Delegation of Authority to the State of West Virginia To Implement and Enforce Additional or Revised National Emission Standards for Hazardous Air Pollutants and New Source Performance Standards, 47838-47839 [2012-19685]
Download as PDF
mstockstill on DSK4VPTVN1PROD with NOTICES
47838
Federal Register / Vol. 77, No. 155 / Friday, August 10, 2012 / Notices
the remedial phase of the Superfund
program and in associated community
involvement activities throughout the
Superfund process.
Title: National Oil and Hazardous
Substance Pollution Contingency Plan
(NCP) (Renewal).
ICR Numbers: EPA ICR No. 1463.08,
OMB Control No. 2050–0096.
ICR Status: This ICR is currently
scheduled to expire on August 31, 2015.
Abstract: This Information Collection
Request is a renewal ICR that covers the
remedial portion of the Superfund
program, as specified in the
Comprehensive Environmental
Response, Compensation, and Liability
Act of 1980 as amended (CERCLA) and
the National Oil and Hazardous
Substance Pollution Contingency Plan
(NCP). All remedial actions covered by
this ICR (e.g., remedial investigations/
feasibility studies) are stipulated in the
statute (CERCLA) and are instrumental
in the process of cleaning up National
Priorities List (NPL) sites to be
protective of human health and the
environment. Some community
involvement activities covered by this
ICR are not required at every site (e.g.,
Technical Assistance Grants) and
depend very much on the community
and the nature of the site and cleanup.
All community activities seek to involve
the public in the cleanup of the sites,
gain the input of community members,
and include the community’s
perspective on the potential future reuse
of Superfund NPL sites. Community
involvement activities can enhance the
remedial process and increase
community acceptance and the
potential for productive and beneficial
reuse of the sites.
Burden Statement: The annual public
reporting and recordkeeping burden for
this collection of information is
estimated to average 13.84 hours per
response.
The ICR provides a detailed
explanation of the Agency’s estimate,
which is only briefly summarized here:
Estimated total number of potential
respondents: 11,659.
Frequency of response: On occasion.
Estimated total average number of
responses for each respondent: As
required.
Estimated total annual burden hours:
179,615 hours.
Estimated total annual costs:
$813,440. This includes an estimated
burden cost of $261,440 for states and
an estimated cost of $552,000 for
communities.
VerDate Mar<15>2010
18:02 Aug 09, 2012
Jkt 226001
Are there changes in the estimates from
the last approval?
There is no change in the total
estimated respondent burden compared
with that identified in the ICR currently
approved by OMB.
What is the next step in the process for
this ICR?
EPA will consider the comments
received and amend the ICR as
appropriate. The final ICR package will
then be submitted to OMB for review
and approval pursuant to 5 CFR
1320.12. At that time, EPA will issue
another Federal Register notice
pursuant to 5 CFR 1320.5(a)(1)(iv) to
announce the submission of the ICR to
OMB and the opportunity to submit
additional comments to OMB. If you
have any questions about this ICR or the
approval process, please contact the
technical person listed under FOR
FURTHER INFORMATION CONTACT.
Dated: August 6, 2012.
Bruce Means,
Acting Director, Assessment and Remediation
Division, Office of Superfund Remediation
and Technology Innovation.
[FR Doc. 2012–19719 Filed 8–9–12; 8:45 am]
BILLING CODE 6560–50–P
ENVIRONMENTAL PROTECTION
AGENCY
[FRL–9715–5]
Delegation of Authority to the State of
West Virginia To Implement and
Enforce Additional or Revised National
Emission Standards for Hazardous Air
Pollutants and New Source
Performance Standards
Environmental Protection
Agency (EPA).
ACTION: Notice of delegation of
authority.
AGENCY:
On June 22, 2012, EPA sent
the State of West Virginia (West
Virginia) a letter acknowledging that
West Virginia’s delegation of authority
to implement and enforce National
Emissions Standards for Hazardous Air
Pollutants (NESHAP) and New Source
Performance Standards (NSPS) had been
updated, as provided for under
previously approved delegation
mechanisms. To inform regulated
facilities and the public of West
Virginia’s updated delegation of
authority to implement and enforce
NESHAP and NSPS, EPA is making
available a copy of EPA’s letter to West
Virginia through this notice.
DATES: On June 22, 2012, EPA sent West
Virginia a letter acknowledging that
SUMMARY:
PO 00000
Frm 00039
Fmt 4703
Sfmt 4703
West Virginia’s delegation of authority
to implement and enforce NESHAP and
NSPS had been updated.
