Proposed International Isotopes Fluorine Extraction Process and Depleted Uranium Deconversion Plant in Lea County, New Mexico, 53236-53237 [2012-21486]
Download as PDF
53236
Federal Register / Vol. 77, No. 170 / Friday, August 31, 2012 / Notices
materials will be made available in
alternative formats to accommodate
individuals with disabilities.
Individuals who need other
accommodations due to disability in
order to attend the meeting in person or
telephonically should contact Katherine
Ward, at (202) 295–1500 or
FR_NOTICE_QUESTIONS@lsc.gov, at
least 2 business days in advance of the
meeting. If a request is made without
advance notice, LSC will make every
effort to accommodate the request but
cannot guarantee that all requests can be
fulfilled.
designation of certain animals and
certain geographic areas a requiring
special protection. The regulations
establish such a permit system to
designate Antarctic Specially Protected
Areas.
The applications received are as
follows:
Dated: August 28, 2012.
Victor M. Fortuno,
Vice President & General Counsel.
Enter Antarctic Specially Protected
Areas. The applicant plans to enter
ASPA 105-Beaufort Island, ASPA 121Cape Royds, ASPA 122-Arrival Heights,
ASPA 124-Cape Crozier, ASPA 130Transway Ridge, ASPA 131-Canada
Glacier, ASPA 137-Northwest White
Island, ASPA 138-Linnaeus Terrace,
and, ASPA 154-Botany Bay to conduct
a review of their management plans.
The Antarctic Support Contract (ASC)
Environmental Health and Safety (EHS)
Department would enter the ASPA’s to
collect information on site status in
anticipation of the 5 year ASPA review,
general management and maintenance
concerns such as ensuring that all signs
and boundary markers are legible and
secured, or to address any
environmental concerns or potential
environmental release with the ASPA.
Information would be gathered on any
installations or facilities that may be
present, verify that the reasons for
special protection remain valid, verify
that the management measures in place
are sufficient to provide protection, and,
recommend any management measures
that may be necessary to maintain the
values being protected. The plan
revisions will take into account recent
developments within the Antarctic
Treaty System to ensure consistency
with recently adopted plans, policies
and guidelines amongst the Treaty
Nations.
[FR Doc. 2012–21611 Filed 8–29–12; 11:15 am]
BILLING CODE 7050–01–P
NATIONAL SCIENCE FOUNDATION
Notice of Permit Applications Received
Under the Antarctic Conservation Act
of 1978 (Pub. L. 95–541)
National Science Foundation.
Notice of Permit Applications
Received under the Antarctic
Conservation Act of 1978, Public Law
95–541.
AGENCY:
ACTION:
The National Science
Foundation (NSF) is required to publish
a notice of permit applications received
to conduct activities regulated under the
Antarctic Conservation Act of 1978.
NSF has published regulations under
the Antarctic Conservation Act at Title
45 Part 670 of the Code of Federal
Regulations. This is the required notice
of permit applications received.
DATES: Interested parties are invited to
submit written data, comments, or
views with respect to this permit
application by October 1, 2012. This
application may be inspected by
interested parties at the Permit Office,
address below.
ADDRESSES: Comments should be
addressed to Permit Office, Room 755,
Office of Polar Programs, National
Science Foundation, 4201 Wilson
Boulevard, Arlington, Virginia 22230.
FOR FURTHER INFORMATION CONTACT:
Polly A. Penhale at the above address or
(703) 292–7420.
SUPPLEMENTARY INFORMATION: The
National Science Foundation, as
directed by the Antarctic Conservation
Act of 1978 (Pub. L. 95–541), as
amended by the Antarctic Science,
Tourism and Conservation Act of 1996,
has developed regulations for the
establishment of a permit system for
various activities in Antarctica and
EMCDONALD on DSK67QTVN1PROD with NOTICES
SUMMARY:
VerDate Mar<15>2010
15:22 Aug 30, 2012
Jkt 226001
Permit Application: 2013–019
1. Applicant: Lockheed Martin IS&GS,
Antarctic Support Contract, 7400 S.
