Final Standard Review Plan, Branch Technical Position 7-19 on Guidance for Evaluation of Diversity and Defense-in-Depth in Digital Computer-Based Instrumentation and Control Systems, 43405-43406 [2012-18018]
Download as PDF
Federal Register / Vol. 77, No. 142 / Tuesday, July 24, 2012 / Notices
3.17 No Undue Risk to Public Health
and Safety
The underlying purpose of 10 CFR
Part 50, Appendix R, Section III.G is to
ensure that at least one means of
achieving and maintaining hot
shutdown remains available during and
following a postulated fire event. Based
on the above, no new accident
precursors are created by the use of the
specific OMAs, in conjunction with the
other installed fire protection features,
in response to a fire in the analyzed fire
areas. Therefore, the probability of
postulated accidents is not increased.
Also based on the above, the
consequences of postulated accidents
are not increased. Therefore, there is no
undue risk to public health and safety.
3.18 Consistent with Common Defense
and Security
This exemption would allow MPS2 to
credit the use of the specific OMAs, in
conjunction with the other installed fire
protection features, in response to a fire
in the analyzed fire areas, discussed
above, in lieu of meeting the
requirements specified in III.G.2. This
change, to the operation of the plant,
has no relation to security issues.
Therefore, the common defense and
security is not diminished by this
exemption.
3.19
sroberts on DSK5SPTVN1PROD with NOTICES
Conclusion
Based on the all of the features of the
defense-in-depth concept discussed
above, the NRC staff concludes that the
use of the requested OMAs, in these
particular instances and in conjunction
with the other installed fire protection
features, in lieu of strict compliance
with the requirements of III.G.2 is
consistent with the underlying purpose
of the rule. As such, the level of safety
present at MPS2 is commensurate with
VerDate Mar<15>2010
21:06 Jul 23, 2012
Jkt 226001
Dated at Rockville, Maryland, this 12th day
of July 2012.
For the Nuclear Regulatory Commission.
Michele G. Evans,
Director, Division of Operating Reactor
Licensing, Office of Nuclear Reactor
Regulation.
[FR Doc. 2012–17735 Filed 7–23–12; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
Special Circumstances
One of the special circumstances
described in 10 CFR 50.12(a)(2)(ii) is
that the application of the regulation is
not necessary to achieve the underlying
purpose of the rule. The underlying
purpose of 10 CFR Part 50, Appendix R,
Section III.G is to ensure that at least
one means of achieving and maintaining
hot shutdown remains available during
and following a postulated fire event.
While the licensee does not comply
with the explicit requirements of III.G.2
specifically, they do meet the
underlying purpose of 10 CFR Part 50,
Appendix R, and Section III.G as a
whole. Therefore, special circumstances
exist that warrant the issuance of this
exemption as required by 10 CFR
50.12(a)(2)(ii).
4.0
the established safety standards for
nuclear power plants.
Accordingly, the Commission has
determined that, pursuant to 10 CFR
50.12(a), the exemption is authorized by
law, will not present an undue risk to
the public health and safety, is
consistent with the common defense
and security and that special
circumstances are present to warrant
issuance of the exemption. Therefore,
the Commission hereby grants
Dominion an exemption from the
requirements of Section III.G.2 of
Appendix R of 10 CFR Part 50, to utilize
the OMAs discussed above at MPS2.
Pursuant to 10 CFR 51.32, the
Commission has determined that the
granting of this exemption will not have
a significant effect on the quality of the
human environment (77 FR 39746).
This exemption is effective upon
issuance.
[NRC–2010–0138]
Final Standard Review Plan, Branch
Technical Position 7–19 on Guidance
for Evaluation of Diversity and
Defense-in-Depth in Digital ComputerBased Instrumentation and Control
Systems
Nuclear Regulatory
Commission.
ACTION: Notice of availability.