ADDRESSES: Copies of documents
pertaining to this action are available for
public inspection during normal
business hours at the Air Protection
Division, U.S. Environmental Protection
Agency, Region III, 1650 Arch Street,
Philadelphia, Pennsylvania 19103–
2029. Copies of West Virginia’s
submittal are also available at the West
Virginia Department of Environmental
Protection, Division of Air Quality, 601
57th Street SE., Charleston, West
Virginia 25304. Copies of West
Virginia’s notice to EPA that West
Virginia has updated its incorporation
by reference of Federal NESHAP and
NSPS, and of EPA’s response, may also
be found posted on EPA Region III’s
Web site at: https://www.epa.gov/
reg3artd/airregulations/delegate/
wvdelegation.htm.
FOR FURTHER INFORMATION CONTACT: Ray
Chalmers, (215) 814–2061, or by email
at chalmers.ray@epa.gov.
SUPPLEMENTARY INFORMATION: On June 6,
2012, West Virginia notified EPA that
West Virginia has updated its
incorporation by reference of Federal
NESHAP and NSPS to include many
such standards, to the extent referenced
in the Code of Federal Regulations
(CFR), Parts 60, 61, and 63, effective
June 1, 2011. On June 22, 2012, EPA
sent West Virginia a letter
acknowledging that West Virginia now
has the authority to implement and
enforce the NESHAP and NSPS as
specified by West Virginia in its notice
to EPA, as provided for under
previously approved automatic
delegation mechanisms. All
notifications, applications, reports and
other correspondence required pursuant
to the delegated NESHAP and NSPS
must be submitted to both the US EPA
Region III and to the West Virginia
Department of Environmental Quality.
A copy of EPA’s letter to West Virginia
follows:
‘‘Mr. John Benedict, Director, Division of Air
Quality, West Virginia Department of
Environmental Protection, 601 57th
Street, Charleston, West Virginia 25304
Dear Mr. Benedict: The United States
Environmental Protection Agency (EPA) has
previously delegated to the State of West
Virginia (West Virginia) the authority to
implement and enforce various federal
National Emissions Standards for Hazardous
Air Pollutants (NESHAP) and New Source
Performance Standards (NSPS), which are
found at 40 C.F.R. Parts 60, 61 and 63.1 In
1 EPA has posted copies of these actions at: http:
//www.epa.gov/reg3artd/airregulations/delegate/
wvdelegation.htm
E:\FR\FM\10AUN1.SGM
10AUN1
mstockstill on DSK4VPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 155 / Friday, August 10, 2012 / Notices
those actions EPA also delegated to West
Virginia the authority to implement and
enforce any future EPA NESHAP or NSPS on
the condition that West Virginia legally adopt
the future standards, make only allowed
wording changes, and provide specified
notice to EPA.
In a letter dated June 6, 2012, West Virginia
informed EPA that West Virginia had
updated its incorporation by reference of
federal NESHAP and NSPS to include many
such standards, to the extent referenced in 40
C.F.R. Parts 60, 61, and 63, effective June 1,
2011. West Virginia noted that it understood
that it was automatically delegated the
authority to implement these standards. West
Virginia committed to enforcing the
standards in conformance with the terms of
EPA’s previous delegations of authority. West
Virginia made only allowed wording
changes.
West Virginia provided copies of the
revised West Virginia Legislative Rules
which specify the NESHAP and NSPS which
West Virginia has adopted by reference.
These revised Legislative Rules are entitled
45 CSR 34—‘‘Emission Standards for
Hazardous Air Pollutants,’’ and 45 CSR 16—
‘‘Standards of Performance for New
Stationary Sources.’’ These revised Rules
have an effective date of June 1, 2012.
Accordingly, EPA acknowledges that West
Virginia now has the authority, as provided
for under the terms of EPA’s previous
delegation actions, to implement and enforce
the NESHAP and NSPS standards which
West Virginia has adopted by reference in
West Virginia’s revised Legislative Rules 45
CSR 34 and 45 CSR 16, both effective on June
1, 2012.
Please note that on December 19, 2008 in
Sierra Club vs. EPA,2 the United States Court
of Appeals for the District of Columbia
Circuit vacated certain provisions of the
General Provisions of 40 C.F.R. Part 63
relating to exemptions for startup, shutdown,
and malfunction (SSM). On October 16, 2009,
the Court issued the mandate vacating these
SSM exemption provisions, which are found
at 40 C.F.R. Part 63, §§ 63.6(f)(1) and (h)(1).
