Notice of Final Federal Agency Actions on Proposed Highway in Illinois, 61825 [2012-24700]

Download as PDF Federal Register / Vol. 77, No. 197 / Thursday, October 11, 2012 / Notices taken, are described in the Environmental Assessment (EA) for the Federal Highway Administration project approved on March 28, 2012, the Finding of No Significant Impact Notice of Final Federal Agency Actions (FONSI) issued on September 14, 2012, on Proposed Highway in Illinois and in other documents in the FHWA administrative record. The EA, FONSI, AGENCY: Federal Highway and other documents in the FHWA Administration (FHWA), DOT. administrative record file are available ACTION: Notice of Limitation on Claims for Judicial Review of Actions by FHWA by contacting the FHWA or the Illinois Department of Transportation at the and other Federal Agencies. addresses provided above. The EA and SUMMARY: This notice announces actions FONSI and all other supporting taken by the FHWA and other Federal documentation can be viewed and agencies that are final within the downloaded from the project Web site at meaning of 23 U.S.C. 139(l)(1). The www.willowroadfuture.org. actions relate to a proposed highway This notice applies to all Federal project, Willow Road (FAP 305) agency decisions as of the issuance date between Illinois Route 43 (Waukegan of this notice and all laws under which Road) and Interstate 94 (Edens such actions were taken, including but Expressway) in Cook County, Illinois. not limited to: Those actions grant licenses, permits, 1. General: National Environmental and approvals for the project. Policy Act (NEPA) [42 U.S.C. 4321– DATES: By this notice, the FHWA is 4351] Federal-Aid Highway Act [23 advising the public of final agency U.S.C. 109 and 23 U.S.C. 128]. actions subject to 23 U.S.C. 139(l)(1). A 2. Air: Clean Air Act [42 U.S.C. 7401– claim seeking judicial review of the 7671(q)]. Federal agency actions on the highway 3. Land: Section 4(f) of the project will be barred unless the claim Department of Transportation Act of is filed on or before March 10, 2013. If 1966 [49 U.S.C. 303 and 23 U.S.C. 138]. the Federal law that authorizes judicial 4. Social and Economic: Civil Rights review of a claim provides a time period Act of 1964 [42 U.S.C. 2000(d)– of less than 150 days for filing such 2000(d)(1)]. claim, then that shorter time period still 5. Historic and Cultural Resources: applies. Section 106 of the National Historic FOR FURTHER INFORMATION CONTACT: Mr. Preservation Act of 1966, as amended Norman R. Stoner, P.E., Division [16 U.S.C. 470(f) et seq.]; Archaeological Administrator, Federal Highway and Historic Preservation Act (AHPA) Administration, 3250 Executive Park [16 U.S.C. 469–469(c)]. Drive, Springfield, Illinois 62703, 6. Wildlife: Endangered Species Act Phone: (217) 492–4600, Email address: [16 U.S.C. 1531–1544 and Section Norman.Stoner@dot.gov. The FHWA 1536]; Migratory Bird Treaty Act [16 Illinois Division Office’s normal U.S.C. 703–712]. business hours are 7:30 a.m. to 4:15 p.m. 7. Wetlands and Water Resources: You may also contact Mr. John A. Clean Water Act (Section 401 and 404) Fortmann, P.E., Illinois Department of [33 U.S.C. 1251–1377]; Wild and Scenic Transportation, Deputy Director of Rivers Act [16 U.S.C. 1271–1287]. Highways, Acting Region One Engineer, 8. Executive Orders: E.O. 11990 201 West Center Court, Schaumburg, Protection of Wetlands; E.O. 11988 Illinois 60196, Phone: (847) 705–4000. Floodplain Management; E.O. 12898 The Illinois