Discovery Gas Transmission LLC; Notice of Application, 58371-58372 [2012-23226]

Download as PDF Federal Register / Vol. 77, No. 183 / Thursday, September 20, 2012 / Notices revised process plan and schedule, as well as a list of issues, identified through the scoping process. Federal Energy Regulatory Commission [Project No. 3021–088] Pennamaquan Power will conduct a site visit for the proposed project on Thursday, October 25, 2012, starting at 1 p.m. The site visit will begin at the boat ramp parking lot on Boat Landing Road (off of Garnet Head Road), Pembroke, Maine 04666. For information about the meeting location for the site visit, please call Ramez Atiya from Pennamaquan Power at 801–583– 1054. Meeting Objectives At the scoping meetings, staff will: (1) Initiate scoping of the issues; (2) review and discuss existing conditions and resource management objectives; (3) review and discuss existing information and identify preliminary information and study needs; (4) review and discuss the process plan and schedule for prefiling activity that incorporates the time frames provided for in Part 5 of the Commission’s regulations and, to the extent possible, maximizes coordination of federal, state, and tribal permitting and certification processes; and (5) discuss the appropriateness of any federal or state agency or Indian tribe acting as a cooperating agency for development of an environmental document. Meeting participants should come prepared to discuss their issues and/or concerns. Please review the PAD in preparation for the scoping meetings. Directions on how to obtain a copy of the PAD and SD1 are included in item n. of this document. Meeting Procedures The meetings will be recorded by a stenographer and will be placed in the public records of the project. Dated: September 14, 2012. Kimberly D. Bose, Secretary. [FR Doc. 2012–23229 Filed 9–19–12; 8:45 am] mstockstill on DSK4VPTVN1PROD with NOTICES BILLING CODE 6717–01–P VerDate Mar<15>2010 link of Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–3021) in the docket number field to access the document. For assistance, call toll-free 1–866–208–3372. DEPARTMENT OF ENERGY Site Visit 16:11 Sep 19, 2012 Jkt 226001 Allegheny Hydro No. 8, L.P., Allegheny Hydro No. 9, L.P., and U.S. Bank National Association Allegheny Hydro, LLC; Notice of Application for Transfer of License, and Soliciting Comments and Motions To Intervene On August 31, 2012, Allegheny Hydro No. 8, L.P., Allegheny Hydro No. 9, L.P., and U.S. Bank National Association (in its capacity as owner trustee) (colicensees) and Allegheny Hydro, LLC (transferee) filed an application for transfer of license for the Allegheny River Lock and Dam Nos. 8 and 9 Hydroelectric Project No. 3021, located at the U.S. Army Corps of Engineers’ Allegheny River Lock and Dam No. 8 and Allegheny River Lock and Dam No. 9 on the Allegheny River in Armstrong County, Pennsylvania. Applicants seek Commission approval to transfer the license for the Allegheny River Lock and Dam Nos. 8 and 9 Hydroelectric Project from Allegheny Hydro No. 8, L.P., Allegheny Hydro No. 9, L.P., and the U.S. Bank National Association as co-licensees to Allegheny Hydro, LLC as sole licensee. Applicants’ Contact: Mr. Curt Whittaker, Rath, Young and Pignatelli, P.C., One Capital Plaza, Concord, NH 03302, phone: (603) 226–2600 and Mr. Mark C. Williams, Bingham McCutchen LLP, 2020 K Street NW., Suite 1100, Washington, DC 20006, phone (202) 373–6181. FERC Contact: Patricia W. Gillis (202) 502–8735, patricia.gillis@ferc.gov. Deadline for filing comments and motions to intervene: 15 days from the issuance date of this notice. Comments and motions to intervene may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1) and the instructions on the Commission’s Web site under https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original plus seven copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. More information about this project can be viewed or printed on the eLibrary PO 00000 Frm 00018 Fmt 4703 Sfmt 4703 58371 Dated: September 13, 2012. Kimberly D. Bose, Secretary. [FR Doc. 2012–23228 Filed 9–19–12; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP12–516–000] Discovery Gas Transmission LLC; Notice of Application Take notice that on September 7, 2012, Discovery Gas Transmission LLC (Discovery), 2800 Post Oak Boulevard, Houston, Texas 77056, filed in Docket No. CP12–516–000 an application pursuant to section 7 of the Natural Gas Act and Part 157 the Commission’s Rules and Regulations for all the necessary authorizations required to construct, own and operate its Junction Platform Project (Project) in the Gulf of Mexico offshore Louisiana, all as more fully set forth in the application which is on file with the Commission and open to public inspection. Discovery proposes construction and operation of a new junction platform located in South Timbalier Area (ST) Block 283; construction and operation of approximately 10 miles of 30-inch pipeline connecting the new platform to a subsea interconnect with Discovery’s existing 30-inch mainline in Ewing Banks Area Block 873; construction and operation of approximately 10 miles of 12-inch pipeline connecting the new platform to Sea Robin Pipeline Company, LLC’s offshore pipeline system in ST Block 280; and appurtenant facilities on the new platform to provide pigging and other