Public Service Company of Colorado; Notice Revising Precedural Schedule, 16496-16497 [2013-05944]
Download as PDF
16496
Federal Register / Vol. 78, No. 51 / Friday, March 15, 2013 / Notices
have an average annual generation of
approximately 764,000 kilowatt-hours.
Applicant Contact: James World, 55
Main Street, Lancaster, NH 03584;
phone: (802) 376–7677.
FERC Contact: Brandon Cherry;
phone: (202) 502–8328.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36. Comments, motions to
intervene, notices of intent, and
competing applications may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–13643) in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
Dated: March 8, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–05945 Filed 3–14–13; 8:45 am]
srobinson on DSK4SPTVN1PROD with NOTICES
BILLING CODE 6717–01–P
VerDate Mar<14>2013
17:37 Mar 14, 2013
Jkt 229001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 14443–000]
Consolidated Irrigation Company;
Notice of Preliminary Permit
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Competing Applications
On July 30, 2011, the Consolidated
Irrigation Company of Preston, Idaho,
filed an application for a preliminary
permit, pursuant to section 4(f) of the
Federal Power Act (FPA), proposing to
study the feasibility of the Consolidated
Irrigation Glendale Conduit Hydro
Project (Glendale Conduit Project or
project) to be located on Mink and Cub
Creeks, near Preston, in Franklin
County, Idaho. The project would not
occupy any Federal lands. The sole
purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land-disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
The proposed project would consist of
the following: (1) An existing screened
intake on Mink Creek; (2) an existing
screened intake on Cub Creek; (3) a new
pipeline and penstock consisting of
8,520 feet of 24-inch-diameter, highdensity polyethylene (HDPE) pipe,
4,340 feet of 30-inch-diameter HDPE
pipe, and 4,060 feet of 36-inch-diameter
HDPE pipe; (4) a powerhouse containing
a 500-kilowatt turbine-generator; (5) a
1,700-foot-long, underground 12kilovolt transmission cable connecting
to an existing transmission line owned
by Rocky Mountain Power; and (6)
appurtenant facilities. The estimated
annual generation of the Glendale
Conduit Project would be 2,526
megawatt-hours.
Applicant Contact: Mr. Lyle Porter,
President, Consolidated Irrigation
Company, 33 South 1st East, Preston, ID
83263; phone: (208) 852–2364.
FERC Contact: Joseph Hassell; phone:
(202) 502–8079.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36. Comments, motions to
intervene, notices of intent, and
competing applications may be filed
electronically via the Internet. See 18
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street
NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–14443) in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
Dated: March 7, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–05952 Filed 3–14–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2351–017]
Public Service Company of Colorado;
Notice Revising Precedural Schedule
On January 25, 2013, the Commission
issued a public Notice of Application
Accepted for Filing, Soliciting Motions
to Intervene and Protests, Ready for
Environmental Analysis, and Soliciting
Comments, Recommendations,
Preliminary Terms and Conditions, and
Preliminary Fishway Prescriptions for
the relicensing of the Public Service
Company of Colorado’s Cabin Creek
Pumped Storage Project No. 2351,
located on the South Clear Creek and its
tributary Cabin Creek in Clear Creek
County, Colorado. The project, as
currently licensed, is located on 267
acres of U.S. Forest Service lands within
the Arapahoe National Forest.
The procedural schedule published in
the prior notice has been revised due to
an error. The application will be
processed according to the following
E:\FR\FM\15MRN1.SGM
15MRN1
16497
Federal Register / Vol. 78, No. 51 / Friday, March 15, 2013 / Notices
revised Hydro Licensing Schedule.
Revisions to the schedule may be made
as appropriate.
Milestone
Ready for Environmental Analysis and
Application Acceptance.
Comments, Interventions, recommendations, prescriptions
due.
Requests 401 Certification.
Reply Comments due
Issue single EA .........
Comments on EA due
Modified 4(e) and
Fishway Prescriptions.
Target date
Friday, January 25,
2013.
Tuesday, March 26,
2013.
Tuesday, March 26,
2013.
Friday, May 10,
2013.
Wednesday, July 24,
2013.
Friday, August 23,
2013.
Tuesday, October 22,
2013.
Dated: March 7, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–05944 Filed 3–14–13; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP13–81–000]
srobinson on DSK4SPTVN1PROD with NOTICES
Columbia Gas Transmission, LLC;
Notice of Request Under Blanket
Authorization
Take notice that on February 21, 2013,
Columbia Gas Transmission, LLC
(Columbia Gas), 5151 San Felipe, Suite
2500, Houston, Texas 77056, filed in
Docket No. CP13–81–000, a prior notice
request pursuant to sections 157.205,
157.210, and 157.216(b) of the
Commission’s regulations under the
Natural Gas Act (NGA), seeking
authorization to abandon and construct
compressor units at its Rockport
Compressor Station in Wood County,
West Virginia, all as more fully set forth
in the application which is on file with
the Commission and open for public
inspection.
Specifically, Columbia Gas proposes
to abandon three 1,000 horsepower (hp)
compressor units and replace them with
two 1,775 hp compressor units at its
Rockport Compressor Station as part of
its modernization project. Each new
unit will be derated to produce 1,686 hp
of compression. The estimated cost of
the proposed facilities is $22,000,000.
