Drawbridge Operation Regulations; Saugus River, Lynn and Revere, MA, 9588 [2013-02958]
Download as PDF
9588
Federal Register / Vol. 78, No. 28 / Monday, February 11, 2013 / Rules and Regulations
erowe on DSK2VPTVN1PROD with RULES
(757) 398–6227, email
Kashanda.l.booker@uscg.mil. If you
have questions on viewing the docket,
call Docket Operations, telephone 202–
366–9826.
SUPPLEMENTARY INFORMATION: The North
Carolina Department of Transportation,
who owns and operates this vertical lift
bridge, has requested a temporary
deviation to conduct the bi-annual
trunnion inspection.
Under the regular operating schedule,
the bridge opens on signal as required
by 33 CFR 117.5, except that under 33
CFR 117.823, the draw need not open
for the passage of vessels from 8 a.m. to
10 a.m. on the second Saturday of July
and from 7 a.m. to 11 a.m. on the first
or second Sunday of November every
year.
The Cape Fear River Memorial Bridge,
at mile 26.8, at Wilmington, NC, has
vertical clearances in the open and
closed positions of 135 feet and 65 feet
above mean high water, respectively.
Under this temporary deviation, the
drawbridge will be closed to navigation
beginning each day from 7 a.m. to 7
p.m., on March 11, 2013, through March
14, 2013; however, vessel openings will
be provided if at least two hours
advance notice is given. At all other
times, the drawbridge opens on signal.
There are no alternate routes for vessels
transiting this section of the Cape Fear
River. The drawbridge will be able to
open in the event of an emergency.
Typical vessel traffic on the Cape Fear
River includes a variety of vessels from
freighters, tug and barge traffic, and
recreational vessels. Vessels that can
pass under the bridge without a bridge
opening may continue to do so at
anytime.
The Coast Guard has carefully
coordinated the restrictions with
commercial and recreational waterway
users. The Coast Guard will inform all
users of the waterway through our Local
and Broadcast Notice to Mariners of the
closure periods for the bridge so that
vessels can arrange their transits to
minimize any impacts caused by the
temporary deviation.
In accordance with 33 CFR 117.35(e),
the drawbridge must return to its regular
operating schedule immediately at the
end of the effective period of this
temporary deviation. This deviation
from the operating regulations is
authorized under 33 CFR 117.35.
Dated: January 30, 2013.
Waverly W. Gregory, Jr.,
Bridge Program Manager, Fifth Coast Guard
District.
[FR Doc. 2013–02962 Filed 2–8–13; 8:45 am]
BILLING CODE 9110–04–P
VerDate Mar<15>2010
14:06 Feb 08, 2013
Jkt 229001
DEPARTMENT OF HOMELAND
SECURITY
Coast Guard
33 CFR Part 117
[Docket No. USCG–2012–1072]
Drawbridge Operation Regulations;
Saugus River, Lynn and Revere, MA
Coast Guard, DHS.
Notice of temporary deviation
from regulation.
AGENCY:
ACTION:
The U.S. Coast Guard has
issued a temporary deviation from the
regulation governing the operation of
the General Edwards Bridge, mile 1.7,
across the Saugus River between Lynn
and Revere, Massachusetts. The
deviation is necessary to facilitate
architectural rehabilitation of the bridge
towers. This deviation allows the bridge
to remain in the closed position to allow
scaffolding be attached to the bascule
lift span to access work area.
DATES: This deviation is effective from
March 1, 2013, through April 27, 2013.
ADDRESSES: The docket for this notice,
USCG–2012–1072, is available online at
www.regulations.gov by typing the
docket number in the ‘‘SEARCH’’ box
and clicking ‘‘SEARCH’’. You may also
visit the Docket Management Facility
(M–30), U.S. Department of
Transportation, West Building Ground
Floor, Room W12–140, 1200 New Jersey
Avenue SE., Washington, DC 20590,
between 9 a.m. and 5 p.m., Monday
through Friday, except Federal holidays.
FOR FURTHER INFORMATION CONTACT: If
you have questions on this temporary
deviation, call or email Mr. John W.
McDonald, Project Officer, First Coast
Guard District,
john.w.mcdonald@uscg.mil, or
telephone 617–223–8364. If you have
questions on viewing the docket, call
Barbara Hairston, Program Manager,
Docket Operations, telephone 202–366–
9826.
SUPPLEMENTARY INFORMATION: The
General Edwards Bridge, across the
Saugus River, mile 1.7, between Lynn
and Revere, Massachusetts, has a
vertical clearance in the closed position
of 27 feet at mean high water and 36 feet
at mean low water. The drawbridge
operation regulations are listed at 33
CFR 117.618(b).
The waterway users are recreational
vessels of various sizes. The bridge
rarely opens March through April since
the recreational vessels that transit this
waterway are normally in winter
storage. The bridge has opened two
SUMMARY:
PO 00000
Frm 00014
Fmt 4700
Sfmt 4700
times on average since 2002 during this
time period.
The owner of the bridge,
Massachusetts Department of
Transportation, requested a temporary
deviation from the regulations to help
facilitate rehabilitation of the bridge
towers that requires scaffolding be
attached to the bascule lift span to
access the work area.
