Notice of Cancellation of Environmental Impact Statement for the Proposed Interconnection of the Buffalo Ridge III Wind Project, Brookings and Deuel Counties, SD (DOE/EIS-0437), 52320 [2012-21302]
Download as PDF
52320
Federal Register / Vol. 77, No. 168 / Wednesday, August 29, 2012 / Notices
Interested persons are invited to
submit comments on or before October
29, 2012.
ADDRESSES: Written comments
regarding burden and/or the collection
activity requirements should be
electronically mailed to
ICDocketMgr@ed.gov or mailed to U.S.
Department of Education, 400 Maryland
Avenue SW., LBJ, Washington, DC
20202–4537. Copies of the proposed
information collection request may be
accessed from https://edicsweb.ed.gov,
by selecting the ‘‘Browse Pending
Collections’’ link and by clicking on
link number 04922. When you access
the information collection, click on
‘‘Download Attachments’’ to view.
Written requests for information should
be addressed to U.S. Department of
Education, 400 Maryland Avenue SW.,
LBJ, Washington, DC 20202–4537.
Requests may also be electronically
mailed to ICDocketMgr@ed.gov or faxed
to 202–401–0920. Please specify the
complete title of the information
collection and OMB Control Number
when making your request.
Individuals who use a
telecommunications device for the deaf
(TDD) may call the Federal Information
Relay Service (FIRS) at 1–800–877–
8339.
SUPPLEMENTARY INFORMATION: Section
3506 of the Paperwork Reduction Act of
1995 (44 U.S.C. chapter 35) requires that
Federal agencies provide interested
parties an early opportunity to comment
on information collection requests. The
Director, Information Collection
Clearance Division, Privacy, Information
and Records Management Services,
Office of Management, publishes this
notice containing proposed information
collection requests at the beginning of
the Departmental review of the
information collection. The Department
of Education is especially interested in
public comment addressing the
following issues: (1) Is this collection
necessary to the proper functions of the
Department; (2) will this information be
processed and used in a timely manner;
(3) is the estimate of burden accurate;
(4) how might the Department enhance
the quality, utility, and clarity of the
information to be collected; and (5) how
might the Department minimize the
burden of this collection on the
respondents, including through the use
of information technology. Please note
that written comments received in
response to this notice will be
considered public records.
Title of Collection: Needs Sensing
Survey under the REL program: (Sample
survey Instrument for School Board
Members and District Administrators.
TKELLEY on DSK3SPTVN1PROD with NOTICES
DATES:
VerDate Mar<15>2010
17:37 Aug 28, 2012
Jkt 226001
OMB Control Number: 1850–NEW.
Type of Review: New.
Total Estimated Number of Annual
Responses: 2,240.
Total Estimated Number of Annual
Burden Hours: 983.
Abstract: The needs assessment
consists of an online survey of a sample
of school board members, district
administrators, principals, and teachers
in Illinois, Indiana, Iowa, Michigan,
Minnesota, Ohio, and Wisconsin. The
purpose of the sample survey is to
assess: the importance these
populations attach to the four issues
identified in advance by REL Midwest
as priorities for the region; for each
issue, the types of data and analysis
supports, and research and evaluation
needs which respondents anticipate
would be of particular value; and what
factors would increase the likelihood
respondents and the populations they
represent would turn to the REL for data
and analysis supports, or research and
evaluation needs in the future. The
results of the survey will be used to
prioritize the assistance that REL
Midwest provides to educators in the
region for utilizing their longitudinal
data systems, conducting high quality
research and evaluation; learning about
the best education research; and
incorporating data into policy and
practice.
Dated: August 24, 2012.
Stephanie Valentine,
Acting Director, Information Collection
Clearance Division, Privacy, Information and
Records Management Services, Office of
Management.
[FR Doc. 2012–21309 Filed 8–28–12; 8:45 am]
BILLING CODE 4000–01–P
DEPARTMENT OF ENERGY
Western Area Power Administration
Notice of Cancellation of
Environmental Impact Statement for
the Proposed Interconnection of the
Buffalo Ridge III Wind Project,
Brookings and Deuel Counties, SD
(DOE/EIS–0437)
Western Area Power
Administration, DOE.
ACTION: Notice of Cancellation of
Environmental Impact Statement.
AGENCY:
The U.S. Department of
Energy (DOE), Western Area Power
Administration (Western) is issuing this
notice to advise the public that it is
cancelling the preparation of an
environmental impact statement (EIS)
under the National Environmental
Policy Act (NEPA) on an
SUMMARY:
PO 00000
Frm 00012
Fmt 4703
Sfmt 9990
interconnection request by Heartland
Wind, LLC (Heartland), a wholly owned
subsidiary of Iberdrola Renewables, Inc.
This cancellation is effective on
August 29, 2012.
