Proposed Revision to Design of Structures, Components, Equipment and Systems, 13911-13912 [2013-04514]
Download as PDF
Federal Register / Vol. 78, No. 41 / Friday, March 1, 2013 / Notices
Ms.
Amy E. Cubbage, Office of New
Reactors, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001; telephone: 301–415–2875, email:
Amy.Cubbage@nrc.gov.
SUPPLEMENTARY INFORMATION:
FOR FURTHER INFORMATION CONTACT:
NUCLEAR REGULATORY
COMMISSION
[NRC–2013–0041]
Proposed Revision to Design of
Structures, Components, Equipment
and Systems
I. Accessing Information and
Submitting Comments
Nuclear Regulatory
Commission.
ACTION: Standard review plan-draft
section revision; request for comment
and use.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC) is revising the
following sections in Chapter 3, ‘‘Design
of Structures, Components, Equipment,
and Systems’’ and is soliciting public
comment on NUREG–0800, ‘‘Standard
Review Plan for the Review of Safety
Analysis Reports for Nuclear Power
Plants: LWR Edition,’’ Section 3.7.1,
‘‘Seismic Design Parameters,’’ Section
3.7.2, ‘‘Seismic System Analysis,’’
Section 3.7.3, ‘‘Seismic Subsystem
Analysis,’’ Section 3.8.1, ‘‘Concrete
Containment,’’ Section 3.8.3, ‘‘Concrete
And Steel Internal Structures of Steel Or
Concrete Containments, ‘‘Section 3.8.4,
‘‘Other Seismic Category I Structures,’’
and Section 3.8.5, ‘‘Foundations.’’
DATES: Submit comments by April 1,
2013. Comments received after this date
will be considered, if it is practical to do
so, but the Commission is able to ensure
consideration only for comments
received on or before this date.
ADDRESSES: You may access information
and comment submissions related to
this document, which the NRC
possesses and are publically available,
by searching on https://
www.regulations.gov under Docket ID
NRC–2013–0041. You may submit
comments by any of the following
methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2013–0041. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–492–3668;
email: Carol.Gallagher@nrc.gov.
• Mail comments to: Cindy Bladey,
Chief, Rules, Announcements, and
Directives Branch (RADB), Office of
Administration, Mail Stop: TWB–05–
B01M, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001.
• Fax comments to: RADB at 301–
492–3446.
For additional direction on accessing
information and submitting comments,
see ‘‘Accessing Information and
Submitting Comments’’ in the
SUPPLEMENTARY INFORMATION section of
this document.
mstockstill on DSK4VPTVN1PROD with NOTICES
SUMMARY:
VerDate Mar<15>2010
16:40 Feb 28, 2013
Jkt 229001
A. Accessing Information
Please refer to Docket ID NRC–2013–
0041 when contacting the NRC about
the availability of information regarding
this document. You may access
information related to this document,
which the NRC possesses and are
publicly available, by any of the
following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2013–0041.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may access publicly
available documents online in the NRC
Library at https://www.nrc.gov/readingrm/adams.html. To begin the search,
select ‘‘ADAMS Public Documents’’ and
then select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS Accession numbers for redline
documents comparing current revisions
and the proposed revisions of
individual sections are available in
ADAMS under Accession Nos.: Section
3.7.1, Proposed Revision 4
(ML12352A305), Current Revision 3
(ML070640306), Redline
(ML12354A050); Section 3.7.2,
Proposed Revision 4 (ML12353A354)
Current Revision 3 (ML070640311),
Redline (ML12354A053); Section 3.7.3,
Proposed Revision 4 (ML12353A357),
Current Revision 3 (ML070640313),
Redline (ML12354A043); Section 3.8.1,
Proposed Revision 4 (ML12353A365),
Current Revision 3 (ML100620888),
Redline (ML12354A052); Section 3.8.3,
Proposed Revision 4
(MLML12353A377), Current Revision 3
(ML100620981), Redline
(ML12354A089); and Section 3.8.4,
Proposed Revision 4 (ML12353A382),
Current Revision 3 (ML100630323),
Redline (ML12354A092); Section 3.8.5,
Proposed Revision 4 (ML12353A388),
Current Revision 3 (ML100621093),
Redline (ML12354A096).