Accordingly, EPA no longer allows sources
the SSM exemption as provided for in the
vacated provisions at 40 C.F.R. Part 63,
§§ 63.6(f)(1) and (h)(1), even though EPA has
not yet formally removed the SSM exemption
provisions from the General Provisions of 40
C.F.R. Part 63. Because West Virginia
incorporated 40 C.F.R. Part 63 by reference,
West Virginia should also no longer allow
sources to use the former SSM exemption
from the General Provisions of 40 C.F.R. Part
63 due to the Court’s ruling in Sierra Club
vs. EPA.
EPA appreciates West Virginia’s
continuing NESHAP and NSPS enforcement
efforts, and also West Virginia’s decision to
take automatic delegation of additional and
more recent NESHAP and NSPS by adopting
them by reference.
If you have any questions, please contact
me or Ms. Kathleen Cox, Associate Director,
Office of Permits and Air Toxics, at 215–814–
2173.
2 Sierra Club v. EPA, 551 F.3rd 1019 (D.C. Cir.
2008)
VerDate Mar<15>2010
18:02 Aug 09, 2012
Jkt 226001
Sincerely,
Diana Esher, Director
Air Protection Division’’
This notice acknowledges the update
of West Virginia’s delegation of
authority to implement and enforce
NESHAP and NSPS.
Dated: August 1, 2012.
Diana Esher,
Director, Air Protection Division, Region III.
[FR Doc. 2012–19685 Filed 8–9–12; 8:45 am]
BILLING CODE 6560–50–P
ENVIRONMENTAL PROTECTION
AGENCY
[ER–FRL–9004–4]
Environmental Impacts Statements;
Notice of Availability
Responsible Agency: Office of Federal
Activities, General Information (202)
564–7146 or https://www.epa.gov/
compliance/nepa/
Weekly receipt of Environmental Impact
Statements
Filed 07/30/2012 Through 08/03/2012
Pursuant to 40 CFR 1506.9.
Notice
Section 309(a) of the Clean Air Act
requires that EPA make public its
comments on EISs issued by other
Federal agencies. EPA’s comment letters
on EISs are available at: https://
www.epa.gov/compliance/nepa/
eisdata.html.
Information
Starting October 1, 2012, EPA will not
accept paper copies or CDs of EISs for
filing purposes; all submissions on or
after October 1, 2012 must be made
through e-NEPA.
While this system eliminates the need
to submit paper or CD copies to EPA to
meet filing requirements, electronic
submission does not change
requirements for distribution of EISs for
public review and comment. To begin
using e-NEPA, you must first register
with EPA’s electronic reporting site—
https://cdx.epa.gov/epa_home.asp
EIS No. 20120257, Final EIS, BR, CA,
San Joaquin River Restoration
Program, A Comprehensive LongTerm Effort to Restore Flows to the
San Joaquin River from Friant Dam to
the Confluence of Merced River and
Restore a Self-Sustaining Chinook
Salmon Fishery in the River while
Reducing or Avoiding Adverse Water
Supply Impacts from Interim and
Restoration Flows, Implementation,
CA, Review Period Ends: 09/10/2012,
Contact: Michelle Banonis 916–978–
5457.
PO 00000
Frm 00040
Fmt 4703
Sfmt 4703
47839
EIS No. 20120258, Draft EIS, USN, CA,
LEGISLATIVE—Renewal of Naval Air
Weapons Station China Lake Public
Land Withdrawal, To Conduct
Research, Development, Acquisition,
Test and Evaluation Activities, Kern,
Inyo, and San Bernardino Counties,
CA, Comment Period Ends: 11/08/
2012, Contact: Gene Beale 619–532–
1027.
EIS No. 20120259, Final EIS, MARAD,
CA, ADOPTION—Middle Harbor
Redevelopment Project, Funding, Port
of Long Beach, Los Angeles County,
CA, Review Period Ends: 09/10/2012,
Contact: Kristine Gilson 202–366–
1969. The U.S. Department of
Transportation’s Maritime
Administration (MARAD) has
adopted the U.S. Corps of Engineers
final EIS filed 5/21/2008. The
MARAD was not a cooperating agency
for the above final EIS. Recirculation
of the document is necessary under
Section 1506.3(b) of the Council on
Environmental Quality Regulations.
