Colorado Interstate Gas Company, L.L.C.; Notice of Intent To Prepare an Environmental Assessment for the Proposed High Plains 2013 Expansion Project and Request for Comments on Environmental Issues, 58122-58124 [2012-23032]

Download as PDF 58122 Federal Register / Vol. 77, No. 182 / Wednesday, September 19, 2012 / Notices Accession Number: 20120912–5122. Comments Due: 5 p.m. e.t. 9/24/12. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. Filings in Existing Proceedings Docket Numbers: RP12–900–001. Applicants: Sea Robin Pipeline Company, LLC. Description: Compliance with RP12– 900–000. Filed Date: 9/12/12. Accession Number: 20120912–5027. Comments Due: 5 p.m. e.t. 9/24/12. Any person desiring to protest in any of the above proceedings must file in accordance with Rule 211 of the Commission’s Regulations (18 CFR 385.211) on or before 5 p.m. Eastern time on the specified comment date. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, and service can be found at: https:// www.ferc.gov/docs-filing/efiling/filingreq.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: September 13, 2012. Nathaniel J. Davis, Sr. Deputy Secretary. [FR Doc. 2012–23079 Filed 9–18–12; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP12–496–000] tkelley on DSK3SPTVN1PROD with NOTICES Colorado Interstate Gas Company, L.L.C.; Notice of Intent To Prepare an Environmental Assessment for the Proposed High Plains 2013 Expansion Project and Request for Comments on Environmental Issues The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the High Plains 2013 Expansion Project involving construction and operation of facilities by Colorado Interstate Gas VerDate Mar<15>2010 19:20 Sep 18, 2012 Jkt 226001 Company, L.L.C. (CIG) in Weld County, Colorado. The Commission will use this EA in its decision-making process to determine whether the project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies on the project. Your input will help the Commission staff determine what issues they need to evaluate in the EA. Please note that the scoping period will close on October 11, 2012. This notice is being sent to the Commission’s current environmental mailing list for this project. State and local government representatives should notify their constituents of this proposed project and encourage them to comment on their areas of concern. If you are a landowner receiving this notice, a pipeline company representative may contact you about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The company would seek to negotiate a mutually acceptable agreement. However, if the Commission approves the project, that approval conveys with it the right of eminent domain. Therefore, if easement negotiations fail to produce an agreement, the pipeline company could initiate condemnation proceedings where compensation would be determined in accordance with state law. CIG provided landowners with a fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility On My Land? What Do I Need To Know?’’. This fact sheet addresses a number of typically-asked questions, including the use of eminent domain and how to participate in the Commission’s proceedings. It is also available for viewing on the FERC Web site (www.ferc.gov). Summary of the Proposed Project CIG proposes to construct and operate the High Plains 2013 Expansion Project in response to demand for additional takeaway capacity from the DenverJulesburg (DJ) Basin to the Cheyenne Hub located in Weld County, Colorado. The High Plains 2013 Expansion Project would provide initially about 225,000 dekatherms per day (Dth per day) and over time, may become capable of transporting up to 600,000 dekatherms per day of natural gas from a new natural gas processing plant to an interconnect with CIG’s exising High Plains System. The High Plains 2013 Expansion Project would consist of the following facilities: PO 00000 Frm 00035 Fmt 4703 Sfmt 4703 • An approximate 7.75 mile 24-inchdiameter lateral pipeline (Lancaster Lateral) connecting natural gas production and processing facilities in the DJ Basin to a connection with its existing High Plains System in Weld County, Colorado; • An overpressure protection facility and pigging facilities at the interconnection of the proposed Lancaster Lateral and CIG’s High Plains System; • Two new receipt meter stations used to measure new sources of supply into the existing High Plains System; • Modify an existing meter station known as the Flying Hawk Meter Station which connects the High Plains System with the Wyoming Interstate Company, L.L.C. System at the Cheyenne Hub to make the meter bidirectional; and • Modifying an existing block valve on the High Plains System by installing pressure control equipment. The general location of the project facilities is shown in appendix 1.1 Land Requirements for Construction Construction of the proposed facilities would disturb about 125.7 acres of land for the aboveground facilities and the pipeline. Following construction, CIG would maintain about 57.9 acres for permanent operation of the project’s facilities; the remaining acreage would be restored and revert to former uses. About 23.2 percent of the proposed pipeline route parallels existing pipeline, utility, or road rights-of-way. The EA Process The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires us 2 to discover and address concerns the public may have about proposals. This process is referred to as ‘‘scoping.’’ The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of the issues to address in the EA. We will consider all 1 The appendices referenced in this notice will not appear in the Federal Register. Copies of appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called ‘‘eLibrary’’ or from the Commission’s Public Reference Room, 888 First Street NE., Washington, DC 20426, or call (202) 502–8371. For instructions on connecting to eLibrary, refer to the last page of this notice. 2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the environmental staff of the Commission’s Office of Energy Projects. E:\FR\FM\19SEN1.SGM 19SEN1 Federal Register / Vol. 77, No. 182 / Wednesday, September 19, 2012 / Notices filed comments during the preparation of the EA. In the EA we will discuss impacts that could occur as a result of the construction and operation of the proposed project under these general headings: • Geology and soils; • Land use; • Water resources, fisheries, and wetlands; • Cultural resources; • Vegetation and wildlife; • Air quality and noise; • Endangered and threatened species; and • Public safety. We will also evaluate reasonable alternatives to the proposed project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas. The EA will present our independent analysis of the issues. The EA will be available in the public record through eLibrary. Depending on the comments received during the scoping process, we may also publish and distribute the EA to the public for an allotted comment period. We will consider all comments on the EA before making our recommendations to the Commission. To ensure we have the opportunity to consider and address your comments, please carefully follow the instructions in the Public Participation section beginning on page 5. With this notice, we are asking agencies with jurisdiction by law and/ or special expertise with respect to the environmental issues of this project to formally cooperate with us in the preparation of the EA 3. Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. tkelley on DSK3SPTVN1PROD with NOTICES Consultations Under Section 106 of the National Historic Preservation Act In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, we are using this notice to initiate consultation with applicable State Historic Preservation Office (SHPO), and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project’s potential effects on 3 The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Part 1501.6. VerDate Mar<15>2010 19:20 Sep 18, 2012 Jkt 226001 historic properties.4 We will define the project-specific Area of Potential Effects (APE) in consultation with the SHPO as the project develops. On natural gas facility projects, the APE at a minimum encompasses all areas subject to ground disturbance (examples include construction right-of-way, contractor/ pipe storage yards, compressor stations, and access roads). Our EA for this project will document our findings on the impacts on historic properties and summarize the status of consultations under section 106. Currently Identified Environmental Issues We have already identified several issues that we think deserve attention based on a preliminary review of the proposed facilities and the environmental information provided by CIG. This preliminary list of issues may be changed based on your comments and our analysis. • The project could potentially impact federally listed endangered or threatened species. • Several residences along the pipeline route may by impacted by noise from horizontal directional drilling. Public Participation You can make a difference by providing us with your specific comments or concerns about the project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure that your comments are timely and properly recorded, please send your comments so that the Commission receives them in Washington, DC on or before October 11, 2012. For your convenience, there are three methods which you can use to submit your comments to the Commission. In all instances please reference the project docket number (CP12–496–000) with your submission. The Commission encourages electronic filing of comments and has expert staff available to assist you at (202) 502–8258 or efiling@ferc.gov. (1) You can file your comments electronically using the eComment feature on the Commission’s Web site (www.ferc.gov) under the link to 4 The Advisory Council on Historic Preservation’s regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places. PO 00000 Frm 00036 Fmt 4703 Sfmt 4703 58123 Documents and Filings. This is an easy method for interested persons to submit brief, text-only comments on a project; (2) You can file your comments electronically using the eFiling feature on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You must select the type of filing you are making. If you are filing a comment on a particular project, please select ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments by mailing them to the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 20426. Environmental Mailing List The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project. We will update the environmental mailing list as the analysis proceeds to ensure that we send the information related to this environmental review to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. If