Notice of Application, 58368-58369 [2012-23225]
Download as PDF
58368
Federal Register / Vol. 77, No. 183 / Thursday, September 20, 2012 / Notices
Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item (h) above.
m. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Procedural Schedule: A
preliminary Hydro Licensing Schedule
will be provided in a subsequent notice.
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Dated: September 13, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–23224 Filed 9–19–12; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Application
mstockstill on DSK4VPTVN1PROD with NOTICES
Corpus Christi LiqueDocket No. CP12–
faction, LLC.
507–000.
Cheniere Corpus
Docket No. CP12–
Christi Pipeline, L.P.
508–000, PF12–3–
000.
On August 31, 2012, Corpus Christi
Liquefaction, LLC (CCL), located at 700
Milam Street, Suite 800, Houston, Texas
77002, filed with the Federal Energy
Regulatory Commission (Commission)
an application in Docket No. CP12–507–
000, under section 3(a) of the Natural
Gas Act (NGA), as amended, and parts
153 and 380 of the Commission’s
regulations for authorization to site,
construct, and operate a liquefied
natural gas (LNG) export and import
facility to be located near Corpus
Christi, in San Patricio and Nueces
Counties, Texas, at the site of the
previously authorized, but never
constructed, Corpus Christi LNG, LLC
LNG import terminal.
In the same application, Cheniere
Corpus Christi Pipeline, L.P. (CCP)
(together Corpus Christi), located at 700
Milam Street, Suite 800, Houston, Texas
77002, filed with the Commission an
application in Docket No. CP12–508–
000, under section 7(c) of the NGA and
parts 157, 284, and 380 of the
Commission’s regulations for (1) A
certificate of public convenience and
VerDate Mar<15>2010
16:11 Sep 19, 2012
Jkt 226001
necessity (i) authorizing ccp to
construct, own and operate a new
natural gas pipeline, (ii) approving a pro
forma Tariff, and (iii) approving the
proposed initial rates for service; (2) a
blanket certificate authorizing CCP to
engage in certain self-implementing
routine activities under Part 157,
Subpart F, of the Commission’s
regulations; and (3) a blanket certificate
authorizing CCP to transport natural gas,
on an open access and selfimplementing basis, under Part 284,
Subpart G of the Commission’s
regulations.
Any questions regarding the
application should be directed to
Patricia Outtrim, Cheniere Energy, Inc.,
700 Milam Street, Suite 800, Houston,
Texas 77002 (713) 375–5212 or Lisa M.
Tonery, Fulbright & Jaworski L.L.P., 666
Fifth Avenue, New York, NY 10103,
(212) 318–3009, ltonery@fulbright.com.
On December 22, 2011, the
Commission staff granted CCL’s request
to use the pre-filing process and
assigned Docket No. PF12–3–000 for
this proceeding during the pre-filing
review of the project. Now, as of the
filing of CCL’s application on August
31, 2012, the pre-filing process for this
project has ended. From this time
forward, CCL’s proceeding will be
conducted in Docket No. CP12–507–
000, as noted in the caption of this
Notice.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify federal and
state agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
PO 00000
Frm 00015
Fmt 4703
Sfmt 4703
First Street NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
seven copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental cementers will be placed
on the Commission’s environmental
mailing list, will receive copies of the
environmental documents, and will be
notified of meetings associated with the
Commission’s environmental review
process. Environmental cementers will
not be required to serve copies of filed
documents on all other parties.
However, the nonparty commenters will
not receive copies of all documents filed
by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and seven
copies of the protest or intervention to
the Federal Energy Regulatory
Commission, 888 First Street NE.,
Washington, DC 20426. This filing is
accessible on-line at https://www.ferc.gov
E:\FR\FM\20SEN1.SGM
20SEN1
Federal Register / Vol. 77, No. 183 / Thursday, September 20, 2012 / Notices
using the ‘‘eLibrary’’ link and is
available for review in the
Commission’s Public Reference Room in
Washington, DC. There is an
‘‘eSubscription’’ link on the web site
that enables subscribers to receive email
notification when a document is added
to a subscribed docket(s). For assistance
with any FERC Online service, please
email FERCOnlineSupport@ferc.gov, or
call (866) 208–3676 (toll free) or TTY,
call (202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on October 5, 2012.