EIS No. 20120260, Final EIS, USFS, NE.,
Allotment Management Planning in
the McKelvie Geographic Area
Project, Managing Livestock Grazing,
Bessey Ranger District, Samuel R.
McKelvie National Forest, Cherry
County, NE., Review Period Ends: 09/
10/2012, Contact: Michael Croxen
308–533–2257.
EIS No. 20120261, Final EIS, USFS, CO,
Federal Coal Lease Modifications
COC–1362 and COC 67232, Adding
800 and 921 Additional Acres, Paonia
Ranger District, Grand Mesa,
Uncompahgre and Gunnison National
Forests, Gunnison County, CO,
Review Period Ends: 09/10/2012,
Contact: Niccole Mortenson 406–329–
3163.
EIS No. 20120262, Draft EIS, BR, CA,
San Luis Reservoir State Recreation
Area Resource Management Plan/
General Plan, Implementation,
Vicinity of Los Banos, CA, Comment
Period Ends: 10/05/2012, Contact:
Dave Woolley 559–487–5049.
EIS No. 20120263, Final EIS, USFS,
BLM, CA, Barren Ridge Renewable
Transmission Project, Construct,
Operate, Maintain and Upgrade
220kV Electrical Transmission Lines
and Switching Stations, Kern and Los
Angeles Counties, CA, Contact: Justin
Seastrand, 626–574–5278(AFS) or
Lynette Elser 951–697–5233(BLM).
The U.S. Department of Agriculture’s
Forest Service and the U.S. Department
of the Interior’s Bureau of Land
Management are joint lead agencies for
this project.
The U.S. Forest Service has a formally
established appeal process which allows
E:\FR\FM\10AUN1.SGM
10AUN1
Agencies
[Federal Register Volume 77, Number 155 (Friday, August 10, 2012)]
[Notices]
[Pages 47838-47839]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-19685]
-----------------------------------------------------------------------
ENVIRONMENTAL PROTECTION AGENCY
[FRL-9715-5]
Delegation of Authority to the State of West Virginia To
Implement and Enforce Additional or Revised National Emission Standards
for Hazardous Air Pollutants and New Source Performance Standards
AGENCY: Environmental Protection Agency (EPA).
ACTION: Notice of delegation of authority.
-----------------------------------------------------------------------
SUMMARY: On June 22, 2012, EPA sent the State of West Virginia (West
Virginia) a letter acknowledging that West Virginia's delegation of
authority to implement and enforce National Emissions Standards for
Hazardous Air Pollutants (NESHAP) and New Source Performance Standards
(NSPS) had been updated, as provided for under previously approved
delegation mechanisms. To inform regulated facilities and the public of
West Virginia's updated delegation of authority to implement and
enforce NESHAP and NSPS, EPA is making available a copy of EPA's letter
to West Virginia through this notice.
DATES: On June 22, 2012, EPA sent West Virginia a letter acknowledging
that West Virginia's delegation of authority to implement and enforce
NESHAP and NSPS had been updated.
ADDRESSES: Copies of documents pertaining to this action are available
for public inspection during normal business hours at the Air
Protection Division, U.S. Environmental Protection Agency, Region III,
1650 Arch Street, Philadelphia, Pennsylvania 19103-2029. Copies of West
Virginia's submittal are also available at the West Virginia Department
of Environmental Protection, Division of Air Quality, 601 57th Street
SE., Charleston, West Virginia 25304. Copies of West Virginia's notice
to EPA that West Virginia has updated its incorporation by reference of
Federal NESHAP and NSPS, and of EPA's response, may also be found
posted on EPA Region III's Web site at: https://www.epa.gov/reg3artd/airregulations/delegate/wvdelegation.htm.
FOR FURTHER INFORMATION CONTACT: Ray Chalmers, (215) 814-2061, or by
email at chalmers.ray@epa.gov.