necessary functions to enhance efficient operations. The estimated cost of the Project is approximately $126 million. Copies of this filing are available for review at the Commission in the Public Reference Room, or may be viewed on the Commission’s Web site web at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TTY, (202) 502–8659. E:\FR\FM\20SEN1.SGM 20SEN1 mstockstill on DSK4VPTVN1PROD with NOTICES 58372 Federal Register / Vol. 77, No. 183 / Thursday, September 20, 2012 / Notices Questions regarding this application should be directed to Larry Jensen, 2800 Post Oak Boulevard, Houston, Texas 77056, telephone (713) 215–3034. Discovery has requested that the Commission issue a final order in this proceeding by January 31, 2013, to enable Discovery to commence construction of the proposed facilities to meet a July 1, 2014 in-service date. As Discovery’s proposed facilities entirely in the federal waters of the Gulf of Mexico, the Project facilities will qualify for categorical exclusions in accordance with 18 CFR 380.(4)(a)(33) and 18 CFR 380.4(a)(34) which state ‘‘* * * neither an environmental assessment nor an environmental impact statement shall be prepared for the following projects or actions: * * * (33) construction or abandonment of facilities constructed entirely in Federal offshore waters that has been approved by the Mineral Management Service and the Corps of Engineers, as necessary; (34) Abandonment or construction facilities on an existing offshore platform.’’ Thus the application must be approved by the Bureau of Safety and Environmental Enforcement of the U.S. Department of the Interior, successor to the Mineral Management Service for this approval function, prior to the project being considered by the Commission as eligible for a categorical exclusion classification under the Commission’s environmental review process. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, before the comment date of this notice, file with the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 14 copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of VerDate Mar<15>2010 16:11 Sep 19, 2012 Jkt 226001 comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. The Commission strongly encourages electronic filings of comments, protests, and interventions via the internet in lieu of paper. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site (www.ferc.gov) under the ‘‘e-Filing’’ link. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy regulatory Commission, 888 First Street NE., Washington, DC 20426. Comment Date: 5 p.m. Eastern Time on October 5, 2012. Dated: September 14, 2012. Kimberly D. Bose, Secretary. [FR Doc. 2012–23226 Filed 9–19–12; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #1 Take notice that the Commission received the following electric rate filings: Docket Numbers: ER10–2639–002; ER11–2200–002; ER12–1716–001. Applicants: Noble Americas Gas & Power Corp., Noble Americas Energy Solutions LLC, Your Energy Holdings, LLC. Description: Noble Americas Gas & Power Corp., et al. submit revised Asset Appendix A. Filed Date: 9/7/12. Accession Number: 20120907–5238. Comments Due: 5 p.m. ET 9/28/12. Docket Numbers: ER12–1280–001. Applicants: Wolverine Creek Energy LLC. Description: Wolverine Creek Energy LLC submits tariff filing per 35: Compliance Filing of Amended Common Facilities Agreement to be effective 9/7/2012. Filed Date: 9/13/12. Accession Number: 20120913–5031. Comments Due: 5 p.m. ET 10/4/12. Docket Numbers: ER12–1281–001. Applicants: Wolverine Creek Goshen Interconnection LLC. PO 00000 Frm 00019 Fmt 4703 Sfmt 4703 Description: Wolverine Creek Goshen Interconnection LLC submits tariff filing per 35: Compliance Filing of Amended Common Facilities Agreement to be effective 9/7/2012. Filed Date: 9/13/12. Accession Number: 20120913–5032. Comments Due: 5 p.m. ET 10/4/12. Docket Numbers: ER12–2127–002. Applicants: ITC Midwest LLC. Description: Amendment Filing of ITC Midwest to be effective 8/28/2012. Filed Date: 9/12/12. Accession Number: 20120912–5136. Comments Due: 5 p.m. ET 10/3/12. Docket Numbers: ER12–2618–000. Applicants: Southern California Edison Company. Description: GIA and Distribution Serv Agmt SunEdison Utility Solutions LLC S. Dupont Project to be effective 9/ 14/2012. Filed Date: 9/13/12. Accession Number: 20120913–5017. Comments Due: 5 p.m. ET 10/4/12. Docket Numbers: ER12–2619–000. Applicants: Eligo Energy, LLC. Description: Eligo Energy, LLC submits tariff filing per 35.12: Initial Eligo Energy Market Based Rate Filing to be effective 11/15/2012. Filed Date: 9/13/12. Accession Number: 20120913–5030. Comments Due: 5 p.m. ET 10/4/12. Docket Numbers: ER12–2620–000. Applicants: Idaho Power Company. Description: Idaho Power Company submits tariff filing per 35.13(a)(2)(iii: September 2012 Baseline Filing Correction (Attachment K) to be effective 1/7/2011. Filed Date: 9/13/12. Accession Number: 20120913–5036. Comments Due: 5 p.m. ET 10/4/12. Docket Numbers: ER12–2621–000. Applicants: Wolverine Power Supply Cooperative, Inc. Description: Wolverine Power Supply Cooperative, Inc. submits tariff filing per 35: Re-File -Amend Filing FERC Rate Schedules 1, 2 and 3 to be effective 9/13/2012. Filed Date: 9/13/12. Accession Number: 20120913–5044. Comments Due: 5 p.m. ET 10/4/12. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but E:\FR\FM\20SEN1.SGM 20SEN1