Dated: September 14, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–23225 Filed 9–19–12; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 1888–030]
mstockstill on DSK4VPTVN1PROD with NOTICES
York Haven Power Company, LLC;
Notice of Application Tendered for
Filing With the Commission and
Establishing Deadline for Submission
of Final Amendments
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 1888–030.
c. Date Filed: August 30, 2012.
d. Applicant: York Haven Power
Company, LLC.
e. Name of Project: York Haven
Hydroelectric Project.
f. Location: On the Susquehanna
River, in Dauphin, Lancaster, and York
Counties, Pennsylvania. The project
does not occupy any federal lands.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: David R. David,
York Haven Power Company, York
Haven Hydro Station, P.O. Box 67, York
Haven, PA 17370, at (717) 266–9470 or
email at DDavid@yorkhavenpower.com
and Dennis T. O’Donnell, Olympus
Power, LLC, 67 Park Place East,
Morristown, NJ 07960.
i. FERC Contact: Emily Carter, (202)
502–6512 or emily.carter@ferc.gov.
j. This application is not ready for
environmental analysis at this time.
k. The Project Description: The York
Haven Project consists of a headrace
wall, main dam, east channel dam,
powerhouse, and forebay bulkhead. The
stone masonry headrace wall extends
VerDate Mar<15>2010
16:11 Sep 19, 2012
Jkt 226001
3,000 feet upstream from the north end
of the powerhouse and, with an average
height of 20 feet, directs flow to the
powerhouse. The main dam is attached
to the north end of the headrace where
it runs diagonally across the main
channel of the river approximately
4,970 feet to the west shore of Three
Mile Island. The main dam is
constructed of concrete fill, and has a
maximum height at the crest of 17 feet
and an average height of 10 feet. The
east channel dam consists of a concrete
gravity dam that extends approximately
950 feet east from the east shore of
Three Mile Island to the east bank of the
river. The east channel dam has an
average height of 10 feet. The stone
masonry forebay bulkhead wall, 155 feet
long, extends west from the south end
of the powerhouse to the transformer
building, perpendicular to the shoreline.
From the transformer building, the
forebay bulkhead wall extends 475 feet
north along the property line to the west
bank of the river. A 14-foot-wide by
10.5-foot-tall trash sluice gate and
associated spillway are located adjacent
to the southern end of the powerhouse
at the eastern end of the forebay wall.
York Haven’s main dam and east
channel dam impound the Susquehanna
River, forming Lake Frederic that
extends 3.5 miles upstream from the
dam. Total storage in the 1,849-acre
reservoir is approximately 8,000 acrefeet, and total useable storage is
approximately 1,980 acre-feet. The
current FERC license allows a 1.1-foot
fluctuation in the project impoundment,
but is not used under normal run-ofriver operation. The normal water
surface elevation of the project
impoundment is 276.5 feet. The
elevation of the normal river surface
below the dam is approximately 251.40
feet. The impoundment provides
approximately 22.5 feet of net head for
power generation purposes.
The brick and stone masonry
powerhouse has approximate
dimensions of 470 feet by 48 feet and is
located at the southern end of the
headrace wall and at the eastern end of
the forebay bulkhead wall. The
powerhouse includes 20 turbinegenerator units and appurtenant
equipment. The hydraulic equipment
for units 1–3 are vertical-shaft, fixedblade, Kaplan turbines; unit 4 is a
vertical-shaft, manually adjustable
blade, Kaplan turbine; units 5 and 6 are
vertical-shaft, fixed-blade, propellertype turbines; units 7, 8, 10–13, and 15–
20 each consist of two vertical-shaft,
Francis turbines connected through
bevel gears to a single horizontal shaft;
unit 9 is a two vertical-shaft, Francis
turbine connected through a gearbox to
PO 00000
Frm 00016
Fmt 4703
Sfmt 9990
58369
a single horizontal shaft; and unit 14 is
a vertical-shaft, Francis turbine. Units
1–5 have 1.6–MW generators; unit 6 has
a 1.32–MW generator; unit 14 has a 1.2–
MW generator; and units 7–13 and 15–
20 have 0.7–MW generators. Water
flowing through the turbines is
discharged into the tailrace immediately
downstream of the dam.
Electricity generated at the project is
transmitted by 115-kilovolt (kV)
transmission lines extending from the
project substation to the grid.
The York Haven Project has an
authorized nameplate generating
capacity of 19.65 MW and generates an
average of 130,812 MWh annually. York
Haven Power is currently studying the
feasibility of providing a nature-like
fishway to enhance fish passage
facilities at the project.
l. Locations of the Application: A
copy of the application is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item (h) above.
m. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Procedural Schedule: A
preliminary Hydro Licensing Schedule
will be provided in a subsequent notice.