Tucson Way, Centennial, CO
80112–3938.
Activity for Which Permit Is Requested
Location
ASPA 105-Beaufort Island, ASPA 121Cape Royds, ASPA 122-Arrival Heights,
ASPA 124-Cape Crozier, ASPA 130Transway Ridge, ASPA 131-Canada
Glacier, ASPA 137-Northwest White
Island, ASPA 138-Linnaeus Terrace,
and, ASPA 154-Botany Bay.
Dates
August 15, 2012 to August 31, 2017.
Nadene G. Kennedy,
Permit Officer, Office of Polar Programs.
[FR Doc. 2012–21604 Filed 8–30–12; 8:45 am]
BILLING CODE 7555–01–P
PO 00000
Frm 00069
Fmt 4703
Sfmt 4703
NEIGHBORHOOD REINVESTMENT
CORPORATION
Sunshine Act Meeting Notice
Corporate Administration Committee
Meeting of The Board of Directors
1 p.m., Thursday,
September 13, 2012.
PLACE: 1325 G Street NW., Suite 800,
Boardroom, Washington, DC 20005.
STATUS: Open.
TIME AND DATE:
CONTACT PERSON FOR MORE INFORMATION:
Erica Hall, Assistant Corporate
Secretary; (202) 220–2376;
ehall@nw.org.
AGENDA:
I. Call to Order
II. Nominations
III. Employee Performance Management
System
IV. Policy Changes
V. Human Resources Update
VI. Washington, DC Lease Update
VII. Adjournment
Erica Hall,
Assistant Corporate Secretary.
[FR Doc. 2012–21737 Filed 8–29–12; 4:15 pm]
BILLING CODE 7570–02–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2010–0143]
Proposed International Isotopes
Fluorine Extraction Process and
Depleted Uranium Deconversion Plant
in Lea County, New Mexico
Nuclear Regulatory
Commission.
ACTION: Final environmental impact
statement; issuance.
AGENCY:
Notice is hereby given that
the U.S. Nuclear Regulatory
Commission (NRC or the Commission)
has published the Final Environmental
Impact Statement (EIS) for the proposed
International Isotopes Fluorine
Extraction Process and Depleted
Uranium Deconversion Plant (INIS) in
Lea County, New Mexico. On December
30, 2009, International Isotopes Fluorine
Products, Inc. (IIFP), a wholly-owned
subsidiary of International Isotopes,
Inc., submitted a license application
that proposes the construction,
operation, and decommissioning of a
fluorine extraction and depleted
uranium deconversion facility (the
‘‘proposed action’’). IIFP proposes to
locate the facility near Hobbs, New
Mexico.
ADDRESSES: Please refer to Docket ID
NRC–2010–0143 when contacting the
SUMMARY:
E:\FR\FM\31AUN1.SGM
31AUN1
Federal Register / Vol. 77, No. 170 / Friday, August 31, 2012 / Notices
NRC about the availability of
information regarding this document.
You may access information related to
this document using any of the
following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2010–0143. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–492–3668;
email: Carol.Gallagher@nrc.gov.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may access publiclyavailable documents online in the NRC
Library at https://www.nrc.gov/readingrm/adams.html. To begin the search,
select ‘‘ADAMS Public Documents’’ and
then select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov.
Additional information regarding
accessing materials related to this action
is under the Document Availability
heading in the SUPPLEMENTARY
INFORMATION section of this document.
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: For
information about the Final EIS or the
environmental review process, please
contact Asimios Malliakos, telephone:
301–415–6458; email:
Asimios.Malliakos@nrc.gov; Office of
Federal and State Materials and
Environmental Management Programs,
U.S. Nuclear Regulatory Commission,
Washington, DC 20555–0001. For
general or technical information
associated with the licensing process as
it relates to the INIS application, please
contact Matthew Bartlett, telephone:
301–492–3119; email:
Matthew.Bartlett@nrc.gov; Office of
Nuclear Material Safety and Safeguards,
U.S. Nuclear Regulatory Commission,
Washington, DC 20555–0001.
