San Francisco Public Utilities Commission; Notice of Application Accepted for Filing and Soliciting Comments, Motions To Intervene, Protests, Recommendations, and Terms and Conditions, 45594-45595 [2012-18773]
Download as PDF
45594
Federal Register / Vol. 77, No. 148 / Wednesday, August 1, 2012 / Notices
tkelley on DSK3SPTVN1PROD with NOTICES
90th day after the end of the report year
(March 31), Form EIA 64A information
was due by April 11 following the end
of the calendar year, and Form 816
information was due within 20 days of
the end of the report period.
Pending authorization to administer
the proposed new form, EIA has
terminated the EIA–895. Thus, the
following items will no longer be
collected: gas well gas, oil well gas,
coalbed methane wells, shale gas, gross
withdrawals, repressured gas, natural
gas vented and flared, nonhydrocarbon
gases removed, marketed production,
natural gas used as fuel on leases,
wellhead price, and number of
producing gas wells. However, through
the EIA–914 and the new form EIA–915
the following products will be made
accessible with caveats:
• Total gross withdrawals: The monthly
data will be supplied from the EIA–
914
• Total dry production: The monthly
data will be provided by a calculation
from the EIA–914 and EIA–915 as
follows:
D Form EIA–914 will provide natural
gas lease production
D Form EIA–915 will provide the total
plant intake and natural gas sent to
transmission lines (pipelines)
D The actual value of the dry natural gas
production will have two steps:
1. The difference of subtracting
natural gas lease production from
the total plant inlet will result in
pipeline quality gas that does not
require processing
2. The value of total natural gas sent
to a transmission lines (pipelines)
will be added to pipeline quality
gas resulting in dry production
• Total marketed production is
calculated by adding together the dry
production value and the extraction
loss value
Better quality data should result in the
new form, because dry production will
be calculated as a result of metered
production from the EIA–915 and EIA–
914 (Note, the EIA–914 value is
estimated from a statistical sample). All
data elements collected from the Form
EIA–816 are to be transferred to the
Form EIA–915. Form EIA–64A elements
will also be collected through the Form
EIA–915 with the addition of data
elements such as:
Volume of Natural Gas Intake
Processed
• Gas Received from Operators and Gas
Gatherers Within a Processor’s State
Boundaries
• Gas Received From Other Processing
Plants (provide the plant and state
VerDate Mar<15>2010
19:53 Jul 31, 2012
Jkt 226001
where the gas was previously
processed)
Federal Energy Regulatory
Commission
Disposition of Plant Intake
•
•
•
•
Plant Outlet (from plant meters)
Extraction Loss
Non-Hydrocarbons
Vented and Flared Hydrocarbon Gas
from the Processing Plant
Disposition of Plant Outlet
• Repressuring/Cycled
• Returned For Lease Fuel
• Natural Gas Sent to Fractionators for
Fuel Use
• Delivered To Other Process Plant
• Transmission Line
Form EIA–915 is mandatory and must
be completed by the operators of ALL
facilities that extract liquid
hydrocarbons from a natural gas stream
(natural gas processing plants) and/or
separate a liquid hydrocarbon stream
into its component products
(fractionators). In addition, gas
sweetening plants (plants that extract
CO2, H2S, sulfur, etc.) will be required
to submit this form.
EIA proposes that companyidentifiable data from Form EIA–915 be
released to the public in order to meet
increasing data user needs for more
company-level data. (Currently, 10
states release the gas plant data for free,
while Bentek Energy releases the data
for a fee.) EIA also proposes that the
survey frame administrative data (e.g.,
company’s name, county) from the EIA–
915 be available to the public. This
information can currently be obtained
free on 10 states agencies’ Web pages,
the Office of Natural Resources
Revenue, or for a fee from Bentek
Energy and Sulpetro Inc.;
(5) Annual Estimated Number of
Respondents: 550 monthly respondents;
(6) Annual Estimated Number of
Total Responses: 6,660 responses on an
annual basis;
(7) Annual Estimated Number of
Burden Hours: 13,200;
(8) Annual Estimated Reporting and
Recordkeeping Cost Burden: No
additional costs beyond burden hours
are anticipated from the proposed new
collection instrument.