DATES:
For
additional information on the
cancellation of this EIS process, contact
Matt Marsh, NEPA Document Manager,
Upper Great Plains Regional Office,
Western Area Power Administration,
P.O. Box 35800, Billings, MT 59107–
5800, email MMarsh@wapa.gov,
telephone (406) 255–2811. For general
information on DOE’s NEPA review
process, contact Carol M. Borgstrom,
Director of NEPA Policy and
Compliance, GC–54, Department of
Energy, 1000 Independence Avenue
SW., Washington, DC 20585–0119,
telephone (202) 586–4600 or (800) 472–
2756, facsimile (202) 586–7031.
FOR FURTHER INFORMATION CONTACT:
Heartland
proposed to design, construct, operate,
and maintain a 170-megawatt Buffalo
Ridge III Wind Project (Project) in
Brookings and Deuel counties, South
Dakota, and interconnect that Project
with Western’s transmission system.
Heartland’s interconnection request
caused Western to initiate a NEPA
review of its proposal to allow the
interconnection. Western published a
Notice of Intent for the EIS in the
Federal Register on November 27, 2009
(74 FR 62298), and started the EIS
process. A public scoping meeting was
held subsequent to the Notice of Intent,
but a Draft EIS was not produced
because Heartland decided to suspend
further action on its proposed Project.
Heartland notified Western of its
decision, and Western is now
terminating the NEPA review process on
its interconnection proposal and
Heartland’s proposed Project. Heartland
could decide to reinitiate the proposed
Project at some future date. In that event
Western would issue a new Notice of
Intent, and would start a new NEPA
process.
The DOE’s Acting General Counsel
provided a ‘‘Restatement of Delegations
of Environmental Impact Statement
Authorities’’ to Western’s Administrator
in a November 16, 2011, memorandum.
Under the authority granted by that
memorandum, I have terminated the
NEPA process for Heartland’s proposed
Buffalo Ridge III Wind Project with the
publication of this notice.
SUPPLEMENTARY INFORMATION:
Dated: August 17, 2012.
Anthony H. Montoya,
Acting Administrator.
[FR Doc. 2012–21302 Filed 8–28–12; 8:45 am]
BILLING CODE 6450–01–P
E:\FR\FM\29AUN1.SGM
29AUN1
Agencies
[Federal Register Volume 77, Number 168 (Wednesday, August 29, 2012)]
[Notices]
[Page 52320]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-21302]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Western Area Power Administration
Notice of Cancellation of Environmental Impact Statement for the
Proposed Interconnection of the Buffalo Ridge III Wind Project,
Brookings and Deuel Counties, SD (DOE/EIS-0437)
AGENCY: Western Area Power Administration, DOE.
ACTION: Notice of Cancellation of Environmental Impact Statement.
-----------------------------------------------------------------------
SUMMARY: The U.S. Department of Energy (DOE), Western Area Power
Administration (Western) is issuing this notice to advise the public
that it is cancelling the preparation of an environmental impact
statement (EIS) under the National Environmental Policy Act (NEPA) on
an interconnection request by Heartland Wind, LLC (Heartland), a wholly
owned subsidiary of Iberdrola Renewables, Inc.
DATES: This cancellation is effective on August 29, 2012.
FOR FURTHER INFORMATION CONTACT: For additional information on the
cancellation of this EIS process, contact Matt Marsh, NEPA Document
Manager, Upper Great Plains Regional Office, Western Area Power
Administration, P.O. Box 35800, Billings, MT 59107-5800, email
MMarsh@wapa.gov, telephone (406) 255-2811. For general information on
DOE's NEPA review process, contact Carol M. Borgstrom, Director of NEPA
Policy and Compliance, GC-54, Department of Energy, 1000 Independence
Avenue SW., Washington, DC 20585-0119, telephone (202) 586-4600 or
(800) 472-2756, facsimile (202) 586-7031.
SUPPLEMENTARY INFORMATION: Heartland proposed to design, construct,
operate, and maintain a 170-megawatt Buffalo Ridge III Wind Project
(Project) in Brookings and Deuel counties, South Dakota, and
interconnect that Project with Western's transmission system.
Heartland's interconnection request caused Western to initiate a NEPA
review of its proposal to allow the interconnection. Western published
a Notice of Intent for the EIS in the Federal Register on November 27,
2009 (74 FR 62298), and started the EIS process. A public scoping
meeting was held subsequent to the Notice of Intent, but a Draft EIS
was not produced because Heartland decided to suspend further action on
its proposed Project. Heartland notified Western of its decision, and
Western is now terminating the NEPA review process on its
interconnection proposal and Heartland's proposed Project. Heartland
could decide to reinitiate the proposed Project at some future date. In
that event Western would issue a new Notice of Intent, and would start
a new NEPA process.
The DOE's Acting General Counsel provided a ``Restatement of
Delegations of Environmental Impact Statement Authorities'' to
Western's Administrator in a November 16, 2011, memorandum. Under the
authority granted by that memorandum, I have terminated the NEPA
process for Heartland's proposed Buffalo Ridge III Wind Project with
the publication of this notice.
Dated: August 17, 2012.
Anthony H. Montoya,
Acting Administrator.
[FR Doc. 2012-21302 Filed 8-28-12; 8:45 am]