Agencies

[Federal Register Volume 77, Number 183 (Thursday, September 20, 2012)]
[Notices]
[Pages 58371-58372]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-23226]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP12-516-000]


Discovery Gas Transmission LLC; Notice of Application

    Take notice that on September 7, 2012, Discovery Gas Transmission 
LLC (Discovery), 2800 Post Oak Boulevard, Houston, Texas 77056, filed 
in Docket No. CP12-516-000 an application pursuant to section 7 of the 
Natural Gas Act and Part 157 the Commission's Rules and Regulations for 
all the necessary authorizations required to construct, own and operate 
its Junction Platform Project (Project) in the Gulf of Mexico offshore 
Louisiana, all as more fully set forth in the application which is on 
file with the Commission and open to public inspection.
    Discovery proposes construction and operation of a new junction 
platform located in South Timbalier Area (ST) Block 283; construction 
and operation of approximately 10 miles of 30-inch pipeline connecting 
the new platform to a subsea interconnect with Discovery's existing 30-
inch mainline in Ewing Banks Area Block 873; construction and operation 
of approximately 10 miles of 12-inch pipeline connecting the new 
platform to Sea Robin Pipeline Company, LLC's offshore pipeline system 
in ST Block 280; and appurtenant facilities on the new platform to 
provide pigging and other necessary functions to enhance efficient 
operations. The estimated cost of the Project is approximately $126 
million.
    Copies of this filing are available for review at the Commission in 
the Public Reference Room, or may be viewed on the Commission's Web 
site web at  https://www.ferc.gov using the ``eLibrary'' link. Enter the 
docket number excluding the last three digits in the docket number 
field to access the document. For assistance, contact FERC at 
FERCOnlineSupport@ferc.gov or call toll-free, (886) 208-3676 or TTY, 
(202) 502-8659.

[[Page 58372]]

    Questions regarding this application should be directed to Larry 
Jensen, 2800 Post Oak Boulevard, Houston, Texas 77056, telephone (713) 
215-3034.
    Discovery has requested that the Commission issue a final order in 
this proceeding by January 31, 2013, to enable Discovery to commence 
construction of the proposed facilities to meet a July 1, 2014 in-
service date. As Discovery's proposed facilities entirely in the 
federal waters of the Gulf of Mexico, the Project facilities will 
qualify for categorical exclusions in accordance with 18 CFR 
380.(4)(a)(33) and 18 CFR 380.4(a)(34) which state ``* * * neither an 
environmental assessment nor an environmental impact statement shall be 
prepared for the following projects or actions: * * * (33) construction 
or abandonment of facilities constructed entirely in Federal offshore 
waters that has been approved by the Mineral Management Service and the 
Corps of Engineers, as necessary; (34) Abandonment or construction 
facilities on an existing offshore platform.'' Thus the application 
must be approved by the Bureau of Safety and Environmental Enforcement 
of the U.S. Department of the Interior, successor to the Mineral 
Management Service for this approval function, prior to the project 
being considered by the Commission as eligible for a categorical 
exclusion classification under the Commission's environmental review 
process.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, before the 
comment date of this notice, file with the Federal Energy Regulatory 
Commission, 888 First Street NE., Washington, DC 20426, a motion to 
intervene in accordance with the requirements of the Commission's Rules 
of Practice and Procedure (18 CFR 385.214 or 385.211) and the 
Regulations under the NGA (18 CFR 157.10). A person obtaining party 
status will be placed on the service list maintained by the Secretary 
of the Commission and will receive copies of all documents filed by the 
applicant and by all other parties. A party must submit 14 copies of 
filings made with the Commission and must mail a copy to the applicant 
and to every other party in the proceeding. Only parties to the 
proceeding can ask for court review of Commission orders in the 
proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    The Commission strongly encourages electronic filings of comments, 
protests, and interventions via the internet in lieu of paper. See 18 
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web 
site (www.ferc.gov) under the ``e-Filing'' link. Persons unable to file 
electronically should submit an original and 14 copies of the protest 
or intervention to the Federal Energy regulatory Commission, 888 First 
Street NE., Washington, DC 20426.
    Comment Date: 5 p.m. Eastern Time on October 5, 2012.

    Dated: September 14, 2012.
 Kimberly D. Bose,
 Secretary.
[FR Doc. 2012-23226 Filed 9-19-12; 8:45 am]