we publish and distribute the EA, copies will be sent to the environmental mailing list for public review and comment. If you would prefer to receive a paper copy of the document instead of the CD version or would like to remove your name from the mailing list, please return the attached Information Request (appendix 2). Becoming an Intervenor In addition to involvement in the EA scoping process, you may want to become an ‘‘intervenor’’ which is an official party to the Commission’s proceeding. Intervenors play a more formal role in the process and are able to file briefs, appear at hearings, and be heard by the courts if they choose to appeal the Commission’s final ruling. An intervenor formally participates in E:\FR\FM\19SEN1.SGM 19SEN1 58124 Federal Register / Vol. 77, No. 182 / Wednesday, September 19, 2012 / Notices the proceeding by filing a request to intervene. Instructions for becoming an intervenor are in the User’s Guide under the ‘‘e-filing’’ link on the Commission’s Web site. Additional Information Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC Web site at www.ferc.gov using the ‘‘eLibrary’’ link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number, excluding the last three digits in the Docket Number field (i.e., CP12–496). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission now offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/ esubscribenow.htm. Finally, public meetings or site visits will be posted on the Commission’s calendar located at www.ferc.gov/ EventCalendar/EventsList.aspx along with other related information. Dated: September 11, 2012. Kimberly D. Bose, Secretary. [FR Doc. 2012–23032 Filed 9–18–12; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 6492–009] tkelley on DSK3SPTVN1PROD with NOTICES Hardins Manufacturing Company, Hardins Resources Company; Notice of Transfer of Exemption 1. By email filed April 23, 2012, Hardins Manufacturing Company informed the Commission that its exemption from licensing for the Hardins Hydro-Power Project No. 6492, originally issued December 8, 1982,1 has 1 21 FERC ¶ 62,400, Order Granting Exemption From Licensing of a Small Hydroelectric Project of 5 Megawatts or Less. VerDate Mar<15>2010 19:20 Sep 18, 2012 Jkt 226001 been transferred to Hardins Resources Company. The project is located on the South Fork, Catawba River in Gaston County, North Carolina. The transfer of an exemption does not require Commission approval. 2. Hardins Resources Company, located at 11800 Henderson Road, Clifton, VA 20124 is now the exemptee of the Hardins Hydro-Power Project No. 6492. Dated: September 12, 2012. Kimberly D. Bose, Secretary. [FR Doc. 2012–23026 Filed 9–18–12; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. ER12–2614–000] Dynamo Power LLC; Supplemental Notice That Initial Market-Based Rate Filing Includes Request for Blanket Section 204 Authorization This is a supplemental notice in the above-referenced proceeding, of Dynamo Power LLC’s application for market-based rate authority, with an accompanying rate schedule, noting that such application includes a request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability. Any person desiring to intervene or to protest should file with the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426, in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant. Notice is hereby given that the deadline for filing protests with regard to the applicant’s request for blanket authorization, under 18 CFR part 34, of future issuances of securities and assumptions of liability is October 3, 2012. The Commission encourages electronic submission of protests and interventions in lieu of paper, using the FERC Online links at https:// www.ferc.gov. To facilitate electronic service, persons with Internet access who will eFile a document and/or be listed as a contact for an intervenor must create and validate an eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. PO 00000 Frm 00037 Fmt 4703 Sfmt 9990 Persons unable to file electronically should submit an original and 14 copies of the intervention or protest to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The filings in the above-referenced proceeding(s) are accessible in the Commission’s eLibrary system by clicking on the appropriate link in the above list. They are also available for review in the Commission’s Public Reference Room in Washington, DC. There is an eSubscription link on the web site that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov. or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: September 13, 2012. Nathaniel J. Davis, Sr., Deputy Secretary. [FR Doc. 2012–23044 Filed 9–18–12; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 14436–000] Kaweah River Power Authority; Errata Notice On August 22, 2012, the Commission issued a Notice in the above-referenced proceeding. Notice of Preliminary Permit Application Accepted For Filing And Soliciting Comments, Motions To Intervene, And Competing Applications, August 22, 2012. (August 22, 2012). The county location of the project was incorrectly identified as Tulare County, Nevada. The correct county location of the project is Tulare County, California. Dated: September 11, 2012. Kimberly D. Bose, Secretary. [FR Doc. 2012–23021 Filed 9–18–12; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\19SEN1.SGM 19SEN1

