Download as PDF 55202 Federal Register / Vol. 77, No. 174 / Friday, September 7, 2012 / Notices Orders-2012.html. They are also available for inspection and copying in the Office of Fossil Energy, Office of Natural Gas Regulatory Activities, Docket Room 3E–033, Forrestal Building, 1000 Independence Avenue SW., Washington, DC 20585, (202) 586– 9478. The Docket Room is open between Order No. Date issued the hours of 8:00 a.m. and 4:30 p.m., Monday through Friday, except Federal holidays. Appendix—DOE/FE Orders Granting Import/Export Authorizations FE Docket No. Authorization holder Description of action 3126 ......... 07/19/12 12–64–NG J. Aron & Company ............. 3127 ......... 07/24/12 12–71–NG Iberdrola Renewables, LLC [FR Doc. 2012–22081 Filed 9–6–12; 8:45 am] BILLING CODE 6450–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13005–003] srobinson on DSK4SPTVN1PROD with NOTICES Oliver Hydro LLC; Notice of Application Accepted for Filing and Soliciting Motions To Intervene and Protests Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Original Major License. b. Project No.: 13005–003. c. Date filed: December 14, 2011. d. Applicant: Oliver Hydro LLC. e. Name of Project: William Bacon Oliver Lock and Dam Hydroelectric Project. f. Location: At the U.S. Army Corps of Engineers’ (Corps) William Bacon Oliver Lock and Dam on the Black Warrior River, in Tuscaloosa County, Alabama. The project would occupy 8.7 acres of United States lands administered by the Corps’ Mobile District. g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)—825(r). h. Applicant Contact: Brent Smith, Symbiotics LLC, 371 Upper Terrace, Suite 2, Bend, OR 97702; (541) 330– 8779; or email at brent.smith@symbioticsenergy.com. i. FERC Contact: Allan Creamer at (202) 502–8365, or via email at allan.creamer@ferc.gov. j. Deadline for filing motions to intervene and protests: 60 days from the issuance date of this notice. All documents may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the VerDate Mar<15>2010 17:04 Sep 06, 2012 Jkt 226001 Issued in Washington, DC, on August 30, 2012. John A. Anderson, Manager, Natural Gas Regulatory Activities, Office of Oil and Gas Global Security and Supply, Office of Fossil Energy. Order granting blanket authority to import/export gas from/to Canada/Mexico and vacating prior ity, Order 2797. Order granting blanket authority to import/export gas from/to Canada/Mexico and vacating prior ity, Order 2792. instructions on the Commission’s Web site https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov, or toll free at 1–866–208–3676, or for TTY, (202) 502–8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and seven copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The Commission’s Rules of Practice require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. This application has been accepted, but is not ready for environmental analysis at this time. l. The proposed project would utilize the Corps’ existing William Bacon Oliver Lock and Dam, and would consist of the following new facilities: (1) A forebay; (2) an intake structure; (3) a powerhouse containing two generating units with a total capacity of 11.72 megawatts (MW); (4) a 150-foot-long, 68foot-wide tailrace; (5) a proposed 1.7mile-long, 25 kilovolt (kV) transmission line; (6) a switchyard; and (7) appurtenant facilities. The proposed project would have an average annual generation of 42.6 GWh, and operate in PO 00000 Frm 00023 Fmt 4703 Sfmt 4703 natural authornatural author- a run-of-river mode utilizing surplus water from the William Bacon Oliver Lock and Dam, as directed by the Corps. m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https://www.ferc.gov, using the ‘‘eLibrary’’ link. Enter the docket number, excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. A copy is also available for inspection and reproduction at the address in item h above. You may also register online at https:// www.ferc.gov/docs-filing/ esubscription.asp to be notified via email of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. n. Anyone may submit a protest or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, 385.211, and 385.214. In determining the appropriate action to take, the Commission will consider all protests filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any protests or motions to intervene must be received on, or before, the specified deadline date for the particular application. All filings must: (1) Bear in all capital letters the title ‘‘PROTEST’’ or ‘‘MOTION TO INTERVENE;’’ (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to E:\FR\FM\07SEN1.SGM 07SEN1 Federal Register / Vol. 77, No. 174 / Friday, September 7, 2012 / Notices intervene must be served upon each representative of the applicant specified in the particular application. o. Procedural schedule and final amendments: The application will be processed according to the following Hydro Licensing Schedule. Revisions to the schedule will be made as appropriate. Issue Scoping Document 1 Issue Scoping Document 2 (if necessary). Notice of application is ready for environmental analysis. Notice of availability of the EA. August 2012. October 2012. February 2013. October 2013. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis. n. Any qualified applicant desiring to file a competing application must submit to the Commission, on or before the specified intervention deadline date, a competing development application, or a notice of intent to file such an application. Submission of a timely notice of intent allows an interested person to file the competing development application no later than 120 days after the specified intervention deadline date. Applications for preliminary permits will not be accepted in response to this notice. A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit a development application. A notice of intent must be served on the applicant(s) named in this public notice. Dated: August 31, 2012. Kimberly D. Bose, Secretary. [FR Doc. 2012–22052 Filed 9–6–12; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission srobinson on DSK4SPTVN1PROD with NOTICES [Project No. 14441–000] Monroe City, UT: Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, Protests, Recommendations, and Terms and Conditions Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. VerDate Mar<15>2010 17:04 Sep 06, 2012 Jkt 226001 a. Type of Application: Conduit Exemption. b. Project No.: 14441–000. c. Date filed: July 27, 2012. d. Applicant: Monroe City, Utah. e. Name of Project: Monroe Cold Spring Hydroelectric Project. f. Location: The proposed Monroe Cold Spring Hydroelectric Project would be located on a water supply pipeline for Monroe City in Sevier County, Utah. The land on which all the project structures are located is owned by the applicant. g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791a–825r. h. Applicant Contact: Mr. R. Kirk Nilsson, Monroe City, Utah, 10 North Main, Monroe, UT 84754, phone (435) 527–4621. i. FERC Contact: Robert Bell, (202) 502–6062, robert.bell@ferc.gov. j. Status of Environmental Analysis: This application is ready for environmental analysis at this time, and the Commission is requesting comments, reply comments, recommendations, terms and conditions, and prescriptions. k. Deadline for filing responsive documents: Due to the small size of the proposed project, as well as the resource agency consultation letters filed with the application, the 60-day timeframe specified in 18 CFR 4.34(b) for filing all comments, motions to intervene, protests, recommendations, terms and conditions, and prescriptions is shortened to 30 days from the issuance date of this notice. All reply comments filed in response to comments submitted by any resource agency, Indian tribe, or person, must be filed with the Commission within 45 days from the issuance date of this notice. Comments, protests, and interventions may be filed electronically via the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site at https://www.ferc.gov/docs-filing/ efiling.asp. The Commission strongly encourages electronic filings. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person in the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. l. Description of the project: The proposed Monroe Cold Spring Hydroelectric Project would consist of: (1) A proposed powerhouse containing PO 00000 Frm 00024 Fmt 4703 Sfmt 4703 55203 one proposed generating unit with an installed capacity of 37 kilowatts; and (2) appurtenant facilities. The applicant estimates the project would have an average annual generation of 0.229 gigawatt-hours. m. This filing is available for review and reproduction at the Commission in the Public Reference Room, Room 2A, 888 First Street NE., Washington, DC 20426. The filing may also be viewed on the Web at https://www.ferc.gov/docsfiling/elibrary.asp using the ‘‘eLibrary’’ link. Enter the docket number, P–14441, in the docket number field to access the document. For assistance, call toll-free 1–866–208–3676 or email FERCOnlineSupport@ferc.gov. For TTY, call (202) 502–8659. A copy is also available for review and reproduction at the address in item h above. n. Development Application—Any qualified applicant desiring to file a competing application must submit to the Commission, on or before the specified deadline date for the particular application, a competing development application, or a notice of intent to file such an application. Submission of a timely notice of intent allows an interested person to file the competing development application no later than 120 days after the specified deadline date for the particular application. Applications for preliminary permits will not be accepted in response to this notice. p. Protests or Motions to Intervene— Anyone may submit a protest or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, 385.211, and 385.214. In determining the appropriate action to take, the Commission will consider all protests filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any protests or motions to intervene must be received on or before the specified deadline date for the particular application. q. All filings must (1) bear in all capital letters the title ‘‘PROTEST’’, ‘‘MOTION TO INTERVENE’’, ‘‘COMMENTS’’, ‘‘REPLY COMMENTS’’, ‘‘RECOMMENDATIONS’’, ‘‘TERMS AND CONDITIONS’’, or ‘‘PRESCRIPTIONS’’; (2) set forth in the heading, the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. All comments, recommendations, terms and conditions, or prescriptions must set E:\FR\FM\07SEN1.SGM 07SEN1