AGENCY:
The U.S. Nuclear Regulatory
Commission (NRC or the Commission)
staff is issuing Final Revision 6 to
NUREG–0800, ‘‘Standard Review Plan
for the Review of Safety Analysis
Reports for Nuclear Power Plants,’’
Branch Technical Position (BTP) 7–19
on ‘‘Guidance for Evaluation of
Diversity and Defense-in-Depth in
Digital Computer-Based Instrumentation
and Control Systems.’’ This BTP is to be
cited as the acceptance criteria for
Diversity and Defense-in-Depth in
Digital Computer-Based Instrumentation
and Control Systems in the Standard
Review Plan (SRP), Chapter 7, for those
standard reactor designs that have not
been certified prior to the date of this
BTP. The purpose of this SRP update is
SUMMARY:
PO 00000
Frm 00178
Fmt 4703
Sfmt 4703
43405
to provide staff guidance for assessing
combined license (COL) applicant
compliance with the requirements.
DATES: The effective date of this SRP
update is August 23, 2012.
ADDRESSES: Please refer to Docket ID
NRC–2010–0138 when contacting the
NRC about the availability of
information regarding this document.
You may access information related to
this document, which the NRC
possesses and are publicly available by
any of the following methods:
• Federal Rulemaking Web site: Go to
https://www.regulations.gov and search
for Docket ID NRC–2010–0138. Address
questions about NRC dockets to Carol
Gallagher; telephone: 301–492–3668;
email: Carol.Gallagher@nrc.gov.
• NRC’s Agencywide Documents
Access and Management System
(ADAMS): You may access publiclyavailable documents online in the NRC
Library at https://www.nrc.gov/readingrm/adams.html. To begin the search,
select ‘‘ADAMS Public Documents’’ and
then select ‘‘Begin Web-based ADAMS
Search.’’ For problems with ADAMS,
please contact the NRC’s Public
Document Room (PDR) reference staff at
1–800–397–4209, 301–415–4737, or by
email to pdr.resource@nrc.gov. The
ADAMS accession number for each
document referenced in this notice (if
that document is available in ADAMS)
is provided the first time that a
document is referenced. The Final
Revision 6 to NUREG–0800, ‘‘Standard
Review Plan for the Review of Safety
Analysis Reports for Nuclear Power
Plants,’’ Branch Technical Position
(BTP) 7–19 on ‘‘Guidance for Evaluation
of Diversity and Defense-in-Depth in
Digital Computer-Based Instrumentation
and Control Systems’’ (Package)
(ADAMS Accession No. ML110550767),
Final Revision 6 to NUREG–0800,
‘‘Standard Review Plan for the Review
of Safety Analysis Reports for Nuclear
Power Plants,’’ Branch Technical
Position (BTP) 7–19 on ‘‘Guidance for
Evaluation of Diversity and Defense-inDepth in Digital Computer-Based
Instrumentation and Control Systems,’’
(ADAMS Accession No. ML110550791),
and Comment Response Document for
BTP 7–19, (ADAMS Accession No.
ML120830075).
• NRC’s PDR: You may examine and
purchase copies of public documents at
the NRC’s PDR, Room O1–F21, One
White Flint North, 11555 Rockville
Pike, Rockville, Maryland 20852.
• The NRC posts its issued staff
guidance on the NRC’s external Web
page (https://www.nrc.gov/reading-rm/
doc-collections/nuregs/staff/sr0800/).
E:\FR\FM\24JYN1.SGM
24JYN1
43406
Federal Register / Vol. 77, No. 142 / Tuesday, July 24, 2012 / Notices
Mr.
Ian C. Jung, Chief, Instrumentation,
Controls and Electrical Engineering
Branch 2, Division of Engineering,
Office of New Reactors, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001; telephone: 301–415–
2969 or email at Ian.Jung@nrc.gov.
FOR FURTHER INFORMATION CONTACT:
The NRC
staff issues SRPs and BTPs to facilitate
timely implementation of current staff
guidance and to facilitate activities
associated with the review of
applications for design certifications
and combined licenses by the Office of
New Reactors. Additionally, the SRPs
and BTPs are used by the Office of
Nuclear Reactor Regulation staff in the
review of applications for license
amendments in currently operating
nuclear power plants. The NRC staff
will also incorporate the revised SRP
section and BTP 7–19 into the next
revision of Regulatory Guide 1.206 and
any related guidance documents.
