with the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 14 copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenters will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commenters will not be PO 00000 Frm 00016 Fmt 4703 Sfmt 4703 16845 required to serve copies of filed documents on all other parties. However, the non-party commenters will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy regulatory Commission, 888 First Street NE., Washington, DC 20426. Comment Date: April 2, 2013. Dated: March 12, 2013. Kimberly D. Bose, Secretary. [FR Doc. 2013–06204 Filed 3–18–13; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP13–87–000] Equitrans, L.P.; Equitable Gas Company, LLC; Notice of Application Take notice that on March 1, 2013, Equitrans, L.P. (Equitrans), 625 Liberty Avenue, Suite 1700, Pittsburgh, Pennsylvania 15222, and Equitable Gas Company, LLC (EGC), 225 North Shore Drive, Pittsburgh, Pennsylvania 15212, jointly filed in Docket No. CP13–87–000 an application pursuant to section 7(b) of the Natural Gas Act (NGA) requesting that the Commission grants approval to abandon, by transfer from Equitrans to EGC, a pipeline lateral designated as the H–153 Line and all equipment and associated appurtenances. Also, EGC requests that the Commission determines that, upon abandonment, the H–153 Line will provide local distribution service exempt from the Commission’s jurisdiction, all as more fully set forth in the application which is on file with the Commission and open to public inspection. The filing may also be viewed on the Web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll E:\FR\FM\19MRN1.SGM 19MRN1 tkelley on DSK3SPTVN1PROD with NOTICES 16846 Federal Register / Vol. 78, No. 53 / Tuesday, March 19, 2013 / Notices free at (866) 208–3676, or TTY, contact (202) 502–8659. Any questions concerning this application may be directed to Paul W. Diehl, Senior Counsel-Midstream, EQT Corporation, 625 Liberty Avenue, Suite 1700, Pittsburgh, Pennsylvania 15222 at (412) 395–540 or by email at PDiehl@eqt.com. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below, file with the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit original and 7 copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in VerDate Mar<15>2010 17:00 Mar 18, 2013 Jkt 229001 determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https:// www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment date: 5:00 p.m. Eastern Time on April 2, 2013. Dated: March 12, 2013. Kimberly D. Bose, Secretary. [FR Doc. 2013–06205 Filed 3–18–13; 8:45 am] BILLING CODE 6717–01–P PO 00000 Frm 00017 Fmt 4703 Sfmt 4703 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP13–88–000] Notice of Application; Equitrans, L.P. Take notice that on March 1, 2013, Equitrans, L.P. (Equitrans), 625 Liberty Avenue, Suite 1700, Pittsburgh, Pennsylvania 15222, filed in Docket No. CP13–88–000 an application pursuant to section 7(b) of the Natural Gas Act (NGA) requesting the Commission authorize the abandonment, by transfer from Equitrans to Equitable Gas Company, LLC (EQC), of certain gathering facilities. Specifically, the gathering facilities consists of six pipeline laterals (M–23, M–25, M–30, M–31, M–32, and M–71), all as more fully set forth in the application which is on file with the Commission and open to public inspection. The filing may also be viewed on the web at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at (866) 208–3676, or TTY, contact (202) 502–8659. Any questions concerning this application may be directed to Paul W. Diehl, Senior Counsel-Midstream, EQT Corporation, 625 Liberty Avenue, Suite 1700, Pittsburgh, Pennsylvania 15222 at (412)-395–540 or by email at PDiehl@eqt.com. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. There are two ways to become involved in the Commission’s review of E:\FR\FM\19MRN1.SGM 19MRN1

Agencies

[Federal Register Volume 78, Number 53 (Tuesday, March 19, 2013)]
[Notices]
[Pages 16845-16846]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-06205]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP13-87-000]


Equitrans, L.P.; Equitable Gas Company, LLC; Notice of 
Application

    Take notice that on March 1, 2013, Equitrans, L.P. (Equitrans), 625 
Liberty Avenue, Suite 1700, Pittsburgh, Pennsylvania 15222, and 
Equitable Gas Company, LLC (EGC), 225 North Shore Drive, Pittsburgh, 
Pennsylvania 15212, jointly filed in Docket No. CP13-87-000 an 
application pursuant to section 7(b) of the Natural Gas Act (NGA) 
requesting that the Commission grants approval to abandon, by transfer 
from Equitrans to EGC, a pipeline lateral designated as the H-153 Line 
and all equipment and associated appurtenances. Also, EGC requests that 
the Commission determines that, upon abandonment, the H-153 Line will 
provide local distribution service exempt from the Commission's 
jurisdiction, all as more fully set forth in the application which is 
on file with the Commission and open to public inspection. The filing 
may also be viewed on the Web at https://www.ferc.gov using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. For 
assistance, please contact FERC Online Support at 
FERCOnlineSupport@ferc.gov or toll

[[Page 16846]]

free at (866) 208-3676, or TTY, contact (202) 502-8659.
    Any questions concerning this application may be directed to Paul 
W. Diehl, Senior Counsel-Midstream, EQT Corporation, 625 Liberty 
Avenue, Suite 1700, Pittsburgh, Pennsylvania 15222 at (412) 395-540 or 
by email at PDiehl@eqt.com.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either complete 
its environmental assessment (EA) and place it into the Commission's 
public record (eLibrary) for this proceeding; or issue a Notice of 
Schedule for Environmental Review. If a Notice of Schedule for 
Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below, file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit original and 7 copies of filings made with the Commission and 
must mail a copy to the applicant and to every other party in the 
proceeding. Only parties to the proceeding can ask for court review of 
Commission orders in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commentors will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentors will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at https://www.ferc.gov. Persons unable to file electronically should 
submit an original and 14 copies of the protest or intervention to the 
Federal Energy Regulatory Commission, 888 First Street NE., Washington, 
DC 20426.
    This filing is accessible on-line at https://www.ferc.gov, using the 
``eLibrary'' link and is available for review in the Commission's 
Public Reference Room in Washington, DC. There is an ``eSubscription'' 
link on the Web site that enables subscribers to receive email 
notification when a document is added to a subscribed docket(s). For 
assistance with any FERC Online service, please email 
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For 
TTY, call (202) 502-8659.
    Comment date: 5:00 p.m. Eastern Time on April 2, 2013.

    Dated: March 12, 2013.
Kimberly D. Bose,
Secretary.