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
PO 00000
Frm 00057
Fmt 4703
Sfmt 4703
13911
B. Submitting Comments
Please include Docket ID NRC–2013–
0041 in the subject line of your
comment submission, in order to ensure
that the NRC is able to make your
comment submission available to the
public in this docket.
The NRC cautions you not to include
identifying or contact information in
comment submissions that you do not
want to be publicly disclosed. The NRC
posts all comment submissions at
https://www.regulations.gov as well as
enters the comment submissions into
ADAMS. The NRC does not routinely
edit comment submissions to remove
identifying or contact information.
If you are requesting or aggregating
comments from other persons for
submission to the NRC, then you should
inform those persons not to include
identifying or contact information in
their comment submissions that they do
not want to be publicly disclosed. Your
request should state that the NRC does
not routinely edit comment submissions
to remove such information before
making the comment submissions
available to the public or entering the
comment submissions into ADAMS.
II. Further Information
The Office of New Reactors and Office
of Nuclear Reactor Regulation are
revising these sections from the current
versions. In respect of these revisions,
details of specific changes are included
in the end of each of the revised
sections themselves and are shown in
the description of changes.
The changes to this Standard Review
Plan (SRP) Chapter reflect current staff
review methods and practices based on
lessons learned from NRC reviews of
design certification and combined
license applications completed since the
last revision of this chapter. Changes
include: (1) Enhancements to guidance
to the staff for evaluating the
acceptability of the seismic and civil
structural design and analysis issues, (2)
updates to review interfaces to improve
the efficiency and consistency of staff
reviews and (3) updates to references
covered in SRP Chapter 3.
The NRC staff is issuing this notice to
solicit public comments on the
proposed SRP Sections in Chapter 3.
After the NRC staff considers any public
comments, it will make a determination
regarding the proposed SRP Sections in
Chapter 3.
Dated at Rockville, Maryland, this 14th day
of February 2012.
For the Nuclear Regulatory Commission.
Amy E. Cubbage,
E:\FR\FM\01MRN1.SGM
01MRN1
13912
Federal Register / Vol. 78, No. 41 / Friday, March 1, 2013 / Notices
Chief, Policy Branch, Division of Advanced
Reactors and Rulemaking, Office of New
Reactors.
OFFICE ............
NAME ..............
DATE ...............
OFFICE ............
NAME ..............
DATE ...............
OFFICE ............
NAME ..............
DATE ...............
ADAMS Accession No.: ML12352A297—*Concurrence via email—ADM–012.
PM:NRO/DARR/
LA:NRO/DARR/
PM:NRO/DE/SEB1 ..... BC:NRO/DE:SEB ........
NRGA*.
APOB*.
RSubbaratnam ............ BAbeywickrama ......... J Xu ............................. BThomas .....................
12/27/2013 ................. 12/21/2012 ................. 1/7/2013 ..................... 1/7/2013 .....................
PM:NRR/DE/EMCB .... BC:NRR/DE/EMCB ..... PM?DPR/NRR ............. D:NRR/DE ...................
ATsirigotis .................. MMurphy ................... K.Lenning ................... PHiland .......................
1/18/2013 ................... 1/22/2013 ................... 1/24/2013 ................... 1/23/2013 ...................
OGC/NLO ................... BC:NRO/DARR/APOB.
S. Kirkwood ............... ACubbage.
2/11/2013 ................... 02/14/2013.
DD:NRO/DE
MSuhaibi
1/10/2013
DPS/OIS
TDonnel
2/13/2013
OFFICIAL RECORDS COPY
Distribution:
PUBLIC .............................................................
APOB R/F .........................................................
RSubbaratnam ..................................................
ACubbage .........................................................
BThomas ...........................................................
TDonnel.
BAbeywickrama ...............................................