SUPPLEMENTARY INFORMATION: On June 6, 2012, West Virginia notified EPA
that West Virginia has updated its incorporation by reference of
Federal NESHAP and NSPS to include many such standards, to the extent
referenced in the Code of Federal Regulations (CFR), Parts 60, 61, and
63, effective June 1, 2011. On June 22, 2012, EPA sent West Virginia a
letter acknowledging that West Virginia now has the authority to
implement and enforce the NESHAP and NSPS as specified by West Virginia
in its notice to EPA, as provided for under previously approved
automatic delegation mechanisms. All notifications, applications,
reports and other correspondence required pursuant to the delegated
NESHAP and NSPS must be submitted to both the US EPA Region III and to
the West Virginia Department of Environmental Quality. A copy of EPA's
letter to West Virginia follows:
``Mr. John Benedict, Director, Division of Air Quality, West
Virginia Department of Environmental Protection, 601 57th Street,
Charleston, West Virginia 25304
Dear Mr. Benedict: The United States Environmental Protection
Agency (EPA) has previously delegated to the State of West Virginia
(West Virginia) the authority to implement and enforce various
federal National Emissions Standards for Hazardous Air Pollutants
(NESHAP) and New Source Performance Standards (NSPS), which are
found at 40 C.F.R. Parts 60, 61 and 63.\1\ In
[[Page 47839]]
those actions EPA also delegated to West Virginia the authority to
implement and enforce any future EPA NESHAP or NSPS on the condition
that West Virginia legally adopt the future standards, make only
allowed wording changes, and provide specified notice to EPA.
---------------------------------------------------------------------------
\1\ EPA has posted copies of these actions at: https://www.epa.gov/reg3artd/airregulations/delegate/wvdelegation.htm
---------------------------------------------------------------------------
In a letter dated June 6, 2012, West Virginia informed EPA that
West Virginia had updated its incorporation by reference of federal
NESHAP and NSPS to include many such standards, to the extent
referenced in 40 C.F.R. Parts 60, 61, and 63, effective June 1,
2011. West Virginia noted that it understood that it was
automatically delegated the authority to implement these standards.
West Virginia committed to enforcing the standards in conformance
with the terms of EPA's previous delegations of authority. West
Virginia made only allowed wording changes.
West Virginia provided copies of the revised West Virginia
Legislative Rules which specify the NESHAP and NSPS which West
Virginia has adopted by reference. These revised Legislative Rules
are entitled 45 CSR 34--``Emission Standards for Hazardous Air
Pollutants,'' and 45 CSR 16--``Standards of Performance for New
Stationary Sources.'' These revised Rules have an effective date of
June 1, 2012.
Accordingly, EPA acknowledges that West Virginia now has the
authority, as provided for under the terms of EPA's previous
delegation actions, to implement and enforce the NESHAP and NSPS
standards which West Virginia has adopted by reference in West
Virginia's revised Legislative Rules 45 CSR 34 and 45 CSR 16, both
effective on June 1, 2012.
Please note that on December 19, 2008 in Sierra Club vs. EPA,\2\
the United States Court of Appeals for the District of Columbia
Circuit vacated certain provisions of the General Provisions of 40
C.F.R. Part 63 relating to exemptions for startup, shutdown, and
malfunction (SSM). On October 16, 2009, the Court issued the mandate
vacating these SSM exemption provisions, which are found at 40
C.F.R. Part 63, Sec. Sec. 63.6(f)(1) and (h)(1).
---------------------------------------------------------------------------
\2\ Sierra Club v. EPA, 551 F.3rd 1019 (D.C. Cir. 2008)
---------------------------------------------------------------------------
Accordingly, EPA no longer allows sources the SSM exemption as
provided for in the vacated provisions at 40 C.F.R. Part 63,
Sec. Sec. 63.6(f)(1) and (h)(1), even though EPA has not yet
formally removed the SSM exemption provisions from the General
Provisions of 40 C.F.R. Part 63. Because West Virginia incorporated
40 C.F.R. Part 63 by reference, West Virginia should also no longer
allow sources to use the former SSM exemption from the General
Provisions of 40 C.F.R. Part 63 due to the Court's ruling in Sierra
Club vs. EPA.
EPA appreciates West Virginia's continuing NESHAP and NSPS
enforcement efforts, and also West Virginia's decision to take
automatic delegation of additional and more recent NESHAP and NSPS
by adopting them by reference.
If you have any questions, please contact me or Ms. Kathleen
Cox, Associate Director, Office of Permits and Air Toxics, at 215-
814-2173.
Sincerely,
Diana Esher, Director
Air Protection Division''
This notice acknowledges the update of West Virginia's delegation
of authority to implement and enforce NESHAP and NSPS.
Dated: August 1, 2012.
Diana Esher,
Director, Air Protection Division, Region III.
[FR Doc. 2012-19685 Filed 8-9-12; 8:45 am]