Statutory Authority: Section 13(b) of the
Federal Energy Administration Act of 1974,
Pub. L. 93–275, codified at 15 U.S.C. 772(b).
Issued in Washington, DC, July 26, 2012.
Richard Reeves,
Acting Director, Office of Survey Development
and Statistical Integration, U. S. Energy
Information Administration.
[FR Doc. 2012–18751 Filed 7–31–12; 8:45 am]
BILLING CODE 6450–01–P
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
[Project No. 14406–000]
San Francisco Public Utilities
Commission; Notice of Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene,
Protests, Recommendations, and
Terms and Conditions
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Conduit
Exemption.
b. Project No.: 14406–000.
c. Date filed: May 9, 2012, and
supplemented on July 11 and July 25,
2012.
d. Applicant: San Francisco Public
Utilities Commission (San Francisco
PUC).
e. Name of Project: University Mound
Reservoir Renewable Hydroelectric
Project.
f. Location: The proposed University
Mound Reservoir Renewable
Hydroelectric Project would be located
adjacent to the existing McLaren
Pumping Plant which is located at the
Northwest corner of the intersection at
Bowdoin Street and Woosley Street in
San Francisco, California. The project
would use the existing Crystal Springs
Pipelines (CSPL1 and CSPL2), which
ultimately deliver water from the San
Francisco Public Utilities Commission’s
Water Supply and Treatment Divisions
transmission system (located in San
Mateo County on the San Francisco
peninsula) to the University Mound
Reservoir south and north basins
(located in San Francisco). The land on
which all the project structures are
located is owned by the applicant.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contact: Mr. John Doyle,
Manager Energy Infrastructure, Planning
and Development, San Francisco Public
Utilities Commission, Power Enterprise
Division, 1155 Market Street, 4th Floor,
San Francisco, California 94103;
telephone (415) 554–0725.
i. FERC Contact: Kim Carter,
telephone (202) 502–6486, and email
address Kim.Carter@ferc.gov.
j. Status of Environmental Analysis:
This application is ready for
environmental analysis at this time, and
the Commission is requesting
comments, reply comments,
recommendations, terms and
conditions, and prescriptions.
E:\FR\FM\01AUN1.SGM
01AUN1
tkelley on DSK3SPTVN1PROD with NOTICES
Federal Register / Vol. 77, No. 148 / Wednesday, August 1, 2012 / Notices
k. Deadline for filing responsive
documents: Due to the small size of the
proposed project, as wells as the
resource agency consultation letters
filed with the application, the 60-day
timeframe specified in 18 CFR 4.43(b)
for filing all comments, motions to
intervene, protests, recommendations,
terms and conditions, and prescriptions
is shortened to 30 days from the
issuance date of this notice. All reply
comments filed in response to
comments submitted by any resource
agency, Indian tribe, or person, must be
filed with the Commission within 45
days from the issuance date of this
notice.
Comments, protests, and
interventions may be filed electronically
via the Internet in lieu of paper; see 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site under the ‘‘e-Filing’’ link. The
Commission strongly encourages
electronic filings.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person in the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
l. Description of Project: The proposed
University Mound Reservoir Renewable
Hydroelectric Project would consist of:
(1) A new intake on the San Francisco
Public Utilities Commission’s existing
42-inch-diameter Crystal Springs
Pipeline No. 1, connecting to a new 24inch-diameter, 68-feet-long intake
pipeline; (2) a new intake on the San
Francisco Public Utilities Commission’s
existing 60-inch-diameter Crystal
Springs Pipeline No. 2, connecting to a
new 36-inch-diameter, approximately
40-feet-long intake pipeline; (3) a new,
36.5 feet-wide by 41.5 feet-long, 1-story
Mission Style powerhouse, containing 3
turbine/generator units, each rated 80.3
kW, for a total installed capacity of
240.9 kW; (4) a new 36-inch-diameter,
40-feet-long pipeline that discharges to
the 60-inch-diameter Crystal Springs
Pipeline No. 2; (5) a new 24-inchdiameter, 67-feet-long pipeline that
discharges to the 42-inch-diameter
Crystal Springs Pipeline No. 1; and (6)
appurtenant facilities. The project
would have an estimated annual
generation of 1,586,494 kilowatt-hours.