JXu ....................................................................
RidsNroDarr .....................................................
RidsNrrDe .........................................................
JXu ....................................................................
RidsNroDsarRpac
RidsNrrDpr
RidsNroDarrApob
RidsOgcMailCenter
MSuhaibi
[FR Doc. 2013–04514 Filed 2–28–13; 8:45 am]
OPIC’s Corporate Secretary no later than
5 p.m. Friday, March 8, 2013. Such
statement must be typewritten, doublespaced, and may not exceed twenty-five
(25) pages.
Upon receipt of the required notice,
OPIC will prepare an agenda, which
will be available at the hearing, that
identifies speakers, the subject on which
each participant will speak, and the
time allotted for each presentation.
A written summary of the hearing will
be compiled, and such summary will be
made available, upon written request to
OPIC’s Corporate Secretary, at the cost
of reproduction.
Written summaries of the projects to
be presented at the March 21, 2013
Board meeting will be posted on OPIC’s
Web site on or about Friday, March 1,
2013.
CONTACT PERSON FOR INFORMATION:
Information on the hearing may be
obtained from Connie M. Downs at (202)
336–8438, via facsimile at (202) 408–
0297, or via email at
Connie.Downs@opic.gov.
in the Federal Register (Volume 78,
Number 17, Page 5516) on January 25,
2013. No requests were received to
provide testimony or submit written
statements for the record; therefore,
OPIC’s Annual Public Hearing
scheduled for 2 p.m., March 13, 2013
has been cancelled.
CONTACT PERSON FOR INFORMATION:
Information on the hearing cancellation
may be obtained from Connie M. Downs
at (202) 336–8438, via facsimile at (202)
218–0136, or via email at
Connie.Downs@opic.gov.
BILLING CODE 7590–01–P
OVERSEAS PRIVATE INVESTMENT
CORPORATION
Sunshine Act; Cancellation Notice of
Annual Public Hearing
3:00 p.m., Wednesday,
March 13, 2013.
PLACE: Offices of the Corporation,
Twelfth Floor Board Room, 1100 New
York Avenue NW., Washington, DC.
STATUS: Hearing OPEN to the Public at
3:00 p.m.
PURPOSE: Public Hearing in conjunction
with each meeting of OPIC’s Board of
Directors, to afford an opportunity for
any person to present views regarding
the activities of the Corporation.
PROCEDURES:
Individuals wishing to address the
hearing orally must provide advance
notice to OPIC’s Corporate Secretary no
later than 5 p.m. Friday, March 8, 2013.
The notice must include the
individual’s name, title, organization,
address, and telephone number, and a
concise summary of the subject matter
to be presented.
Oral presentations may not exceed ten
(10) minutes. The time for individual
presentations may be reduced
proportionately, if necessary, to afford
all participants who have submitted a
timely request an opportunity to be
heard.
Participants wishing to submit a
written statement for the record must
submit a copy of such statement to
mstockstill on DSK4VPTVN1PROD with NOTICES
TIME AND DATE:
VerDate Mar<15>2010
16:40 Feb 28, 2013
Jkt 229001
Dated: February 26, 2013.
Connie M. Downs,
OPIC Corporate Secretary.
[FR Doc. 2013–04858 Filed 2–27–13; 11:15 am]
BILLING CODE 3210–01–P
OVERSEAS PRIVATE INVESTMENT
CORPORATION
Sunshine Act; Cancellation Notice of
Annual Public Hearing
OPIC’s Sunshine Act notice of its
Annual Public Hearing was published
PO 00000
Frm 00058
Fmt 4703
Sfmt 4703
Dated: February 26, 2013.
Connie M. Downs,
OPIC Corporate Secretary.
[FR Doc. 2013–04859 Filed 2–27–13; 11:15 am]
BILLING CODE 3210–01–P
OFFICE OF PERSONNEL
MANAGEMENT
Submission for Review: Application for
Refund of Retirement Deductions/
FERS (SF 3106) and Current/Former
Spouse(s) Notification of Application
for Refund of Retirement Deductions
Under FERS (SF 3106A)
U.S. Office of Personnel
Management.
