7. Project Sponsor and Facility:
Enerplus Resources (USA) Corporation
(West Branch Susquehanna River), East
Keating Township, Clinton County, Pa.
Surface water withdrawal of up to 2.000
mgd (peak day).
8. Project Sponsor and Facility: EXCO
Resources (PA), LLC (Larrys Creek),
Mifflin Township, Lycoming County,
Pa. Renewal of surface water
withdrawal with modification, for a
total of 0.200 mgd (peak day) (Docket
No. 20080936).
9. Project Sponsor and Facility: Forest
Springs Water Company, Wayne
Township, Schuylkill County, Pa.
Groundwater withdrawal of up to 0.075
mgd (30-day average) from Borehole
BH–1, and modification to consumptive
water use approval removing previous
sources Spring 1 and Spring 2 and
adding new source Borehole BH–1
(Docket No. 20010206).
10. Project Sponsor: Hydro RecoveryAntrim LP. Project Facility: Antrim
Treatment Plant, Duncan Township,
Tioga County, Pa. Modification to
project features and to increase surface
water withdrawal by an additional 1.152
mgd, for a total of 1.872 mgd (peak day)
(Docket No. 20090902).
11. Project Sponsor and Facility:
Keystone Clearwater Solutions, LLC
(Lycoming Creek), Lewis Township,
Lycoming County, Pa. Modification to
increase surface water withdrawal, for a
total of 2.125 mgd (peak day) (Docket
No. 20110616).
12. Project Sponsor and Facility:
Keystone Clearwater Solutions, LLC
(Moshannon Creek), Snow Shoe
Township, Centre County, Pa. Renewal
of surface water withdrawal of up to
1.000 mgd (peak day) (Docket No.
20080946).
13. Project Sponsor and Facility:
Keystone Clearwater Solutions, LLC
(West Branch Susquehanna River),
Goshen Township, Clearfield County,
Pa. Renewal of surface water
withdrawal of up to 1.000 mgd (peak
day) (Docket No. 20080944).
14. Project Sponsor and Facility:
Roaring Spring Water—Division of
Roaring Spring Blank Book, Roaring
Spring Borough, Blair County, Pa.
Modification to increase consumptive
water use by an additional 0.125 mgd,
for a total of 0.255 mgd (peak day)
(Docket No. 20120309), and to increase
surface water withdrawal by an
additional 0.131 mgd, for a total of 0.302
mgd (peak day) (Docket No. 20120309).
15. Project Sponsor and Facility:
Talisman Energy USA Inc.
VerDate Mar<15>2010
12:56 Nov 01, 2012
Jkt 229001
(Susquehanna River), Sheshequin
Township, Bradford County, Pa.
Renewal of surface water withdrawal of
up to 1.500 mgd (peak day) (Docket No.
20080909).
Project Applications Tabled
The following project applications
were tabled by the Commission:
1. Project Sponsor and Facility:
Caernarvon Township Authority,
Caernarvon Township, Berks County,
Pa. Application for renewal of
groundwater withdrawal of up to 0.035
mgd (30-day average) from Well 6
(Docket No. 19820912).
2. Project Sponsor and Facility: EQT
Production Company (Pine Creek),
Porter Township, Lycoming County, Pa.
Application for surface water
withdrawal of up to 1.000 mgd (peak
day).
3. Project Sponsor and Facility:
Falling Springs Water Works, Inc.
(Falling Springs Reservoir), Ransom
Township, Lackawanna County, Pa.
Application for surface water
withdrawal of up to 0.800 mgd (peak
day).
4. Project Sponsor and Facility:
Gaberseck Brothers (Odin Pond 2),
Keating Township, Potter County, Pa.
Application for surface water
withdrawal of up to 0.249 mgd (peak
day).
5. Project Sponsor and Facility:
Houtzdale Municipal Authority
(Beccaria Springs), Gulich Township,
Clearfield County, Pa. Application for
surface water withdrawal of up to
10.000 mgd (peak day).