m. This filing is available for review
and reproduction at the Commission in
the Public Reference Room, Room 2A,
888 First Street NE., Washington, DC
VerDate Mar<15>2010
19:53 Jul 31, 2012
Jkt 226001
20426. The filing may also be viewed on
the Web at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number, here P–14406, in the docket
number field to access the document.
For assistance, call toll-free 1–866–208–
3676 or email
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for review and reproduction at
the address in item h above.
n. Development Application—Any
qualified applicant desiring to file a
competing application must submit to
the Commission, on or before the
specified deadline date for the
particular application, a competing
development application, or a notice of
intent to file such an application.
Submission of a timely notice of intent
allows an interested person to file the
competing development application no
later than 120 days after the specified
deadline date for the particular
application. Applications for
preliminary permits will not be
accepted in response to this notice.
o. Notice of Intent — A notice of
intent must specify the exact name,
business address, and telephone number
of the prospective applicant, and must
include an unequivocal statement of
intent to submit a competing
development application. A notice of
intent must be served on the
applicant(s) named in this public notice.
p. Protests or Motions To Intervene—
Anyone may submit a protest or a
motion to intervene in accordance with
the requirements of Rules of Practice
and Procedure, 18 CFR 385.210,
385.211, and 385.214. In determining
the appropriate action to take, the
Commission will consider all protests
filed, but only those who file a motion
to intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any protests or
motions to intervene must be received
on or before the specified deadline date
for the particular application.
q. All filings must (1) bear in all
capital letters the title ‘‘PROTEST’’,
‘‘MOTION TO INTERVENE’’, ‘‘NOTICE
OF INTENT TO FILE COMPETING
APPLICATION’’, ‘‘COMPETING
APPLICATION’’, ‘‘COMMENTS’’,
‘‘REPLY COMMENTS,’’
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or
‘‘PRESCRIPTIONS;’’ (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
PO 00000
Frm 00021
Fmt 4703
Sfmt 9990
45595
comments, recommendations, terms and
conditions, or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requirements
of 18 CFR 4.34(b). Agencies may obtain
copies of the application directly from
the applicant. Any of these documents
must be filed by providing the original
and eight copies to: The Secretary,
Federal Energy Regulatory Commission,
888 First Street NE., Washington, DC
20426. An additional copy must be sent
to Director, Division of Hydropower
Administration and Compliance, Office
of Energy Projects, Federal Energy
Regulatory Commission, at the above
address. A copy of any protest or motion
to intervene must be served upon each
representative of the applicant specified
in the particular application. A copy of
all other filings in reference to this
application must be accompanied by
proof of service on all persons listed in
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
r. Waiver of Pre-filing Consultation:
The applicant requested agencies to
support the waiver of the Commission’s
consultation requirements under 18 CFR
4.38(c). In June 2011, the National Park
Service and the U.S. Fish and Wildlife
Service advised by written
correspondence that they do not require
further consultation. The Bay Area
Regional Water Quality Control Board
advised that they had no plans to send
comments. The Office of Historic
Preservation, U.S. Environmental
Protection Agency—Region 9, California
Department of Fish and Game, National
Marine Fisheries Service, Department of
Water Resources Division of Dam
Safety, and the California Division of
Dam Safety and Inspections were
contacted by phone and verbally
responded that they will not be replying
in writing, nor would they comment on
the application. Therefore, we intend to
accept the consultation that has
occurred on this project during the prefiling period and we intend to waive
pre-filing consultation under section
4.38(c), which requires, among other
things, conducting studies requested by
resource agencies, and distributing and
consulting on a draft exemption
application.