ACTION: 60-Day Notice and request for
comments.
AGENCY:
The Retirement Services,
Office of Personnel Management (OPM),
is offering the general public and other
Federal agencies the opportunity to
comment on an extension, without
change, of a currently approved
SUMMARY:
E:\FR\FM\01MRN1.SGM
01MRN1
Agencies
[Federal Register Volume 78, Number 41 (Friday, March 1, 2013)]
[Notices]
[Pages 13911-13912]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-04514]
[[Page 13911]]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[NRC-2013-0041]
Proposed Revision to Design of Structures, Components, Equipment
and Systems
AGENCY: Nuclear Regulatory Commission.
ACTION: Standard review plan-draft section revision; request for
comment and use.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is revising the
following sections in Chapter 3, ``Design of Structures, Components,
Equipment, and Systems'' and is soliciting public comment on NUREG-
0800, ``Standard Review Plan for the Review of Safety Analysis Reports
for Nuclear Power Plants: LWR Edition,'' Section 3.7.1, ``Seismic
Design Parameters,'' Section 3.7.2, ``Seismic System Analysis,''
Section 3.7.3, ``Seismic Subsystem Analysis,'' Section 3.8.1,
``Concrete Containment,'' Section 3.8.3, ``Concrete And Steel Internal
Structures of Steel Or Concrete Containments, ``Section 3.8.4, ``Other
Seismic Category I Structures,'' and Section 3.8.5, ``Foundations.''
DATES: Submit comments by April 1, 2013. Comments received after this
date will be considered, if it is practical to do so, but the
Commission is able to ensure consideration only for comments received
on or before this date.
ADDRESSES: You may access information and comment submissions related
to this document, which the NRC possesses and are publically available,
by searching on https://www.regulations.gov under Docket ID NRC-2013-
0041. You may submit comments by any of the following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2013-0041. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-492-
3668; email: Carol.Gallagher@nrc.gov.
Mail comments to: Cindy Bladey, Chief, Rules,
Announcements, and Directives Branch (RADB), Office of Administration,
Mail Stop: TWB-05-B01M, U.S. Nuclear Regulatory Commission, Washington,
DC 20555-0001.
Fax comments to: RADB at 301-492-3446.
For additional direction on accessing information and submitting
comments, see ``Accessing Information and Submitting Comments'' in the
SUPPLEMENTARY INFORMATION section of this document.
FOR FURTHER INFORMATION CONTACT: Ms. Amy E. Cubbage, Office of New
Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001; telephone: 301-415-2875, email: Amy.Cubbage@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Accessing Information and Submitting Comments
A. Accessing Information
Please refer to Docket ID NRC-2013-0041 when contacting the NRC
about the availability of information regarding this document. You may
access information related to this document, which the NRC possesses
and are publicly available, by any of the following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2013-0041.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may access publicly available documents online in the NRC
Library at https://www.nrc.gov/reading-rm/adams.html. To begin the
search, select ``ADAMS Public Documents'' and then select ``Begin Web-
based ADAMS Search.'' For problems with ADAMS, please contact the NRC's
Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-
4737, or by email to pdr.resource@nrc.gov. The ADAMS Accession numbers
for redline documents comparing current revisions and the proposed
revisions of individual sections are available in ADAMS under Accession
Nos.: Section 3.7.1, Proposed Revision 4 (ML12352A305), Current
Revision 3 (ML070640306), Redline (ML12354A050); Section 3.7.2,
Proposed Revision 4 (ML12353A354) Current Revision 3 (ML070640311),
Redline (ML12354A053); Section 3.7.3, Proposed Revision 4
(ML12353A357), Current Revision 3 (ML070640313), Redline (ML12354A043);
Section 3.8.1, Proposed Revision 4 (ML12353A365), Current Revision 3
(ML100620888), Redline (ML12354A052); Section 3.8.3, Proposed Revision
4 (MLML12353A377), Current Revision 3 (ML100620981), Redline
(ML12354A089); and Section 3.8.4, Proposed Revision 4 (ML12353A382),
Current Revision 3 (ML100630323), Redline (ML12354A092); Section 3.8.5,
Proposed Revision 4 (ML12353A388), Current Revision 3 (ML100621093),
Redline (ML12354A096).
