Public Service Company of New Hampshire; Notice of Intent To File License Application, Filing of Pre-Application Document (PAD), Commencement of Pre-Filing Process, and Scoping; Request for Comments on the PAD And Scoping Document, and Identification of Issues and Associated Study Requests, 55210-55211 [2012-22054]

Download as PDF 55210 Federal Register / Vol. 77, No. 174 / Friday, September 7, 2012 / Notices to Documents and Filings. This is an easy method for interested persons to submit brief, text-only comments on a project; (2) You can file your comments electronically using the eFiling feature located on the Commission’s Web site (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You must select the type of filing you are making. If you are filing a comment on a particular project, please select ‘‘Comment on a Filing’’; or (3) You can file a paper copy of your comments by mailing them to the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC 20426. srobinson on DSK4SPTVN1PROD with NOTICES Environmental Mailing List The environmental mailing list includes Federal, State, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-of-way grantors, whose property may be used temporarily for Project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the Project. We will update the environmental mailing list as the analysis proceeds to ensure that we send the information related to this environmental review to all individuals, organizations, and government entities interested in and/or potentially affected by the planned Project. Copies of the completed EA will be sent to the environmental mailing list for public review and comment. If you would prefer to receive a paper copy of the document instead of the CD version or would like to remove your name from the mailing list, please return the attached Information Request (Appendix 3). An intervenor formally participates in the proceeding by filing a request to intervene. Instructions for becoming an intervenor are in the User’s Guide under the ‘‘e-filing’’ link on the Commission’s Web site. Please note that the Commission will not accept requests for intervenor status at this time. You must wait until the Commission receives a formal application for the Project. Additional Information Additional information about the Project is available from the Commission’s Office of External Affairs, at (866) 208–FERC, or on the FERC Web site (www.ferc.gov) using the eLibrary link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number, excluding the last three digits in the Docket Number field (i.e., PF12– 15). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to www.ferc.gov/ esubscribenow.htm. Finally, public meetings or site visits will be posted on the Commission’s calendar located at www.ferc.gov/ EventCalendar/EventsList.aspx along with other related information. Dated: August 30, 2012. Kimberly D. Bose, Secretary. [FR Doc. 2012–22044 Filed 9–6–12; 8:45 am] BILLING CODE 6717–01–P Becoming an Intervenor Once Transco files its application with the Commission, you may want to become an ‘‘intervenor,’’ which is an official party to the Commission’s proceeding. Intervenors play a more formal role in the process and are able to file briefs, appear at hearings, and be heard by the courts if they choose to appeal the Commission’s final ruling. VerDate Mar<15>2010 17:04 Sep 06, 2012 Jkt 226001 PO 00000 Frm 00031 Fmt 4703 Sfmt 4703 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2457–038] Public Service Company of New Hampshire; Notice of Intent To File License Application, Filing of PreApplication Document (PAD), Commencement of Pre-Filing Process, and Scoping; Request for Comments on the PAD And Scoping Document, and Identification of Issues and Associated Study Requests a. Type of Filing: Notice of Intent to File License Application for a New License and Commencing Pre-filing Process. b. Project No.: 2457–038. c. Dated Filed: July 2, 2012. d. Submitted By: Public Service Company of New Hampshire (PSNH). e. Name of Project: Eastman Falls Hydroelectric Project. f. Location: On the Pemigewasset River in the city of Franklin and the towns of Hill, Sanbornton, Bristol, and New Hampton, within Merrimack and Belknap Counties, New Hampshire. The project does not affect federal lands. g. Filed Pursuant to: 18 CFR part 5 of the Commission’s Regulations. h. Potential Applicant Contact: Mr. Curtis R. Mooney; Project Manager, PSNH; 780 North Commercial Street, Manchester, NH 03105–0330; (603) 669– 4000. i. FERC Contact: Samantha Davidson at (202) 502–6839 or email at samantha.davidson@ferc.gov. j. Cooperating agencies: Federal, state, local, and tribal agencies with jurisdiction and/or special expertise with respect to environmental issues that wish to cooperate in the preparation of the environmental document should follow the instructions for filing such requests described in item o below. Cooperating agencies should note the Commission’s policy that agencies that cooperate in the preparation of the environmental document cannot also intervene. See 94 FERC ¶ 61,076 (2001). k. With this notice, we are initiating informal consultation with: (a) The U.S. Fish and Wildlife Service and/or NOAA Fisheries under section 7 of the Endangered Species Act and the joint agency regulations thereunder at 50 CFR, Part 402; and (b) the State Historic Preservation Officer, as required by section 106, National Historical Preservation Act, and the implementing regulations of the Advisory Council on Historic Preservation at 36 CFR 800.2. E:\FR\FM\07SEN1.SGM 07SEN1 srobinson on DSK4SPTVN1PROD with NOTICES Federal Register / Vol. 77, No. 174 / Friday, September 7, 2012 / Notices l. With this notice, we are designating PSNH as the Commission’s non-federal