SUPPLEMENTARY INFORMATION:
EMCDONALD on DSK67QTVN1PROD with NOTICES
Discussion
IIFP submitted a license application
and Environmental Report (ER) in
support of its proposed facility on
December 30, 2009. The proposed site is
located in Lea County, New Mexico,
approximately 22.55 kilometers (km) (14
miles [mi]) west of the city of Hobbs.
The Final EIS is being issued as part
of the NRC’s process to decide whether
to issue a license to IIFP, pursuant to
Part 40 of Title 10 of the Code of Federal
Regulations (10 CFR), to construct and
VerDate Mar<15>2010
15:22 Aug 30, 2012
Jkt 226001
operate the proposed depleted uranium
deconversion facility. Specifically, IIFP
proposes to deconvert depleted uranium
hexafluoride (DUF6) into oxide
compounds for long-term disposal. In
the Final EIS, the NRC staff assessed the
potential environmental impacts from
construction, operation, and
decommissioning of the proposed INIS
project.
The Final EIS was prepared in
compliance with the National
Environmental Policy Act of 1969, as
amended (NEPA), and the NRC’s
regulations for implementing NEPA in
10 CFR Part 51. The NRC staff assessed
the impacts of the proposed action on
land use, historic and cultural
resources, visual resources, climatology,
meteorology, and air quality, geology,
minerals, and soil, water resources,
ecological resources, socioeconomics
and environmental justice, traffic and
transportation, noise, public and
occupational health, and waste
management. Additionally, the NRC
staff analyzed and compared the
benefits and costs of the proposed
action. In preparing this Final EIS, the
NRC staff also reviewed, considered,
evaluated, and addressed the public
comments received on the Draft EIS.
In addition to the proposed action, the
NRC staff considered a reasonable range
of alternatives, including the no-action
alternative. Under the no-action
alternative, the NRC would deny IIFP’s
request to construct and operate a
depleted uranium deconversion facility
in Hobbs, New Mexico. The no-action
alternative serves as a baseline for
comparison of the potential
environmental impacts of the proposed
action. Other alternatives the NRC staff
considered but eliminated from further
analysis include: (1) Alternative sites;
(2) alternative technologies; (3)
shipment of the U.S. generated DUF6 to
overseas facilities; (4) indefinite storage
at the enrichment facilities; and (5)
construction and operation of
deconversion facilities at the four U.S.based uranium enrichment companies.
These alternatives were eliminated from
further analysis due to economic,
environmental, or other reasons.
After weighing the impacts of the
proposed action and comparing
alternatives, the NRC staff, in
accordance with 10 CFR 51.91(d), sets
forth its recommendation regarding the
proposed action. The NRC staff
recommends that, unless safety issues
mandate otherwise, the proposed
license be issued to IIFP. In this regard,
the NRC staff has concluded that the
environmental impacts of the proposed
action are generally small, and taken in
combination with the proposed IIFP
PO 00000
Frm 00070
Fmt 4703
Sfmt 4703
53237
environmental monitoring program and
proposed mitigation measures discussed
in the Final EIS would eliminate or
substantially lessen any adverse
environmental impacts associated with
the proposed action.
Document Availability
Documents related to this notice are
available on the NRC’s Licensing Web
Site at: https://www.nrc.gov/materials/
fuel-cycle-fac/inisfacility.html. The
Final EIS for the proposed INIS project
may also be accessed at: https://
www.nrc.gov/reading-rm/doccollections/nuregs/staff/ by selecting
‘‘NUREG–2113.’’
The IIFP’s license application,
Environmental Report, and the NRC’s
Final EIS are available in ADAMS under
Accession Numbers ML100630503,
ML100120758, and ML12220A380.