Department of Federal Actions to Address Transportation Region One’s normal Environmental Justice in Minority business hours are 8 a.m. to 4:15 p.m. Populations and Low Income SUPPLEMENTARY INFORMATION: Notice is Populations. hereby given that the FHWA and other (Catalog of Federal Domestic Assistance Federal agencies have taken final agency Program Number 20.205, Highway Planning actions by issuing licenses, permits, and and Construction. The regulations approvals for the following highway implementing Executive Order 12372 project in the State of Illinois: regarding intergovernmental consultation on reconstruct and widen Willow Road Federal programs and activities apply to this (FAP 305) from Illinois Route 43 program.) (Waukegan Road) to Interstate 94 (Edens Authority: 23 U.S.C. 139(l)(1). Expressway), a distance of Issued on: October 1, 2012. approximately 1.8 miles including Norman R. Stoner, replacing the bridge over the Middle Fork North Branch of the Chicago River. Division Administrator, Springfield, Illinois. The actions by the Federal agencies, and [FR Doc. 2012–24700 Filed 10–10–12; 8:45 am] the laws under which such actions were BILLING CODE 4910–RY–P pmangrum on DSK3VPTVN1PROD with NOTICES DEPARTMENT OF TRANSPORTATION VerDate Mar<15>2010 14:03 Oct 10, 2012 Jkt 229001 PO 00000 Frm 00090 Fmt 4703 Sfmt 4703 61825 DEPARTMENT OF TRANSPORTATION Pipeline and Hazardous Materials Safety Administration [Docket ID PHMSA–2012–0244] Pipeline Safety: Notice of Public Meeting on Pipeline Data Pipeline and Hazardous Materials Safety Administration (PHMSA), DOT. ACTION: Notice of public meeting. AGENCY: PHMSA and the National Association of Pipeline Safety Representatives (NAPSR) are sponsoring this public meeting to discuss how pipeline data is currently used by stakeholders and identify potential improvements in pipeline safety performance measures. PHMSA pipeline safety regulations require integrity management program performance measures for gas distribution, gas transmission, and hazardous liquids pipelines. The National Transportation Safety Board (NTSB) and the U.S. Department of Transportation’s (DOT) Office of the Inspector General have recommended that PHMSA improve pipeline safety performance measures and generate meaningful metrics. This meeting provides an opportunity for pipeline safety stakeholders to suggest improvements to existing performance measures and new measures representing meaningful pipeline safety metrics. The meeting will include breakout sessions on voluntary reporting, data discrepancies, data collected but not needed, and performance measures. DATES: The public meeting on pipeline data will be held on Monday, October 29, 2012, from 1 p.m. to 5:30 p.m. and Tuesday, October 30, 2012, from 8 a.m. to 5 p.m. Name badge pickup and onsite registration will be available starting at 12:30 p.m. on October 29 and 7:30 a.m. on October 30. Registration: Please register at https://primis.phmsa.dot.gov/meetings/ MtgHome.mtg?mtg=81. Please note that the meeting will be webcast, including the voluntary reporting breakout on October 30. The webcast link will be posted on the registration Web page prior to the event. ADDRESSES: The public meeting will be held at the Hyatt Regency Washington on Capitol Hill, 400 New Jersey Avenue NW., Washington, DC 20001, phone: 888–421–1442. Please contact the Hyatt Regency before October 16, 2012, to reserve a room in the ‘‘US DOT’’ room block by phone or at https://resweb. SUMMARY: E:\FR\FM\11OCN1.SGM 11OCN1