representative for carrying out informal consultation, pursuant to section 7 of the Endangered Species Act and section 106 of the National Historic Preservation Act. m. PSNH filed with the Commission a Pre-Application Document (PAD; including a proposed process plan and schedule), pursuant to 18 CFR 5.6 of the Commission’s regulations. n. A copy of the PAD is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site (https:// www.ferc.gov), using the ‘‘eLibrary’’ link. Enter the docket number, excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCONlineSupport@ferc.gov or toll free at 1–866–208–3676, or for TTY, (202) 502–8659. A copy is also available for inspection and reproduction at the address in paragraph h. Register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filing and issuances related to this or other pending projects. For assistance, contact FERC Online Support. o. With this notice, we are soliciting comments on the PAD and Commission’s staff Scoping Document 1 (SD1), as well as study requests. All comments on the PAD and SD1, and study requests should be sent to the address above in paragraph h. In addition, all comments on the PAD and SD1, study requests, requests for cooperating agency status, and all communications to and from Commission staff related to the merits of the potential application must be filed with the Commission. Documents may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and seven copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. VerDate Mar<15>2010 17:04 Sep 06, 2012 Jkt 226001 All filings with the Commission must include on the first page, the project name (Eastman Falls Hydroelectric Project) and number (P–2457–038), and bear the appropriate heading: ‘‘Comments on Pre-Application Document,’’ ‘‘Study Requests,’’ ‘‘Comments on Scoping Document 1,’’ ‘‘Request for Cooperating Agency Status,’’ or ‘‘Communications to and from Commission Staff.’’ Any individual or entity interested in submitting study requests, commenting on the PAD or SD1, and any agency requesting cooperating status must do so by October 30, 2012. p. Although our current intent is to prepare an environmental assessment (EA), there is the possibility that an Environmental Impact Statement (EIS) will be required. Nevertheless, this meeting will satisfy the NEPA scoping requirements, irrespective of whether an EA or EIS is issued by the Commission. Scoping Meetings Commission staff will hold two scoping meetings in the vicinity of the project at the time and place noted below. The daytime meeting will focus on resource agency, Indian tribes, and non-governmental organization concerns, while the evening meeting is primarily for receiving input from the public. We invite all interested individuals, organizations, and agencies to attend one or both of the meetings, and to assist staff in identifying particular study needs, as well as the scope of environmental issues to be addressed in the environmental document. The times and locations of these meetings are as follows: Daytime Scoping Meeting Date: Wednesday, September 19, 2012. Time: 1:00 p.m. (EST). Location: Franklin City Hall Opera House, 316 Central Street, Franklin, NH, 03235. Phone: (603) 934–1901. Evening Scoping Meeting Date: Wednesday, September 19, 2012. Time: 7:00 p.m. (EST). Location: Franklin City Hall Opera House, 316 Central Street, Franklin, NH, 03235. Phone: (603) 934–1901. Scoping Document 1 (SD1), which outlines the subject areas to be addressed in the environmental document, was mailed to the individuals and entities on the Commission’s mailing list. Copies of SD1 will be available at the scoping meetings, or may be viewed on the web PO 00000 Frm 00032 Fmt 4703 Sfmt 9990 55211 at https://www.ferc.gov, using the ‘‘eLibrary’’ link. Follow the directions for accessing information in paragraph n. Based on all oral and written comments, a Scoping Document 2 (SD2) may be issued. SD2 may include a revised process plan and schedule, as well as a list of issues, identified through the scoping process. Site Visit The potential applicant and Commission staff will conduct a site visit of the project on Tuesday, September 18, 2012, starting at 11:00 a.m. All participants should meet at the Eastman Falls dam, located at 215 North Main Street, Franklin, NH 03235. All participants are responsible for their own transportation. Anyone with questions about the site visit should contact Mr. Curtis Mooney at (603) 744– 5841 (ext. 5841) or curtis.mooney@nu.com on or before September 12, 2012. Meeting Objectives At the scoping meetings, staff will: (1) Initiate scoping of the issues; (2) review and discuss existing conditions and resource management objectives; (3) review and discuss existing information and identify preliminary information and study needs; (4) review and discuss the process plan and schedule for prefiling activity that incorporates the time frames provided for in Part 5 of the Commission’s regulations and, to the extent possible, maximizes coordination of federal, state, and tribal permitting and certification processes; and (5) discuss the appropriateness of any federal or state agency or Indian tribe acting as a cooperating agency for development of an environmental document. Meeting participants should come prepared to discuss their issues and/or concerns. Please review the PAD in preparation for the scoping meetings. Directions on how to obtain a copy of the PAD and SD1 are included in item n. of this document. Meeting Procedures The meetings will be recorded by a stenographer and will be placed in the public records of the project. Dated: August 31, 2012. Kimberly D. Bose, Secretary. [FR Doc. 2012–22054 Filed 9–6–12; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\07SEN1.SGM 07SEN1