6. Project Sponsor and Facility:
Southwestern Energy Production
Company (Middle Lake), New Milford
Township, Susquehanna County, Pa.
Application for surface water
withdrawal of up to 0.720 mgd (peak
day).
Authority: Pub. L. 91–575, 84 Stat. 1509
et seq., 18 CFR parts 806, 807, and 808.
Dated: October 19, 2012.
Thomas W. Beauduy,
Deputy Executive Director.
[FR Doc. 2012–26877 Filed 11–1–12; 8:45 am]
BILLING CODE 7040–01–P
DEPARTMENT OF TRANSPORTATION
Federal Highway Administration
Notice of Final Federal Agency Actions
on the Tappan Zee Hudson River
Crossing Project in New York
Correction
In notice document 2012–26799,
appearing on page 65929 in the issue of
PO 00000
Frm 00038
Fmt 4703
Sfmt 4703
66215
Wednesday, October 31, 2012, make the
following correction:
On page 65929, in the first column,
under the DATES heading, in the seventh
line, ‘‘[Insert date 150 days after
publication in the Federal Register]’’
should read ‘‘March 30, 2013’’.
[FR Doc. C1–2012–26799 Filed 11–1–12; 8:45 am]
BILLING CODE 1505–01–D
DEPARTMENT OF TRANSPORTATION
Federal Highway Administration
Limitation of Claims Notice for Judicial
Review of Actions by FHWA and Other
Federal Agencies in the City of
Cincinnati, Hamilton County, OH and
the City of Covington, Kenton County,
KY
Federal Highway
Administration (FHWA), DOT.
ACTION: Notice of limitation on claims
for judicial review of actions by FHWA
and other federal agencies.
AGENCY:
By this notice, the FHWA is
advising the public of final agency
actions subject to 23 U.S.C. 139(l)(1).
The actions relate to a proposed project
to improve the Brent Spence Bridge over
the Ohio River, as well as improvements
to Interstate Routes 71 and 75 and
interchanges in the City of Cincinnati,
Hamilton County, State of Ohio and City
of Covington, Kenton County,
Commonwealth of Kentucky, including
a new bridge over the Ohio River. This
notice covers those Federal agency
actions to grant licenses, permits, and
approvals for the project.
DATES: A claim seeking judicial review
of the Federal agency actions on the
highway project will be barred unless
the claim is filed on or before May 1,
2013. If the Federal law that authorizes
judicial review of a claim provides a
time period of less than 180 days for
filing such claim, then that shorter time
period still applies.
FOR FURTHER INFORMATION CONTACT: Noel
F. Mehlo Jr., Environmental Program
Manager, Federal Highway
Administration, 200 North High Street,
Room 328, Columbus, Ohio 43215,
Telephone: (614) 280–6896; or Stefan
Spinosa, PE, Ohio Department of
Transportation (ODOT), 505 South State
Route 741, Lebanon, Ohio 45036,
Telephone: (513) 933–6639.
SUPPLEMENTARY INFORMATION: Notice is
hereby given that the FHWA and other
Federal agencies including, but not
limited to; the United States Coast
Guard, United States Army Corps of
Engineers, United States Fish and
Wildlife Service, Advisory Council on
SUMMARY:
E:\FR\FM\02NON1.SGM
02NON1
Agencies
[Federal Register Volume 77, Number 213 (Friday, November 2, 2012)]
[Notices]
[Page 66215]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: C1-2012-26799]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Federal Highway Administration
Notice of Final Federal Agency Actions on the Tappan Zee Hudson
River Crossing Project in New York
Correction
In notice document 2012-26799, appearing on page 65929 in the issue
of Wednesday, October 31, 2012, make the following correction:
On page 65929, in the first column, under the DATES heading, in the
seventh line, ``[Insert date 150 days after publication in the Federal
Register]'' should read ``March 30, 2013''.
[FR Doc. C1-2012-26799 Filed 11-1-12; 8:45 am]