A copy of the Final EIS will be
available at the Hobbs Public Library,
509 North Shipp, Hobbs, New Mexico
88240.
Dated at Rockville, Maryland, this 22nd
day of August, 2012.
For the Nuclear Regulatory Commission.
Gregory Suber,
Acting Deputy Director, Environmental
Protection and Performance Assessment
Directorate, Division of Waste Management
and Environmental Protection, Office of
Federal and State Materials and
Environmental Management Programs.
[FR Doc. 2012–21486 Filed 8–30–12; 8:45 am]
BILLING CODE 7590–01–P
OFFICE OF PERSONNEL
MANAGEMENT
Submission for Review; Information
Collection: Freedom of Information/
Privacy Act Record Request Form (INV
100)
U.S. Office of Personnel
Management.
ACTION: 60-Day Notice and request for
comments.
AGENCY:
Federal Investigative Services
(FIS), U.S. Office of Personnel
Management (OPM) offers the general
public and other federal agencies the
opportunity to comment on an
information collection request (ICR),
Office of Management and Budget
(OMB) Control No. 3206–NEW,
Freedom of Information/Privacy Act
Record Request Form (INV 100). As
required by the Paperwork Reduction
Act of 1995, (Pub. L. 104–13, 44 U.S.C.
chapter 35) as amended by the ClingerCohen Act (Pub. L. 104–106), OPM is
soliciting comments for this collection.
The Office of Management and Budget
SUMMARY:
E:\FR\FM\31AUN1.SGM
31AUN1
Agencies
[Federal Register Volume 77, Number 170 (Friday, August 31, 2012)]
[Notices]
[Pages 53236-53237]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-21486]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[NRC-2010-0143]
Proposed International Isotopes Fluorine Extraction Process and
Depleted Uranium Deconversion Plant in Lea County, New Mexico
AGENCY: Nuclear Regulatory Commission.
ACTION: Final environmental impact statement; issuance.
-----------------------------------------------------------------------
SUMMARY: Notice is hereby given that the U.S. Nuclear Regulatory
Commission (NRC or the Commission) has published the Final
Environmental Impact Statement (EIS) for the proposed International
Isotopes Fluorine Extraction Process and Depleted Uranium Deconversion
Plant (INIS) in Lea County, New Mexico. On December 30, 2009,
International Isotopes Fluorine Products, Inc. (IIFP), a wholly-owned
subsidiary of International Isotopes, Inc., submitted a license
application that proposes the construction, operation, and
decommissioning of a fluorine extraction and depleted uranium
deconversion facility (the ``proposed action''). IIFP proposes to
locate the facility near Hobbs, New Mexico.
ADDRESSES: Please refer to Docket ID NRC-2010-0143 when contacting the
[[Page 53237]]
NRC about the availability of information regarding this document. You
may access information related to this document using any of the
following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2010-0143. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-492-
3668; email: Carol.Gallagher@nrc.gov.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may access publicly-available documents online in the NRC
Library at https://www.nrc.gov/reading-rm/adams.html. To begin the
search, select ``ADAMS Public Documents'' and then select ``Begin Web-
based ADAMS Search.'' For problems with ADAMS, please contact the NRC's
Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-
4737, or by email to pdr.resource@nrc.gov. Additional information
regarding accessing materials related to this action is under the
Document Availability heading in the SUPPLEMENTARY INFORMATION section
of this document.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: For information about the Final EIS or
the environmental review process, please contact Asimios Malliakos,
telephone: 301-415-6458; email: Asimios.Malliakos@nrc.gov; Office of
Federal and State Materials and Environmental Management Programs, U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001. For general
or technical information associated with the licensing process as it
relates to the INIS application, please contact Matthew Bartlett,
telephone: 301-492-3119; email: Matthew.Bartlett@nrc.gov; Office of
Nuclear Material Safety and Safeguards, U.S. Nuclear Regulatory
Commission, Washington, DC 20555-0001.