Agencies

[Federal Register Volume 77, Number 174 (Friday, September 7, 2012)]
[Notices]
[Pages 55210-55211]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-22054]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2457-038]


Public Service Company of New Hampshire; Notice of Intent To File 
License Application, Filing of Pre-Application Document (PAD), 
Commencement of Pre-Filing Process, and Scoping; Request for Comments 
on the PAD And Scoping Document, and Identification of Issues and 
Associated Study Requests

    a. Type of Filing: Notice of Intent to File License Application for 
a New License and Commencing Pre-filing Process.
    b. Project No.: 2457-038.
    c. Dated Filed: July 2, 2012.
    d. Submitted By: Public Service Company of New Hampshire (PSNH).
    e. Name of Project: Eastman Falls Hydroelectric Project.
    f. Location: On the Pemigewasset River in the city of Franklin and 
the towns of Hill, Sanbornton, Bristol, and New Hampton, within 
Merrimack and Belknap Counties, New Hampshire. The project does not 
affect federal lands.
    g. Filed Pursuant to: 18 CFR part 5 of the Commission's 
Regulations.
    h. Potential Applicant Contact: Mr. Curtis R. Mooney; Project 
Manager, PSNH; 780 North Commercial Street, Manchester, NH 03105-0330; 
(603) 669-4000.
    i. FERC Contact: Samantha Davidson at (202) 502-6839 or email at 
samantha.davidson@ferc.gov.
    j. Cooperating agencies: Federal, state, local, and tribal agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues that wish to cooperate in the preparation of the 
environmental document should follow the instructions for filing such 
requests described in item o below. Cooperating agencies should note 
the Commission's policy that agencies that cooperate in the preparation 
of the environmental document cannot also intervene. See 94 FERC ] 
61,076 (2001).
    k. With this notice, we are initiating informal consultation with: 
(a) The U.S. Fish and Wildlife Service and/or NOAA Fisheries under 
section 7 of the Endangered Species Act and the joint agency 
regulations thereunder at 50 CFR, Part 402; and (b) the State Historic 
Preservation Officer, as required by section 106, National Historical 
Preservation Act, and the implementing regulations of the Advisory 
Council on Historic Preservation at 36 CFR 800.2.

[[Page 55211]]