Any questions regarding the
applications should be directed to
Fredric J. George, Senior Counsel,
VerDate Mar<14>2013
19:07 Mar 14, 2013
Jkt 229001
Columbia Gas Transmission, LLC, P.O.
Box 1273, Charleston, West Virginia
25325–1273, phone (304) 357–2359, fax
(304) 357–3206.
Any person may, within 60 days after
the issuance of the instant notice by the
Commission, file pursuant to Rule 214
of the Commission’s Procedural Rules
(18 CFR 385.214) a motion to intervene
or notice of intervention. Any person
filing to intervene or the Commission’s
staff may, pursuant to section 157.205 of
the Commission’s Regulations under the
NGA (18 CFR 157.205) file a protest to
the request. If no protest is filed within
the time allowed therefore, the proposed
activity shall be deemed to be
authorized effective the day after the
time allowed for protest. If a protest is
filed and not withdrawn within 30 days
after the time allowed for filing a
protest, the instant request shall be
treated as an application for
authorization pursuant to section 7 of
the NGA.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commenter’s will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commenter’s will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentary,
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests,
and interventions via the internet in lieu
of paper. See 18 CFR 385.2001(a)(1)(iii)
and the instructions on the
Commission’s Web site (www.ferc.gov)
under the ‘‘e-Filing’’ link. Persons
unable to file electronically should
submit an original and 14 copies of the
protest or intervention to the Federal
Energy regulatory Commission, 888
First Street NE., Washington, DC 20426.
Dated: March 7, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013–05943 Filed 3–14–13; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00035
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of FERC Staff Attendance
Docket No.
PacifiCorp .....................
Deseret Generation &
Transmission Cooperative, Inc.
Northwestern Corporation (Montana).
Portland General Electric Company.
Idaho Power Company
Public Service Company
of Colorado.
Terra-Gen Dixie Valley,
LLC.
Tucson Electric Power
Company.
UNS Electric, Inc ...........
Public Service Company
of New Mexico.
Arizona Public Service
Company.
El Paso Electric Company.
Black Hills Power, Inc.,
et al.
Black Hills Colorado
Electric Utility Company.
NV Energy, Inc .............
Cheyenne Light, Fuel
and Power Company.
Avista Corporation ........
Avista Corporation ........
Puget Sound Energy ....
Puget Sound Energy ....
Bonneville Power Administration.
California Independent
System Operator Corporation.
ER13–64–000
ER13–65–000
ER13–67–000
ER13–68–000
ER13–127–000
ER13–75–000
ER13–76–000
ER13–77–000
ER13–78–000
ER13–79–000
ER13–82–000
ER13–91–000
ER13–96–000
ER13–97–000
ER13–105–000
ER13–120–000
ER13–93–000
ER13–94–000
ER13–98–000
ER13–99–000
NJ13–1–000
ER13–103–000
The Federal Energy Regulatory
Commission (Commission) hereby gives
notice that on March 11, 2013, members
of its staff will attend a conference call
conducted by representatives of
California Independent System Operator
Corporation, ColumbiaGrid, Northern
Tier Transmission Group, and
WestConnect regarding the interregional
coordination requirements established
by Order No. 1000. The agenda and
other documents for the meeting are
available at https://
www.columbiagrid.org/O1000Interdocuments.cfm.
The meeting is open to all
stakeholders and Commission staff’s
attendance is part of the Commission’s
ongoing outreach efforts. The meeting
may discuss matters at issue in the
above captioned dockets.
For further information, contact Saeed
Farrokhpay at
saeed.farrokhpay@ferc.gov.
E:\FR\FM\15MRN1.SGM
15MRN1
Agencies
[Federal Register Volume 78, Number 51 (Friday, March 15, 2013)]
[Notices]
[Pages 16496-16497]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-05944]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2351-017]
Public Service Company of Colorado; Notice Revising Precedural
Schedule
On January 25, 2013, the Commission issued a public Notice of
Application Accepted for Filing, Soliciting Motions to Intervene and
Protests, Ready for Environmental Analysis, and Soliciting Comments,
Recommendations, Preliminary Terms and Conditions, and Preliminary
Fishway Prescriptions for the relicensing of the Public Service Company
of Colorado's Cabin Creek Pumped Storage Project No. 2351, located on
the South Clear Creek and its tributary Cabin Creek in Clear Creek
County, Colorado. The project, as currently licensed, is located on 267
acres of U.S. Forest Service lands within the Arapahoe National Forest.
The procedural schedule published in the prior notice has been
revised due to an error. The application will be processed according to
the following
[[Page 16497]]
revised Hydro Licensing Schedule. Revisions to the schedule may be made
as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Ready for Environmental Analysis and Friday, January 25, 2013.
Application Acceptance.
Comments, Interventions, recommendations, Tuesday, March 26, 2013.
prescriptions due.
Requests 401 Certification................ Tuesday, March 26, 2013.
Reply Comments due........................ Friday, May 10, 2013.
Issue single EA........................... Wednesday, July 24, 2013.
Comments on EA due........................ Friday, August 23, 2013.
Modified 4(e) and Fishway Prescriptions... Tuesday, October 22, 2013.
------------------------------------------------------------------------
Dated: March 7, 2013.
Kimberly D. Bose,
Secretary.
[FR Doc. 2013-05944 Filed 3-14-13; 8:45 am]