SUPPLEMENTARY INFORMATION:
Discussion
IIFP submitted a license application and Environmental Report (ER)
in support of its proposed facility on December 30, 2009. The proposed
site is located in Lea County, New Mexico, approximately 22.55
kilometers (km) (14 miles [mi]) west of the city of Hobbs.
The Final EIS is being issued as part of the NRC's process to
decide whether to issue a license to IIFP, pursuant to Part 40 of Title
10 of the Code of Federal Regulations (10 CFR), to construct and
operate the proposed depleted uranium deconversion facility.
Specifically, IIFP proposes to deconvert depleted uranium hexafluoride
(DUF6) into oxide compounds for long-term disposal. In the
Final EIS, the NRC staff assessed the potential environmental impacts
from construction, operation, and decommissioning of the proposed INIS
project.
The Final EIS was prepared in compliance with the National
Environmental Policy Act of 1969, as amended (NEPA), and the NRC's
regulations for implementing NEPA in 10 CFR Part 51. The NRC staff
assessed the impacts of the proposed action on land use, historic and
cultural resources, visual resources, climatology, meteorology, and air
quality, geology, minerals, and soil, water resources, ecological
resources, socioeconomics and environmental justice, traffic and
transportation, noise, public and occupational health, and waste
management. Additionally, the NRC staff analyzed and compared the
benefits and costs of the proposed action. In preparing this Final EIS,
the NRC staff also reviewed, considered, evaluated, and addressed the
public comments received on the Draft EIS.
In addition to the proposed action, the NRC staff considered a
reasonable range of alternatives, including the no-action alternative.
Under the no-action alternative, the NRC would deny IIFP's request to
construct and operate a depleted uranium deconversion facility in
Hobbs, New Mexico. The no-action alternative serves as a baseline for
comparison of the potential environmental impacts of the proposed
action. Other alternatives the NRC staff considered but eliminated from
further analysis include: (1) Alternative sites; (2) alternative
technologies; (3) shipment of the U.S. generated DUF6 to
overseas facilities; (4) indefinite storage at the enrichment
facilities; and (5) construction and operation of deconversion
facilities at the four U.S.-based uranium enrichment companies. These
alternatives were eliminated from further analysis due to economic,
environmental, or other reasons.
After weighing the impacts of the proposed action and comparing
alternatives, the NRC staff, in accordance with 10 CFR 51.91(d), sets
forth its recommendation regarding the proposed action. The NRC staff
recommends that, unless safety issues mandate otherwise, the proposed
license be issued to IIFP. In this regard, the NRC staff has concluded
that the environmental impacts of the proposed action are generally
small, and taken in combination with the proposed IIFP environmental
monitoring program and proposed mitigation measures discussed in the
Final EIS would eliminate or substantially lessen any adverse
environmental impacts associated with the proposed action.
Document Availability
Documents related to this notice are available on the NRC's
Licensing Web Site at: https://www.nrc.gov/materials/fuel-cycle-fac/inisfacility.html. The Final EIS for the proposed INIS project may also
be accessed at: https://www.nrc.gov/reading-rm/doc-collections/nuregs/staff/ by selecting ``NUREG-2113.''
The IIFP's license application, Environmental Report, and the NRC's
Final EIS are available in ADAMS under Accession Numbers ML100630503,
ML100120758, and ML12220A380.
A copy of the Final EIS will be available at the Hobbs Public
Library, 509 North Shipp, Hobbs, New Mexico 88240.
Dated at Rockville, Maryland, this 22nd day of August, 2012.
For the Nuclear Regulatory Commission.
Gregory Suber,
Acting Deputy Director, Environmental Protection and Performance
Assessment Directorate, Division of Waste Management and Environmental
Protection, Office of Federal and State Materials and Environmental
Management Programs.
[FR Doc. 2012-21486 Filed 8-30-12; 8:45 am]