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Dated: September 13, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–23227 Filed 9–19–12; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\20SEN1.SGM
20SEN1
Agencies
[Federal Register Volume 77, Number 183 (Thursday, September 20, 2012)]
[Notices]
[Pages 58368-58369]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-23225]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Application
------------------------------------------------------------------------
------------------------------------------------------------------------
Corpus Christi Liquefaction, LLC.......... Docket No. CP12-507-000.
Cheniere Corpus Christi Pipeline, L.P..... Docket No. CP12-508-000,
PF12-3-000.
------------------------------------------------------------------------
On August 31, 2012, Corpus Christi Liquefaction, LLC (CCL), located
at 700 Milam Street, Suite 800, Houston, Texas 77002, filed with the
Federal Energy Regulatory Commission (Commission) an application in
Docket No. CP12-507-000, under section 3(a) of the Natural Gas Act
(NGA), as amended, and parts 153 and 380 of the Commission's
regulations for authorization to site, construct, and operate a
liquefied natural gas (LNG) export and import facility to be located
near Corpus Christi, in San Patricio and Nueces Counties, Texas, at the
site of the previously authorized, but never constructed, Corpus
Christi LNG, LLC LNG import terminal.
In the same application, Cheniere Corpus Christi Pipeline, L.P.
(CCP) (together Corpus Christi), located at 700 Milam Street, Suite
800, Houston, Texas 77002, filed with the Commission an application in
Docket No. CP12-508-000, under section 7(c) of the NGA and parts 157,
284, and 380 of the Commission's regulations for (1) A certificate of
public convenience and necessity (i) authorizing ccp to construct, own
and operate a new natural gas pipeline, (ii) approving a pro forma
Tariff, and (iii) approving the proposed initial rates for service; (2)
a blanket certificate authorizing CCP to engage in certain self-
implementing routine activities under Part 157, Subpart F, of the
Commission's regulations; and (3) a blanket certificate authorizing CCP
to transport natural gas, on an open access and self-implementing
basis, under Part 284, Subpart G of the Commission's regulations.
Any questions regarding the application should be directed to
Patricia Outtrim, Cheniere Energy, Inc., 700 Milam Street, Suite 800,
Houston, Texas 77002 (713) 375-5212 or Lisa M. Tonery, Fulbright &
Jaworski L.L.P., 666 Fifth Avenue, New York, NY 10103, (212) 318-3009,
ltonery@fulbright.com.
On December 22, 2011, the Commission staff granted CCL's request to
use the pre-filing process and assigned Docket No. PF12-3-000 for this
proceeding during the pre-filing review of the project. Now, as of the
filing of CCL's application on August 31, 2012, the pre-filing process
for this project has ended. From this time forward, CCL's proceeding
will be conducted in Docket No. CP12-507-000, as noted in the caption
of this Notice.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice the Commission staff will either:
complete its environmental assessment (EA) and place it into the
Commission's public record (eLibrary) for this proceeding; or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or EA for this
proposal. The filing of the EA in the Commission's public record for
this proceeding or the issuance of a Notice of Schedule for
Environmental Review will serve to notify federal and state agencies of
the timing for the completion of all necessary reviews, and the
subsequent need to complete all federal authorizations within 90 days
of the date of issuance of the Commission staff's FEIS or EA.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below, file with the Federal Energy
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit seven copies of filings made with the Commission and must mail a
copy to the applicant and to every other party in the proceeding. Only
parties to the proceeding can ask for court review of Commission orders
in the proceeding.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental cementers will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental cementers will not be required to serve copies of filed
documents on all other parties. However, the nonparty commenters will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
The Commission encourages electronic submission of protests and
interventions in lieu of paper using the ``eFiling'' link at https://www.ferc.gov. Persons unable to file electronically should submit an
original and seven copies of the protest or intervention to the Federal
Energy Regulatory Commission, 888 First Street NE., Washington, DC
20426. This filing is accessible on-line at https://www.ferc.gov
[[Page 58369]]
using the ``eLibrary'' link and is available for review in the
Commission's Public Reference Room in Washington, DC. There is an
``eSubscription'' link on the web site that enables subscribers to
receive email notification when a document is added to a subscribed
docket(s). For assistance with any FERC Online service, please email
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free) or TTY,
call (202) 502-8659.
Comment Date: 5 p.m. Eastern Time on October 5, 2012.
Dated: September 14, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-23225 Filed 9-19-12; 8:45 am]
BILLING CODE 6717-01-P