    l. With this notice, we are designating PSNH as the Commission's 
non-federal representative for carrying out informal consultation, 
pursuant to section 7 of the Endangered Species Act and section 106 of 
the National Historic Preservation Act.
    m. PSNH filed with the Commission a Pre-Application Document (PAD; 
including a proposed process plan and schedule), pursuant to 18 CFR 5.6 
of the Commission's regulations.
    n. A copy of the PAD is available for review at the Commission in 
the Public Reference Room or may be viewed on the Commission's Web site 
(https://www.ferc.gov), using the ``eLibrary'' link. Enter the docket 
number, excluding the last three digits in the docket number field to 
access the document. For assistance, contact FERC Online Support at 
FERCONlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY, 
(202) 502-8659. A copy is also available for inspection and 
reproduction at the address in paragraph h.
    Register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filing and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    o. With this notice, we are soliciting comments on the PAD and 
Commission's staff Scoping Document 1 (SD1), as well as study requests. 
All comments on the PAD and SD1, and study requests should be sent to 
the address above in paragraph h. In addition, all comments on the PAD 
and SD1, study requests, requests for cooperating agency status, and 
all communications to and from Commission staff related to the merits 
of the potential application must be filed with the Commission. 
Documents may be filed electronically via the Internet. See 18 CFR 
385.2001(a)(1)(iii) and the instructions on the Commission's Web site 
https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support. Although the Commission strongly encourages electronic filing, 
documents may also be paper-filed. To paper-file, mail an original and 
seven copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory 
Commission, 888 First Street NE., Washington, DC 20426.
    All filings with the Commission must include on the first page, the 
project name (Eastman Falls Hydroelectric Project) and number (P-2457-
038), and bear the appropriate heading: ``Comments on Pre-Application 
Document,'' ``Study Requests,'' ``Comments on Scoping Document 1,'' 
``Request for Cooperating Agency Status,'' or ``Communications to and 
from Commission Staff.'' Any individual or entity interested in 
submitting study requests, commenting on the PAD or SD1, and any agency 
requesting cooperating status must do so by October 30, 2012.
    p. Although our current intent is to prepare an environmental 
assessment (EA), there is the possibility that an Environmental Impact 
Statement (EIS) will be required. Nevertheless, this meeting will 
satisfy the NEPA scoping requirements, irrespective of whether an EA or 
EIS is issued by the Commission.

Scoping Meetings

    Commission staff will hold two scoping meetings in the vicinity of 
the project at the time and place noted below. The daytime meeting will 
focus on resource agency, Indian tribes, and non-governmental 
organization concerns, while the evening meeting is primarily for 
receiving input from the public. We invite all interested individuals, 
organizations, and agencies to attend one or both of the meetings, and 
to assist staff in identifying particular study needs, as well as the 
scope of environmental issues to be addressed in the environmental 
document. The times and locations of these meetings are as follows:

Daytime Scoping Meeting

    Date: Wednesday, September 19, 2012.
    Time: 1:00 p.m. (EST).
    Location: Franklin City Hall Opera House, 316 Central Street, 
Franklin, NH, 03235.
    Phone: (603) 934-1901.

Evening Scoping Meeting

    Date: Wednesday, September 19, 2012.
    Time: 7:00 p.m. (EST).
    Location: Franklin City Hall Opera House, 316 Central Street, 
Franklin, NH, 03235.
    Phone: (603) 934-1901.
    Scoping Document 1 (SD1), which outlines the subject areas to be 
addressed in the environmental document, was mailed to the individuals 
and entities on the Commission's mailing list. Copies of SD1 will be 
available at the scoping meetings, or may be viewed on the web at 
https://www.ferc.gov, using the ``eLibrary'' link. Follow the directions 
for accessing information in paragraph n. Based on all oral and written 
comments, a Scoping Document 2 (SD2) may be issued. SD2 may include a 
revised process plan and schedule, as well as a list of issues, 
identified through the scoping process.

Site Visit

    The potential applicant and Commission staff will conduct a site 
visit of the project on Tuesday, September 18, 2012, starting at 11:00 
a.m. All participants should meet at the Eastman Falls dam, located at 
215 North Main Street, Franklin, NH 03235. All participants are 
responsible for their own transportation. Anyone with questions about 
the site visit should contact Mr. Curtis Mooney at (603) 744-5841 (ext. 
5841) or curtis.mooney@nu.com on or before September 12, 2012.

Meeting Objectives

    At the scoping meetings, staff will: (1) Initiate scoping of the 
issues; (2) review and discuss existing conditions and resource 
management objectives; (3) review and discuss existing information and 
identify preliminary information and study needs; (4) review and 
discuss the process plan and schedule for pre-filing activity that 
incorporates the time frames provided for in Part 5 of the Commission's 
regulations and, to the extent possible, maximizes coordination of 
federal, state, and tribal permitting and certification processes; and 
(5) discuss the appropriateness of any federal or state agency or 
Indian tribe acting as a cooperating agency for development of an 
environmental document.
    Meeting participants should come prepared to discuss their issues 
and/or concerns. Please review the PAD in preparation for the scoping 
meetings. Directions on how to obtain a copy of the PAD and SD1 are 
included in item n. of this document.

Meeting Procedures

    The meetings will be recorded by a stenographer and will be placed 
in the public records of the project.

    Dated: August 31, 2012.
Kimberly D. Bose,
Secretary.