Dated: July 26, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012–18773 Filed 7–31–12; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\01AUN1.SGM
01AUN1
Agencies
[Federal Register Volume 77, Number 148 (Wednesday, August 1, 2012)]
[Notices]
[Pages 45594-45595]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-18773]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 14406-000]
San Francisco Public Utilities Commission; Notice of Application
Accepted for Filing and Soliciting Comments, Motions To Intervene,
Protests, Recommendations, and Terms and Conditions
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Conduit Exemption.
b. Project No.: 14406-000.
c. Date filed: May 9, 2012, and supplemented on July 11 and July
25, 2012.
d. Applicant: San Francisco Public Utilities Commission (San
Francisco PUC).
e. Name of Project: University Mound Reservoir Renewable
Hydroelectric Project.
f. Location: The proposed University Mound Reservoir Renewable
Hydroelectric Project would be located adjacent to the existing McLaren
Pumping Plant which is located at the Northwest corner of the
intersection at Bowdoin Street and Woosley Street in San Francisco,
California. The project would use the existing Crystal Springs
Pipelines (CSPL1 and CSPL2), which ultimately deliver water from the
San Francisco Public Utilities Commission's Water Supply and Treatment
Divisions transmission system (located in San Mateo County on the San
Francisco peninsula) to the University Mound Reservoir south and north
basins (located in San Francisco). The land on which all the project
structures are located is owned by the applicant.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
h. Applicant Contact: Mr. John Doyle, Manager Energy
Infrastructure, Planning and Development, San Francisco Public
Utilities Commission, Power Enterprise Division, 1155 Market Street,
4th Floor, San Francisco, California 94103; telephone (415) 554-0725.
i. FERC Contact: Kim Carter, telephone (202) 502-6486, and email
address Kim.Carter@ferc.gov.
j. Status of Environmental Analysis: This application is ready for
environmental analysis at this time, and the Commission is requesting
comments, reply comments, recommendations, terms and conditions, and
prescriptions.
[[Page 45595]]
k. Deadline for filing responsive documents: Due to the small size
of the proposed project, as wells as the resource agency consultation
letters filed with the application, the 60-day timeframe specified in
18 CFR 4.43(b) for filing all comments, motions to intervene, protests,
recommendations, terms and conditions, and prescriptions is shortened
to 30 days from the issuance date of this notice. All reply comments
filed in response to comments submitted by any resource agency, Indian
tribe, or person, must be filed with the Commission within 45 days from
the issuance date of this notice.
Comments, protests, and interventions may be filed electronically
via the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and
the instructions on the Commission's Web site under the ``e-Filing''
link. The Commission strongly encourages electronic filings.
The Commission's Rules of Practice and Procedure require all
intervenors filing documents with the Commission to serve a copy of
that document on each person in the official service list for the
project. Further, if an intervenor files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency.
l. Description of Project: The proposed University Mound Reservoir
Renewable Hydroelectric Project would consist of: (1) A new intake on
the San Francisco Public Utilities Commission's existing 42-inch-
diameter Crystal Springs Pipeline No. 1, connecting to a new 24-inch-
diameter, 68-feet-long intake pipeline; (2) a new intake on the San
Francisco Public Utilities Commission's existing 60-inch-diameter
Crystal Springs Pipeline No. 2, connecting to a new 36-inch-diameter,
approximately 40-feet-long intake pipeline; (3) a new, 36.5 feet-wide
by 41.5 feet-long, 1-story Mission Style powerhouse, containing 3
turbine/generator units, each rated 80.3 kW, for a total installed
capacity of 240.9 kW; (4) a new 36-inch-diameter, 40-feet-long pipeline
that discharges to the 60-inch-diameter Crystal Springs Pipeline No. 2;
(5) a new 24-inch-diameter, 67-feet-long pipeline that discharges to
the 42-inch-diameter Crystal Springs Pipeline No. 1; and (6)
appurtenant facilities. The project would have an estimated annual
generation of 1,586,494 kilowatt-hours.