Agencies

[Federal Register Volume 77, Number 174 (Friday, September 7, 2012)]
[Notices]
[Pages 55202-55203]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-22052]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13005-003]


Oliver Hydro LLC; Notice of Application Accepted for Filing and 
Soliciting Motions To Intervene and Protests

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Original Major License.
    b. Project No.: 13005-003.
    c. Date filed: December 14, 2011.
    d. Applicant: Oliver Hydro LLC.
    e. Name of Project: William Bacon Oliver Lock and Dam Hydroelectric 
Project.
    f. Location: At the U.S. Army Corps of Engineers' (Corps) William 
Bacon Oliver Lock and Dam on the Black Warrior River, in Tuscaloosa 
County, Alabama. The project would occupy 8.7 acres of United States 
lands administered by the Corps' Mobile District.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)--825(r).
    h. Applicant Contact: Brent Smith, Symbiotics LLC, 371 Upper 
Terrace, Suite 2, Bend, OR 97702; (541) 330-8779; or email at 
brent.smith@symbioticsenergy.com.
    i. FERC Contact: Allan Creamer at (202) 502-8365, or via email at 
allan.creamer@ferc.gov.
    j. Deadline for filing motions to intervene and protests: 60 days 
from the issuance date of this notice.
    All documents may be filed electronically via the Internet. See 18 
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web 
site https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at FERCOnlineSupport@ferc.gov, or toll free at 1-866-208-3676, 
or for TTY, (202) 502-8659. Although the Commission strongly encourages 
electronic filing, documents may also be paper-filed. To paper-file, 
mail an original and seven copies to: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE., Washington, 
DC 20426.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted, but is not ready for 
environmental analysis at this time.
    l. The proposed project would utilize the Corps' existing William 
Bacon Oliver Lock and Dam, and would consist of the following new 
facilities: (1) A forebay; (2) an intake structure; (3) a powerhouse 
containing two generating units with a total capacity of 11.72 
megawatts (MW); (4) a 150-foot-long, 68-foot-wide tailrace; (5) a 
proposed 1.7-mile-long, 25 kilovolt (kV) transmission line; (6) a 
switchyard; and (7) appurtenant facilities. The proposed project would 
have an average annual generation of 42.6 GWh, and operate in a run-of-
river mode utilizing surplus water from the William Bacon Oliver Lock 
and Dam, as directed by the Corps.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at https://www.ferc.gov, using the ``eLibrary'' 
link. Enter the docket number, excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. Anyone may submit a protest or a motion to intervene in 
accordance with the requirements of Rules of Practice and Procedure, 18 
CFR 385.210, 385.211, and 385.214. In determining the appropriate 
action to take, the Commission will consider all protests filed, but 
only those who file a motion to intervene in accordance with the 
Commission's Rules may become a party to the proceeding. Any protests 
or motions to intervene must be received on, or before, the specified 
deadline date for the particular application.
    All filings must: (1) Bear in all capital letters the title 
``PROTEST'' or ``MOTION TO INTERVENE;'' (2) set forth in the heading 
the name of the applicant and the project number of the application to 
which the filing responds; (3) furnish the name, address, and telephone 
number of the person protesting or intervening; and (4) otherwise 
comply with the requirements of 18 CFR 385.2001 through 385.2005. 
Agencies may obtain copies of the application directly from the 
applicant. A copy of any protest or motion to

[[Page 55203]]

intervene must be served upon each representative of the applicant 
specified in the particular application.
    o. Procedural schedule and final amendments: The application will 
be processed according to the following Hydro Licensing Schedule. 
Revisions to the schedule will be made as appropriate.

------------------------------------------------------------------------
 
------------------------------------------------------------------------
Issue Scoping Document 1...............  August 2012.
Issue Scoping Document 2 (if necessary)  October 2012.
Notice of application is ready for       February 2013.
 environmental analysis.
Notice of availability of the EA.......  October 2013.
------------------------------------------------------------------------

    Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of the notice 
of ready for environmental analysis.
    n. Any qualified applicant desiring to file a competing application 
must submit to the Commission, on or before the specified intervention 
deadline date, a competing development application, or a notice of 
intent to file such an application. Submission of a timely notice of 
intent allows an interested person to file the competing development 
application no later than 120 days after the specified intervention 
deadline date. Applications for preliminary permits will not be 
accepted in response to this notice.
    A notice of intent must specify the exact name, business address, 
and telephone number of the prospective applicant, and must include an 
unequivocal statement of intent to submit a development application. A 
notice of intent must be served on the applicant(s) named in this 
public notice.

    Dated: August 31, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-22052 Filed 9-6-12; 8:45 am]