On March 19, 2010, the NRC staff
issued the proposed Revision 6 of
NUREG–0800, ‘‘Standard Review Plan
for the Review of Safety Analysis
Reports for Nuclear Power Plants: LWR
Edition,’’ BTP 7–19 on ‘‘Guidance for
Evaluation of Diversity and Defense-inDepth in Digital Computer-Based
Instrumentation and Control Systems’’
(ADAMS Accession No. ML093490771).
The NRC staff considered comments
received on the proposed revision to
BTP 7–19 as well as recommendations
from the ACRS, and incorporated the
changes suggested in the comments in
this final issuance. The NRC staff
responses to these comments can be
found under ADAMS Accession No.
ML120830075.
Backfitting: This SRP update does not
constitute backfitting as defined in Title
10 of the Code of Federal Regulations
(10 CFR) 50.109, nor is it inconsistent
with any of the issue finality provisions
in 10 CFR Part 52. This SRP does not
contain any new requirements for COL
applicants or holders under Part 52, or
for licensees of existing operating units
licensed under part 50. Rather, it
contains additional guidance and
clarification on compliance with 10 CFR
52.79(a)(31), which may be used by COL
applicants in the preparation of their
applications.
Congressional Review Act: This SRP
update is a rule as designated in the
Congressional Review Act (5 U.S.C.
801–808). However, OMB has not found
it to be a major rule as designated in the
Congressional Review Act.
sroberts on DSK5SPTVN1PROD with NOTICES
SUPPLEMENTARY INFORMATION:
Dated at Rockville, Maryland, this 16th day
of July 2012.
VerDate Mar<15>2010
21:06 Jul 23, 2012
Jkt 226001
For the Nuclear Regulatory Commission.
Amy E. Cubbage,
Chief, Policy Branch, Division of Advanced
Reactors and Rulemaking, Office of New
Reactors.
[FR Doc. 2012–18018 Filed 7–23–12; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[ NRC–2012–0002]
Notice of Sunshine Act Meetings
AGENCY HOLDING THE MEETINGS: Nuclear
Regulatory Commission.
DATES: Weeks of July 23, 30, August 6,
13, 20, 27, 2012.
PLACE: Commissioners’ Conference
Room, 11555 Rockville Pike, Rockville,
Maryland.
STATUS: Public and Closed.
Week of July 23, 2012
There are no meetings scheduled for
the week of July 23, 2012.
Week of July 30, 2012—Tentative
There are no meetings scheduled for
the week of July 30, 2012.
Week of August 6, 2012—Tentative
Tuesday, August 7, 2012
9:00 a.m. Briefing on the Status of
Lessons Learned from the
Fukushima Dai-ichi Accident
(Public Meeting) (Contact: John
Monninger, 301–415–0610).
This meeting will be webcast live at
the Web address—www.nrc.gov.
Week of August 13, 2012—Tentative
There are no meetings scheduled for
the week of August 13, 2012.
Week of August 20, 2012—Tentative
There are no meetings scheduled for
the week of August 20, 2012.
Week of August 27, 2012—Tentative
There are no meetings scheduled for
the week of August 27, 2012.
*
*
*
*
*
* The schedule for Commission
meetings is subject to change on short
notice. To verify the status of meetings,
call (recording)—301–415–1292.
Contact person for more information:
Rochelle Bavol, 301–415–1651.
*
*
*
*
*
The NRC Commission Meeting
Schedule can be found on the Internet
at: https://www.nrc.gov/public-involve/
public-meetings/schedule.html.