Agencies

[Federal Register Volume 77, Number 182 (Wednesday, September 19, 2012)]
[Notices]
[Pages 58122-58124]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-23032]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP12-496-000]


Colorado Interstate Gas Company, L.L.C.; Notice of Intent To 
Prepare an Environmental Assessment for the Proposed High Plains 2013 
Expansion Project and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the High Plains 2013 Expansion 
Project involving construction and operation of facilities by Colorado 
Interstate Gas Company, L.L.C. (CIG) in Weld County, Colorado. The 
Commission will use this EA in its decision-making process to determine 
whether the project is in the public convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the project. Your input will help the Commission staff 
determine what issues they need to evaluate in the EA. Please note that 
the scoping period will close on October 11, 2012.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    CIG provided landowners with a fact sheet prepared by the FERC 
entitled ``An Interstate Natural Gas Facility On My Land? What Do I 
Need To Know?''. This fact sheet addresses a number of typically-asked 
questions, including the use of eminent domain and how to participate 
in the Commission's proceedings. It is also available for viewing on 
the FERC Web site (www.ferc.gov).

Summary of the Proposed Project

    CIG proposes to construct and operate the High Plains 2013 
Expansion Project in response to demand for additional takeaway 
capacity from the Denver-Julesburg (DJ) Basin to the Cheyenne Hub 
located in Weld County, Colorado. The High Plains 2013 Expansion 
Project would provide initially about 225,000 dekatherms per day (Dth 
per day) and over time, may become capable of transporting up to 
600,000 dekatherms per day of natural gas from a new natural gas 
processing plant to an interconnect with CIG's exising High Plains 
System.
    The High Plains 2013 Expansion Project would consist of the 
following facilities:
     An approximate 7.75 mile 24-inch-diameter lateral pipeline 
(Lancaster Lateral) connecting natural gas production and processing 
facilities in the DJ Basin to a connection with its existing High 
Plains System in Weld County, Colorado;
     An overpressure protection facility and pigging facilities 
at the interconnection of the proposed Lancaster Lateral and CIG's High 
Plains System;
     Two new receipt meter stations used to measure new sources 
of supply into the existing High Plains System;
     Modify an existing meter station known as the Flying Hawk 
Meter Station which connects the High Plains System with the Wyoming 
Interstate Company, L.L.C. System at the Cheyenne Hub to make the meter 
bi-directional; and
     Modifying an existing block valve on the High Plains 
System by installing pressure control equipment.
    The general location of the project facilities is shown in appendix 
1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called ``eLibrary'' or from the Commission's Public 
Reference Room, 888 First Street NE., Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the proposed facilities would disturb about 125.7 
acres of land for the aboveground facilities and the pipeline. 
Following construction, CIG would maintain about 57.9 acres for 
permanent operation of the project's facilities; the remaining acreage 
would be restored and revert to former uses. About 23.2 percent of the 
proposed pipeline route parallels existing pipeline, utility, or road 
rights-of-way.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\2\ to discover and address concerns the public may have about 
proposals. This process is referred to as ``scoping.'' The main goal of 
the scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all

[[Page 58123]]

filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed project under these 
general headings:
     Geology and soils;
     Land use;
     Water resources, fisheries, and wetlands;
     Cultural resources;
     Vegetation and wildlife;
     Air quality and noise;
     Endangered and threatened species; and
     Public safety.
    We will also evaluate reasonable alternatives to the proposed 
project or portions of the project, and make recommendations on how to 
lessen or avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary. Depending on 
the comments received during the scoping process, we may also publish 
and distribute the EA to the public for an allotted comment period. We 
will consider all comments on the EA before making our recommendations 
to the Commission. To ensure we have the opportunity to consider and 
address your comments, please carefully follow the instructions in the 
Public Participation section beginning on page 5.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues of 
this project to formally cooperate with us in the preparation of the EA 
\3\. Agencies that would like to request cooperating agency status 
should follow the instructions for filing comments provided under the 
Public Participation section of this notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with applicable State Historic Preservation Office (SHPO), and to 
solicit their views and those of other government agencies, interested 
Indian tribes, and the public on the project's potential effects on 
historic properties.\4\ We will define the project-specific Area of 
Potential Effects (APE) in consultation with the SHPO as the project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EA for this project will document our 
findings on the impacts on historic properties and summarize the status 
of consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Currently Identified Environmental Issues

    We have already identified several issues that we think deserve 
attention based on a preliminary review of the proposed facilities and 
the environmental information provided by CIG. This preliminary list of 
issues may be changed based on your comments and our analysis.
     The project could potentially impact federally listed 
endangered or threatened species.
     Several residences along the pipeline route may by 
impacted by noise from horizontal directional drilling.

Public Participation

    You can make a difference by providing us with your specific 
comments or concerns about the project. Your comments should focus on 
the potential environmental effects, reasonable alternatives, and 
measures to avoid or lessen environmental impacts. The more specific 
your comments, the more useful they will be. To ensure that your 
comments are timely and properly recorded, please send your comments so 
that the Commission receives them in Washington, DC on or before 
October 11, 2012.
    For your convenience, there are three methods which you can use to 
submit your comments to the Commission. In all instances please 
reference the project docket number (CP12-496-000) with your 
submission. The Commission encourages electronic filing of comments and 
has expert staff available to assist you at (202) 502-8258 or 
efiling@ferc.gov.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for interested persons to 
submit brief, text-only comments on a project;
    (2) You can file your comments electronically using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' You must select the type of filing you are making. If 
you are filing a comment on a particular project, please select 
``Comment on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 
20426.

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
proposed project.
    If we publish and distribute the EA, copies will be sent to the 
environmental mailing list for public review and comment. If you would 
prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in

[[Page 58124]]

the proceeding by filing a request to intervene. Instructions for 
becoming an intervenor are in the User's Guide under the ``e-filing'' 
link on the Commission's Web site.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., CP12-
496). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission now offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/esubscribenow.htm.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: September 11, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-23032 Filed 9-18-12; 8:45 am]