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
B. Submitting Comments
Please include Docket ID NRC-2013-0041 in the subject line of your
comment submission, in order to ensure that the NRC is able to make
your comment submission available to the public in this docket.
The NRC cautions you not to include identifying or contact
information in comment submissions that you do not want to be publicly
disclosed. The NRC posts all comment submissions at https://www.regulations.gov as well as enters the comment submissions into
ADAMS. The NRC does not routinely edit comment submissions to remove
identifying or contact information.
If you are requesting or aggregating comments from other persons
for submission to the NRC, then you should inform those persons not to
include identifying or contact information in their comment submissions
that they do not want to be publicly disclosed. Your request should
state that the NRC does not routinely edit comment submissions to
remove such information before making the comment submissions available
to the public or entering the comment submissions into ADAMS.
II. Further Information
The Office of New Reactors and Office of Nuclear Reactor Regulation
are revising these sections from the current versions. In respect of
these revisions, details of specific changes are included in the end of
each of the revised sections themselves and are shown in the
description of changes.
The changes to this Standard Review Plan (SRP) Chapter reflect
current staff review methods and practices based on lessons learned
from NRC reviews of design certification and combined license
applications completed since the last revision of this chapter. Changes
include: (1) Enhancements to guidance to the staff for evaluating the
acceptability of the seismic and civil structural design and analysis
issues, (2) updates to review interfaces to improve the efficiency and
consistency of staff reviews and (3) updates to references covered in
SRP Chapter 3.
The NRC staff is issuing this notice to solicit public comments on
the proposed SRP Sections in Chapter 3. After the NRC staff considers
any public comments, it will make a determination regarding the
proposed SRP Sections in Chapter 3.
Dated at Rockville, Maryland, this 14th day of February 2012.
For the Nuclear Regulatory Commission.
Amy E. Cubbage,
[[Page 13912]]
Chief, Policy Branch, Division of Advanced Reactors and Rulemaking,
Office of New Reactors.
ADAMS Accession No.: ML12352A297--*Concurrence via email--ADM-012.
OFFICE............................. PM:NRO/DARR/NRGA*..... LA:NRO/DARR/APOB*..... PM:NRO/DE/SEB1....... BC:NRO/DE:SEB........ DD:NRO/DE
NAME............................... RSubbaratnam.......... BAbeywickrama......... J Xu................. BThomas.............. MSuhaibi
DATE............................... 12/27/2013............ 12/21/2012............ 1/7/2013............. 1/7/2013............. 1/10/2013
OFFICE............................. PM:NRR/DE/EMCB........ BC:NRR/DE/EMCB........ PM?DPR/NRR........... D:NRR/DE............. DPS/OIS
NAME............................... ATsirigotis........... MMurphy............... K.Lenning............ PHiland.............. TDonnel
DATE............................... 1/18/2013............. 1/22/2013............. 1/24/2013............ 1/23/2013............ 2/13/2013
OFFICE............................. OGC/NLO............... BC:NRO/DARR/APOB......
NAME............................... S. Kirkwood........... ACubbage..............
DATE............................... 2/11/2013............. 02/14/2013............
OFFICIAL RECORDS COPY
Distribution:
PUBLIC...................... BAbeywickrama....... RidsNroDsarRpac
APOB R/F.................... JXu................. RidsNrrDpr
RSubbaratnam................ RidsNroDarr......... RidsNroDarrApob
ACubbage.................... RidsNrrDe........... RidsOgcMailCenter
BThomas..................... JXu................. MSuhaibi
TDonnel.....................
[FR Doc. 2013-04514 Filed 2-28-13; 8:45 am]
BILLING CODE 7590-01-P