Under this temporary deviation the
General Edwards Bridge may remain in
the closed position from March 1, 2013,
through April 27, 2013.
Vessels that can pass under the bridge
in the closed position may do so at any
time.
The Coast Guard believes that this
temporary deviation meets the
reasonable needs of navigation because
the recreational users that normally use
this bridge are recreational vessels that
do not operate during the winter months
when this deviation will be in effect.
In accordance with 33 CFR 117.35(e),
the bridge must return to its regular
operating schedule immediately at the
end of the designated time period. This
deviation from the operating regulations
is authorized under 33 CFR 117.35.
Dated: January 29, 2012.
Gary Kassof,
Bridge Program Manager, First Coast Guard
District.
[FR Doc. 2013–02958 Filed 2–8–13; 8:45 am]
BILLING CODE 9110–04–P
DEPARTMENT OF HOMELAND
SECURITY
Coast Guard
33 CFR Part 117
[Docket No. USCG–2013–0043]
Drawbridge Operation Regulation; Mile
535.0, Upper Mississippi River, Sabula,
IA
Coast Guard, DHS.
Notice of deviation from
drawbridge regulation.
AGENCY:
ACTION:
The Coast Guard has issued a
temporary deviation from the operating
schedule that governs the Sabula
Railroad Drawbridge across the Upper
Mississippi River, mile 535.0, at Sabula,
Iowa. The deviation is necessary to
allow the bridge owner time to perform
preventive maintenance that is essential
to the continued safe operation of the
drawbridge. Maintenance is scheduled
in the winter when there is less impact
on navigation; instead of scheduling
work in the summer, when river traffic
increases. This deviation allows the
bridge to remain in the closed-to-
SUMMARY:
E:\FR\FM\11FER1.SGM
11FER1
Agencies
[Federal Register Volume 78, Number 28 (Monday, February 11, 2013)]
[Rules and Regulations]
[Page 9588]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2013-02958]
-----------------------------------------------------------------------
DEPARTMENT OF HOMELAND SECURITY
Coast Guard
33 CFR Part 117
[Docket No. USCG-2012-1072]
Drawbridge Operation Regulations; Saugus River, Lynn and Revere,
MA
AGENCY: Coast Guard, DHS.
ACTION: Notice of temporary deviation from regulation.
-----------------------------------------------------------------------
SUMMARY: The U.S. Coast Guard has issued a temporary deviation from the
regulation governing the operation of the General Edwards Bridge, mile
1.7, across the Saugus River between Lynn and Revere, Massachusetts.
The deviation is necessary to facilitate architectural rehabilitation
of the bridge towers. This deviation allows the bridge to remain in the
closed position to allow scaffolding be attached to the bascule lift
span to access work area.
DATES: This deviation is effective from March 1, 2013, through April
27, 2013.
ADDRESSES: The docket for this notice, USCG-2012-1072, is available
online at www.regulations.gov by typing the docket number in the
``SEARCH'' box and clicking ``SEARCH''. You may also visit the Docket
Management Facility (M-30), U.S. Department of Transportation, West
Building Ground Floor, Room W12-140, 1200 New Jersey Avenue SE.,
Washington, DC 20590, between 9 a.m. and 5 p.m., Monday through Friday,
except Federal holidays.
FOR FURTHER INFORMATION CONTACT: If you have questions on this
temporary deviation, call or email Mr. John W. McDonald, Project
Officer, First Coast Guard District, john.w.mcdonald@uscg.mil, or
telephone 617-223-8364. If you have questions on viewing the docket,
call Barbara Hairston, Program Manager, Docket Operations, telephone
202-366-9826.
SUPPLEMENTARY INFORMATION: The General Edwards Bridge, across the
Saugus River, mile 1.7, between Lynn and Revere, Massachusetts, has a
vertical clearance in the closed position of 27 feet at mean high water
and 36 feet at mean low water. The drawbridge operation regulations are
listed at 33 CFR 117.618(b).
The waterway users are recreational vessels of various sizes. The
bridge rarely opens March through April since the recreational vessels
that transit this waterway are normally in winter storage. The bridge
has opened two times on average since 2002 during this time period.
The owner of the bridge, Massachusetts Department of
Transportation, requested a temporary deviation from the regulations to
help facilitate rehabilitation of the bridge towers that requires
scaffolding be attached to the bascule lift span to access the work
area.
Under this temporary deviation the General Edwards Bridge may
remain in the closed position from March 1, 2013, through April 27,
2013.
Vessels that can pass under the bridge in the closed position may
do so at any time.
The Coast Guard believes that this temporary deviation meets the
reasonable needs of navigation because the recreational users that
normally use this bridge are recreational vessels that do not operate
during the winter months when this deviation will be in effect.
In accordance with 33 CFR 117.35(e), the bridge must return to its
regular operating schedule immediately at the end of the designated
time period. This deviation from the operating regulations is
authorized under 33 CFR 117.35.
Dated: January 29, 2012.
Gary Kassof,
Bridge Program Manager, First Coast Guard District.
[FR Doc. 2013-02958 Filed 2-8-13; 8:45 am]