m. This filing is available for review and reproduction at the
Commission in the Public Reference Room, Room 2A, 888 First Street NE.,
Washington, DC 20426. The filing may also be viewed on the Web at
https://www.ferc.gov using the ``eLibrary'' link. Enter the docket
number, here P-14406, in the docket number field to access the
document. For assistance, call toll-free 1-866-208-3676 or email
FERCOnlineSupport@ferc.gov. For TTY, call (202) 502-8659. A copy is
also available for review and reproduction at the address in item h
above.
n. Development Application--Any qualified applicant desiring to
file a competing application must submit to the Commission, on or
before the specified deadline date for the particular application, a
competing development application, or a notice of intent to file such
an application. Submission of a timely notice of intent allows an
interested person to file the competing development application no
later than 120 days after the specified deadline date for the
particular application. Applications for preliminary permits will not
be accepted in response to this notice.
o. Notice of Intent -- A notice of intent must specify the exact
name, business address, and telephone number of the prospective
applicant, and must include an unequivocal statement of intent to
submit a competing development application. A notice of intent must be
served on the applicant(s) named in this public notice.
p. Protests or Motions To Intervene--Anyone may submit a protest or
a motion to intervene in accordance with the requirements of Rules of
Practice and Procedure, 18 CFR 385.210, 385.211, and 385.214. In
determining the appropriate action to take, the Commission will
consider all protests filed, but only those who file a motion to
intervene in accordance with the Commission's Rules may become a party
to the proceeding. Any protests or motions to intervene must be
received on or before the specified deadline date for the particular
application.
q. All filings must (1) bear in all capital letters the title
``PROTEST'', ``MOTION TO INTERVENE'', ``NOTICE OF INTENT TO FILE
COMPETING APPLICATION'', ``COMPETING APPLICATION'', ``COMMENTS'',
``REPLY COMMENTS,'' ``RECOMMENDATIONS,'' ``TERMS AND CONDITIONS,'' or
``PRESCRIPTIONS;'' (2) set forth in the heading the name of the
applicant and the project number of the application to which the filing
responds; (3) furnish the name, address, and telephone number of the
person protesting or intervening; and (4) otherwise comply with the
requirements of 18 CFR 385.2001 through 385.2005. All comments,
recommendations, terms and conditions, or prescriptions must set forth
their evidentiary basis and otherwise comply with the requirements of
18 CFR 4.34(b). Agencies may obtain copies of the application directly
from the applicant. Any of these documents must be filed by providing
the original and eight copies to: The Secretary, Federal Energy
Regulatory Commission, 888 First Street NE., Washington, DC 20426. An
additional copy must be sent to Director, Division of Hydropower
Administration and Compliance, Office of Energy Projects, Federal
Energy Regulatory Commission, at the above address. A copy of any
protest or motion to intervene must be served upon each representative
of the applicant specified in the particular application. A copy of all
other filings in reference to this application must be accompanied by
proof of service on all persons listed in the service list prepared by
the Commission in this proceeding, in accordance with 18 CFR 4.34(b)
and 385.2010.
r. Waiver of Pre-filing Consultation: The applicant requested
agencies to support the waiver of the Commission's consultation
requirements under 18 CFR 4.38(c). In June 2011, the National Park
Service and the U.S. Fish and Wildlife Service advised by written
correspondence that they do not require further consultation. The Bay
Area Regional Water Quality Control Board advised that they had no
plans to send comments. The Office of Historic Preservation, U.S.
Environmental Protection Agency--Region 9, California Department of
Fish and Game, National Marine Fisheries Service, Department of Water
Resources Division of Dam Safety, and the California Division of Dam
Safety and Inspections were contacted by phone and verbally responded
that they will not be replying in writing, nor would they comment on
the application. Therefore, we intend to accept the consultation that
has occurred on this project during the pre-filing period and we intend
to waive pre-filing consultation under section 4.38(c), which requires,
among other things, conducting studies requested by resource agencies,
and distributing and consulting on a draft exemption application.
Dated: July 26, 2012.
Kimberly D. Bose,
Secretary.
[FR Doc. 2012-18773 Filed 7-31-12; 8:45 am]
BILLING CODE 6717-01-P