(on behalf of NSPM and NSPW) are each
entitled to own and construct fifty
percent of the 345 kV facilities from the
Twin Cities area in Minnesota to the
Madison area in Wisconsin.
ATCLLC certifies that copies of the
complaint were served on the contacts
for Xcel Energy and the state public
utility commissions of Minnesota and
Wisconsin.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211 and
385.214). Protests will be considered by
the Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. The Respondent’s answer
and all interventions, or protests must
be filed on or before the comment date.
The Respondent’s answer, motions to
intervene, and protests must be served
on the Complainants.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on October 22, 2012.
Dated: October 3, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–24907 Filed 10–9–12; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL13–10–000]
North American Natural Resources,
Inc. Complainant v. PJM
Interconnection, L.L.C, American
Electric Power Service Corporation,
Indiana Michigan Power Company,
Respondents; Notice of Complaint
Take notice that on October 2, 2012,
pursuant to section 206 of the Federal
Energy Regulatory Commission’s
(Commission) Rules of Practice and
Procedure, 18 CFR 385.206 and sections
206 of the Federal Power Act (FPA), 16
U.S.C. 824(e), North American Natural
Resource, Inc. (NSANR) filed a formal
complaint against PJM Interconnection,
L.L.C, (PJM), American Electric Power
Service Corporation (AEP), and AEP’s
wholly owned subsidiary Indiana
Michigan Power Company (I & M)
alleging, that contrary to sections
1.7A.02, 1.3A, 1.17A, 1.26, 212.4, 217.3,
205, 206 and 217 of PJM’s Open Access
Transmission Tariff (OATT), the
Interconnection Construction Service
Agreement (ICSA) between AEP and
NANR, the Interconnection Service
Agreement (ISA) between AEP and
NANR, the Commission’s Order No.
2003 1 and other applicable FERC
decisions, and the FPA, AEP and PJM
have refused to properly categorize
$2,269,012 of the interconnection costs
as Network Upgrades and allocate those
costs to AEP and its customers, failed to
update AEP’s Regional Transmission
System Expansion (RTEP) and
wrongfully foisted the costs of the
Network Upgrades onto NANR by
mischaracterizing them as Attachment
Facilities, and wrongfully utilized the
interconnection of Project T–111 as a
means of upgrading its inadequate 69
kV line, which had previously not
included adequate re-closing or breaker
failure protection, and replacing
obsolete relays and other equipment.
NANR certifies that copies of the
complaint were served on the contacts
for PJM, AEP, and I & M as listed on the
Commission’s list of Corporate Officials.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
1 Standardization of Generator Interconnection
Agreements and Procedure, Order No. 2003, 104
FERC ¶ 61,103 (2003).
VerDate Mar<15>2010
15:15 Oct 09, 2012
Jkt 229001
PO 00000
Frm 00025
Fmt 4703
Sfmt 4703
61593
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. The Respondent’s answer
and all interventions, or protests must
be filed on or before the comment date.
The Respondent’s answer, motions to
intervene, and protests must be served
on the Complainants.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive email notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please email
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on October 22, 2012.
Dated: October 3, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–24908 Filed 10–9–12; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL12–101–000]
New York Association of Public Power
v. Niagara Mohawk Power Corporation,
New York Independent System
Operator, Inc.; Notice of Amendment to
Complaint
Take notice that on October 2, 2012,
New York Association of Public Power
(Complainant) amended its September
11, 2012 filed Complaint against Niagara
Mohawk Power Corporation and New
York Independent System Operator, Inc.
(Respondents) submitting workpapers of
Jonathan A. Lesser, the witness for the
Complainant, in support of the
Complaint.
The Complainant certifies that copies
were served on the parties shown on the
official service listed compiled by the
Commission.
E:\FR\FM\10OCN1.SGM
10OCN1
Agencies
[Federal Register Volume 77, Number 196 (Wednesday, October 10, 2012)]
[Notices]
[Page 61593]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-24908]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. EL13-10-000]
North American Natural Resources, Inc. Complainant v. PJM
Interconnection, L.L.C, American Electric Power Service Corporation,
Indiana Michigan Power Company, Respondents; Notice of Complaint
Take notice that on October 2, 2012, pursuant to section 206 of the
Federal Energy Regulatory Commission's (Commission) Rules of Practice
and Procedure, 18 CFR 385.206 and sections 206 of the Federal Power Act
(FPA), 16 U.S.C. 824(e), North American Natural Resource, Inc. (NSANR)
filed a formal complaint against PJM Interconnection, L.L.C, (PJM),
American Electric Power Service Corporation (AEP), and AEP's wholly
owned subsidiary Indiana Michigan Power Company (I & M) alleging, that
contrary to sections 1.7A.02, 1.3A, 1.17A, 1.26, 212.4, 217.3, 205, 206
and 217 of PJM's Open Access Transmission Tariff (OATT), the
Interconnection Construction Service Agreement (ICSA) between AEP and
NANR, the Interconnection Service Agreement (ISA) between AEP and NANR,
the Commission's Order No. 2003 \1\ and other applicable FERC
decisions, and the FPA, AEP and PJM have refused to properly categorize
$2,269,012 of the interconnection costs as Network Upgrades and
allocate those costs to AEP and its customers, failed to update AEP's
Regional Transmission System Expansion (RTEP) and wrongfully foisted
the costs of the Network Upgrades onto NANR by mischaracterizing them
as Attachment Facilities, and wrongfully utilized the interconnection
of Project T-111 as a means of upgrading its inadequate 69 kV line,
which had previously not included adequate re-closing or breaker
failure protection, and replacing obsolete relays and other equipment.
---------------------------------------------------------------------------
\1\ Standardization of Generator Interconnection Agreements and
Procedure, Order No. 2003, 104 FERC ] 61,103 (2003).
---------------------------------------------------------------------------
NANR certifies that copies of the complaint were served on the
contacts for PJM, AEP, and I & M as listed on the Commission's list of
Corporate Officials.
Any person desiring to intervene or to protest this filing must
file in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211, 385.214). Protests will be
considered by the Commission in determining the appropriate action to
be taken, but will not serve to make protestants parties to the
proceeding. Any person wishing to become a party must file a notice of
intervention or motion to intervene, as appropriate. The Respondent's
answer and all interventions, or protests must be filed on or before
the comment date. The Respondent's answer, motions to intervene, and
protests must be served on the Complainants.
The Commission encourages electronic submission of protests and
interventions in lieu of paper using the ``eFiling'' link at https://www.ferc.gov. Persons unable to file electronically should submit an
original and 14 copies of the protest or intervention to the Federal
Energy Regulatory Commission, 888 First Street NE., Washington, DC
20426.
This filing is accessible on-line at https://www.ferc.gov, using the
``eLibrary'' link and is available for review in the Commission's
Public Reference Room in Washington, DC. There is an ``eSubscription''
link on the Web site that enables subscribers to receive email
notification when a document is added to a subscribed docket(s). For
assistance with any FERC Online service, please email
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For
TTY, call (202) 502-8659.
Comment Date: 5 p.m. Eastern Time on October 22, 2012.
Dated: October 3, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-24908 Filed 10-9-12; 8:45 am]