*
*
*
*
*
The NRC provides reasonable
accommodation to individuals with
PO 00000
Frm 00179
Fmt 4703
Sfmt 4703
disabilities where appropriate. If you
need a reasonable accommodation to
participate in these public meetings, or
need this meeting notice or the
transcript or other information from the
public meetings in another format (e.g.
braille, large print), please notify Bill
Dosch, Chief, Work Life and Benefits
Branch, at 301–415–6200, TDD: 301–
415–2100, or by email at
william.dosch@nrc.gov. Determinations
on requests for reasonable
accommodation will be made on a caseby-case basis.
*
*
*
*
*
This notice is distributed
electronically to subscribers. If you no
longer wish to receive it, or would like
to be added to the distribution, please
contact the Office of the Secretary,
Washington, DC 20555 (301–415–1969),
or send an email to
darlene.wright@nrc.gov.
Dated: July 19, 2012.
Rochelle C. Bavol,
Policy Coordinator, Office of the Secretary.
[FR Doc. 2012–18129 Filed 7–20–12; 4:15 pm]
BILLING CODE 7590–01–P
SECURITIES AND EXCHANGE
COMMISSION
Sunshine Act Meeting Notice
Notice is hereby given, pursuant to
the provisions of the Government in the
Sunshine Act, Public Law 94–409, that
the Securities and Exchange
Commission will hold a Closed Meeting
on Thursday, July 26, 2012 at 2:00 p.m.
Commissioners, Counsel to the
Commissioners, the Secretary to the
Commission, and recording secretaries
will attend the Closed Meeting. Certain
staff members who have an interest in
the matters also may be present.
The General Counsel of the
Commission, or his designee, has
certified that, in his opinion, one or
more of the exemptions set forth in 5
U.S.C. 552b(c)(3), (5), (7), 9(B) and (10)
and 17 CFR 200.402(a)(3), (5), (7), 9(ii)
and (10), permit consideration of the
scheduled matters at the Closed
Meeting.
Commissioner Aguilar, as duty
officer, voted to consider the items
listed for the Closed Meeting in a closed
session.
The subject matter of the Closed
Meeting scheduled for Thursday, July
26, 2012 will be:
Institution and settlement of
injunctive actions;
Institution and settlement of
administrative proceedings;
Adjudicatory matters; and
E:\FR\FM\24JYN1.SGM
24JYN1
Agencies
[Federal Register Volume 77, Number 142 (Tuesday, July 24, 2012)]
[Notices]
[Pages 43405-43406]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2012-18018]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[NRC-2010-0138]
Final Standard Review Plan, Branch Technical Position 7-19 on
Guidance for Evaluation of Diversity and Defense-in-Depth in Digital
Computer-Based Instrumentation and Control Systems
AGENCY: Nuclear Regulatory Commission.
ACTION: Notice of availability.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC or the Commission)
staff is issuing Final Revision 6 to NUREG-0800, ``Standard Review Plan
for the Review of Safety Analysis Reports for Nuclear Power Plants,''
Branch Technical Position (BTP) 7-19 on ``Guidance for Evaluation of
Diversity and Defense-in-Depth in Digital Computer-Based
Instrumentation and Control Systems.'' This BTP is to be cited as the
acceptance criteria for Diversity and Defense-in-Depth in Digital
Computer-Based Instrumentation and Control Systems in the Standard
Review Plan (SRP), Chapter 7, for those standard reactor designs that
have not been certified prior to the date of this BTP. The purpose of
this SRP update is to provide staff guidance for assessing combined
license (COL) applicant compliance with the requirements.
DATES: The effective date of this SRP update is August 23, 2012.