Agencies

[Federal Register Volume 77, Number 197 (Thursday, October 11, 2012)]
[Notices]
[Page 61825]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-24700]



[[Page 61825]]

-----------------------------------------------------------------------

DEPARTMENT OF TRANSPORTATION

Federal Highway Administration


Notice of Final Federal Agency Actions on Proposed Highway in 
Illinois

AGENCY: Federal Highway Administration (FHWA), DOT.

ACTION: Notice of Limitation on Claims for Judicial Review of Actions 
by FHWA and other Federal Agencies.

-----------------------------------------------------------------------

SUMMARY: This notice announces actions taken by the FHWA and other 
Federal agencies that are final within the meaning of 23 U.S.C. 
139(l)(1). The actions relate to a proposed highway project, Willow 
Road (FAP 305) between Illinois Route 43 (Waukegan Road) and Interstate 
94 (Edens Expressway) in Cook County, Illinois. Those actions grant 
licenses, permits, and approvals for the project.

DATES: By this notice, the FHWA is advising the public of final agency 
actions subject to 23 U.S.C. 139(l)(1). A claim seeking judicial review 
of the Federal agency actions on the highway project will be barred 
unless the claim is filed on or before March 10, 2013. If the Federal 
law that authorizes judicial review of a claim provides a time period 
of less than 150 days for filing such claim, then that shorter time 
period still applies.

FOR FURTHER INFORMATION CONTACT: Mr. Norman R. Stoner, P.E., Division 
Administrator, Federal Highway Administration, 3250 Executive Park 
Drive, Springfield, Illinois 62703, Phone: (217) 492-4600, Email 
address: Norman.Stoner@dot.gov. The FHWA Illinois Division Office's 
normal business hours are 7:30 a.m. to 4:15 p.m. You may also contact 
Mr. John A. Fortmann, P.E., Illinois Department of Transportation, 
Deputy Director of Highways, Acting Region One Engineer, 201 West 
Center Court, Schaumburg, Illinois 60196, Phone: (847) 705-4000. The 
Illinois Department of Transportation Region One's normal business 
hours are 8 a.m. to 4:15 p.m.

SUPPLEMENTARY INFORMATION: Notice is hereby given that the FHWA and 
other Federal agencies have taken final agency actions by issuing 
licenses, permits, and approvals for the following highway project in 
the State of Illinois: reconstruct and widen Willow Road (FAP 305) from 
Illinois Route 43 (Waukegan Road) to Interstate 94 (Edens Expressway), 
a distance of approximately 1.8 miles including replacing the bridge 
over the Middle Fork North Branch of the Chicago River. The actions by 
the Federal agencies, and the laws under which such actions were taken, 
are described in the Environmental Assessment (EA) for the project 
approved on March 28, 2012, the Finding of No Significant Impact 
(FONSI) issued on September 14, 2012, and in other documents in the 
FHWA administrative record. The EA, FONSI, and other documents in the 
FHWA administrative record file are available by contacting the FHWA or 
the Illinois Department of Transportation at the addresses provided 
above. The EA and FONSI and all other supporting documentation can be 
viewed and downloaded from the project Web site at 
www.willowroadfuture.org.
    This notice applies to all Federal agency decisions as of the 
issuance date of this notice and all laws under which such actions were 
taken, including but not limited to:
    1. General: National Environmental Policy Act (NEPA) [42 U.S.C. 
4321-4351] Federal-Aid Highway Act [23 U.S.C. 109 and 23 U.S.C. 128].
    2. Air: Clean Air Act [42 U.S.C. 7401-7671(q)].
    3. Land: Section 4(f) of the Department of Transportation Act of 
1966 [49 U.S.C. 303 and 23 U.S.C. 138].
    4. Social and Economic: Civil Rights Act of 1964 [42 U.S.C. 
2000(d)-2000(d)(1)].
    5. Historic and Cultural Resources: Section 106 of the National 
Historic Preservation Act of 1966, as amended [16 U.S.C. 470(f) et 
seq.]; Archaeological and Historic Preservation Act (AHPA) [16 U.S.C. 
469-469(c)].
    6. Wildlife: Endangered Species Act [16 U.S.C. 1531-1544 and 
Section 1536]; Migratory Bird Treaty Act [16 U.S.C. 703-712].
    7. Wetlands and Water Resources: Clean Water Act (Section 401 and 
404) [33 U.S.C. 1251-1377]; Wild and Scenic Rivers Act [16 U.S.C. 1271-
1287].
    8. Executive Orders: E.O. 11990 Protection of Wetlands; E.O. 11988 
Floodplain Management; E.O. 12898 Federal Actions to Address 
Environmental Justice in Minority Populations and Low Income 
Populations.

(Catalog of Federal Domestic Assistance Program Number 20.205, 
Highway Planning and Construction. The regulations implementing 
Executive Order 12372 regarding intergovernmental consultation on 
Federal programs and activities apply to this program.)

    Authority:  23 U.S.C. 139(l)(1).

    Issued on: October 1, 2012.
Norman R. Stoner,
Division Administrator, Springfield, Illinois.
[FR Doc. 2012-24700 Filed 10-10-12; 8:45 am]
BILLING CODE 4910-RY-P