ADDRESSES: Please refer to Docket ID NRC-2010-0138 when contacting the
NRC about the availability of information regarding this document. You
may access information related to this document, which the NRC
possesses and are publicly available by any of the following methods:
Federal Rulemaking Web site: Go to https://www.regulations.gov and search for Docket ID NRC-2010-0138. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-492-
3668; email: Carol.Gallagher@nrc.gov.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may access publicly-available documents online in the NRC
Library at https://www.nrc.gov/reading-rm/adams.html. To begin the
search, select ``ADAMS Public Documents'' and then select ``Begin Web-
based ADAMS Search.'' For problems with ADAMS, please contact the NRC's
Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-
4737, or by email to pdr.resource@nrc.gov. The ADAMS accession number
for each document referenced in this notice (if that document is
available in ADAMS) is provided the first time that a document is
referenced. The Final Revision 6 to NUREG-0800, ``Standard Review Plan
for the Review of Safety Analysis Reports for Nuclear Power Plants,''
Branch Technical Position (BTP) 7-19 on ``Guidance for Evaluation of
Diversity and Defense-in-Depth in Digital Computer-Based
Instrumentation and Control Systems'' (Package) (ADAMS Accession No.
ML110550767), Final Revision 6 to NUREG-0800, ``Standard Review Plan
for the Review of Safety Analysis Reports for Nuclear Power Plants,''
Branch Technical Position (BTP) 7-19 on ``Guidance for Evaluation of
Diversity and Defense-in-Depth in Digital Computer-Based
Instrumentation and Control Systems,'' (ADAMS Accession No.
ML110550791), and Comment Response Document for BTP 7-19, (ADAMS
Accession No. ML120830075).
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
The NRC posts its issued staff guidance on the NRC's
external Web page (https://www.nrc.gov/reading-rm/doc-collections/nuregs/staff/sr0800/).
[[Page 43406]]
FOR FURTHER INFORMATION CONTACT: Mr. Ian C. Jung, Chief,
Instrumentation, Controls and Electrical Engineering Branch 2, Division
of Engineering, Office of New Reactors, U.S. Nuclear Regulatory
Commission, Washington, DC 20555-0001; telephone: 301-415-2969 or email
at Ian.Jung@nrc.gov.
SUPPLEMENTARY INFORMATION: The NRC staff issues SRPs and BTPs to
facilitate timely implementation of current staff guidance and to
facilitate activities associated with the review of applications for
design certifications and combined licenses by the Office of New
Reactors. Additionally, the SRPs and BTPs are used by the Office of
Nuclear Reactor Regulation staff in the review of applications for
license amendments in currently operating nuclear power plants. The NRC
staff will also incorporate the revised SRP section and BTP 7-19 into
the next revision of Regulatory Guide 1.206 and any related guidance
documents.
On March 19, 2010, the NRC staff issued the proposed Revision 6 of
NUREG-0800, ``Standard Review Plan for the Review of Safety Analysis
Reports for Nuclear Power Plants: LWR Edition,'' BTP 7-19 on ``Guidance
for Evaluation of Diversity and Defense-in-Depth in Digital Computer-
Based Instrumentation and Control Systems'' (ADAMS Accession No.
ML093490771). The NRC staff considered comments received on the
proposed revision to BTP 7-19 as well as recommendations from the ACRS,
and incorporated the changes suggested in the comments in this final
issuance. The NRC staff responses to these comments can be found under
ADAMS Accession No. ML120830075.
Backfitting: This SRP update does not constitute backfitting as
defined in Title 10 of the Code of Federal Regulations (10 CFR) 50.109,
nor is it inconsistent with any of the issue finality provisions in 10
CFR Part 52. This SRP does not contain any new requirements for COL
applicants or holders under Part 52, or for licensees of existing
operating units licensed under part 50. Rather, it contains additional
guidance and clarification on compliance with 10 CFR 52.79(a)(31),
which may be used by COL applicants in the preparation of their
applications.
Congressional Review Act: This SRP update is a rule as designated
in the Congressional Review Act (5 U.S.C. 801-808). However, OMB has
not found it to be a major rule as designated in the Congressional
Review Act.
Dated at Rockville, Maryland, this 16th day of July 2012.
For the Nuclear Regulatory Commission.
Amy E. Cubbage,
Chief, Policy Branch, Division of Advanced Reactors and Rulemaking,
Office of New Reactors.
[FR Doc. 2012-18018 Filed 7-23-12; 8:45 am]
BILLING CODE 7590-01-P